PJFogarty.

advertisement
Water Services Training Group
14th Annual Conference
New Decade – New Challenges
9th September 2010
New Decade - New Challenges
Annual Conference September 2010
Trenchless Watermain
Rehabilitation Techniques
Padraic J Fogarty
Director
New Decade - New Challenges
Annual Conference September 2010
Outline of Presentation





Introduction
Rehabilitation Techniques
Review of Rehabilitation Techniques
Other Issues
Conclusions
New Decade - New Challenges
Annual Conference September 2010
Introduction
New Decade - New Challenges
Annual Conference September 2010
The Good News

Water Services Investment Programme
(WSIP) 2010 to 2012



Contracts with a total value of €321 million
to commence construction in the period
2010 to 2012.
90% Funding
WSIP 2010-2012 the Start!
New Decade - New Challenges
Annual Conference September 2010
Mains Rehabilitation Strategy


Starting Point
Identifies



Mains for Rehabilitation
Reasons for Rehabilitation
Pipe Materials
New Decade - New Challenges
Annual Conference September 2010
Objectives

Bang for Buck (More for Less)



Quality Installation




Water Quality - Drinking Water Regulations - “Protect Human
Health"
Watertightness - Reducing UFW
Robust and Durable Installation
Minimise Impact





Selection of Mains
Selection of Techniques
Interruption to Supply
Traffic and Access
Environmental – drilling fluids etc.
Nuisance - dust, noise etc.
Sustainable Construction
New Decade - New Challenges
Annual Conference September 2010
Terms and Abbreviations

Rehabilitation –


Replacement –





All methods for restoring or upgrading the performance of an
existing pipeline system
Methods of rehabilitation of an existing pipeline system by the
installation of a new system, either on or off the existing line,
without incorporating the original fabric
Host Pipe – Existing pipe/mains to be rehabilitated
Spray in Place Pipe (SIPP)
Cured in Place Pipe (CIPP)
Horizontal Directional Drilling (HDD)
New Decade - New Challenges
Annual Conference September 2010
Rehabilitation Techniques
New Decade - New Challenges
Annual Conference September 2010
Slide with photo or graph
New Decade - New Challenges
Annual Conference September 2010
Structural Rehabilitation


Cured in Place Pipe (CIPP)
Close Fit Sliplining





Diameter Reduction
Rolldown
Sliplining
Pipe Bursting/Pipe Splitting
Horizontal Directional Drilling
New Decade - New Challenges
Annual Conference September 2010
Non Structural & Semi Structural
Rehabilitation


Internal Joint Seals
Spray in Place Pipe (SIPP)




Cement Mortar Lining
Epoxy Lining
Cured in Place Pipe (CIPP)
Close Fit Sliplining


Diameter Reduction
Rolldown
New Decade - New Challenges
Annual Conference September 2010
Spray in Place Pipe - Epoxy


Thorough
cleaning of host
pipe
Spray host pipe
with a thin lining
of resin (typically
1mm thick)
 Advantages:
Minimal excavation
 Disadvantage: Requires a completely clean
and dry host pipe
New Decade - New Challenges
Annual Conference September 2010
Cured in Place Pipe


Fabric tube impregnated
with thermosetting resin
Inserted in host pipe and
heat cured – 2 Methods
 Pulled into host pipe
and expanded by
water pressure
 Liner turned inside
out (Inversion)
 Advantages:
Service connections
can be reinstated by robotic cutters
 Disadvantage: Requires extensive
pre-investigation
New Decade - New Challenges
Annual Conference September 2010
Close Fit Sliplining – Diameter
Reduction


New pipe temporarily
deformed
Two methods


Swaging
Compression Rollers
 Advantages:
Limited loss of pipe diameter
 Disadvantage: Difficult to install if irregularities in host
pipe
New Decade - New Challenges
Annual Conference September 2010
Close Fit Sliplining – Rolldown


Liner is heated
and folded
Liner is winched
into host pipe
and reshaped by
heat and
pressure
 Advantages:
Limited loss of pipe diameter and
accommodates bends
 Disadvantage: Reversion process may be difficult
New Decade - New Challenges
Annual Conference September 2010
Sliplining

HPPE pipe is
pulled into host
pipe
 Advantages:
Not reliant on integrity of host pipe
 Disadvantages: Reduction in pipe diameter (but
maybe not in capacity)
New Decade - New Challenges
Annual Conference September 2010
Pipe Bursting/Pipe Splitting



HPPE pipe is
attached to
bursting head
Break and
displace host
pipe
Pull replacement
pipe into the void
 Advantages:
No cleaning required; facilitates upsizing
 Disadvantage: Difficult in some situations; not suitable
for Asbestos Cement mains
New Decade - New Challenges
Annual Conference September 2010
Pipe Bursting - Execution
New Decade - New Challenges
Annual Conference September 2010
Horizontal Directional Drilling


