Barnstable Public Schools Integrated Preschool Presentation Town Council Meeting November 20, 2014 Education Laws and Regulations 603 CMR 28.00: Special Education (7) Programs for young children. The school district shall ensure programs are available for eligible children three and four years of age. Such programs shall be developmentally appropriate and specially designed for children ages three and four years. Timeline FY ’13 budget Request $125,000 for removal of portable trailers and space needs assessment study – town council approves funding October 2013 Space needs assessment study completed November 2013 Presented space needs assessment findings to school committee April 2014 Submission of FY’15 CIP to town manager; approved by town council July, October, November, 2014 Meetings with town council members (Jessica, Ann, Jim, Sarah, Paul), school committee members (Margeaux, Chris), superintendent, town manager, administration August 11, 2014 Bid # 1 for modular construction Early Learning Center September 12, 2014 Bid # 1 opened October 14, 2014 Rebid project: Bid #2 October 31, 2014 Bid # 2 opened Bid #1 Barnstable Early Childhood Center Design Area (SF) 8,647 Triumph Proposed Price 3,677,475 Innovative 425.29 4,170,500 482.31 Deduct 1 Transformer (98,000) (54,100) Deduct 2 Canopy (29,425) (17,400) Deduct 3 Reduce Classroom by 2'-0" Deduct 4 Reduce Classroom by 2'-0" Proposed Price less Deducts (11,300) 37.67 (20,100) 67.00 (32,300) 107.67 (49,800) 166.00 3,506,450 405.51 4,029,100 465.95 Bid #2 Barnstable Early Childhood Center Design Area (SF) 8,647 Triumph Proposed Price Innovative 2,255,036 260.79 3,150,000 364.29 Deduct 1 Reduce Classroom by 2'-0" (11,300) 37.67 (10,000) 33.33 Deduct 2 Reduce Classroom by 2'-0" (32,300) 107.67 (20,000) 6.67 Proposed Price less Deducts 2,211,425 255.74 3,120,000 360.82 Bid #2 Proposed Budget Funding Sale of Bonds Funding Total Design Construction Documents Design Total Advertising Design Total Construction Building - Triumph @ 8647 SF Construction Administration-TBA Contingency-Construction @ 5% Transformer – quote Construction Total Furniture, Fixtures and Equipment FFE Funding Surplus/ (Deficit) $2,000,000 $2,000,000 $(98,400) $(14,400) $(201) $(113,001) $(2,255,025) $(49,200) $(112,751) $(35,000) $260.79 $(2,451,976) District to cover $(564,977) Fiscal Impact Request for Appropriation and Transfer Order of $564,977 Council order 2014-092 appropriation for Barnstable Early Learning Center $2,000,000 Final design resulted in additional 1,147 Sq Ft & contingency funding Request redirection of funds from completed school projects $275,831.60 Remaining funds needed to complete project $289,145.40 Additional funding request $564,977 Request transfer of funds from School Department's allocation of General Fund Reserves: Available balance of $4.7 million