Kaizen

advertisement
Kaizen
Kai + zen
(Change for the better)
6
1
© 2009 RLM & Associates LLC
4/9/2015
Kaizen Defined
• Continuous, incremental improvement of an
activity to create more value with less waste.
A process of continually making incremental,
ongoing changes and not as a single, separate
event.
4/9/2015
© 2009 RLM & Associates LLC
2
Kaizen
• Small-scale improvements are easier and
faster.
• The risks are lower because they generally
have limited effect.
• The accumulated effect is often greater than
a single large improvement
4/9/2015
© 2009 RLM & Associates LLC
3
Change Management
• The Lean journey is paved by kaizen events
• Lean concepts are simple -- sustaining is hard
• Lean as a business strategy and supported by
top mgt.
4/9/2015
© 2009 RLM & Associates LLC
4
Kaizen Teams
4/9/2015
© 2009 RLM & Associates LLC
5
Kaizen Teams
• Daily work teams
– Multi-skilled, cross-trained team working in a cell
– TPM team (mgt, engr, maint., operators)
– Do not disband
• Kaizen team
– Multi-skilled, cross-trained and cross-functional
– Led by a facilitator
– Trained in problem solving, conflict resolution, etc
4/9/2015
© 2009 RLM & Associates LLC
6
Kaizen Events
(Creativity before capitol)
•
•
•
•
•
•
Identify a problem
Brainstorm with employees
Make the improvement
Monitor results
Adjust as necessary
Apply to like processes
4/9/2015
© 2009 RLM & Associates LLC
7
Pre-Event: Planning
Meeting Task Name
4/9/2015
Duration
1
Team Introductions
1 hr
2
Resource Planning
2 hrs
3
4
5
6
Preparation
Kaizen event
Follow-up
Follow-up & closeout
1 hr
5 days
4 hrs
4 hrs
Kaizen event
completed
© 2009 RLM & Associates LLC
8
Pre-Event: People
• Project Leader
• Lean Champion
• Team Members
4/9/2015
© 2009 RLM & Associates LLC
9
Day 1
•
•
•
•
•
•
•
Team Introductions
Project Scope
Overview with goals
Team Charter
Determine current state map
Brainstorm ideas for future state map
Set up plant walk-through
4/9/2015
© 2009 RLM & Associates LLC
10
4/9/2015
© 2009 RLM & Associates LLC
11
Day 2
•
•
•
•
•
Communicate, Communicate!
Select Metrics
Select method for improvement
Build team consensus and select actual tasks
Organize tasks
– A Tasks - the team can do without permission
– B Tasks - requiring help from maint., IT, accounting
– C Tasks - requiring management approval
4/9/2015
© 2009 RLM & Associates LLC
12
Effort and Impact Matrix
4/9/2015
© 2009 RLM & Associates LLC
13
Day 3
•
•
•
•
Identify items or material you need
Discuss possible obstacles to implementation
Communicate with target area people
Start implementation of ideas
4/9/2015
© 2009 RLM & Associates LLC
14
Day 4
• Continue with improvement implementation
• Work in teams of at least two
• Identify action items to address in order to
complete kaizen event effort
4/9/2015
© 2009 RLM & Associates LLC
15
Day 5
•
•
•
•
Complete the Kaizen event
Develop a 30-day action item follow-up list
Document improvements
Calculate savings
4/9/2015
© 2009 RLM & Associates LLC
16
Closeout and Presentation
• Create a short presentation to management
and people in the area.
• Everyone participate
• Have accounting present the cost savings
4/9/2015
© 2009 RLM & Associates LLC
17
Follow-up
• Ensure that all assigned tasks have been
completed (infrastructure)
• Help build the habits and discipline of lean
and reinforces the concepts.
