CHP (VA Dallas Case Study)

advertisement
CHP (VA Dallas Case Study)
Technologies 1
Dallas VA Medical Center
A CHP Case Study
Design Build Delivery of a Combined Heat and
Power (CHP) Project for a Federal Client
Proprietary Information Of
Energy 2013
Agenda
1. Introductions
2. Project Overview
3. Vision
4. Construction Activities
5. Challenges/Lessons Learned
6. Q&A
Proprietary Information Of
Energy 2013
Introductions
Mike McLaughlin, PE
Vice President of Engineering
Proprietary Information Of
Energy 2013
Jeff Gunlicks
Project Manager
Project Overview
Dallas VA Medical Center
•
•
•
•
•
Proprietary Information Of
Energy 2013
The referral center for VA North Texas Health Care System
A major teaching and medical research center.
An 84 acre campus less than 10 miles south of Dallas
Providing a wide range of medical specialties
Includes 544 beds and over 1 million sf of healthcare space
Project Overview
Existing Central
Utility Plant
Electrical Support
Building
Turbine Yard
Project Scope
• Add a 4.6 MW natural gas fired turbine to an existing
central energy plant.
• Replace an existing steam boiler with a dual fuel fired Heat
Recovery Steam Generator (HRSG) to replace an existing
steam boiler.
• Integrate electricity into the existing 11MW usage.
Proprietary Information Of
Energy 2013
Project Vision
What were the project goals?
• Reducing operating costs and saving energy
• Leveraging renewable energy and improve “Green” footprint
• Energy Security
Why was CHP chosen?
• Consistent demand for power and heat.
• Integrated well with existing infrastructure
• Improved energy independence
Where did the owner start?
• Feasibility study that assessed the economical, technical and
funding options.
• Investigation included Biodiesel, Landfill Gas and Biomass and
conventional (natural gas)
Proprietary Information Of
Energy 2013
Traditional System
Heat
Power
45%
Efficient
Power Plant
Proprietary Information Of
Energy 2013
Boiler Plant
Combined System
Heat
Power
80%
Efficient
Generator
Proprietary Information Of
Energy 2013
Heat Recovery
Combined Heat & Power
Power
Gas fired engines
½ – 2.5 MW
Heat
Heating Water
180F-220F
Micro Turbines
½ - 1 MW
Dallas VA
Gas Turbines
5 – 50 MW
Proprietary Information Of
Energy 2013
Steam
25,000lbs/hr
400,000 lbs/hr
Combined Heat & Power
Heat
Power
Generator
Air Inlet
Filter
Bypass Duct
Gas
Turbine
Diverter
Valve
Turbine
Proprietary Information Of
Energy 2013
Heat
Recovery
Steam
Generator
Supplementary
Burner
Heat Recovery
Combined Heat & Power
Heat Recovery Steam Generator
Heat
A custom piece of equipment design and
fabricated to meet the project requirements
•
Essentially a large water tube boiler using
turbine exhaust heat as heat source
Heat
Recovery
Steam
Generator
Supplementary
Burner
Actual Dallas VAMC HRSG during hydrostatic
pressure test
Proprietary Information Of
Energy 2013
Heat Recovery
Project Schedule
DESIGN
CONSTRUCTION
MAR
APR
MAY
DRAWINGS COMPLETE
DRAWINGS ISSUED FOR
CONSTRCTUION
CONSTTRUCTION STARTS
Aug 2011: Proposal Submitted
JUN
JUL
AUG
SEP
OCT
NOV
DEC
JAN
FEB
MAR
Dec 2013: NG Pipeline Complete
Dec 2013: Target Turnover
Proprietary Information Of
Energy 2013
APR
CONSTRUCTION COMPLETE
FEB
2013
TUBRINE DELIVERED
JAN
PURHCASE HRSG
CONTRACT SIGNED
DEC
2012
PURCHASE TURBINE
2011
CHP Construction
Equipment Delivery & Rigging:
Considerations:
• Access to site
• Space for cranes to set up
Proprietary Information Of
Energy 2013
Turbine
CHP Construction
Equipment Delivery & Rigging:
Considerations:
• Access to site
• Space for cranes to set up
• Size of doors in facility
Proprietary Information Of
Energy 2013
HRSG
CHP Construction
Equipment Delivery & Rigging:
Considerations:
• Access to site
• Space for cranes to set up
Proprietary Information Of
Energy 2013
NG Compressor
CHP Construction
Site Construction:
Considerations:
• Accessibility
• Noise & Emissions
• Proximity to Utilities
Proprietary Information Of
Energy 2013
CHP Construction
Site Construction:
Turbine exhaust
Inlet Air Chilling Coils
Generator and Turbine
(Inside Enclosure)
Proprietary Information Of
Energy 2013
CHP Construction
Site Construction:
Main Stack
Economizer
Proprietary Information Of
Energy 2013
Steam Connection Water Tube Boiler
Fuel Train
Exhaust
from Turbine
Duct Burner
CHP Construction
Natural Gas Supply:
•
•
•
•
•
Proprietary Information Of
Energy 2013
Availability of Natural Gas will dictate
size/cost of the Natural Gas
Compressor.
Turbine required 230 psig natural
gas.
Existing gas supply was 20 psig which
would have required a 300 HP
compressor.
Government opted to contract for a
dedicated 100-180 psig natural gas
line which dropped NG Compressor
to 100 HP saving significant energy
Start up currently waiting on
completion of NG line.
CHP Construction
Other Considerations:
1.
Construction in an operating Central Energy Plant
•
2.
Shut-downs/high risk operations: Hot tap, Electrical tie-ins
Working closely with the end-user throughout the duration of
the project facilitated:
•
Deliver the owner products that meet
their needs
(example: sight glass change out).
•
•
•
Proprietary Information Of
Energy 2013
Facility operators become familiar with
equipment, and manufacturers
representatives.
RFI’s answered quickly with design-build
delivery and access to end user.
Extensive training at facility turnover for
the operators.
CHP Construction
Other Considerations:
3.
Manufacturers Representatives are vital to the effort
•
•
4.
Planning for Long Lead Items
•
•
5.
Production of Shop Drawing
Payment Schedule and Financing
Allow for innovation and design flexibility (design-build):
•
•
Proprietary Information Of
Energy 2013
Coordination is critical
Expertise is invaluable
Alternative Solutions within the contractual requirements
Improved performance with cost savings
Summary
Benefits:
•
•
•
•
Improved energy efficiency
Energy Independence
Opportunities to leverage renewable energy sources
Environmental Stewardship
Options:
•
•
•
Available for systems from ½ MW to 50+ MW
Heat is available as heating hot water or steam
Systems can utilize packaged or custom equipment
Unique Considerations:
•
•
•
Design to best match your application
Construction offers different challenges that traditional construction.
Financing and Utility Rebates are commonly available.
Select qualified partners to and contract delivery methods
Proprietary Information Of
Energy 2013
Questions
Proprietary Information Of
Energy 2013
Download