PINOLE VALLEY HIGH SCHOOL FACILITIES SUBCOMMITTEE MEETING December 13, 2011 Pinole Valley High School Campus Reconstruction Site Plan Pg. 2 Pinole Valley High School Campus Reconstruction Project Status Update Goal: To Review New School Campus Program, Geotechnical and Off-Site Scope of Work. Pg. 3 Pinole Valley HS New School Campus Project Schedule Phase 1 – Temporary Housing Campus: Site Retention Basin Completion: Campus Occupancy: 07/ 05/ 2012 08/ 20/ 2013 Phase 2 – Demolition of Existing Buildings: Demolition Completion: 08/ 16/ 2013 Phase 3 – Hillside Corrective Work: Construction Completion: 11/ 15/ 2013 Phase 4 – New Academic Buildings Campus/Offsite Improvement: Construction Completion: 8/ 15/ 2016 Phase 5 – Demolition of Temporary Housing Campus: Construction Completion: 9/ 15/ 2016 Phase 6 – New Bleachers, New Field Houses, Track and Field Modernization: Construction Completion: 9/ 15/ 2017 Pg. 4 Original Pinole Valley HS Program Overview: 1. Building Program: Based on educational program similar to El Cerrito HS. 2. Temporary Housing: (89) Portables 3. Project Components: Performance Theater (600 seats ) (66) Teaching Stations Library Gymnasium (1,500 seat capacity) Athletic Field Buildings Synthetic Turf Baseball fields with backstops Re-coat existing running track Replace Football Field Synthetic Turf Replace Existing Bleachers 4. Program square footage: 225,000 sq. ft. 5. Student population: 1,600 students. 6. Construction Budget: $84.6M* * - Does not include: Fabrication and leasing of portables, hillside corrective work and Off-Site scope of work. Budget reflects 2009 – 2010 bidding trends. Pg. 5 Current Pinole Valley HS Program Overview: 1. Building Program: Increased by Linked Learning, District Equity & Site Specific Educational Programs. 2. Temporary Housing: (94) Portables 3. Project Components: Performance Theater (600 seat ) (71) Teaching Stations Increased Classroom Capacity Requirement (32 to 40 students) (3) Linked Learning Academy & Multi-Use Rooms (1) School Site Specific Teaching Station Library Gymnasium (1,800 seat capacity) Increased Maintenance Service/ Utility Spaces Athletic Field Bldgs, Additional Team Rooms and Weight Room Synthetic Turf Baseball fields with backstops Re-coat existing running track Replace Football Field Synthetic Turf Replace Existing Bleachers 4. Program square footage: Approx. 267,246 sq. ft. 5. Student population: 1,600 students. 6. Construction Budget: $84.6M (unadjusted).* Pg. 6 Non-Building Program Construction Cost Increases: • C-3 Storm Water Management Regulatory Requirements: Underground storm water retention basin at baseball field area; consisting of 11,200 feet of 36-inch diameter piping 5-feet below grade. $ .2M • Hillside Slide Corrective Stabilization: Hillside removal and recompaction with installation of 108-feet of 4-foot diameter steel pier shoring. $3.6M • Temporary Campus Parking: Off-site parking lot developed at nearby church and public library. TBD • Off-site traffic improvements: Bus drop-offs and traffic lights. $1.7M Total Non-Building Program Construction Cost Increase: $5.5M Pg. 7 Comparative Summary between ECHS and PVHS: Dec. 13, 2011 Original PVHS Program (based on El Cerrito HS) Current PVHS Program Comparison 1,600 1,600 89 Portables 94 Portables Construction Cost Increase From Expanded Building Program (numbers are in million dollars) Student Population Temporary Housing on separate areas Theater 600 Seat Performance Theater 600 Seat Performance Theater Larger Choir, Addditional Piano Lab $0.7 66 71 $1.9 960 sq ft. (33 students) 1070 sf ft. ( 40 students) $2.2 Link Learning Classrooms None 4 @ 1,500 sf ft. each + circulation $2.3 Lecture/Multi-Use Classroom None 1 @ 1,700 sf ft. + circulation $0.7 Number of Teaching Stations Classroom Size Gymnasium Seat Capacity RSP Classroom Size Maintenance/Custodial Central Plant Increase over Furnace Closets 1,500 1,800 (+3,000 sf ft) $1.1 480 sf ft. 960 sf ft (4 x 480sf + circulation) $0.8 1,200 sf ft. 2,500 sf ft $0.4 Furnace Closets Central Plant $1.0 Site Area Increased Smaller Site (less improved area) Larger Site with more level change, longer dropoff, more landscape area, more parking Athletic Field Buildings $2.2 1 set of team rooms 1 Weight Room 2 Sets of Team Rooms/Restrooms Larger Fitness/ 2 Weight Rooms $3.6 none Synthetic Track and Fields Replace Existing Bleachers Baseball Fields w/Backstops $5.5 2007 Codes 2010 Codes -Additional 2,650 sf ft for Stairs $0.9 225,000 sf ft. 267,246 sq ft. High Performance Incentives -CHPS None Approx. 5% Increase Construction Cost *Non Building Program Cost Increase None Athletic Fields/Bleachers Code Requirements Program Square Footage $5.5 C-3 Strom Water Management: Underground Retention Basin ($0.2M) Hillside Stabilization work ($3.6M) Off-site Street Improvement/Traffic Lights/WestCat Bus Stops ($1.7M) Temporary Campus Parking Subtotal Construction Estimate Increase Original PVHS Construction Budget EL Cerrito Multi-PurposeField/Stadium/Football Construction Cost for ECHS Soft Cost for ECHS Total Project Cost for ECHS $84.6M 14.0 98.6 38.0 136.6 $4.5 Current Construction Estimate for PVHS Current Soft Cost for PVHS (30%) Total Project Cost Estimate for PVHS TBD $33.1 $84.6 $117.7 $50.5 $168.2 Pg. 8 Summary 1. Original Project Cost Budget: 2. Original Construction Budget: Construction Estimate Increase: Current Construction Estimate: Current Soft Cost (30%) Current Project Cost Estimate: 3. $120.00M $84.6M $33.1M $117.7M $50.5M $168.2M 4. The Building Program has expanded to accommodate additional school program requirements and non-building program cost impacts. However, construction funding has not been increased. 5. The Project construction budget must be reconciled with the building program to proceed. The following list of options have been prepared for your consideration. Pg. 9 Construction Estimate Project Cost (numbers are in million dollars) Phase Construction of Field Houses, Ball Field, Bleachers, Track 13.5 19.2 Phase Street Improvement Work 1.7 2.4 Decrease Gym Seating Capacity to 1500 1.1 1.5 Eliminate HPI - Sustainability Requirements 4.5 6.4 Eliminate Increased Classroom Capacity 2.2 3.1 Eliminate Linked Learning Classrooms 2.3 3.3 Eliminate Lecture/Multi-Use Classroom 0.7 0.9 Revise exterior building finish from Brick Veneer to Plaster Eliminate Performance Theater in lieu of Auditorium 0.7 0.9 4.5 6.4 Modernize Existing Gymnasium and Redesign onsite parking 7.5 10.7 Program Reduction Options: Pg. 10 End of Presentation Pg. 11