4/9/2015
© 2009 RLM & Associates LLC
18
Project Closeout
• Captures the total qualitative, quantitative,
and financial improvements
• Collect lessons learned
• Update your VSM
• Have official celebration to reward and
recognize the team’s efforts
4/9/2015
© 2009 RLM & Associates LLC
19
Points to Consider for Implementing
JIT and Changing Layouts
1. Study the process thoroughly first
2. Don’t under estimate the cost of changes
3. Know your people capabilities because of additional duties
4. Training is Vital
5. Identify Goals and Objectives
6. Be creative
7. Don’t be afraid to make mistakes
8. Involve everyone concerned
9. Educate your people about the goals and objectives
10.Keep it as simple as possible
11.Stress flexibility of tools and equipment
12.Keep areas open, avoiding walls and barriers
4/9/2015
© 2009 RLM & Associates LLC
20
Kanban
Order to Produce
21
© 2009 RLM & Associates LLC
4/9/2015
Kanban
• Agenda
– Introduction
– Kanban video
– Benefits
– Push vs. Pull systems
– Kanban process
– Visual factory
– Tiny Tag factory activity
4/9/2015
© 2009 RLM & Associates LLC
22
Introduction to Kanban
• Kanban
– A signal to indicate when more parts are needed
– Card, empty bin, In-process Kanban on plant floor
• Kanban System - a pull system that uses colorcoded cards attached to parts or part
containers to regulate the upstream
production and delivery flow.
4/9/2015
© 2009 RLM & Associates LLC
23
Kanban Video
4/9/2015
© 2009 RLM & Associates LLC
24
Takt Time
Takt Time - customer demand rate. Takt time sets the
pace of production to match the rate of customer
demand. It is the drum or heartbeat of any lean
system.
The concept carries backward through a process
stream. Every step is synchronizes with the final
output.
Customer
4/9/2015
Retailer
Manufacturer
© 2009 RLM & Associates LLC
Suppliers
25
Leveling Manpower
Leveling Manpower to Meet Demand
One worker can produce a part
every 8 minutes
Two workers can produce a part
every 4 minutes
Eight workers can produce a part
every one minute
Start and finish are close together
Multiple machines can be “watched”
by one operator
This provides JUST
the quantity needed
JUST-IN-TIME
4/9/2015
Some machines can be
programmed (1,4,6) to have
intelligence and stop when broken
or stop after one Cycle (Jidoka)
© 2009 RLM & Associates LLC
26
Takt Time Calculation
Calculated by taking the work time available and
dividing it by the number of units sold.
Net Operating Time
480 min.
Lunch/Breaks
- 50 min.
Maintenance/Cleanup
- 30 min.
Net time available
400 min.
400 min x 60 sec/min
1000 Units/Day
Takt Time = 24 Sec./Unit
4/9/2015
© 2009 RLM & Associates LLC
27
Pull versus Push Production Strategy
4/9/2015
© 2009 RLM & Associates LLC
28
Push System
Push System – Products are provided to the
consumer based on forecasts or schedules.
• Build product to forecast
• Create excess inventory
Extra Inventory costs
Extra floor space
Expired product
Damaged product
4/9/2015
© 2009 RLM & Associates LLC
29
Large Lot Size
Disadvantages of Large Lot Size
Inventory waste – large sums of money are
tied up in stored products
Quality loss – Good product becomes
defective as it sets in storage, from bumping,
scraping, water damage
Customer waiting – Customers must wait
until a long run is finished before getting
their portion of the run
4/9/2015
© 2009 RLM & Associates LLC
30
4/9/2015
© 2009 RLM & Associates LLC
31
Push System
4/9/2015
© 2009 RLM & Associates LLC
32
Push System
4/9/2015
© 2009 RLM & Associates LLC
33
4/9/2015
© 2009 RLM & Associates LLC
34
4/9/2015
© 2009 RLM & Associates LLC
35
Pull System
4/9/2015
© 2009 RLM & Associates LLC
36
4/9/2015
© 2009 RLM & Associates LLC
37
4/9/2015
© 2009 RLM & Associates LLC
38
4/9/2015
© 2009 RLM & Associates LLC
39
4/9/2015
© 2009 RLM & Associates LLC
40
4/9/2015
© 2009 RLM & Associates LLC
41
4/9/2015
© 2009 RLM & Associates LLC
42
4/9/2015
© 2009 RLM & Associates LLC
43
4/9/2015
© 2009 RLM & Associates LLC
44
4/9/2015
© 2009 RLM & Associates LLC
45
4/9/2015
© 2009 RLM & Associates LLC
46
4/9/2015
© 2009 RLM & Associates LLC
47
4/9/2015
© 2009 RLM & Associates LLC
48
4/9/2015
© 2009 RLM & Associates LLC
49
4/9/2015
© 2009 RLM & Associates LLC
50
4/9/2015
© 2009 RLM & Associates LLC
51
?
