IPR VW International, Inc Background & Scope Approach to Study Conceptual Definitions – Past Lessons Results… Questions Mod performed to the HFPO Guide (wiki) update process with the idea to incorporate the results/processes into the Guide. The scope is to evaluate, determine, and recommend the optimal way for HFPA Construction Management Division (CMD) to support the initial outfitting/facility provisioning and transition of operations for all projects within HFPA’s construction program. Specific requirement was to provide recommendations regarding: • Programming of funds and resources • Staffing / Organization of CMD, Project Offices, and local MTF’s • • • • • transition committees Development of IO&T budget requirements, management of funds, and execution tracking Transition , IO planning, consulting support & execution management IO procurement and management Development of policies, procedures, checklists and other items to document the plan Other functions and actions required to provision and transition operations into the new facility. Ft Richardson (1) FY07 $37.2M ($17.2M MCA) Ft Wainwright (1) $215.0M Ft Lewis (1) FY13 $8.0M Ft Irwin (1) FY07 $6.0M Aberdeen (2) FY09-13 $381.0.0M Ft Carson (1) FY13 $3.1M Pike’s Peak (1) FY12 $4.2M White Sands (1) FY13 $8.0M Germany (1) $13.0M Germany (3) FY12-13 $65.2M Ft Detrick (2) FY07-13 $735.0M Ft Leonard Wood (1) FY09 $20.0M Korea (2) $62.0M Korea (1) FY13 $11.8M Ft Detrick (2) FY06 $54.2M Ft Drum (1) FY07 $9.7M Italy (1) FY07 $52.0M ($29.5M MCA) Ft Riley (1) FY13 $20.0M Ft Bragg (1) $4.3M Camp Zama (1) FY13 $6.7M Tripler (1) FY13 $35.0M 07 Ft Stewart (1) FY13 $4.0M Legend Medical MILCON In Construction Total Projects: 10 Total PA: $372.1M Medical MILCON Program FY 07-13 Total Projects: 26 Total PA: $1,596.3M / $46.7 MCA Ft Hood (2) $16.5M Ft Hood (1) FY07 $18.0M FY Camp Bullis (1) FY08 $7.4M Ft Sam Houston (1) FY09 $11.0M Ft Benning (1) $7.1M 08 09 10 11 Ft Benning (2) FY12-13 $153.0M NOTE: From TMA FY08-13 POM Submission 12 13 Study and recommend best approach for HFPA to support the Initial Outfitting and Transition of the incoming Construction workload Analyze available historical data for resourcing patterns Create model to determine tasks Extrapolate scale given input parameters: $, location, FY, type, quantities Research task suitability for contracting Consolidation by location, type of activity, designbuild options Estimate alternatives Identify risks due to capacity issues Determine the distribution of total requirements as defined by the anticipated construction program Determine funding model using construction program as input parameter (pie-sizer) Create a Task Allocation model (pieslicer) Propose a model of task consolidation based upon timing and location Utilizing data from BAMC and Basset AHC Analyze and catalogue expenditures into task groupings. Determine allocation of funds expended by Task Category Arrive at a model as to how to slice the IO&T resource pie into Task Slices, which could then be addressed as requirements Analyze prospective from three aspects: time (FY), location, and scale. Determine Group Slice size of each project’s pie. the pies (by location & time). each pie into tasks. Group pies”. the task “slices” into new “requirements A look back to Brooke Army Medical Center (as detailed data source) Conceptual definitions Transition Funds Investment • Supports all costs required to move the “steady state” of the facility from the current level to the newly proposed level of the project. Currently MEDCOM and HFPA IO& transition budgets pay some of these costs. Transition • Supports all costs that are temporal in nature, and that do not result in a change of the “steady state.” Currently MEDCOM and HFPA transition budgets pay for more than this category. Operations • Supports annually recurring costs required to sustain the new “steady state.” Currently MEDCOM and HFPA transition budgets pay some of these costs. Certification & Commissioning Dual Operations Phasing Planning Post-BOD Initiatives Preparation Project Management Promotion Provisioning Military Construction / Renewal Moving Operations/Sustainment Training Reclamation Certification & Commissioning • Testing building systems, safety inspections-assessments. Construction/Renewal • The actual project appropriation, i.e MILCON, BRAC, or Renewal. Dual Operations • Operating two physical plants during occupation phase from BOD through FOD. Phasing • Operating costs incurred due to phasing through the project period (temp buildings, moving of functions temporarily, etc.) Planning • Actions not directly related to project