Welcome to the Developers Working Group (Your are in safe hands) The shape and tinting of the building were chosen to minimise the effects of an indirect nuclear blast. Despite being a major London landmark, until the mid-1990s the tower did not officially exist and was not marked on Ordnance Survey maps. Due to expansion and contraction caused by the cold of winter and the heat of summer, the tower's height varies by as much as 23 centimetres (9 inches). Around 50,000 square feet of glass encase the tower's concrete shaft. The tower is designed to sway by as much as 38 centimetres (15 inches) in a 175 kilometres-per-hour (110 miles-per-hour) wind. There are 95 tonnes of high tensile steel in the base, 695 tonnes of mild steel in the structure and 13,000 tons of concrete. Lewis Benn New Site Construction & Local Authorities lewis.benn@openreach.co.uk Openreach makes every effort to ensure the information in this presentation is accurate at the time of compilation, however, Openreach does no represent that it is complete and Communications Providers should check with Openreach for the latest available information. Openreach reserves the right to modify delivery criteria and delivery dates. © British Telecommunications plc Safety & Domestics Agenda Openreach Policy Update Future of the Connected Home New Sites Portal Next Generation Access & Communication Provider Update Lunch – 33rd Floor Securing the Network Service to Construction Sites FTTP – Strategic Sites Didcot Story Olympic Village Caution Advised Some information in this presentation relates to plans currently under development and are subject to consultation, and may be subject to change Information in this presentation is subject to change Policy Mick Lennon FTTC Copper, Copper Growth and New Sites Policy Manager Openreach makes every effort to ensure the information in this presentation is accurate at the time of compilation, however, Openreach does no represent that it is complete and Communications Providers should check with Openreach for the latest available information. Openreach reserves the right to modify delivery criteria and delivery dates. © British Telecommunications plc Policy Service Costs - RFT - SLG’s - Plant costs - Tails - Access - Lead times plus - Pair bonding - Universal service obligation - Broadband Speed - Broadband Availability Capabilities Strategic Issues 7 Removal of the External Network Termination Point (Copper) Withdraw of External Network Termination Point Information Subject To Change Confidential Any Questions? Mick Lennon, New Sites Policy mick.lennon@openreach.co.uk Future of the Connected Home Adrian Thurlow Creative Technologist Openreach makes every effort to ensure the information in this presentation is accurate at the time of compilation, however, Openreach does no represent that it is complete and Communications Providers should check with Openreach for the latest available information. Openreach reserves the right to modify delivery criteria and delivery dates. © British Telecommunications plc What is the Connected Home A combination of: • A selection of interoperable devices • A range of services which take advantage of these • The interconnecting home network Information Subject To Change Confidential Emerging consumer needs • Consumers are increasingly demanding access to content on multiple devices: − 40% of people time-shift content daily (Source: Nielsen) − Only 43% of total video consumption takes place on a TV (Source: Ericsson) − Sky, Virgin, LoveFilm, Netflix etc. all offering content across multiple platforms • Growing need to push large amounts of content to, around and out of the home: − e.g. Multi-room high-definition services − e.g. Back-up/sharing of content from devices including those equipped with HD cameras • Simplicity and reliability: − Key reason for continued of physical media (e.g. DVDs) is perceived lack of reliability of digital alternatives (Source: Ericsson) − Existing home networking solutions account for significant proportion of support calls Information Subject To Change Confidential Current limitations of the Connected Home • Lack of interoperability: − Multiple ‘stove-piped’ solutions e.g. media services, home energy management systems − Incompatibility issues • Complexity to set up and use: − Devices and services do not work together “off-the-shelf” • Home networking issues: − Delivering required bandwidth for advanced services such as multi-room HD − Complexity of setting up home networks − Less than 100% reliability Evolution of Connected Home devices The next few years will see explosive growth in connected, inhome devices: – DisplaySearch forecasts that over 100 million Internetconnected TV sets will ship worldwide in 2013 – Set-top-boxes, games consoles and Blu-Ray players will be similarly enabled, if not already Accessing content services across multiple devices will become a baseline feature of content