4/9/2015
© 2009 RLM & Associates LLC
52
handout
4/9/2015
© 2009 RLM & Associates LLC
53
How many pull signals
• What should be considered in establishing
maximum inventory levels?
– Long change over times
– Long lead times
– Machine downtime
– Schedule increases / decreases
– Large process or transfer or batch sizes
– Poor quality
– Long cycle times
4/9/2015
© 2009 RLM & Associates LLC
54
How will the pull system change your job?
• The pull system provides more time for
constructive activities that will make your job
and working conditions better tomorrow
because with pull you only run the parts that
are needed shut down time can be spent on:
– Preventive maintenance
– Quality improvements
– House keeping
– Team meetings
4/9/2015
© 2009 RLM & Associates LLC
55
• Implementation of a pull system is affected by
many factors:
– The process itself
– Cost and availability of transportation
– Relationship and logistics with supplier
– Level scheduling
– Containerization
– Supplier and customer floor space
4/9/2015
© 2009 RLM & Associates LLC
56
Benefits of a Pull System
• Increases employee involvement
• Allows decision making at appropriate levels
• Allows manufacture of only what is needed by
customer
• Improves communication with customer
through visual controls
• Provides a common system for moving
material through the plant
4/9/2015
© 2009 RLM & Associates LLC
57
Benefits continued
•
•
•
•
•
•
Eliminates scheduling complexities
Reduces lead time and WIP inventory
Highlights quality issues quickly
Organizes the workplace
Leads to lower unit cost
Supports continuous improvement
4/9/2015
© 2009 RLM & Associates LLC
58
Pull System
Eliminating waste of:
•
•
•
•
•
•
•
4/9/2015
Handling
Storage
Expediting
Obsolescence
Shelf life, expiration
Facilities
Excess inventory (work-in-process and finished).
© 2009 RLM & Associates LLC
59
Pull System Conclusion
•Pull System is a flexible and simple method of
controlling/balancing the flow of resources.
– Produce exactly what the customer wants
– Minimum inventory
– Small lots
– Simplifies production scheduling and MRP
–Management by sight/signals
–The Pull takes place throughout the supply
chain, not just inside your production facility
4/9/2015
© 2009 RLM & Associates LLC
60
Pull at your company
• Identify the opportunity for Kanbans
– In your department
– With your suppliers
– With your customers
4/9/2015
© 2009 RLM & Associates LLC
61
Pull System Scheduling
4/9/2015
Courtesy of Ingersoll-Rand Co., Southern Pines, NC
© 2009 RLM & Associates LLC
62
Pull System Scheduling
• Workstation
4/9/2015
© 2009 RLM & Associates LLC
63
Kanban cards
4/9/2015
© 2009 RLM & Associates LLC
64
Kanban Cards
• Production Kanban – describes how many of
what item a particular operation needs to
produce.
• Withdrawal Kanban – is used to pull items
from a preceding operation or a supermarket.
4/9/2015
© 2009 RLM & Associates LLC
65
Supermarket System
• A stocking system in which materials are
stored by the operation that produces them
until they are retrieved by the operation that
needs them. When the store is full, production
stops
4/9/2015
© 2009 RLM & Associates LLC
66
Kanban Supermarkets
4/9/2015
© 2009 RLM & Associates LLC
67
Kanban Supermarkets
•Vendor maintained kanbans
4/9/2015
© 2009 RLM & Associates LLC
68
Kanban Limits
• Workstations
4/9/2015
© 2009 RLM & Associates LLC
69
FIFO
4/9/2015
© 2009 RLM & Associates LLC
70
Visual Factory
Visual Factory Management
Definition:
Innovative method of providing valuable
information to everyone!
Employee involvement and
management support
is CRUCIAL!!!!
