COSMIC 2: Status, plan and schedule

advertisement

COSMIC 2 Update

Dave Ector

COSMIC PM for OSD

4 November 10

COSMIC 2

2

Requirements

• GNSSRO Level 1 Requirements Documents (L1RD) status

L1RD Completed and signed 5 May 2010

• L1RD assessment underway

Initial budget/partnerships for COSMIC-2 do not fully support all

L1RD requirements

C-2 was designed to be a replication of C-1 – except X2 satellites

(12)

All at 72 degrees

2 northern tracking stations with current latency (around 60 min average)

• L1RD requires 2 inclinations – 72 degrees and 24 degrees

L1RD requires 45 min average latency

Partnering with the AF for SSAEM sensors – 2 secondary payloads on 6 satellites

AF purchase of rockets will close budget shortfall – allow us to meet all

L1RD threshold requirements

COSMIC 2 Schedule

JPL TriG Schedule

5

Acquisition Environment

• Acquisition Environment

• Solid support from NESDIS

• Very strong support from Weather Service

• Historically solid support from OMB

• New start – clearly at risk in this political environment

Being sold as a VERY low hanging fruit – very large forecasting impacts for a small price – compared to other satellite programs

Why not do this commercially? Is the #1 question from

OMB and congress.

International and government partnership leverage is one of our major selling points – we have outside contributions up to double the NOAA investment ($200+M)

COSMIC 2 Current Activity

Mission Definition Review – successfully completed in August

TriG Payload

– SRR complete in August

– PDR planned for November

– Antenna design kicked off for COSMIC-2

– Procurement strategy in draft

Air Force is proceeding with partnership

– Payloads contracts work

– Discussions with STP for the Minotaur 4 – received ‘11 funding

– AF provided draft MOA under review at NOAA

NSPO is moving forward quickly on spacecraft procurement

– RFI released in May

– 5 RFIs under review

– Plans to release RFP for 12 spacecraft by January

NOAA working ground planning

– Discussions with KSAT on ground station options

– Working with UCAR on proposal to “operationalize” CDAAC processing software to install at NSOF

PM Summary

• COSMIC 2 is on schedule even with a 3-6 month CR

– NASA started the NRE for the payload in April

– Internal planning money has help us get our international agreements complete

– JPL is working risk mitigation activities for the NOAA paylaod

– Taiwan is on track to award spacecraft contracts

• USAF partnership is imminent – comes with 2 launch vehicles

– Letter of intent from the AF

– Reviewing AF draft MOA

• Well coordinated L1RD is complete

– Pushed the limits of the original budget which was based on COSMIC 1

– Can meet threshold requirements of L1RD now that the AF has joined the team by allocating LV money to ground stations – without requesting additional money

8