services Information Subject To Change Confidential Device compatibility – Digital Living Network Alliance (DLNA) DLNA is the only ‘standard’ that provides a common interoperability scheme between all devices that create, serve and render (play or display) content within the Connected Home 96% of Internet-enabled TVs from the top 5 manufacturers support content playback via DLNA 68% of leading Blu-Ray players are DLNA certified Proprietary alternatives exist but are restricted to a limited range of devices e.g. Apple Airplay The growth in DLNA will increase the usage of in inter-connected home devices Information Subject To Change Confidential Home networking The home network must have the capacity to concurrently support both services, such as IPTV, delivered via the access network and customer owned systems resident within the home Connected Home bandwidth requirements (Mbit/s) Information Subject To Change Confidential Home networking in existing housing 2 pair Cat5 can deliver 100 Mbits/s 4 pair Cat5 can deliver 1 Gbit/s Given the time & expense and to ensure that the installation is future proof always install 4 pair Wi-Fi Technology No new wires New wires Data networking Best effort unmanaged (2 Mbps – 10 Mbps) Powerline Multi-media networking Managed QoS (>50 Mbps) Ease of install/use Aesthetic impact Wi-Fi Powerline Cat5 2 & 4 pair Cat5 Wired solutions Retro fit – Disruptive – Self install? – Unacceptable aesthetics? – Susceptible to damage Internal corner Install during construction – Better looking, available in a wide range of styles – Qualified installers – Ready for use – Whole home coverage, varying socket density between rooms – Reliable – Flexible External corner Single socket connection The benefits of the Connected Home Interoperability of devices Easy management and sharing of multimedia content Part of the Smart Home The benefits of the pre-installed home network Ease of use and simplicity Much reduced headaches from home networking issues Little aesthetic impact Best possible performance Ensures that NGA speeds are available throughout the home Information Subject To Change Confidential Final thought The home network is the foundation that the ‘Connected Home’ is built upon and it is an essential link in the delivery of both existing & future products and services destined to be used in the home Information Subject To Change Confidential Any Questions? Adrian Thurlow, Creative Technologist adrian.thurlow@bt.com New Sites Portal Tim Jacobs Openreach Programmes Openreach makes every effort to ensure the information in this presentation is accurate at the time of compilation, however, Openreach does no represent that it is complete and Communications Providers should check with Openreach for the latest available information. Openreach reserves the right to modify delivery criteria and delivery dates. © British Telecommunications plc NGA & Communication Provider Update Kevin McNulty NGA Commercial Partner Sales Openreach makes every effort to ensure the information in this presentation is accurate at the time of compilation, however, Openreach does no represent that it is complete and Communications Providers should check with Openreach for the latest available information. Openreach reserves the right to modify delivery criteria and delivery dates. © British Telecommunications plc Our Next Generation Access Managing Director Mike Galvin appointed 1st July 2011 Homes Passed to Date • • Over a 1/5th of the UK homes can now access our Super-fast Broadband Network (5.5m homes) 14,000 DSLAMs now standing We’re announcing more Exchanges Exchange Name ARCHERS COURT Exchange Name Exchange Name FOXHALL MIDHURST Exchange Name SOUTHWICK (SOUTH DOWNS) BALDSLOW GALASHIELS MILDENHALL STEYNING BANNOCKBURN GILLINGHAM, KENT MILFORD STOKE BISHOP BASILDON GORLESTON MILNSBRIDGE STORRINGTON BECCLES GREAT BADDOW MOORHILL STOWMARKET BELSTEAD GRESFORD NEWHAVEN STRATHAVEN BEXHILL HADLEIGH, SUFFOLK NORWICH THORPE SUDBURY, SUFFOLK BOGNOR REGIS HAILSHAM NORWICH WEST SUNDERLAND BRIGHTON ROTTINGDEAN HAMPDEN PARK PADDOCK WOOD SUNDERLAND NORTH BROADSTAIRS HASSOCKS PAGHAM THANET BRUNDALL HATFIELD PEEBLES THETFORD BUNGAY HEXHAM PERTH THORPE BAY BURSLEDON HISTON POLEGATE TILBURY CAISTER ON SEA HOO PURFLEET TIPTREE CARLISLE HYTHE, HAMPSHIRE RAINHAM, KENT VANGE CASTLETON, GWENT HYTHE, KENT RAMSGATE WARE CHERRY HINTON IPSLEY RAWDON WASHINGTON CLACTON-ON-SEA IPSWICH REDDITCH OLD TOWN WELWYN GARDEN COLCHESTER KIDDERMINSTER RUSTINGTON WEYMOUTH COSTESSEY KINGS LYNN RYHOPE WHITSTABLE CUFFLEY LANCING SALISBURY WHITTON, SUFFOLK DANBURY LEWES SAWBRIDGEWORTH WIVENHOE DOVER LITTLEHAMPTON SEAFORD WOODBRIDGE EAST BAY LOOSE SELSEY WORTHING CENTRAL EASTBOURNE PEVENSEY LOWESTOFT SHOEBURYNESS WORTHING SWANDEAN EASTWOOD MAIDSTONE SHOREHAM WORTHING WEST EDINBURGH MORNINGSIDE MANNINGTREE SNODLAND WREXHAM NORTH FELIXSTOWE MARINE SOUTH OCKENDON FORDINGBRIDGE MIDDLETON, WEST SUSSEX SOUTHPORT