Pilot bore to line
and grade
Reamer and new
HPPE pipe
pulled through in
reverse direction
 Advantages:
Less disruption compared to open cut;
existing supplies not cut-off
 Disadvantage: Depends on suitable soil conditions
and corridor free from existing services
New Decade - New Challenges
Annual Conference September 2010
Review of Rehabilitation
Techniques
New Decade - New Challenges
Annual Conference September 2010
Selecting Appropriate Technique (1)

Flow Chart for Selecting the Rehabilitation
Technology



Scale of Contract


Replacement/Structural Rehabilitation
Non-Structural and Semi Structural Rehabilitation
Is it large enough to justify use of specialist
equipment?
Availability of specialist contractors and
equipment or option for knowledge transfer to
local contractors
New Decade - New Challenges
Annual Conference September 2010
Selecting Appropriate Technique (2)

Suitability of materials



Suitability for contact with water
Physical properties (expansion and contraction)
Density of connections

If more than 20 connections per 100m it may be
more economical to open cut
New Decade - New Challenges
Annual Conference September 2010
Sustainable Construction
Open Cut
Directional
Drilling
Other No
Dig
Carbon Footprint
C
B
A
Waste
C
B
A
Local & Sustainable
Materials
C
B
B
Ecology
C
B
A
Archaeology
C
B/C
A
Health & Safety
B
A
A
New Decade - New Challenges
Annual Conference September 2010
Main Options

Pipe Bursting


Horizontal Directional Drilling



Dependent on suitable site conditions
Rural/Semi Urban
Independent of Connections
Cured in Place Pipe?
New Decade - New Challenges
Annual Conference September 2010
Case Study: Arva, Co.Cavan

Contract Details:



Start Date: 8th June, 2010
Contract Period: 15 weeks
Scope of Works


0.8km directional drilling of 180mm
HPPE
4.2km pipe bursting of 125mm HPPE




Host pipe: 4" Cast Iron
New meter boxes on all connections
Replacement of lead services to
property boundary
Key Enabling Works

Alternative Supply to facilitate pipe
bursting
New Decade - New Challenges
Annual Conference September 2010
Other Issues
New Decade - New Challenges
Annual Conference September 2010
Form of Contract

Capital Works Management Framework


Public Works Contract for Civil Engineering
Works Designed by the Employer
Public Works Contract for Civil Engineering
Works Designed by the Contractor
New Decade - New Challenges
Annual Conference September 2010
Standards for Products/Materials

Two Aspects



Strength and Robustness
Suitability for contact with Drinking Water
Products/Materials



Pipes/Liners/Coatings
Valves and Fittings
Service Pipes and Fittings
New Decade - New Challenges
Annual Conference September 2010
Rehabilitation of AC Mains


Elephant in the Room
EPA Response to Pipe Bursting


Not a feasible option
Options



Cured in Place Pipe
Close Fit Sliplining
Offline Replacement Pipe

Dealing with Existing Pipe?
New Decade - New Challenges
Annual Conference September 2010
Records and Monitoring


Requirements of Appendix 7 of L6/07
UFW Reduction


Prior to Rehabilitation
Post Rehabilitation


Maybe no reduction in UFW initially due to
increased pressure
Robust GIS system and procedures:


New infrastructure
Decommissioned infrastructure
New Decade - New Challenges
Annual Conference September 2010
Opportunistic Works


Meter Boxes?
Lead Services?
New Decade - New Challenges
Annual Conference September 2010
Advancing Rehab Implementation
WSAs and Consultants

Adoption of Mains Rehabilitation Strategy


Identification of Contracts
Setting Requirements


Contractor Qualifications
Performance Specifications

Strategy for Rehabilitation of AC Mains
 Advancing Rehabilitation Contracts
 Resource and Training Needs

Site Supervisory Staff
New Decade - New Challenges
Annual Conference September 2010
Advancing Rehab Implementation
Contractors

Provision of Market Information


Overall Programme – WSIP 2010 to 2012
Roll out of Contracts




Contract Size
Design by Employer or Contractor
Rehabilitation Techniques
Reasons

Efficient & Effective Implementation by facilitating
Contractors in identifying


Plant Requirements
Resource and Training Needs
New Decade - New Challenges
Annual Conference September 2010
Conclusions
New Decade - New Challenges
Annual Conference September 2010
Key Success Factors





Information
Technique to match Specific Circumstances
Competent Contractor
Preplanning
Response to Unknowns



Contractor
Employer/Engineer
Engagement with Consumers
New Decade - New Challenges
Annual Conference September 2010
Conclusions

Exciting New Phase in the Management of
Water Infrastructure Assets
 Evolving Situation



Technology and Materials
Contractor Experience
Testing in Ireland



Ground Conditions
Range of Contractors meeting Suitability Criteria
The Challenge 
Leave a Better Water Network Infrastructure for the
Next Generation
New Decade - New Challenges
Annual Conference September 2010
Acknowledgements



Colleagues at TOBIN and Mouchel
Joe Doyle, USA Ltd and USSR Ltd.
Michael Ward, Ward & Burke
Construction Ltd.
New Decade - New Challenges
Annual Conference September 2010
Download