Centro de Estudos e Sistemas Avançados do Recife
Introduction to Project Time Management
Activity Definition
Activity Sequencing
Activity Duration Estimating
Schedule Development
Schedule Control
Glossary
Introduction to Project Time Management
Includes the processes required to ensure timely completion of the project.
The major processes in developing the project time schedule are:
– Activity Definition
– Activity Sequencing
– Activity Duraton Estimating
– Schedule Development
– Schedule Control
Activity Definition
– Identifying and documenting the specific activities that must be performed to produce the various project derivables and subderivables identified in the WBS
Inputs to Activity Definition
1.
Work Breakdown structure
2.
Scope statement
3.
Historical information
4.
Constrants
5.
Assumptions
6.
Expert judgment
Tools and Techniques for Activity Definition
1.
Decomposition
2.
Templates
Outputs from Activity Definition
1.
Activity list
2.
Supporting detail
3.
Work breakdown structure update
Definition
– Identifying and documenting interactivity logical relationships.
Inputs to Activity Sequencing
1.
Activity list
2.
Product description
3.
Mandatory dependencies
4.
Discretionary dependencies
5.
External dependencies
6.
Milestones
Tools and Techniques for Activity Sequencing
1.
Precedence diagramming method (PDM) (fig 6-2)
2.
Arrow diagramming method (ADM) (fig 6-3)
3.
Conditional diagramming methods
4.
Network templates
Outputs from Activity Sequencing
1.
Project network diagrams (fig 6-2 and fig 6-3)
2.
Activity list updates
Definition
– Taking information on the project scope and resources and then developing durations for input to schedules
Inputs to Activity Duration Estimating
1.
Activity list
2.
Constraints
3.
Assumptions
4.
Resource requirements
5.
Resource capabilities
6.
Historical information
7.
Identified risks
Tools and Techniques for Activity Duration
Estimating
1.
Expert judgment
2.
Analogous estimating
3.
Quantitatively based durations
4.
Reserve time (contingency)
Outputs from Activity Duration Estimating
1.
Activity duration estimates
2.
Basis of estimates
3.
Activity list updates
Definition
– Determining start and finish dates for project activities
Inputs to Schedule Development
1.
Project network diagrams
2.
Activity duration estimates
3.
Resource requirements
4.
Resource poll description
5.
Calendars
6.
Constraints
7.
Assumptions
8.
Leads and lags
9.
Risk management plan
10.
Activity atributes
Tools and Techniques for Schedule Development
1.
Mathematical analysis
Critical Path Method (CPM)
Graphical Evaluation and Review Technique
(GERT)
Program Evaluation and Review Technique
(PERT) (fig 6-4)
2.
Duration compression
3.
Simulation
4.
Resource leveling heuristics
5.
Project management software
6.
Coding structure
Outputs from Schedule Development
1.
Project Schedule
Project network diagrams with date information added (fig 6-5)
Bar Charts or Gantt charts (fig 6-6)
Milestone charts (fig 6-7)
2.
Supporting detail
3.
Schedule management plan
4.
Resource requirement updates
Definition
– Controlling changes to the project schedule
Inputs to Schedule Control
1.
Project schedule
2.
Performance reports
3.
Change requests
4.
Schedule management plan
Tools and Techniques for Scope Change Control
1.
Schedule change control system
2.
Performance measurement
3.
Additional planning
4.
Project management software
5.
Variance analysis
Outputs from Scope Change Control
1.
Schedule updates
2.
Corrective action
3.
Lessons learned
Glossary
Decomposition = Refinements
Mandatory dependencies =
Hard logic
Discretionary dependencies
=Preferred logic, Preferential logic, soft Logic
Milestones
Precedence diagraming method (PDM)
Activity-on-node (AON)
Arrow diagraming method
(ADM)
Activity-on-arrow (AOA)
Critical Path Method (CPM)
Grafical Evaluation and
Review Technique (GERT)
Program Evalutation and
Revew Technique (PERT)
Top-down estimating
Reserve, contigency or buffer
Schedule baseline
Revisions
Centro de Estudos e Sistemas Avançados do Recife