Development Process (LTF)

advertisement

Role of Investor Owned Utility in

Development of Wind Energy in

Iowa from an Engineers perspective

Jeff Bales

June 2011

2

Who are we?

 Alliant Energy Corporation is a public utility holding company headquartered in

Madison, Wisconsin. Alliant Energy's two regulated utilities include Interstate

Power and Light Company (IPL) and Wisconsin Power and Light Company

(WPL). In addition it has several other non regulated entities. Two of those are

RMT and CRANDIC.

 WPL generates, purchases and sells power in Wisconsin and has some ownership in the American Transmission Company who provides transmission service in Wisconsin

 IPL generates, purchases and sells power in Iowa and Minnesota. Its service territory serves the southern part of Minnesota and also is scattered throughout the state of Iowa. IPL sold their transmission system to ITC (Iowa

Transmission Company)

3

Who are we ? Alliant Service Territory

 The IPL service territory is scattered due to the merging of several smaller utilities in the past 20 years named Iowa Electric, Iowa Southern, and

Interstate Power and Light.

Energy Delivery Update

Technology

Confidential

5

Alliant Strategic Plan

Alliant Energy Utilities Strategic Plan is built on three key elements:

 Competitive Costs

 Reliable Service

 Balanced Generation

6

Balanced Generation

 Our sources of electric power in 2007 were 54% coal, 6 % natural gas and

39% Purchased Power.

 The 39% purchased power leaves our customers to unpredictable fuel costs.

These fuel cost can sometimes make up 50% of our customers bills.

 Due to state and federal legislation it is important that we have a balance mix of generation.

 Alliant now owns and operates a total of three wind farms

 Cedar Ridge (68 MW near Fon Du Lac Wisconsin)

Whispering Willow (200MW near Iowa Falls Iowa)

Bent Tree (200MW near Albert Lea Minnesota)

 Thru second quarter of this year the owned wind farms and Purchase Power

Agreements made up 6% of the generation in our service territory.

 We have several locations under development such that if it makes sense to add more wind to our fleet we will do so.

7

Role of Investor Owned Utility in

Development of Wind

Investor owned utilities are able to see the entire process from beginning to end.

Have key roles in the paradigm shift as significant milestones occur.

 Contracts for Purchase Power Agreements

 Owning Wind Farms

 Operating Wind Farms

8

Role of Investor Owned Utility in

Development of Wind

 Owning Wind Farms

 Forecasting the output of wind farms

Impact is to Production Tax Credits that are forecasted in our financials on a quarterly basis.

Impact to our fuels forecast

Impact to the remaining fleet of generation in the area

9

Development Process – Long Term

Forecast (LTF)

10

11

Development Process (LTF)- Wind Source

 The P50 number represents the probability of that level of generation being met.

 Probability numbers are used for different circumstances relative to bank loans and in some instances negotiations around a purchase power agreement.

 This number only takes into account the assumed losses and the statistics around long term data.

 One forecasting vendor is presently challenging some of the historical information coming out of these reports (nationally) based on poor data sets from the different ways of collecting long term data and comparisons to actual data.

 Part of due diligence is the comparison of a utility wind owned facility to a purchase power agreement.

 Bottom Line- When comparing different alternatives understand which P value you are comparing to.

12

Development Process (LTF)-

Transmission

 Midwest Independent System Operations is the controlling entity for the state of Iowa at the Regional level

 Two transmission utilities presently provide the majority of services for MISO

 Our two owned wind farms are located in the Iowa Transmission Company footprint of service.

 Currently each of our 200MW wind farms are working within a provisional

Generator Interconnect Agreement.

 MISO continues to do studies to accommodate customer base however timing of such studies and implementation seem to be in the 5-7 year time frame and not in the current two to three year cycle.

 Optional Studies have been completed by MISO for Alliant under, at that time, current conditions and also with certain assumptions by the customer.

 Under these conditions a Provisional Generator Interconnect Agreement can be pursued with implementation in the 14 month timeframe while larger studies continue.