4/9/2015
Be colorful with
signs, displays and
visuals
© 2009 RLM & Associates LLC
71
Visual Management
4/9/2015
© 2009 RLM & Associates LLC
72
Visual Management
4/9/2015
© 2009 RLM & Associates LLC
73
Visual Controls
Benefits of Visual Controls
1. Cleaner and Safer
Workplace
2. Decreased Inventories
3. Less Wasted Time
4. Improved Morale
5. Improved Product Quality
4/9/2015
© 2009 RLM & Associates LLC
74
Tiny Tag Co. Activity
Product
Tiny Tags
Equipment
Hole punch.
Materials
Pre-cut tag blanks.
Ringed Reinforcements, p.n. 05729
Pre-tied strings
Dot sheets, ¾” diameter, p.n. 05466
Bundle rings, nickel plated
Plastic pack bags.
Operations
Punching.
Reinforcement application
Enhancement dot application.
String installation.
Bundling.
Pack-out.
Procedures
1. Punch string attachment hole.
a. Pick up hole punch.
b. Pick up blank tag.
c. Position hole punch on one end of tag, 0.50” in from narrow edge,
and centered left-to-right.
d. Punch hole.
2. Apply Ringed Reinforcement.
a. Pick up tag with punched hole.
b. Remove ringed reinforcement from package.
c. Place reinforcement ring over hole.
3. Apply enhancement dot.
a. Pick up tag assembly.
b. Remove enhancement dot from sheet.
c. Place enhancement dot in the middle of the tag.
4. Add string.
a. Pickup pre-tied string.
b. Pick up tag assembly.
c. Thread string through hole.
d. Thread end through hole through end loop.
e. Pull snug.
5. Bundling operation.
a. Pick up five (5) completed tag assemblies.
b. Thread bundling ring through the string on the tags and snap closed.
6. Packaging operation.
a. Write product identification on plastic bag(s): “TT MK IV”
b. Pick up two (2) completed tag bundles.
c. Place two completed bundles into plastic bag.
Special Notes:
· Any product design changes must be approved, in advance, by the Tiny Tag
Company marketing department.
· All components must be produced in-house. No sub-contracting is allowed.
4/9/2015
© 2009 RLM & Associates LLC
75
Tiny Tag Co. results
Push System
Card
Hole Punch
Reinforce Hole
Dot enhance
Install string
Batch
Packet
WIP Total
Unit Cost
$
4.00
$
1.25
$
1.00
$
0.75
$
0.50
$
0.25
$
0.25
Cum. Cost
$
4.00
$
5.25
$
6.25
$
7.00
$
7.50
$
7.75
$
8.00
Count
9
5
2
6
12
1
1
$
$
$
$
$
$
$
$
Total
36.00
26.25
12.50
42.00
90.00
7.75
8.00
222.50
Pull System
Count
5
1
1
1
1
1
1
$
$
$
$
$
$
$
$
Total
20.00
1.25
1.00
0.75
0.50
0.25
0.25
24.00
Costs includes raw material, labor, and overhead
4/9/2015
© 2009 RLM & Associates LLC
76
Standard Work
77
© 2009 RLM & Associates LLC
4/9/2015
Standardized Work
thru
Standard Operating Procedures (SOPs)
Without standard work there is no continuous improvement!
