materials presented (PPTX 4.1MB) - the Australia and New Zealand

advertisement

Square Kilometre Array (SKA) Project

PRE-CONSTRUCTION PHASE

Briefing for Industry

& Science Organisations

Tuesday 14 th August

Wellington

Chairman’s welcome

John Houlker, NZTE

SKA project update

(Jonathan Kings, MBIE)

PEP work packages

(Michelle Storey, CSIRO)

Australian PEP funding

(David Luchetti, DIISRTE)

NZ perspective

(Howard Markland - MBIE)

Engagement opportunities

(Melanie Johnston-Hollitt

– VUW)

Question & answer session

Duration: 09:00 – 12:00

Organisations Involved

SKA project update

Jonathan Kings, MBIE

NZ Project Director

SKA project status

9 SKA Organisation members

(New Zealand, Australia, S.

Africa, United Kingdom, Netherlands, Italy, China, Canada, Sweden)

Bid evaluation process

Dual-Site Solution

• Shared infrastructure

– Australia gets low-frequency aperture array & survey telescope (extended ASKAP)

– S. Africa gets mid-frequency infrastructure

• Best available outcome for A-NZ bid

• Effectively a 50:50 split for Phase I

(by value)

• No plan for infrastructure in New Zealand

Project Timeline & Phases

Current Activity

Pre-construction Phase underway

• Detailed planning & engineering design

• €90 million budget

• Led by SKA Project Office

(Manchester)

• Funded by participating consortia

SKA Project Office

• Project Execution Plan (PEP)

• Work Breakdown Structure (WBS)

• Developing policies

– industry engagement

– procurement

– intellectual property

PEP work packages

Michelle Storey, CSIRO

SKA Pre-construction

Workpackage structure

SKA pre-construction briefings

6-14 August 2012

CSIRO ASTRONOMY AND SPACE SCIENCE

Structure of pre-construction work

• Work Breakdown Structure (WBS) being developed by SKA

Office with substantial input from the international community.

• Draft released to research partners May 2012.

• SKA Office now working on a new version of the WBS, to incorporate results of the site selection

• Possible that workpackages will stay the same, though their internal structure might be different

• Stage 1 to take system to system requirements review

• WBS for Stage 2 will be developed during/after Stage 1

• Stage 2 to reach construction-ready contracts

Workpackages led by the SKA Office

• Five workpackages led by the SKA Office

– Science

– Project Management

– System engineering to System Requirements Review

– Power

– Site and infrastructure

• There may be some direct contracts available

• Integrated Task Teams will be established for crosscutting areas

Presentation title | Presenter name | Page 12

Consortia-led workpackages

Workpackage

Dishes

Low Frequency Aperture Array (LFAA)

Signal and Data Transport (SaDT)

Central Signal Processor (CSP)

Science Data Processor (SDP)

Telescope Manager (TM)

Synchronisation and Timing (SaT)

Power

Site and Infrastructure

Mid Frequency Aperture Array (MFAA)

Phased Array Feed (PAF)

Wide Band Single Pixel Feed (WBSPF)

 Note that Site and Infrastructure and Power may be led by the SKA Office

Presentation title | Presenter name | Page 13

Dishes

(including Phased Array Feed and

Wide Band Single Pixel Feed)

CSIRO ASTRONOMY AND SPACE SCIENCE

Dish Array – Scope

The work package (preconstruction) covers all of the tasks necessary to plan for the development, construction, delivery and operation of the Dish Arrays for SKA1 on both

SKA sites (SA and AUS), including.

• Dishes

Structure - Pedestal, reflector, mount, …

• Performance Verification/Qualification

Operations - Support, maintenance, logistics

• Octave Band Single Pixel Feed (OBSPF)

Feed – Cryostat, Low Noise Amplifiers, …

Receiver - Amplification, signal transport, digitisation, …

• Elements of the Advanced Instrumentation Program (AIP)

Phased Array Feed (PAF) – Feed, receiver and signal processing

Wide Band Single Pixel Feed (WBSPF) – Feed, receiver and signal processing

Stage 1 work to input to systems requirements review

Dish Array – Possible Consortium partners

Australia

Consortium Management

Phased Array Feed (PAF) and associated dish optics

Receivers – Single pixel and PAF

South Africa

System Engineering

Single Pixel Feeds (SPF)

Dish – Optics, mechanical

Canada

China

Phased Array Feed (PAF)

Receivers – PAF

Dish – Composite reflectors

Dish – Optics, mechanical design

Wide Band Single Pixel receivers (WBSPF)

