JWPCP Steam System Startup and Commissioning February 27, 2014 History Total Energy Facility ● Placed into operation in 1986 Combined cycle power plant Three gas turbines (7.2 MW each) One steam turbine (5.5 MW) Generates ~14 MW ● Capital cost of ~$45 million HRSG’s Steam Turbine History (cont.) 1994 Consent Decree ● Federal and state governments, NRDC and Heal the Bay ● Full secondary by December 31, 2002 Four new Reactor/clarifier trains New cryogenic oxygen plant Seven new digesters ● Higher electricity/steam demand ● Higher digester gas production JWPCP (before) JWPCP (after) History (cont.) TEF Modifications ● Conduct in two stages 1. Replace gas turbines 7.2 MW to 9.9 MW Completed in 2001 2. Replace steam system 5.5 MW to 8.7 MW New HRSG’s Chronology Equipment Procurement ● Steam Turbine Purchased in 2005 for $2.4 million Placed in storage in 2005 ● HRSG’s Purchased in 2005 for $3.3 million Stored outside, beginning 2005 Chronology (cont.) 2007 Advertisement ● Advertise for Engineering, Procurement and Construction (EPC) contractor ● No takers Contractors unable to locate consultants to complete engineering design ● Advertisement terminated ● Negotiate with Engineer to complete design ● Anticipate construction completion in April 2011 Chronology (cont.) Steam Turbine Overspeed Event ● April 3, 2008 ● Board authorizes emergency repairs for $2.5 million Steam Turbine Chronology (cont.) Expedite Project Split into two phases in summer 2008 ● Phase I: mechanical installation of steam turbine and HRSG’s ● Phase II: balance-of-plant installation and startup & commissioning Advance procure additional equipment Anticipated construction completion in May 2010 The Players Sanitation Districts Engineering Design Field Engineering JWPCP Engineer (designer) Phase I Contractor Phase II Contractor Systems Integrator Startup & Commissioning (S&C) Contractor Equipment Suppliers Construction Phase I ● ● ● ● Begins August, 2009 Ends ~April, 2010 Demolish steam turbine and HRSG’s Install new steam turbine and HRSG’s Mechanical installation only HRSG’s Steam Turbine Construction (cont.) Phase II ● ● ● ● ● Begins May, 2010 Estimated completion March, 2011 Balance-of-plant equipment Electrical and instrumentation Startup and commissioning Construction (cont.) Phase II Construction Delays ● Equipment approvals ● Equipment fabrication ● Equipment erection Cooling towers High-pressure gas pretreatment ● In part, due to the multitude of players Construction (cont.) Steam Blows ● Conducted in October 2011 ● Precedes startup and commissioning ● Startup & commissioning contractor needed detailed start up documents ● Startup and commissioning halted for safety reasons Negotiations Engineer Systems Integrator Engineering Design S&C Contractor Field Engineering Phase II Contractor JWPCP Negotiations (cont.) Topics ● ● ● ● ● ● ● ● Functional descriptions Functional test plan Functional testing Control descriptions Logic diagrams O&M manuals Training manuals Training Negotiations (cont.) Summary ● S&C Contractor Didn’t want to provide materials, or wasn’t going to provide materials unless paid more ● Engineer and Systems Integrator Wanted more money; however, we were not confident they had the expertise to do it Negotiations (cont.) May 2012 ● Districts parties agree 1. Remove startup and commissioning from Phase II contract 2. End Phase II contract 3. End contract with Engineer and Systems Integrator 4. Turnover startup and commissioning to JWPCP 5. Engineering Design to assist JWPCP Proposal June 2012 ● JWPCP solicits proposals from four contractors ● Two proposals received ● Select contractor Offers expert in steam systems ● On June 27, 2012, Board of Directors authorizes Purchase Order for $415,000 Proposal (cont.) Proposal Deliverables ● ● ● ● ● Functional test plan Functional testing Logic diagrams Control descriptions O&M manuals Including startup, shutdown, operating, troubleshooting and emergency procedures ● Training manuals ● Training Proposal (cont.) Proposal Deliverables (cont.) ● Schedule Seven-month schedule, completing in February, 2013 ● Programmer Logic review Make changes to programming (200 hours) ● Expertise Make recommendations for improvements ● Project team dedicated to project Startup & Commissioning Divided into Three Stages 1. Document review 2. Document development 3. Startup and commissioning Startup & Commissioning (cont.) Issues ● Steam turbine In storage since 2005 ● Steam blows Conducted more than one year ago ● Chemical cleaning Conducted more than one year ago Startup & Commissioning (cont.) Completed in March, 2013 One month behind schedule Fifty-two recommendations Most implemented Approximately $85,000 in extra work Implementing recommendations Power Production Steam Turbine HRSG’s Lessons Learned Limit involved parties Avoid advance purchased equipment Tighten startup and commissioning language in specifications Purchase all equipment under same contract Questions