NGA Communication Providers CPs are established for all NGA products – FTTC, FTTP and FVA Established NGA Communication Providers (CPs): 12 Direct CPs 30 Downstream CPs Sample of customers who’s permission we have to disclose as trialing or offering Superfast Broadband (see http://www.openreachcommunications.co.uk/superfast/ ) Openreach Activities Openreach FTTP installation work at the Athletes’ Village is now 75% complete, meaning that 75% of all the 2,818 apartments are now fully installed with fibre and copper pair connections all the way to the serving exchanges. The rollout of the NGA Mixed Economy solution, also known as FTTx, started its journey in August 2010, giving us the capability to deliver both Fibre to the Cabinet (FTTC) and Fibre to the Premise (FTTP) off a common spine network Openreach have now finalised the three candidate exchange areas along with the associated NGA Handover Exchanges for the Fibre Only Exchange (FOX) Information Subject To Change Confidential Any Questions? Kevin McNulty, GM NGA Commercial Partner Sales kevin.mcnulty@openreach.co.uk Securing the Network Bryan Waite Network Resilience & Fraud Manager Openreach makes every effort to ensure the information in this presentation is accurate at the time of compilation, however, Openreach does no represent that it is complete and Communications Providers should check with Openreach for the latest available information. Openreach reserves the right to modify delivery criteria and delivery dates. © British Telecommunications plc Lockable Footway Frames & Covers DEVELOPER-BUILT BOXES PROPOSAL We are asking that in future all developer-built boxes in UK are fitted with lockable frames and covers as standard BENEFIT Part of the longer term strategy to improve the resilience of the Openreach network, thus protecting legacy and new technology. e.g. Broadband Unique Selling Point for Developers to offer house buyers improved resilience Estimated to avoid 210 attacks per year on new sites OTHER FACTORS No additional stores cost to developer for standard lockable frame and covers Can be fitted to brick, concrete or modular joint boxes Information Subject To Change Confidential Lockable Footway Frames & Covers Information Subject To Change Confidential Lockable Footway Frames & Covers Information Subject To Change Confidential Lockable Footway Frames & Covers The new range of Footway Frames & Covers, including precinct covers, will be made available with locks. The covers will be secured by either one or two integrated locks and fit into a reinforced frame The frame has been strengthened from 3mm to 5mm steel and has lugs which need to be bent down and bolted to the structure of the box during installation A Turnbuckle lock has been introduced within the lid. It is locked and unlocked by pushing down and turning the new Key through 90 degrees The covers will be delivered to site in the unlocked position. All other activities associated with fitting or opening/closing the joint box remain unchanged Information Subject To Change Confidential Any Questions? Bryan Waite, Network Resilience & Fraud bryan.waite@openreach.co.uk Service to Construction Sites Phil Orr Network Investment Transformation Programme Director Openreach makes every effort to ensure the information in this presentation is accurate at the time of compilation, however, Openreach does no represent that it is complete and Communications Providers should check with Openreach for the latest available information. Openreach reserves the right to modify delivery criteria and delivery dates. © British Telecommunications plc To Cover Today 1. 2. 3. 4. 5. 6. 7. Introduction and background The roll out of the ‘South West’ initiative Compliance The use of site distribution points The new planning prioritisation tool Progress & Timescales Contacts ‘We cannot figure out why things take such an obtuse and frustrating amount of time. We have often completed the construction of multiple floored and expansive multimillion pound buildings before BT have done anything. It’s ridiculous’. Information Subject To Change Confidential What we’re doing about It Carried out root cause analysis of site office L2C jobs Briefed every planner in the UK on the action and importance of service to new developments Liv Garfield personal involvement Agreed a three month action plan: – Implementing a more focused approach to meeting survey task lead times, as trialled in the South West – Implementing a new planning prioritisation tool developed in the North West – Publishing briefs to CP’s and the construction industry – to help them help us Information Subject To Change Confidential Planning Structure in Openreach Information Subject To Change Confidential The South West Initiative Pilot /Trial deployment Trial in the south west planning area took place between April and May Trial initiatives successfully reduced survey lead times 12+ days to 6.9 