Quick ChangeoversSMED

advertisement
Quick Changeovers & SMED
6
Learning Objectives
At the completion of this unit the
participant will be able to:
1.
2.
3.
4.
5.
What are Quick Changeovers?
Why Quick Changeovers?
The 8 Steps to Quick Changeovers
What is SMED?
The 7 Steps to SMED
© 2009 RLM & Associates LLC
2
The Race is Won in the Pits
© 2009 RLM & Associates LLC
3
© 2009 RLM & Associates LLC
4
What is a Changeover?
The amount of time taken to change a
piece of equipment from producing
the last good piece of a production
lot to the first good piece of the next
production lot
© 2009 RLM & Associates LLC
5
When is the
Changeover Complete?
1. Running product A
2. Downtime = Muda or Waste
3. Running product B
© 2009 RLM & Associates LLC
6
Why Quick Changeovers?
1. Quick changeovers reduce lead time
2. Increase overall velocity
3. Machines only create value when
they are running and not sitting idle
© 2009 RLM & Associates LLC
7
Why Quick Changeovers?
1. Reduce lot sizes
2. When lot sizes are reduced, the
customer’s lead time is also reduced
3. This is because most of the lead
time is waiting (queue time)
© 2009 RLM & Associates LLC
8
Quick Changeovers Reduce
Inventory
Fast changeovers greatly reduce the
need for inventory buffers
© 2009 RLM & Associates LLC
9
Improves On-Time Delivery
Performance
Removing the non-value added time
results in the customer getting their
product sooner
© 2009 RLM & Associates LLC
10
8 Techniques to Quick Changeover
1. Separate internal from external setup
operations
2. Convert internal to external setup
3. Standardize function, not shape
4. Use functional clamps or eliminate
fasteners altogether
5. Use intermediate jigs
6. Adopt parallel operations
7. Eliminate adjustments
8. Mechanization
© 2009 RLM & Associates LLC
11
What is SMED?
1. Single Minute Exchange of Dies
2. Developed by Shigeo Shingo
3. A system designed to radically reduce the
amount of time to perform a changeover
or setup
© 2009 RLM & Associates LLC
12
Shingo’s Success
1. “A Revolution in Manufacturing: The
SMED System”
2. Toyota, using his techniques,
reduced setup time from days to
three minutes
© 2009 RLM & Associates LLC
13
Focus on the Process, not
the Technology
1. SMED should be inexpensive
2. Well planned
3. Well practiced
4. Well executed
5. Without Standard Work, there is no
continuous improvement
© 2009 RLM & Associates LLC
14
Shingo’s Success
Changing dies on stamping machines
took up to three days to complete
1. Placed precision measuring devices
on the die – used instead of
eyeballing
2. Tools designated for SMED were
located close by
3. Cut the changeover time to less
than 10 minutes!
© 2009 RLM & Associates LLC
15
7 Steps to Implementing SMED
1. Observe the current methodology
– Watch a full changeover at least once – more is
better
– Videotape is best
© 2009 RLM & Associates LLC
16
7 Steps to Implementing SMED
2. Separate the INTERNAL and EXTERNAL
activities. Internal activities are those that
can only be performed when the process
is stopped, while External activities can be
done while the last batch is being
produced, or once the next batch has
started. For example, go and get the
required tools for the job BEFORE the
machine stops.
© 2009 RLM & Associates LLC
17
7 Steps to Implementing SMED
3. Convert (where possible) Internal
activities into External ones (preheating of tools is a good example of
this).
© 2009 RLM & Associates LLC
18
7 Steps to Implementing SMED
4. Streamline the remaining Internal
activities, by simplifying them.
Focus on fixings - Shigeo Shingo
rightly observed that it's only the last
turn of a bolt that tightens it; the
rest is just movement.
© 2009 RLM & Associates LLC
19
1. Only the final turn on a bolt
adds value
2. The interrupted screw (or
interrupted thread) provides
one means of clamping and unclamping something
quickly. Artillery breeches have been sealed in this
manner since the nineteenth century.
© 2009 RLM & Associates LLC
20
7 Steps to Implementing SMED
5. Streamline the External activities,
so that they are of a similar scale to
the Internal ones.
© 2009 RLM & Associates LLC
21
7 Steps to Implementing SMED
6. Document the new procedure and
the actions that are yet to be
completed.
© 2009 RLM & Associates LLC
22
7 Steps to Implementing SMED
7. Do it all again: For each iteration of
the above process, a 45%
improvement in set-up times should
be expected, so it may take several
iterations to cross the ten-minute
line.
© 2009 RLM & Associates LLC
23
Improvements with
Successive Runs
© 2009 RLM & Associates LLC
24
Look For…
Look for opportunities to eliminate
waste in your changeovers, then go
after them.
In the following video, identify any
wasteful activities.
© 2009 RLM & Associates LLC
25
© 2009 RLM & Associates LLC
26
Look For
1. Shortages, mistakes, inadequate
placement of needed equipment. Can be
avoided by using check tables, especially
visual ones, and setup on an
intermediary jig.
2. Inadequate or incomplete repairs to
equipment.
3. Optimization for least work as opposed
to least delay.
© 2009 RLM & Associates LLC
27
Look For
4. Unheated molds which require several
wasted 'tests' before they will be at the
temperature to work.
5. Equipment using slow, precise
adjustments for the large coarse part of
adjustment.
6. Lack of visual lines or benchmarks for
part placement on the equipment.
© 2009 RLM & Associates LLC
28
Look For
7. Forcing a changeover between different
raw materials when a continuous feed,
or near equivalent, is possible.
8. Lack of functional standardization, that is
standardization of only the parts
necessary for setup, e.g. all bolts use
same size spanner, die grip points are in
the same place on all dies.
© 2009 RLM & Associates LLC
29
Look For
9. Much operator movement around the
equipment during setup.
10.More attachment points than actually
required for the forces to be constrained.
11.Attachment points that take more than
one turn to fasten.
© 2009 RLM & Associates LLC
30
Look For
12.Any adjustments after initial setup.
13.Any use of experts during setup.
14.Any adjustments of assisting tools such
as guides or switches.
© 2009 RLM & Associates LLC
31
© 2009 RLM & Associates LLC
32
© 2009 RLM & Associates LLC
33
Parallel Operations Using
Multiple Operators
Level load the changeover
Balance the tasks
© 2009 RLM & Associates LLC
34
Teamwork - Parallel Operations
Using Multiple Operators
© 2009 RLM & Associates LLC
35
SMED Tool Carts
© 2009 RLM & Associates LLC
36
Download