Fatal Crane Incident at Amin (Nimr) Steam Pilot Project 20/09

advertisement
Fatal Crane Incident at Amin (Nimr) Steam
Pilot Project 20/09/2012, FIM # 869548
Incident Summary
A fatal incident occurred at the Amin (Nimr) Steam Pilot project site on Thursday 20th
September, 2012 at an approximate time of 14:10 hrs. The deceased is a 32 year old Indian
helper working for Al Turki Enterprises (ATE), a PDO contractor.
An ATE mechanical crew was using a 25 ton crane to lift pipe sleeves. During the lifting
operation, the deceased went to fetch slings from the crane’s tool box located above the
cranes battery. The contents of the box cannot be accessed from ground level so he stood
on the outrigger and reached over. In doing so he placed himself in the arc path taken by the
cranes counter weight which as it rotated, crushed the deceased against the toolbox.
He immediately fell unconscious and was brought to STS camp clinic in Amal. The doctor
gave him CPR but could not revive him and at 15:15 hrs he was declared dead.
1
Fatal Crane Incident at Amin (Nimr) Steam
Pilot Project 20/09/2012, FIM # 869548
Events leading to the Incident
• There was no ‘Person In Charge’ or banksman controlling the crane operations
• There were Concurrent Operations leading to conflicting tasks in the area.
• 2 mechanical crews working on two separate PTWs in the same area
• The deceased walked into and within the cordoned off area.
• There were non adherences to the PTW requirements and deviations from the
Lifting Operations Standards and Procedures (PR 1709):
• lifting plan was not followed;
• hazards were not reassessed when there was a change at the work site;
• crew members changed from one crew to another.
2
PDO Emergency Safety Advice
for all crane operators
Learnings from Incident (LFI)
1.
Ensure there is a proper lifting plan in place and it is followed at all
times;
2. Ensure HEMP has been carried out;
3. Ensure the “Ten Questions For A Safe Lift” have been discussed
and properly cascaded during the toolbox talk; (slide 6)
4. Ensure risks of concurrent operations are assessed and mitigated;
5. Ensure lifting operation personnel are competent and qualified;
6. Ensure a Person is In Charge (can be the Banksman) and wears a
high visibility vest;
7.
Never access a crane when it is either operating or about to
operate;
8.
Use steps to access heights, not an outrigger;
9. Always be aware of events around you and expect the unexpected;
10. Barricade the area and ensure only authorized personnel enter;
11. Crane drivers and banksman (signaller) must visually check all
around the crane before operating.
Not complying with crane Operating
Procedures and Standards can kill
Responsibilities
Banksman / Signaler:
The only person, who co-ordinates the lifting movements and maintains radio- and/or
visual communication with crane operator and persons close to the load.
Slinger / Rigger:
The person, who inspects the rigging, selects rigging to suit the load, installs the
equipment and connects/disconnects the load.
Person in charge of the lifting (PIC)
The person, who co-ordinates and controls all aspects of lifting operations on site. (The
PIC and Banksman may be the same person).
Management Learnings
To ensure continual improvement all Contract Managers are to
review their HSE HEMP against the questions asked below:
Confirm the following:
•Do you employ a competent PDO compliant banksmen used for all lifting operations?
•Do you employ trained and competent crane operators?
•Do you create and use lifting plans for all lifting operations?
•Do you adequately supervise lifting operations?
•Do you regularly audit your lifting operations to assure compliance?
•Do you have an effective maintenance and inspection schedule to keep the windows/mirrors
clean and alarms working?
•Do your cranes have warning labeling to warn the unsuspecting of hazardous areas?
•Do you conduct relevant TBTs to staff involved in lifting operations?
•Have you conducted risk assessments of lifting operations and ensured the required controls are
implemented and maintained?
•Have you created and introduced effective Job Safety Plans for lifting operations.
Ten Questions For A Safe Lift
1. Is everyone aware of and fully understands the lifting and hoisting procedures applicable to the
lift?
2. Has everyone attended the toolbox talk?
3. Has a pre-use inspection of the Lifting Equipment been carried out and are the Lifting Accessories
tagged or marked with:
- Safe Working Load (SWL)
- A unique identification number
- A valid certification date
4. Are all safety devices working?
5. Does everyone know the Person-in-Charge of the lift?
6. Is everyone competent and aware of his or her tasks?
7. Is there a current Lift Plan and JHA and does everybody understand the job and precautions?
8. Does everyone know the environmental limits (e.g. maximum permissible wind speed) for the
lift?
9. Is the lift area controlled and is everyone clear if the load falls or swings?
10. Are signaling methods and communication agreed and clear to you?
LSR 7 Never walk under a suspended load
•Every “routine” lift must have a
generic lifting plan.
• Every “non-routine” lift must
have specific lifting plan.
• Person In Charge shall ensure
lift area is cordoned off during
the lifting operations.
• No one should ever be under
any working crane or
suspended load.
Person In Charge (Banksman / Signaler)
Fatal Crane Incident at Amin (Nimr) Steam
Pilot Project 20/09/2012, FIM # 869548
Incident Details
Contractor Name
: ATE
Incident Owner
: OSD
Time, Date, Place
: 14.10 hrs, 20th Sep. 2012 at Amin ‘A’ Street
Persons involved in the Incident
: Mr. Jakhu Naran Maheshwari (ATE Emp. No. 919596),
Age – 32 working as a helper in ATE since 2009
Vehicles / equipment involved in the Incident : TE – 285, 25 Tons Mobile crane, Make Kato, NK 250EV,
Year of manufacture – 2001
Injuries
:1 Fatality
Actual Severity Rating
: Level 4
Potential Severity
: Yellow
9
Download