Dish

Wide Band Single Pixel receivers (WBSPF)

Sweden

Low-frequency Aperture Arrays

• CSIRO ASTRONOMY AND SPACE SCIENCE

SKA1_Low deliverables and potential partners

Covers development requirements and design of SKA1-low at Australian site

70 -<= 450 MHz located entirely in Australia

All-electronic telescope

• No moving parts. Functionality defined by ICT capability (investment)

Stage 1 PEP involves:

• Development and verification work in lead-up to System Requirements Review

• Performance and cost trade-offs via advanced system modelling

• Strong interactions with pathfinder (LOFAR, ...) and precursor (MWA) telescopes

• Science input to SKA System Engineering process

• Planning of Stage 2

Consortium is likely to be led by ASTRON, NL

• Current partners include ICRAR, INAF, UK (Camb, Oxf, Man) + 5 others

(Australian Inputs coordinated via ICRAR)

Science Data Processor

CSIRO ASTRONOMY AND SPACE SCIENCE

20

Science Data Processor WP

• SDP responsible for turning output of beamformers and correlators into final science products i.e. images, cubes, catalogs

• Challenges

Highly dependent on Concept of Operations

Very tightly coupled to Telescope Manager

Vast data flow

High Performance Computing vital (10s Petaflops to 10s Exaflops)

Power consumption for HPC Algorithms for calibrating and imaging not yet sufficiently scalable

Three different telescope designs, two different sites, globally data distribution to regional centers and end-users.

• High risk work package

Coupling to Telescope Manager

Scales of data, processing, complexity very high

SDP consortium

Most likely consortium is led by U Cambridge, UK

• Australia: CSIRO, ICRAR, U Melbourne

• NZ: TBD

• Others

South Africa: SKA team

UK: UCambridge, OERC, STFC (Daresbury), UManchester

Netherlands: ASTRON (Dome project, IBM)

Spain: IAA

Canada: CADC/cyberSKA

Germany: MPIfR

• Discussions with industry partners: IBM, Intel, CISCO

Consortium policy under review

• Good coverage of required capabilities

• Some weakness on operational aspects of large scale facilities

21

We acknowledge the Wajarri Yamatji people as the traditional owners of the Observatory site.

Thank you

CSIRO Astronomy and Space Science

CSIRO ASTRONOMY AND SPACE SCIENCE

Australian PEP Funding

David Luchetti (DIISRTE, Australia)

Pre-construction - business plan

• PEP business plan draw on various resources

• SKA Office to lead several work-packages - funded through a central fund

• Other work-packages to be allocated to consortia partly funded by member governments directly

• Likely consortia already forming – significant global interest

• Opportunities for new entrants

– Linking to existing consortia a good option

Pre-construction Phase Relevance

• Conventional contracting likely to be limited

• R&D partnership the main opportunity

• SKA may be a watching brief for some - with specific contracting opportunities several years away

• R&D partnership – why?:

– Positioning for downstream supply opportunities

– Building expertise/capability

– Reputational benefits

Co-Investment Funding - Objectives

• Support the SKA project

• Support take up of Australian IP & expertise

• Co-investment

(not fully-funded participation)

• In-kind co-investment OK

Co-Investment Funding – Program Structure

• Components for Major & Minor consortia partners

• Major partner component focussed on high priority work-packages

• DIISRTE will ‘pre-qualify’ organisations for SKA RfP

• Winners funded directly by DIISRTE – accountable for their contribution to a work-package

• Co-investment funds to leverage partnering opportunities

Co-investment Funding – Partnering facilitation

• Consortia struggling to use earlier EoI information

• Strategic, targeted EoI process to cut through to consortia lead organisations

Co-investment Funding – Funds distribution

STAGE ONE – 2012-2013

Funding

Major participant:15% of funding

Minor participant: 5% of funding

Number of Grants (Approx.)

Major participant: 2-3 grants

Minor participant: 8-12 grants

Value of Grants (Approx.)

Major participant: $0.5-1 million

Minor participant: $100K

STAGE TWO – 2014-2016

Funding

Major participant: 60% of funding

Minor participant: 20% of funding

Number of Grants (Approx.)

Major participant: 2-3 grants

Minor participant: 8-12 grants

Value of Grants (Approx.)