Everyone must know:
Cycle Time – Takt time
Work Sequence
Work-in-Process quantities
Kanban procedures
Work instructions (SOPs)
Continuous improvement
4/9/2015
© 2009 RLM & Associates LLC
78
Work Instructions
Work Instructions and SOPs
Written by Engineers AND Workers
Reviewed by Management
Operating Instructions
Operator 3
7
8
9
Operator 2
4
5
6
Operator 1
1
2
3
Tested on the line BEFORE use
Approved by QA
Standard Cycle Time
Actual time required to produce one part
Helps determine process capability
4/9/2015
© 2009 RLM & Associates LLC
79
SOPs
220 Motor Line 2
Operation 2
Procedures
1. Get (2) black screws, one in each hand
2. Get motor on pallet/fixture from previous operation with right hand
3. Place RH (Right Hand) screw in Right Rear screw hold. Immediately get screw gun
4. Place LH (Left Hand) screw in gun bit and drive screw into Left Front hole
5. Run down Rear Right screw while getting (1) black screw with left hand
6. Removing guide pin, place screw in the gun bit and drive down screw in Left rear hole
7. Return guide pin to previous operation stage area while getting silver screw with left
hand
8. Get & orient ground lead (split facing up), place silver screw in eyelet & guide to right
Front hole
9. Get screw gun & run down while pressing ground strap wire tight against right side of
bracket. (#1)
10. Move motor on pallet/fixture to next operation. (Repeat entire cycle)
Visual Aide:
Position of screws: Stainless Steel screws on Left staging shelf/Black screws on Right
Install (3) screws and rundown,
placement of grounding strap and
rundown
4/9/2015
© 2009 RLM & Associates LLC
80
Yellow Belt Training Wrap-up
 Lean & Six Sigma
 Value Stream Mapping
 Mistake Proofing
 5S
 SMED
 TPM
 Kaizen
 Kanban
81
© 2009 RLM & Associates LLC
4/9/2015
RLM & Associates LLC
Your Lean Six Sigma & Project Management Trainers
Takt Time
Takt Time Exercise
Availability
Four weeks/month
Five day work week
Two ten hour shifts
Lunch break 1 hour/shift
Two 15 min. breaks/shift
Turn over meeting 10 min./shift
Customer Demand
6 Month average = 20,000 units/month
Customer Demand =
4/9/2015
Takt Time =
© 2009 RLM & Associates LLC
82
Total Productive
Maintenance
A maintenance philosophy designed to integrate
equipment maintenance into the manufacturing
process. The goal is to keep equipment producing only
good product, as fast as possible with no unplanned
downtime.
4/9/2015
•
Improve Productivity
•
Reduce breakdown leading to Zero
breakdown concept
•
Leads to multi-skilling of workers
•
Better safety
•
Improve quality of products
© 2009 RLM & Associates LLC
83
Kaizen &
Productive Maintenance
Lean Tool
Total
Introduction
Benefits
1. Increased Space utilization
2. Increased product quality
Kaizen
Continuous Improvement
3. Better Use of capital
4. Communications
5. Production capacity
6. Employee retention
© 2009 RLM & Associates LLC
84
Andon–Signaling system to stop line
Lean Tool
Introduction
Benefits
1. Bring immediate attention to
problems as they occur in the
manufacturing process.
2. Provide a simple and consistent
mechanism for communicating
information on the plant floor.
Andon –
Signaling
system to
stop line
A Japanese term refers to
3.
the warning lights on an
assembly line that light up
when a defect occurs.
When the lights go on, the 4.
assembly line©is
usually
2009
RLM & Associates LLC
stopped until the problem
Encourage immediate reaction
to quality, down time, and
safety problems.
Improve accountability of
operators by increasing their
85
responsibility for “good”
Jidoka
Andon
A visual management tool that highlights the status of operations in an area at a
single glance and that signals whenever an abnormality occurs.
An andon can indicate production status (for example, which machines are
operating), an abnormality (for example, machine downtime, a quality problem,
tooling faults, operator delays, and material shortages), and needed actions, such as
changeovers. An andon can also be used to display the status of production in
terms of the number of units planned versus actual output.
--- The Lean Lexicon
4/9/2015
© 2009 RLM & Associates LLC
86
Jidoka
Andon
A visual management tool that highlights the status of operations in an area at a
single glance and that signals whenever an abnormality occurs.
An andon can indicate production status (for example, which machines are
operating), an abnormality (for example, machine downtime, a quality problem,
tooling faults, operator delays, and material shortages), and needed actions, such as
changeovers. An andon can also be used to display the status of production in
terms of the number of units planned versus actual output.
