PMBOK - Charter 6 - Project Time Management

advertisement

Centro de Estudos e Sistemas Avançados do Recife

PMBOK - Chapter 6

Project Time

Management

Contents

Introduction to Project Time Management

Activity Definition

Activity Sequencing

Activity Duration Estimating

Schedule Development

Schedule Control

Glossary

Introduction to Project Time Management

Includes the processes required to ensure timely completion of the project.

The major processes in developing the project time schedule are:

– Activity Definition

– Activity Sequencing

– Activity Duraton Estimating

– Schedule Development

– Schedule Control

Activity Definition

Activity Definition

– Identifying and documenting the specific activities that must be performed to produce the various project derivables and subderivables identified in the WBS

Inputs to Activity Definition

1.

Work Breakdown structure

2.

Scope statement

3.

Historical information

4.

Constrants

5.

Assumptions

6.

Expert judgment

Tools and Techniques for Activity Definition

1.

Decomposition

2.

Templates

Activity Definition (cont.)

Outputs from Activity Definition

1.

Activity list

2.

Supporting detail

3.

Work breakdown structure update

Activity Sequencing

Definition

– Identifying and documenting interactivity logical relationships.

Inputs to Activity Sequencing

1.

Activity list

2.

Product description

3.

Mandatory dependencies

4.

Discretionary dependencies

5.

External dependencies

6.

Milestones

Tools and Techniques for Activity Sequencing

1.

Precedence diagramming method (PDM) (fig 6-2)

2.

Arrow diagramming method (ADM) (fig 6-3)

3.

Conditional diagramming methods

4.

Network templates

Activity Sequencing (cont.)

Outputs from Activity Sequencing

1.

Project network diagrams (fig 6-2 and fig 6-3)

2.

Activity list updates

Activity Duration Estimating

Definition

– Taking information on the project scope and resources and then developing durations for input to schedules

Inputs to Activity Duration Estimating

1.

Activity list

2.

Constraints

3.

Assumptions

4.

Resource requirements

5.

Resource capabilities

6.

Historical information

7.

Identified risks

Activity Duration Estimating(cont.)

Tools and Techniques for Activity Duration

Estimating

1.

Expert judgment

2.

Analogous estimating

3.

Quantitatively based durations

4.

Reserve time (contingency)

Outputs from Activity Duration Estimating

1.

Activity duration estimates

2.

Basis of estimates

3.

Activity list updates

Schedule Development

Definition

– Determining start and finish dates for project activities

Inputs to Schedule Development

1.

Project network diagrams

2.

Activity duration estimates

3.

Resource requirements

4.

Resource poll description

5.

Calendars

6.

Constraints

7.

Assumptions

8.

Leads and lags

9.

Risk management plan

10.

Activity atributes

Schedule Development (cont.)

Tools and Techniques for Schedule Development

1.

Mathematical analysis

Critical Path Method (CPM)

Graphical Evaluation and Review Technique

(GERT)

Program Evaluation and Review Technique

(PERT) (fig 6-4)

2.

Duration compression

3.

Simulation

4.

Resource leveling heuristics

5.

Project management software

6.

Coding structure

Schedule Development (cont.)

Outputs from Schedule Development

1.

Project Schedule

Project network diagrams with date information added (fig 6-5)

Bar Charts or Gantt charts (fig 6-6)

Milestone charts (fig 6-7)

2.

Supporting detail

3.

Schedule management plan

4.

Resource requirement updates

Schedule Control

Definition

– Controlling changes to the project schedule

Inputs to Schedule Control

1.

Project schedule

2.

Performance reports

3.

Change requests

4.

Schedule management plan

Tools and Techniques for Scope Change Control

1.

Schedule change control system

2.

Performance measurement

3.

Additional planning

4.

Project management software

5.

Variance analysis

Schedule Control (cont.)

Outputs from Scope Change Control

1.

Schedule updates

2.

Corrective action

3.

Lessons learned

Glossary

Decomposition = Refinements

Mandatory dependencies =

Hard logic

Discretionary dependencies

=Preferred logic, Preferential logic, soft Logic

Milestones

Precedence diagraming method (PDM)

Activity-on-node (AON)

Arrow diagraming method

(ADM)

Activity-on-arrow (AOA)

Critical Path Method (CPM)

Grafical Evaluation and

Review Technique (GERT)

Program Evalutation and

Revew Technique (PERT)

Top-down estimating

Reserve, contigency or buffer

Schedule baseline

Revisions

Centro de Estudos e Sistemas Avançados do Recife

PMBOK - Chapter 6

Project Time

Management

Download