the SKA - Australia Telescope National Facility

advertisement
Project Execution Plan (PEP)
for the
SKA Pre-construction Phase
Aus-NZ Networking workshop
Perth, 25 Nov 2011
Dr Carole Jackson,
CSIRO Astronomy and Space Science
From today ...
ASKAP = one SKA Precursor
36 dish array; 6km extent
Single receiver technology (PAF)
$150M Build (2010)
From today ... to the SKA
SKA
1000’s dish array; 1000’s km extent
Multiple receiver technologies &
receptor arrays
EUR 1.5B start build 2016
ASKAP = one SKA Precursor
36 dish array; 6km extent
Single receiver technology (PAF)
$150M Build (2010)
SKA Schedule
Technical
2008-12
2013-15
2016-19
2018-23
2020
2024
Telescope system design and cost (PrepSKA/precursors)
detailed design in the pre-construction phase (PEP)
Phase 1 construction
Phase 2 construction
Science operations with Phase 1
Science operations with Phase 2
Programmatic
2011
Approve funding for pre-construction (PEP) phase - DONE
Establish SKA organisation as a legal entity – December 2011
Select location for SKA Project Office -> JBO DONE, build progressing!
2012
Site selection (29 Feb 2012)
2014
Approve construction funding for Phase 1 (350 M€, 2007)
2018
Approve construction funding for Phase 2 (1.2 B€, 2007)
CSIRO Confidential
What’s happening now?
Between now and January 2012:
-> The SPDO will become the (legal) SKA Project Office (SPO)
• Interim Director-General (Michiel van Haarlem ex-ASTRON)
• SPO has management & system authority for the whole project
• SPO will oversee the global effort – largely via Work Package
Consortia (i.e. Participating Organisations + Industry)
• The baseline plan for the Pre-construction phase is the PEP (2012 –
end 2015 -> ready to build)
• Funding for the PEP is essentially ‘national’ – with some contracts
possibly emanating from the SPO
SKA Ltd
Goals of the Pre-Construction Phase
Jan 2012 – Dec 2015
1.
Get the SKA design to Production Readiness Review stage and let
contracts for construction of major sub-systems
2.
Progress infrastructure roll-out on the selected site to allow subsystems to be deployed
3.
Mature the SKA legal entity into an organisation capable of carrying
out the construction, verification, and operation of the telescope
Preconstruction phase; build on work in PrepSKA and Precursors
Phase end = ‘ready to build’ the SKA
CSIRO Confidential
SKA Pre-construction Phase
Pre-Construction PEP
NOW
2011
SKA R&D
foundation
Studies ->
Concept
Designs
& SKA
Precursors
CSIRO Confidential
2012-2015
SKA build
Phase I
SKA build
Phase 2
2016
2018
SKA Pre-construction Phase
Pre-Construction PEP
NOW
2011
SKA R&D
foundation
Studies ->
Concept
designs &
SKA
Precursors
2012-2015
Plan for
PEP
Stage 1
CSIRO Confidential
Jun 12 – June 13
Jun 13 - Dec 15
PEP Stage 1
work delivery
PEP WP Stage 2
delivery
Contracts
SKA build
Phase I
SKA build
Phase 2
2016
2018
SKA Pre-construction Phase
Pre-Construction PEP
NOW
2011
SKA R&D
foundation
Studies ->
CoDRs
..................
SKA
Precursors
2012-2015
Jun 12 – June 13
Plan for
PEP
Stage 1
PEP Stage 1
work delivery
SPDO-led working groups
all SKA-interested parties
Institutes, industry... can
be involved; Nov 11 – Mar 12
CSIRO Confidential
SKA build
Phase I
SKA build
Phase 2
2016
2018
SKA Pre-construction Phase
Pre-Construction PEP
NOW
2011
SKA R&D
foundation
Studies ->
CoDRs
..................
SKA
Precursors
2012-2015
SKA build
Phase I
SKA build
Phase 2
2016
2018
Jun 12 – June 13
Plan for
PEP
Stage 1
PEP Stage 1
work delivery
SPDO-led working groups
all SKA-interested parties
Institutes, industry... can
be involved; Nov 11 – Mar 12
Stage 1 work packages will
be awarded via ‘bids’ from
Consortia (bid process ~May
2012, award of Stage 1 work
~July 2012)
Aus-NZ partners
form consortia ready
for Stage 1 bidding
CSIRO Confidential
SKA Pre-construction Phase
Pre-Construction PEP
NOW
2011
SKA R&D
foundation
Studies ->
CoDRs
..................
SKA
Precursors
2012-2015
SKA build
Phase I
SKA build
Phase 2
2016
2018
Jun 13 - Dec 15
Plan for
PEP
Stage 1
PEP Stage 1
work delivery
PEP WP Stage 2
delivery
Contracts
Stage 1 PEP work includes
planning for Stage 2 (the major
prototyping work phase)
CSIRO Confidential
Stage 2 PEP work contracts
awarded second half of 2013
SKA Pre-construction Phase
Pre-Construction PEP
NOW
2011
SKA R&D
foundation
Studies ->
CoDRs
..................
SKA
Precursors
2012-2015
SKA build
Phase I
SKA build
Phase 2
2016
2018
Jun 13 - Dec 15
Plan for
PEP
Stage 1
PEP Stage 1
work delivery
PEP WP Stage 2
delivery
Contracts
End of Stage 2
= ‘ready to
build SKA
Phase I
CSIRO Confidential
SKA PEP Phase Work Packages
1.
