KEY ASPECTS OF FIDIC DBO CONTRACTS 23/09/2011 1 Content 1. INTRODUCTION : THE NGRBA AND THE FRENCH SUPPORT 2. HOW TO CHOOSE THE BEST FIDIC CONSTRUCTION CONTRACT FOR A WASTE/WATER INFRASTRUCTURE PROJECT IN PPP ? 3. MAIN PITFALLS IN CONSTRUCTION CONTRACT BEFORE COMMERCIAL OPERATIONS 2 THE NGRBA AND THE FRENCH SUPPORT THE NGRBA AND THE FRENCH SUPPORT 3 THE NGRBA AND THE FRENCH SUPPORT Technical Assistance to NGRBA for project preparation (FASEP team based in Delhi + experts from France – Consortium Egis / SCE / Egis India) Duration of the services is 15 months Objectives : => Launch Team to facilitate the projects implementation in the 5 states along Ganga river => Move ahead rapidly with the World Bank Program => Support NGRBA in NMCG (ex-PMG) operations 4 FRENCH EXPERIENCE IN WATER MANAGEMENT Major features of water sector in France : Creation of Water agencies since 1964 for the 6 main hydrographical basins they collect water consumption fees and pollution taxes (households, industries, pesticides users) They use them to invest in water infrastructures and environmental actions within the river basin (subsidies to local authorities). 5 6 FRENCH EXPERIENCE IN WATER MANAGEMENT Major features of water sector in France : “Water Parliaments” at the basin level provide the democratic basis for debate and consultation in water management issues. There are water management plans at basin and sub-basin levels. They establish some rules related to water use, licensing and public participation. 7 FRENCH EXPERIENCE IN WATER MANAGEMENT Major features of water sector in France : Private participation through delegation of public service Mainly CONCESSION (BOT) or LEASE CONTRACT in water supply and sanitation. The public authority is still present (regulatory role) and shares the exploitation financial risk with the private actor The Contractor shall produce an annual reports showing incomes and expenses in a transparent way, including reinvestment of savings in infrastructures. 8 MEASURING RESULTS 200 1990 2008 9 FIDIC DBO CONTRACT HOW TO CHOOSE THE BEST FIDIC CONSTRUCTION CONTRACT FOR A WASTE/WATER INFRASTRUCTURE PROJECT IN PPP ? 10 FIDIC PRESENTATION FIDIC founded by French engineers in 1913 as Fédération Internationale des Ingénieurs Conseils (International Federation of Consulting Engineers) 1945 = 40 Engineers Associations ; 2009 = 80 Engineers Associations including India 1957 = 1st Red Book as « Conditions of Contract for Construction for Building Works designed by the Employer », 2008 = 1st Gold Book www.fidic.org , HO in Geneva, Switzerland. 11 FIDIC CONTRACTS / PARTIES INVOLVED Lenders The Employer DESIGN BUILD Disputes (Adjudication Board) SERVICE CONTRACT CONTRACT OPERATION TAKING-OVER The Engineer or Employer’s representative CERTIFICATE SERVICE Auditing Body CONTRACT The Contractor FIDIC contract Administration No contractual link ! 12 Historic Background of FIDIC contracts 13 Historic Background of FIDIC contracts 14 Best choice for FIDIC CONTRACT The Engineer undertakes (small amounts, small risks) the design ? yes no Small project ? yes no The Contractor undertakes the design The project is a plant and includes a balanced risk allocation ? no Fixed Cost Risks borne mainly by the Contractor yes no Discuss in details yes Operations(DBO) yes no 15 Principles FIDIC : Risks allocation Increase cost of Project Increase risk for The Contractor GOLD BOOK / SILVER BOOK YELLOW BOOK RED BOOK Increase risk for the Employer Increase design control by the Employer 16 COMPARISON FIDIC / French law 1 YEAR 1 YEAR 1 YEAR FRANCE CCAG P.I. IDEA => DEGREE OF PRECISION 2 YEARS < 20 YEARS CCAG TRAVAUX LAW CONCEPT PFS -FEED DTL DESIGN CONSTRUCTION OPERATIONS FRENCH CONSTRUCTION LAW FIDIC CONTRACTS GOVERNED BY LOCAL LAWS OF THE COUNTRY White book Red book Yellow book Silver book Gold book 17 FIDIC DBO CONTRACTS : KEY POINTS Employer’s requirements : • • • • Careful technical investigations of site Risk assessments (technical, commercial, financial) Infrastructure to be « fit for purpose » Tender procedure with prequalification Design responsibilities : • Strict definition of design criteria • Unforeseable difficulties to be foreseen (!) • Interfaces management (networks Vs. treatment plant) Claim management : • Special care for drafting the Contract (Particular Conditions of contract to be fit with the Laws) • Contemporary records to be kept • Mechanisms to avoid disputes 18 20 CLAUSES CLAUSE 3 The Employer’s representative CLAUSE 2 The Employer CLAUSE 20.7 Amicable Settlement (DAB) CLAUSE CLAUSE CLAUSE CLAUSE 193 SUB-CLAUSES CLAUSE 4 The Contractor COST € 1 General Provisions 17 Risk allocation 18 Exceptionnal Risks 19 Insurance CLAUSE 13 Variation and Adjustements CLAUSE 14 Contract Price and Payment CLAUSE CLAUSE CLAUSE CLAUSE 15 Termination by Employer 16 Termination by Contractor 19 Force Majeure 20 Claims FIDIC CLAUSE CLAUSE CLAUSE CLAUSE CLAUSE 5 Design 6 Staff and Labour 7 Plant, Materials, Workm 11 Testing 12 Defects QUALITY GOLD BOOK CLAIMS CONTRACT CLAUSE 8 Commencement, Completion and Programme CLAUSE 9 Design-Build CLAUSE 10 Operation Service TIME 19 SOME PITFALLS IN CONSTRUCTION CONTRACT 3. MAIN PITFALLS IN CONSTRUCTION CONTRACT BEFORE COMMERCIAL OPERATIONS 20 21 22 23 24 25 26 27 28 29 SOME PITFALLS IN CONSTRUCTION CONTRACT ACCESS TO SITE DELAYED FOR SITE INVESTIGATIONS TOPOGRAPHY AND GEOTECHNICS (SC 2.1) FORCE MAJEURE (EARTHQUAKE, STRIKE, WAR) (SC 18) New Critical Path Design Civil works ADVERSE SUB-SOIL CONDITIONS => COST +40% (SC 4.12) Procurement CUSTOM DUTIES NOT SOLVED IN TIME DUE TO MINISTRIES DELAYS (SC 9.4) Initial Critical Path Erection Commissioning NO RAW WATER IN TIME AS NETWORKS WORKS ARE DELAYED (SC 11.2) WHO PAYS FOR DELAY ? (SC 9.13) OPERATIONS Time of Completion YEAR 1 Cut-Off Date YEAR 2 UP TO 20 YEARS… 30 CONCLUSION INTERNATIONAL FIDIC DBO CONTRACT « GOLD BOOK » IS PARTICULARLY FIT FOR THE PURPOSE OF PPP WATER TREATMENT; IT IS … • COMPLETE • COMONLY SHARED BY ALL INTERNATIONAL PARTIES • DRAFTED TO AVOID AND TREAT PITFALLS … BUT WHO IS PROVIDING THE FINANCE ? FROM DBO, ADD AN « F » …THERE COMES THE « DB F O » CONTRACT - THANK YOU FOR YOUR ATTENTION THINK ABOUT FRENCH EXPERTISE ON FIDIC AND ON WATER PROCESS ! 31