Major Participant: $3-7 million

Minor participant: $250K to $500K

NZ Perspective

Howard Markland - MBIE

Relationships

Funding

• New Zealand’s pledge:

– NZ$1.6 million (~10% of Australia’s commitment)

– dedicated to the 3-year Pre-construction Phase

– in-kind contribution

• Purpose of funding is to support:

– the SKA project

– capability & participation of NZ science & industry

– A-NZ reputation

Allocation Process

• Under Development

– mechanism, criteria, responsibilities etc.

– will not be inconsistent with the Australian model

(see ‘Minor Participant’ category)

• Process will be:

– appropriate for the funding available

– transparent, inclusive & defensible

– subject to technical peer review

– consistent with ANZSCC objectives

Requirements for Applicants

• Basic requirements:

– relevant & internationally acknowledged capability

– sufficient resource to ‘deliver’

– able to meet co-funding obligations ($ or in kind)

• Engagement process:

– link to an established consortium

– satisfy pre-qualification requirements

– monitor opportunities

– apply for funding

New Zealand Science &

Industry Opportunities

John Houlker (NZ Trade & Enterprise)

Science & Industry

Opportunities

Goal to secure opportunities for New Zealand science and industry to participate and build capability in the development of the leading-edge technology the SKA requires.

• Help build New Zealand science and industry collaboration (initial step SDP-NZ)

• Access to networks of high-technology research and development groups

• Leverage SKA Industry Cluster connections

• Capability building and investment prospects

Science & Industry

Opportunities

• Connection opportunities with major hightechnology Multi-National Corporations

– MNCs seeking to be “Primes” and lead technology developers

– Build IP relationships, paths to market, capability & maturity in engagement with MNCs.

• Pilot project technology development and testing possibilities.

NZ Engagement

Melanie Johnston-Hollitt – VUW

NZ involvement in

SKA

Murchison Wide Field

Array (full partner -

VUW lead institution)

ASKAP surveys (VUW,

UoC, AUT)

NZ involvment in

PEP

• Placeholder group ‘NZ-SDP’ joined Cambridge-led consortium for the SDP WP:

– Administrative lead – John Houler , Science and Industry leads Melanie Johnston-Hollitt, Dougal Watt

– Gave likley initial interest to Cambridge

– Consulted community, requested EoI ’s from community

– Auckland, AUT + Massey + Otago, VUW + IRL + IBM

– National EoI to be submitted to Cambridge / ANZSCC

– Pre-qualification/ peer review step required for funding

• MBIE to clarify process from here

• No funding support at present, limited funding support going forward.

NZ involvment in

PEP

• Immediate next steps ‘NZ-SDP’ national EoI to be finalised – still chance to get involved.

– Current submissions were around cloud computing, data pipeline and algorithm development.

– Strong interest to use MWA involvement at platform for SDP verification (real time imaging and calibration, pipelines, algorithms), hybrid correlators and low frequency science.

Summary

• Lots of moving parts:

– changing work-packages

– evolving work-package consortia

– SDP-NZ interest in Cambridge University consortium

– A-NZ collaboration arrangement

– A & NZ pre-qualification & funding arrangements

– SKA Organisation policies

– MED & MSI amalgamation (MBIE)………….etc.

• There will be opportunities for NZ engagement

• Limited funding support

• No free lunch

Stay engaged to follow developments

Key Contacts

NEW ZEALAND AUSTRALIA

Science

NZ SKA Research & Development Consortium

Melanie Johnston-Hollitt (Victoria University of Wellington)

Tel: +64 4 463 6543 Email: Melanie.Johnston-Hollitt@vuw.ac.nz

Industry

NZ SKA Industry Consortium

John Houlker (NZ Trade & Enterprise)

Tel: +64 4 816 8216 Email: John.Houlker@nzte.govt.nz

Government

Ministry of Business, Innovation & Employment

Howard Markland

Tel: 64 4 474 2981 Email: Howard.Markland @med.govt.nz www.med.govt.nz anzSKA website: www.ska.govt.nz

Science

CSIRO

Dr Carole Jackson

Tel: +61 2 9372 4407 Email: Carole.Jackson@csiro.au www.csiro.au

Industry

Australasian SKA Industry Consortium

John Humphreys

Tel: +61 7 5474 5164 Email: johnh@globalinnovation.com.au www.askaic.com

Government

Department of Industry, Innovation, Science, Research & Technology

Mike Bryson

Tel: +61 2 6276 1120 Email: michael.bryson@innovation.gov.au www.innovation.gov.au

anzSKA website: www.ska.gov.au

SKA Organisation website: www.skatelescope.org

Any Questions ?

Download