13

Example of Optional Study Result (LTF)

14

Development (LTF)- Bringing them together

 Previous number represents the Provisional Limit and is posted by MISO quarterly. In some instances this can change which will effect your forecasted outputs.

 How do Purchase Power Agreements handle Provisional status ?

 Internally owned Wind farms

15

16

Power Curves

EAPC vs. Calculated

250.00

200.00

150.00

100.00

50.00

0.00

0 5 10 15

Wind Speed m/s

20 25

EACP Power Curve

Calculated Power Curve

17

Development Process (LTF)-Internal xxxx - May 2011

Variance Report

70,000

60,000

50,000

40,000

30,000

20,000

10,000

0

-10,000

-20,000

Forecast

Actual

Variance

Wind

47,925

60,920

12,995

Curtailments

0

-12,112

-12,112

Reduction due to 165 MW Op

Limit

0

-1,163

-1,163

Total

47,925

47,645

-280

18 xxxx Observed Power Curve

MAY 2011

180

160

140

120

100

80

60

40

20

0

0

-20

2 4 6 8 10

Wind Speed m/s

12 14 16 18

Series1

19

Development Process (LTF)

 What makes up the other curtailments?

 Two buckets

 Operations Curtailment

 Economic Curtailment

20

Development Process(LTF)-Operations

Curtailment (MISO document June 2010)

 Wind Farm that is registered Intermittent Resource or (IR) cannot be dispatched as part of the real-time dispatch software at MISO

 Result of this necessitates manual curtailment by MISO to relieve transmission constraints

 LMP node under this condition does not reflect congestion

 Results of these conditions were that until April of this year 90% of curtailments were operational in nature and not economically based.

21

22

Development Process(LTF)- Economic

Curtailments

 Beginning in April Alliant Energy wind farms began seeing much more volatility in LMP prices at the wind farms.

 Result of this necessitated manual curtailment by Alliant GDC to relieve economic concerns over negative LMP prices

 Due to timing issues Alliant GDC could not keep up with the changing 5 minute

LMP pricing.

 Results of these conditions were that a large shift in curtailments between operations and economic began to change on a percentage basis.

 As a result Alliant has signed up Wind Farms for Dispatchable Intermittent

Resource so it can take advantage of automatic control to maximize efficiency.

 Two of our Three wind farms will implement this feature in September.

23

Forecasting- Economic Curtailments

Date

1-Apr-11

2-Apr-11

3-Apr-11

4-Apr-11

5-Apr-11

April-11

Generation

(Revenue) /Expense

($28,514.55)

$85,561.15

($10,861.37)

$13,299.28

($10,103.95)

Volume

-1,963,000

-1,040,000

-977,000

-1,499,000

-609,000

24

Development Process (LTF)-Economic

 Existing Purchase Power Agreements do not have language to address issues around negative LMP.

 When new PPA are negotiated this will definitely be taken into account.

 Will have impact on developers ability to execute on loans and quality of their forecast

 Present PPA did not have scrutiny around producing at negative rates.

 Impacts operations as well with most contract services being driven off availability.

 Present take is on shoulder months where load vs generation has base units backed off to minimum will be the months where forecasts will be impacted.

 No longer can assume the best wind months are the best for wind farm output presently at Alliant.

25

Summary Long Term Forecasting

 Investor owned utilities are learning that the wind forecast is just one component of the forecast.

 As wind generation continues to make penetration expect local congestion issues to continue. Investor own utilities will need to understand all conditions as the wind becomes more of a segment of the generation on how there fleet of generation will be dispatched.

 Wind farms must develop a y=f(x) concept to ensure they manage each component of the forecast well to understand the dynamics moving forward and are able to report to their customer base.

 Vendors and suppliers of forecasting services will need to get into the operation segment of wind farms to understand controls and maintenance to provide turn key services. Signals from turbines as it relates to local conditions will become next generation of improvement in short term forecasting

Download