Planned HV Projects for the Amajuba
District Municipality
Simphiwe Ngwenya
Geographical Layout
2020/04/14 2
Eskom’s HV Infrastructure Within The DM
2020/04/14 3
HV Projects
• Kilbarchan 88kV Substation
•
Due to long network lengths, voltage limits have been reached with very little ability to optimally distribute power.
Studies done on the networks indicate the need to migrate from 11kV to 22kV distribution voltage.
• Project need date 2014-2015
2020/04/14 4
HV Projects
• Clontarf 88kV SS
•
Clontarf SS is an 88/11/22 kV
Substation. It has one 7.5MVA
88/11kV transformer and one
2.5MVA 11/22kV transformer.
The original station was built in
1974 and is now 34 years old .
• Project need date 2015-2016
2020/04/14 5
HV Projects
• Rutland 33kV SS
•
Rutland SS will experience loading constraints on the
33kV in feed. This substation has undergone a capacity upgrade to 2X10MVA 33/11kV transformers.
• Plans to convert Rutland to an
88kV SS are being investigated. Mining supply will be used as the trigger for the
HV voltage upgrade.
•
Ikwezi Mine project need date
2014-2015
• Slater Coal project need date
2014-2015
2020/04/14
Ikwezi
Slater Coal
6
HV Projects
• Madadeni 132kV Conversion
• Madadeni/Osizweni township is supplied from Ingagane substation. Need date 2012-
2013
• Madadeni SS to supply Mabuya
Mall
• Need Date 2015-2016
• Matsheketsheni SS Est(deload
Blaauwbosch and Vlaklaagte)
•
Need Date 2015-2016
• Blaauwbosch SS increase
Capacity from 2*10MVA to
2*20MVA
• Need Date 2012-2013
• Parklands SS 132/11kV injection to supply
5.5MVA(Meadowlands
Development)
• Complete
2020/04/14 7
HV Projects
• Kipspruit SS relocation
•
Project need date 2013-2014
• Ingagane Utrecht 88kV Line
Conductor Upgrade
2020/04/14 8
HV Projects
• Ruston 88kV Substation
•
Reliability project raised to increase capacity at the Sub.
• Project need date: 2014-2015
2020/04/14 9
Summary Of Projects
2020/04/14 10
Electrication(Madlangeni and Newcastle)
2020/04/14 11
Cont’d…Electrification(Danhauser)
2020/04/14 12