2.
3.
4.
Management (SPO)
System
Science
Maintenance and support /Operations Plan
5. Dish Array
6. Aperture arrays
7. Signal transport & networks
8. (Digital) Signal processing
9. Computing & software
10. Power
11. Site preparation
CSIRO Confidential
Work Package Allocation
CSIRO Confidential
Aus-NZ Networking workshop
0915 – 0930 ASKAP and SKA infrastructure (Shaun Amy, CSIRO)
0930 – 0945 Networking for SKA: the scope of the system (Charles Smith/ Peter
Elford, Cisco & CSIRO)
0945 – 1000 Networking work package – setting the SKA baselines (Neil Marston,
CSIRO)
1000 – 1020 Coffee
1020 – 1145 Discussion; baseline issues; Chair Peter Elford (Cisco)
1145 – 1200 Workshop summary (Sarah Pearce, CSIRO)
Dr Carole Jackson
carole.jackson@csiro.au
CSIRO Astronomy & Space Science
Web: www.atnf.csiro.au
www.csiro.au/org/CASS.html
Thank you
Contact Us
Phone: 1300 363 400 or +61 3 9545 2176
Email: enquiries@csiro.au Web: www.csiro.au
CSIRO Confidential
Context of Pre-Construction Phase
2009
2010
2011
2012
2013
SKA Preparatory Phase
Science
SKA1
2015
2017
Science / Engineering
Tradeoffs
Early Science Proposals
dCoDR
SKA1
Concept
Concept
PDR
SRR
Preliminary Design
Definition*
REV
Continuous Performance Evaluation
CDR
Detailed
Design
SKA1 Systems integration
Sys Eng
& Change management
SKA1 System Testing
System
PDR
Early Preliminary
Design
SKA2
REV
Science
SKA2
DRM
Development
SKA1
Baseline
Design
2009
2010
REV
Science / Engineering tradeoffs
Extraction of detailed SKA2 requirements
Demonstration
& testing
AIP definition, development and fabrication
Project
Milestones
Preliminary Design
System Definition (includes non-science requirements)
REV
REV
Initial SKA2
User Tech.
Requirements
AIP
Rev K
2010-08-18
Shared
Risk
Science
Refinement of
Early Science
REV
CoDR
2018
REV
REV
SKA1 User
Tech.
Requirements
2016
Phase 1 Construction, Verification, Commissioning,
Acceptance, Integration & First Science
Phase 1 Pre-Construction Phase
REV
DRM
Development
(Ph 1 part)
2014
Site decision
2011
Costed
system
design
2012
* Includes definition of non-science requirements.
SKA1
construction
approval
2013
2014
Start of SKA1
Construction
AIP Decision
2015
2016
SKA2
construction
approval
2017
Baseline
Design for
SKA2
2018
SKA sub-system overview
All SKA sub-systems are to progress through this process
2011
2012
2014
With a narrowing of # options during development of SKA
SKA1 ready
SKA2 ready
CSIRO Confidential
WP7.1 – Engineering and Management
Within the SPO both management and engineering resources are
allocated to this task. The SPO team comprises a Technical Project Manager,
System Engineer and Engineers.
WP7.2 – Preliminary Design
For all the subsystems:
Complete SKA1 preliminary design phase
Conduct SKA1 preliminary design review
Completion and auditing of documentation
Subsystems for review in this phase include:
Dish cabling
Digital data back haul
LO and timing
M+C network
Fibre Network Infrastructure connection schematic delivered
CSIRO Confidential
WP7.3 – Network Infrastructure
This work will include leadership and coordination of the network infrastructure
task, including review of plans and designs. The integration of site information
and network infrastructure designs are included in this task as well as the
preparation of the procurement datapacks. There will be some preparatory
work on plans to manage the ‘as built’ network and test results.
WP7.4 – Digital Data Backhaul
This work will include the detailed definition and monitoring of interfaces,
review of designs and the completion of procurement ready datapacks.
Prototype systems will be constructed and test software/firmware developed,
if applicable.
CSIRO Confidential
WP7.5 – Synchronisation
This work will include the detailed definition and monitoring of
interfaces, review of designs and the completion of procurement ready
datapacks. Prototype systems will be constructed and test software/firmware
developed, if applicable.
WP7.6 – M&C Networks (Physical Layer)
This work will include the detailed definition and monitoring of interfaces, review
of designs and the completion of procurement ready datapacks. Prototype
systems will be constructed and test software/firmware developed, if applicable.
WP7.7 – Antenna Networks
This work will include the detailed definition and monitoring of interfaces, review
of designs and the completion of procurement ready datapacks. Prototype
systems will be constructed and test software/firmware developed, if applicable.
WP7.8 – Central Facility Interconnects
In this task a central facilities fibre network cabling and routing plan will be
developed. Work will include the detailed definition and monitoring of interfaces,
review of designs and the completion of procurement ready datapacks.
WP7.9 – Imaging Distribution
This work will include the detailed definition and monitoring of interfaces, review of designs and the
completion of procurement ready datapacks. Prototype systems will be constructed and test
software/firmware developed, if applicable.
CSIRO Confidential
Download