REPLACEMENT – S4 BRIEFING Jeffrey Allen, Senior Project Manager, USACE, Ft. Worth District Mitchell Alguadich, Senior Project Manager, HDR Architects Maurice Salata, Senior Architect, HDR Architects HOSPITAL El Paso Community College Contractors Networking & Teaming Forum January 17, 2012 BLISS EL P ASO, TEXAS FORT FORT BLISS HOSPITAL REPLACEMENT PROJECT Contractors Networking & Teaming Forum S4 BRIEFING Project Team Overview Project Award Packages REPLACEMENT – Projected Schedule FORT BLISS HOSPITAL HDR Presentation 2 – REPLACEMENT HOSPITAL BLISS Contractors Infrastructure Project – Sundt Construction, Inc. Water Tower Project – Jamco Ventures, LLC FORT HA/TMA – Health Affairs/Tricare Management Activity ACSFAC (MEDCOM) – Assistant Chief of Staff, Facilities HFPA – Army Health Facilities Planning Agency WBAMC – William Beaumont Army Medical Center USACE Ft. Worth District / Ft. Bliss Program Office Ft. Bliss Garrison S4 BRIEFING Project Team • Ft. Bliss Hospital Replacement project includes a 1.132 M square foot World-Class Medical Facility – • Campus buildings & features include - hospital, clinics, admin, research, central utility plant, access control points, therapeutic gardens, nature trails, and surface parking BLISS FORT • The Project Delivery Team have endeavored to incorporate state-ofart design ideas including the latest in Evidence-Based Design (EBD) and Sustainability as well as design innovations promoting family and patient-centered care HOSPITAL • Design-Bid-Build execution REPLACEMENT • Replaces William Beaumont Army Medical Center (WBAMC) S4 BRIEFING Overview JUL 2011 WATER TOWER - - JUN 2011 HOSPITAL >$500 M JUL 2012 DEC 2012 PARKING A $5 – 10 M APR 2012 JUL 2012 HELIPAD $500 K - 1 M MAR 2013 JUN 2013 PARKING B $1 – 5 M OCT 2013 DEC 2013 ACCESS CONTROL POINTS $10 - 25 M DEC 2013 MAR 2014 LANDSCAPING $10 – 25 M DEC 2013 MAR 2014 *Dates – - REPLACEMENT - HOSPITAL INFRASTRUCTURE BLISS MAGNITUDE PLANNED AWARD* FORT PACKAGE PLANNED SOLICITATION* S4 BRIEFING Project Award Packages subject to change 5 Projected Schedule (calendar year) CONSTRUCTION PHASING* MAY 11 - SEPT 12 Infrastructure AUG 11 - DEC 12 Parking A JUL12 – FEB 14 Hospital DEC 12 – JAN 16 Helipad JUN 13 – JUN 14 Parking B DEC 13 – MAR 15 ACPs MAR 14 – DEC 15 Landscaping MAR 14 – DEC 15 Q2 Q3 Q4 Q1 Q2 Q3 2013 Q4 Q1 Q2 Q3 2014 Q4 Q1 Q2 Q3 2015 Q4 Q1 Q2 Q3 2016 Q4 Q1 Q2 Q3 2017 Q4 Q1 Q2 Q3 Q4 Construction Duration HOSPITAL Current Quarter BLISS Legend REPLACEMENT – Water Tower Q1 2012 S4 BRIEFING 2011 *Dates subject to change FORT Construction in-Progress/Duration Construction Completion Initial Outfitting / Transition FOD – Facility Operations Date 6