--- The Lean Lexicon
4/9/2015
© 2009 RLM & Associates LLC
87
RLM & Associates LLC
Your Lean Six Sigma & Project Management Trainers
Lean Six Sigma DMAIC Workshop
Yellow Belt Part 4
4/9/2015
© 2009 RLM & Associates LLC
88
RLM & Associates LLC
Your Lean Six Sigma & Project Management Trainers
Takt Time
Takt Time Exercise
Availability
Four weeks/month
Five day work week
Two ten hour shifts
Lunch break 1 hour/shift
Two 15 min. breaks/shift
Turn over meeting 10 min./shift
Customer Demand
6 Month average = 20,000 units/month
Customer Demand =
4/9/2015
Takt Time =
© 2009 RLM & Associates LLC
89
RLM & Associates LLC
Your Lean Six Sigma & Project Management Trainers
Leveling Manpower
Leveling Manpower to Meet Demand
One worker can produce a part
every 8 minutes
Two workers can produce a part
every 4 minutes
Eight workers can produce a part
every one minute
Start and finish are close together
Multiple machines can be “watched”
by one operator
This provides JUST
the quantity needed
JUST-IN-TIME
4/9/2015
Some machines can be
programmed (1,4,6) to have
intelligence and stop when broken
or stop after one Cycle (Jidoka)
© 2009 RLM & Associates LLC
90
RLM & Associates LLC
Your Lean Six Sigma & Project Management Trainers
Line Balancing
68
60
Line Balancing
Exercise
Improvement Team
Reduced cycle Time
By 44 sec. or approx 18%
60 sec. Takt Time
48
Use Takt
Time/Cycle
Time Bar Chart
40
32
0
How
many
seconds
Total Cycle time =
How many people
-44 sec.
New Cycle time =
Are they working 100% of the time now? If not what portion of the time are they working?
4/9/2015
© 2009 RLM & Associates LLC
91
RLM & Associates LLC
Your Lean Six Sigma & Project Management Trainers
Improve Leveling
Improve Leveling with Small and Mobile Machines
Small machines are
Small machines can
4/9/2015
Easier to set up
Easier to move around
Require less space
Require less walking by operators
Produce closer to SPF
Usually are less expensive
Be easily use to re-arrange a layout
Be used to add 1 or remove 1 for
special needs
Aid in leveling workloads
© 2009 RLM & Associates LLC
92
RLM & Associates LLC
Your Lean Six Sigma & Project Management Trainers
Cross Training
Improve Leveling with Cross Training
Paint booth
Dryer
Bender
John
Mary
Harry
Trainee
4/9/2015
Works with
assistance
Independent
worker
Individuals and
teams can be
blended to meet
changing demands
Identifies who is
certified to fulfill
which positions
Does Changeovers
and Trains
© 2009 RLM & Associates LLC
93
RLM & Associates LLC
Your Lean Six Sigma & Project Management Trainers
Level Production
Level Production
Level production allows organizations to build to the varying demands
of the customer while holding minimum inventories and causing
minimum delays
Start with the final mixed requirements to schedule the raw materials
needed Just-in-time
Combine build for stock orders with customer orders to level workload
Can be used to even out peaks and valleys in production of various
types of products
4/9/2015
© 2009 RLM & Associates LLC
94
RLM & Associates LLC
Level Production
Your Lean Six Sigma & Project Management Trainers
Example of Level Production
XYZ Units w/TUV Packaging
Operation
#
Description
Time
(seconds)
Number of Operators
1
2
3
4
1 Bottom sheet
2 hoist
19
3 Box
12
4 Rubber Guards
7
5 Escutcheon Guard
4
6 Literature
7
7 Top Sheet
10
8 1st Strapper
10
9 2nd Strapper
10
10 Unload & Palletize
31
5
6
19
19
38
19
12
59
18
28
120
31
41
20
32
61
29
29
22
22
29
29
41
11 Print & Add labels
Total Labor
120
Ideal Cycle Time (seconds)
120
60
40
30
24
20
Actual Cycle Time (seconds)
120
61
41
32
31
29
100%
98%
98%
94%
77%
69%
30
59
88
113
116
124
8.0
4.1
2.7
2.1
2.1
1.9
Performance Rate
Units/Hr
4/9/2015
(added to (added to (added to
8 & 9)
9)
9)
12
Time available to move and shrink wrap 2 pallets
© 2009
(minutes)
RLM & Associates LLC
95
Download