UNCW Facilities Update & Action Items August 22, 2014 Action Items • Energy Conservation Performance Contract Financing • Outdoor Enhancement Plan Modifications 2 Energy Conservation Performance Contract Financing 3 Proposed Performance Contract #2 Background: • University was enabled to enter into performance contracts in 2003 • First project ($4.3M) was financed in March 2010 with a 20 year term & was completed in October of 2011 • Verified energy savings from PC #1 to date are $979,387 • Proposed project is the second energy conservation performance contract (PC) undertaken by UNCW • Performance contractor selected and approved by the UNCW BOT for Performance Contract #2 is Ameresco • Investment grade audit with third party oversight by Celtic Energy was undertaken to validate the proposed energy savings • Performance financial risk lies with Ameresco 4 Proposed Performance Contract #2 Benefits of Energy Saving Measures: • Energy cost savings • Efficient and code compliant mechanical, electrical and control systems • Increased levels of safety - correct ventilation rates • Improved HVAC system controls for system monitoring • Increased comfort levels • Efficient exterior lighting • Reduced frequency of re-lamping • Invest savings in excess of the guarantee in other energy saving measures on campus (SB 1292) 5 X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X ECM 17 ECM 18 ECM 21 ECM 30 ECM 52 ECM 53 ECM 54 ECM 55 ECM 59 ECM 60 X X X X X X X X X X X X X X X X X X X X X X X X X Transformers- S&BS X X X X X X X X X X ECM 16 Water Fixtures - S&BS ECM 4 Campus Wide Outside Lighting ECM 3 Irrigation Wells Upgrade and Expand EMS ECM 2 Cooling Tower Wells Water Conservation ECM 1 Vending Machine Controls Lighting Controls Area Almkuist Nixon Sports Medicine Building Bear Hall Burney CEP Cameron Hall Computer Information Systems Cultural Arts Building Dobo Hall Dobo Education Building Friday Annex Friday Hall Hanover Hall Luetze Hall McNeill Hall Morton Hall Morton Natatorium Nixon Annex Oriole-Burevitch Lab PPH Lab Social and Behavioral Science Trask Coliseum Wagoner Energy Plant Main Campus Lighting System Improvements UNC Wilmington Energy Saving Performance Contract # 2 Variable Primary Hot Water Pumping - Trask Chilled Water Pumping Upgrades - Dobo Chilled Water Pumping Upgrades - Trask Convert Fume Hoods to Low Flow - Dobo Replace Trask Complex Steam System - Trask Proposed Performance Contract #2 X X X X X 6 X X X Proposed Performance Contract #2 UNCW and UNC System kBTU per Sq Foot beginning FY 2002-03 180 160 UNCW kBTU/SqFt UNC System kBTU/SqFt 140 100 Implementation of PC#2 will help to reduce per square foot energy consumption by 48% compared to FY 2002-03 80 60 40 84 103 119 104 126 111 137 115 143 124 145 133 144 135 147 138 147 152 151 155 154 20 161 162 kBTU/Sq Ft 120 0 7 Proposed Scope & Terms of Performance Contract #2 • Implement 15 Energy Conservation Measures across 21 buildings and the main campus • Generate guaranteed savings of approximately $16.2M. • Project construction cost estimate is currently $11 Million • Construction duration is approximately 18 months • Ameresco assumes payment risk on the outstanding debt not covered by energy cost savings • Approval by UNCW Board of Trustees required to take next steps • Approval process is multi-faceted through all State agencies where the final scope and estimates are established 8 Proposed Request to BOG for Performance Contract #2 (Action Item) • Total financing including capitalized interest not to exceed $11.5 Million • Finance Term not to exceed 20 years • Annual Interest Rate not to exceed 3.75% • Financing will be competitively bid, once State Agency approval occurs 9 Outdoor Enhancement Plan Modifications 10 Outdoor Enhancement Plan Background: • Student Recreation Center Expansion completed in April 2013 • Expansion included no outdoor enhancements • Competitive construction market yielded cost savings resulting in excess bond proceeds • UNCW initiated a master planning effort for Student Campus Recreation Exterior Facilities & Student Athletics Facilities in August 2013 • UNCW BOT approved the plan in December 2013 • Design of The Outdoor Enhancement Project (phase one of the master plan) began in January 2014 • Initial budget was $5 Million 11 Outdoor Enhancement Plan Budget: • Outdoor Enhancement Project was established with a budget of $5 Million • Resolution of Student Rec Center designer claims, definition of contractor claim exposure, steps toward contract closeout and reallocation of infrastructure costs yielded additional funds of $2.5 Million • Plan to invest the additional $2.5 million into the plan. The present project budget is established at $7.5 million without replacing the track 12 Outdoor Enhancement Plan Proposed Budget & Scope Summary: • • • • • Gateway Bldgs. & Infrastructure Artificial Turf Recreational Field Natural Turf Recreational Field Design Fees Construction budget baseball practice field relocation • Storm water Improvements • Fencing, Irrigation, Streetscape, Landscaping and FF&E • CM Fees, Design & Construction Contingency & Owner’s Reserve Total (without track) $1,500,000 $2,500,000 $ 750,000 $ 695,000 $ 475,000 $ 500,000 $ 600,000 $ 480,000 $7,500,000 • Track