management but which are generated by the project existence (i.e. backfill plans for old facility). Post-BOD Initiatives • Initiatives not part of the original scope but identified to make the facility meet user operational desires/needs (may be ECPs). Preparation • Making the facility ready for occupation but excluding provisioning tasks. ie. pest control, initial pre-cleaning, IBS floor sealing. Project Management • Management tasks required to support construction and all other tasks required to move in and operate it (excludes RE and tasks that would be considered normal medical operational management ie. strategic planning) Promotion • Any promotional actions: dedication ceremony, tours, advertising/marketing materials. Does not include staff training support materials. Provisioning • The bulk of the project support costs. Procurement costs to equip, and install those new items. If part of a central contract, some project management costs may be here. Moving • The task of physically moving from the old to the new, may become blurred with phasing costs in a total renovation project. Operations/Sustainment • Tasks and costs associated with operating the plant, may be higher or lower than current dependent upon adaptation of business practice to new facility. Training • Staff training actions, i.e. orientations, systems hands- on training, TDY Reclamation • Getting out of the old facility prior to release to post. e.g. disposal of old equipment, cleaning, potentially environmental clean-up. Operation 0.32% Transition 2.08% Investment 97.60% BAMC Costs - last year of project, partial data. Minimal Operational cost information. Transition Cost managed by HFPA Investment costs - mixed management, includes MILCON Approximately $297M in addition to MILCON Operational 6.69% Transition 5.71% Investment 87.60% Total: $454,907,502 Programs consist of: Investment, Transition & Operational costs. Operational 7% TOC 2% MEDCASE 18% HFPO 1% IM, Investment 10% Transition 3% Investment 5% BRAC 9% MILCON 46% Programs consist of: Investment, Transition & Operational costs. 4.4% PM 6.0% Transition Applied to some projects : 12.2% Operational 121 Hospital Korea, PA: $7.1M • Transition • Investment 9.2% Investment • Operational 17.7% IM Investment Beach Education Center, PA:$24M • Transition • Investment • Operational 32.5% MEDCASE $0.738M $4.217M $0.866M $ 2.496M $14.256M $ 2.928M Ft Wainwright Hospital, PA:$117M • Transition • Investment • Operational $12.198M $69.498M $14.274M IM Provisioning 19.05% Operations 13.39% Training 1.62% Certification & Promotion 0.24% Post-BOD Initiatives 1.32% Cat E 8.04% Moving 1.36% Project Management 5.37% Phasing 0.89% Decomissioning 0.37% Preparation 1.57% Dual Operations 0.60% Provisioning 46.19% Excludes construction costs, except Cat E ($18M), percents of task costs not total project cost. Training Certification 0.24% 0.96% Operations 6.21% IM Provisioning 20.69% Promotion Post-BOD Initiatives 0.14% Planning 0.00% Moving 0.02% 2.91% Project Management 4.12% Phasing 0.01% Reclamation 7.51% Preparation 0.45% Dual Operations 0.57% Provisioning 56.18% 1997 look Facility / HFPO – Requirements determination / re-use validation I&O Requests to MEDCOM MEDCOM release funds on demand Facility Logistics procurement process Receipt, storage, installation process managed by facility and HFPO / project resources Status Quo Contractor Turn-Key • Central, Regional or Project Specific Contract Support HFPA IO Teams Other … • Central, Regional or Project Specific • Central or Regional Contractor HFPO Requirements identification / re-use validation Facilitating contractor Procurement Installation and acceptance coordination Receipt & Storage Installation / Training Facility • Requirements identification / re-use validation • Receipt & Storage • Installation / training CX • Procurement • Installation / Training HFPO • Coordinating requirements identification • Coordinating logistics’ procurement, receipt & storage • Installation and acceptance coordination HFPA IO Team • Requirements identification / re-use validation • Procurement • Receipt • Storage • Installation / training HFPO • Facilitating requirements identification • Installation and acceptance coordination Western Region Eastern Region NOTE: Location sites ( ) from TMA FY08-13 POM Submission Status Quo Turn-Key MX HFPA Teams Requirements ID 1 2 1 3 Procurement Timeliness 1 3 1 3 Procurement Correct 2 3 3 3 Receipt/Storage 2 3 2 2 Installation 1 2 1 1 Totals 7 15 8 12 1 – Creates a Challenging Management Efficiency 2 – Is an Acceptable Management Efficiency 3 – Creates an Improved Management Efficiency