Williams Companies, Inc. – Overland Pass Pipeline

advertisement
Overland Pass Pipeline
About Overland Pass Pipeline
• Approximately a 750-mile transmission
pipeline
• Originates in Opal, WY and ends at
Conway, KS
• Traverses 23 counties in 3 states
• 90% of route follows existing utility
corridors
• Transports natural gas liquids (NGLs)
Blacks Fork
About Overland Pass Pipeline
•
•
•
•
•
Approximate $450 million capital investment
14 and 16-inch diameter pipe (varies)
Made of high-strength steel
Buried minimum of 36” below ground
Maximum operating pressure 1,440 psig (Prior
to start up pipe is tested to 1800 psig)
• Pipe capacity range 90,000-150,000 barrels per
day
Local Economic Impacts
WY
CO
KS
Miles of pipe
322
171
257
Annual tax
revenue
$1.5 million
$990,000
$7.5 million
Capital
investment
$215 million
$98 million
$145 million
Construction
payroll
$17.6 million $10.4 million $15.3 million
Pump Stations
• 3 pump stations used to move NGLs
– Two in Wyoming - for startup
– One in Kansas - for maximum capacity
• This project is more efficient because gravity
helps move the product (meaning fewer pump
stations required)
Green River
There are two NGL Hubs in the U.S.
where mixed NGL Products are
fractionated, or separated into
individual components
• Mont Belvieu, Texas
• Conway, Kansas (includes multiple areas)
•
•
•
•
Bushton, Kansas
Hutchison, Kansas
Mitchell, Kansas
Conway, Kansas
Medicine Bow
Anticipated Project Schedule
Current
• Ongoing environmental/cultural surveys
• Submit major permit applications
Summer 2007
• Target date to receive regulatory approval
• Begin construction
Winter 2007-08
• Pipeline in service
Regulatory
• Bureau of Land Management (BLM) is lead
federal agency managing the regulatory
process, they will consult additional federal and
state agencies along the pipeline route
• This project is undertaking the completion of an
Environmental Impact Statement (EIS) which will
fall under the federal NEPA and 106 guidelines
More information about the project
is available at
www.overlandpass.com
www.oneok.com
(877) 683-7277
• Latest updates about the project
• Video of the construction process
• Links to educational documents about the Natural
Gas Industry
Regulatory Contact Information
• BLM project manager for this project is:
Tom Hurshman (970) 240-5345
2465 S. Townsend Ave., Montrose, CO
81401
overlandpass@ensr.aecom.com
Download