days We found that − survey lead times >12 days − too many internal hand-offs − queue priority determined by internal dates (ARBD’s) − failure to follow data format rules for line-plant available dates (LADs) and excess construction charges (ECCs) − Building extra time into LADs to prevent failure. ARBD’s – Activity Required By Date LAD – Lineplant Available Date ECC’s – Excess Construction Costs Information Subject To Change 42 Confidential Actions Deployed Nationally • Target is 4 days from order to survey completion • Making a survey appointment < 1 day of receipt • Producing the survey pack on the day of survey appointment • Target ECCs given to CP < 1 day after survey. • Increase priority of construction site surveys (act on receipt instead of waiting for activity required by date) • Calculate LADs to make sure network build is completed without delay. • Mandatory training to planners: o DO not add time unnecessarily to the LAD ‘just in case’ . o Always use the right format for the CSS note (systems will make an appointment based on the LAD you enter). o Prompt installation is vital for our customers. Information Subject To Change • The new planning prioritisation tool in place across UK Confidential Queue Understanding Intelligently Presented (QUIP) Developed by Planning teams in North West, Approval rating on launch 88% Information Subject To Change QUIP is a manually run or Auto driven Order Prioritisation Tool using MS Excel QUIP - Scans ALL Activities in the Users Workstacks Workstacks can be Multiple patch/skill Queues across Multiple CSS Databases All data is collated, prioritised and presented according to SLAs, EU/Customer CRD or Appointments Orders will be highlighted and sorted by the following Rules: 1) Order arrives before 2:00pm on the day – It will be highlighted Green 2) Order arrives after 2:00pm on same day – It be highlighted Amber 3) Order arrives after 5:00pm on the same day – It will be highlighted Red 4) Subsequent days after order arrival – It will remain highlighted Red PST Target - Customer Contact is called the same day order arrives and Survey Appointment is made (Priority - Notes to be updated on CSS stating results of Call) Confidential Correct assessment of ‘LADs’ The Line plant available date (LAD) tells our CPs how long it will take to build new Openreach network for their order. Once the CP has accepted any excess construction charges (ECCs), the order will be re-appointed to the LAD. The new appointment will made by systems and must therefore be in the right format. LADs must be entered in the correct format: LAD=xx working days (with or without spaces?). If network is available immediately use the format LAD=0 working days. The LAD should reflect the actual time required to provide network. It is not acceptable to use default rounded times to avoid failure. Always calculate the date as accurately as possible, taking into account the network build work required and the availability of resource (internal or contract) to do it. Information Subject To Change Confidential Learning points on avoiding incorrect use of data formats Openreach uses automated systems to communicate excess construction charges (ECCs) and line plant available dates (LADs). Systems rely on correctly formatted data to pass information from the surveyors and planners to Communications Providers (CPs) and their customers. It is essential that ECCs and LADs are correctly formatted, or the process will be delayed, resulting in lost business & cost for Openreach and delays and manual intervention for CPs. Excess construction charges must be entered in the format COSTS = £xx.xx WITHOUT VAT. Information Subject To Change Confidential The use of site distribution points What is it? – An SDP is a cabinet in which we fix our external NTE Who installs it? – It is owned and installed by the developer Example site distribution What’s it for? cabinet – It avoids the need to wait for site offices to be located on site (a frequent source of delay) Where should it be located? – Fixed rather than movable – Positioned so Openreach will always be able to get safe access during the life of the service What’s the spec? – Robust enough to protect our NTE from physical damage – Suitable for our NTE to be fixed inside easily – eg. screwed onto a wooden back plate – Big enough to house all the external NTEs we will need for the site – Not shared with other CPs or other utilities (especially electricity suppliers) How is it ordered? – It’s not ordered, it’s agreed between the Openreach surveyor and the developer, at their first site meeting, as part of the site solution When is it removed? – After the service is ceased and we have removed our NTE and cable Where can I get advice and help? – Brian Currie (BEA1)(01368 850782) and Stan Edwards (BEA1)(01244 502025) Information Subject To Change Confidential What Now? Planning teams briefed on construction site offices & temporary site lines, June & July 2011 Planners to assess line plant availability dates (LADs) correctly We need to avoid waiting for site offices to arrive before starting planning Surveyors to proactively suggest the use of site distribution points (installed and owned by developers) to house our NTE’s Deploy across the UK the ‘South West’ approach to the survey process the ‘North West’ approach to planning prioritisation – the ‘QUIP’ tool Information Subject To Change Confidential Current combined Performance Built a new set of internal KPI’s (Step 1) • Order Received • Access & onsite meeting agreed • Survey Completed • Excess Construction Charges on System and available to CP Improve performance • Local & National • Commit to Service Levels for the controllable elements Specific Total Dwell time and commitment metrics under development Information Subject To Change Confidential Any Questions? Phil Orr Transformation Programme philip.orr@openreach.co.uk FTTP - Strategic New Sites Phil Laws Openreach makes every effort to ensure the information in this presentation is accurate at the time of compilation, however, Openreach does no represent that it is complete and Communications Providers should check with Openreach for the latest available information. Openreach reserves the right to modify delivery criteria and delivery dates. © British Telecommunications plc What does the Openreach New Sites solution look like? The ultimate e2e solution for New Sites is based on the Openreach Fibre To The Premise (FTTP) technology and products. These products are already being deployed in Brownfield as part of our NGA roll-out but in many respects the New Sites solution is different. 3 main factors shape the product – the needs of our customers (Developers and CPs), the nature of New Sites development planning/build and very different New Sites service take-up volumes Openreach Story: Modular architecture “Pre-installed” ONT Remote provision of voice and data services Positive customer experience and RFT Developer Story: CP Story: Increased sales Fibre enabled from start (no post sale civils or build activity) Homes Ready for the future (PAS 2016…) FTTP Easy to consume (similar/better than Brownfield) Quality voice-over-fibre Efficient RFS and addressing solution Information Subject To Change Confidential Progress FVA Project planned to launch March 2012 Olympic Athletes Village (2818 FTTP premises) Creation of an NGA Programme horizontal with major projects addressing New sites Worked British Standards Institute to develop PAS2016 and an updated Builders Guide including guidance on structured wiring for fibre served premises Investment in our FTTP network infrastructure design, systems and processes to support deployment to tactical and strategic new sites FTTP Brownfield footprint RFS today 20k premises with 85k in build Information Subject To Change Confidential Strategic New Sites Product Development Plan Development plan on track – November 2011 – Plan & Build – March 2012 – L2C & T2R Strategic product pre-built into 100% of premises and supporting GEA Data and Fibre Voice Access (FVA) 2 phase deployment plan – Phase 1 Pilot – Phase 2 National rollout Sept 2012 - All Tactical New Sites activity ceases (Copper Underlay process) and in-progress developments switch to FTTP on strategic deployment – Vision: All new build sites over c. 25 premises Mar-13 Jul-12 Jun-12 May-12 Apr-12 Mar-12 Feb-12 Jan-12 Dec-11 Nov-11 Oct-11 Sep-11 Aug-11 Jul-11 Jun-11 May-11 Apr-11 Copper Policy Development and Strategic New Sites Trial Planning/Training Strategic New Sites Pilot Planning/Training FOA Consultation Pilot Phase 1 Starts (Plan & Build) Information Subject To Change Pilot Phase 2 Sites Start (across NGA enabled new site regions) Target Rollout complete Confidential New Sites strategy: Copper, FTTP Tactical, FTTP Strategic Apr – Jun ’11 Jul – Sep ‘ 11 Oct – Dec ‘11 Jan – Mar ‘12 Apr – Jun ’12 Jul - Sep ‘12 Oct – Dec ‘12 Jan – Mar ‘13 Strategic New Sites Copper with tubing Tactical New Sites Strategic New Sites Pilot Plan 5 sites − c. 500 units − c. 75 to 100 plots per site November 2011 to October 2012 First trial occupancy (L2C ready) from April 2012 CP dependency Information Subject To Change Confidential Product The network solution and product will closely resemble that provided at Ebbsfleet – a modular tube based infrastructure and planning policy to accommodate flexible deployment – support for both single and MDU premises – ONT commissioning at plot call-off and a records-only (no-visit) L2C fulfilment – ‘Fit & forget’ facilitated through quality installation – Infill Equipment location A key dependency is the availability of Fibre Voice Access (FVA) Fibre only areas Information Subject To Change Confidential New Sites Network Design Information in this presentation is subject to change Any Questions? Phil Laws, Strategic New Sites phil.laws@openreach.co.uk