Manual Flo-tap Installation Instructions Quick Installation Guides: 00825-0400-4809 rev. EA – 485 Flanged Flo-tap 00825-0500-4809 rev. DB – 485 Threaded Flo-tap Nomenclature Instrument Connections Top Plate Full Insertion Marking Nut Support Plate Insertion Drive Nuts Insertion Rods Head Plate Lock Nut (Retraction Drive Nuts) Full Port Isolation Valve Weld the Mounting Hardware Onto the Pipe Threaded Flo-tap Flanged Flo-tap Tack Weld the Mounting Hardware with 4 Equal Length Tacks Tack weld anywhere on the mounting hardware Then again directly across from the first tack weld Then on the other 2 sides 3 1 2 Check to See that the Mounting Hardware is Level and Square If it’s not, use a rubber mallet to lightly adjust the hardware and recheck Verify that the ODF Dimension Matches What is Listed in the QIG The ODF is the dimension from outside pipe diameter to face of flange 485 Verify that the ODF Dimension Matches What is Listed in the QIG The ODF is the dimension from outside pipe diameter to face of flange For Threaded Flo-tap the dimension from the pipe OD to the top of the threadolet is called LMH: 485 Sensor Size 1: 1.38-in. (35 mm) 485 Sensor Size 2: 1.56-in. (40 mm) 485 Sensor Size 3: 2.06-in. (52 mm) Complete a Continuous Weld Around the Perimeter of the Unit Attached the Full Port Valve to the Mounting Hardware Threaded Flo-tap Flanged Flo-tap First, thread the guide nipple into the mounting then thread the valve ODV The valve stem should be in-line with the pipe so it will not interfere with the insertion rods The valve must be a full port valve to allow the Annubar to pass through the valve into the pipe Verify the ODV Dimension The ODV is the dimension from the outer diameter of the pipe to the top of the valve Flo-tap / Flange Rating 485 Sensor Size 585 Sensor Size ODV Dimension 1 --- 7.51-in. (190.9 mm) 2 --- 8.17-in. (207.5 mm) ANSI 150 # 1 11 10.5-in. (266.7 mm) ANSI 300 # 1 11 11.75-in. (298.5 mm) ANSI 600# 1 11 14.06-in. (357.2 mm) ANSI 150 # 2 22 11.25-in. (285.8 mm) ANSI 300 # 2 22 13.00-in. (330.2 mm) ANSI 600# 2 22 16.38-in. (416.0 mm) ANSI 150 # 3 44 12.75-in. (323.9 mm) ANSI 300 # 3 44 16.25-in. (412.8 mm) ANSI 600# 3 44 19.50-in. (495.3 mm) Threaded Drill the Hole by Using a Hot Tap Drilling Machine Guide Ring in Rosemount Supplied Mounting Hardware Tag with correct drill hole size attached to the Annubar After the Hole is Drilled, Retract the Drill Past the Valve and Close the Valve Vent drilling machine and remove the per manufacturers and site procedures Threaded Flo-tap Flanged Flo-tap Remember that the hot tap drilling machine is under pressure and exposed to the process fluid Attach the Fully Retracted Flo-tap Assembly to the Valve Threaded Flo-tap Attach the Fully Retracted Flo-tap Assembly to the Valve Flanged Flo-tap – Use a hoist strap and crane if needed Quickly Open and Close the Valve to Pressurize the Annubar, Check for Leaks If Leaks are Present, Tighten the Packing Gland Nuts Loosen the Insertion Limiting Nuts Simultaneously Tighten the Insertion Drive Nuts to Insert the Annubar Lower the Head Plate Lock and Full Insertion Marking Nuts to the Head Plate Full Insertion Marking Nuts Head Plate Lock Nut To Retract the Annubar – Loosen the Retraction Limiting Nuts Retraction Limiting Nuts (Same as Insertion Drive Nuts) Loosen the Retraction Drive Nuts to Retract the Annubar Other Installation Considerations During insertion, the rods can twist and the top plate and support can come out of alignment. – Makes insertion difficult – Hit the top plate with a rubber to put them back in-line