construction requires additional funding of approximately $2 million (source to be identified) 13 Outdoor Enhancement Plan Timeline: • Baseball Practice Field Relocation Construction Underway • Storm Water Improvements Underway • Artificial Turf Recreational Field Fall 2014 • Design Complete December 2014 • Natural Turf Recreational Field Spring 2015 • Gateway Bldgs. & Infrastructure Spring 2015 • Fencing, Irrigation, Streetscape, Landscaping and FF&E Summer 2015 • Track Construction Awaiting Funding 14 Master Plan Approved in December 2013 Initial Plan for Student Campus Recreation Outdoor Plan with Student Athletics Facilities Enhancements - Approximately $45,000,000 15 Proposed Modifications For Approval • Enhanced Softball Improvements • Adaptive re-use of Baseball Stadium (eliminates relocation costs) • New Site for Tennis Stadium • Replacing pond with green space 16 Site Plan Showing Proposed Modifications for Approval Adaptive reuse of baseball stadium Enhanced Softball Improvements Elimination of Pond & replace with green space New site for Tennis Stadium Reduction of parking at proposed tennis stadium Potential Modifications: Enhanced softball improvements (8D), adaptive reuse of baseball stadium (5A), new site for tennis stadium (6A), elimination of pond & replacing with green space (9), & reduction of parking at proposed tennis stadium. 17 Site Plan Showing the Current Scope of Work Baseball practice 5B field underway. Fields 7B then 7A next. Portal Buildings 4D, 7C, & 7D in the Spring 2015 with site work & infrastructure. Progress on the track currently scheduled to be constructed in 2016 is contingent on budget availability. 18 Outdoor Enhancement Plan Campus Recreation Fields soon to be replaced with a combination of synthetic and natural turf fields to improve drainage and enhance playability 19 Outdoor Enhancement Plan Campus Recreation Fields soon to be replaced with a combination of synthetic and natural turf fields. Multiple sport striping will be provided. 20 Outdoor Enhancement Plan Soils stockpile for use at the baseball practice field 21 Preliminary Rendering of Gateway Building 7C The Gateway Building aesthetic will be coordinated with the landscape, streetscape and long term master plan intent. The design will allow for the inclusion of a multi-modal path and the accessible pedestrian use of Riegel Road. The buildings will provide focal points for secure entry and provide programmatic amenities. The buildings will be strategically located to increase the toilet fixture capacity in support of Athletic Facility improvements. 22 Floor Plan of a Gateway Building The Gateway building shown on the site plan 4D, 7C & 7D provide focused entry points to the recreation & athletic complex. They also provide programmatic amenities. 23 Planned Softball Complex Improvements Future philanthropy will support increased seating, new accessible dugouts & press box, new scoreboard & field replacement with turn for increased playability. 24 Planned Softball Improvements - Scope and Timeline Philanthropic Funding will complete the following improvements: • 2014 – Install new artificial turf field (work is ongoing) • 2014 (fall) or 2015 (summer) – Install new video board/scoreboard to replace existing • 2015 – Replace & relocate existing dugouts: • Provides for new wider dugouts, located 21” below the field, including a connecting restroom • Provides ramps down to the dugout to comply with ADA requirements • 2016 - Provide total seating capacity of approximately 800: • 300 new chair seats behind the home plate backstop • 500 new bleacher seats along the first and third baselines • Seating will comply with ADA requirements • 2017 – Replace the existing press box: • Provides new, larger, two-story structure that will contain team space on the lower level • Includes accommodations for radio and television broadcasting, game operations, and writing press on the second level 25 Outdoor Enhancement Plan Grading the gravel sub-base at the softball field work 26 Outdoor Enhancement Plan View of the softball infield construction showing ongoing drainage work and the synthetic turf application 27 Tennis Complex Feasibility Study • Potentially Funded by anonymous donor gift to Athletics • Potential Benefits Include: • Better orientation for playability, • Elimination of the need for swing space • Lower cost • Integral storm water improvements • Study outcomes will inform potential additional gift to fund the project 28 Tennis Complex Feasibility Study Study funded by anonymous donor gift to Athletics. Potential Benefits Include: Better orientation for playability, elimination of the need for swing space, lower cost, integral storm water improvements. Possible philanthropy to fund outcomes. Tennis Facility View of Ramped Complex: North - South orientation optimizes playability while affording accessible spectator seating. 30 Tennis Complex Feasibility Study View along the east-west axis at building entry and spectator platform. 31 Proposed Modifications For Approval (Action Item) • Endorse the use of additional funds • Enhanced Softball Improvements • Adaptive re-use of Baseball Stadium (no relocation) • New Site for Tennis Stadium • Elimination of pond and replacing pond with green space 32