Joint School District of Beloit Beloit City Council Meeting Monday, February 24, 2014 5 primary buildings ◦ ◦ ◦ ◦ ◦ Converse Robinson Hackett Todd Merrill The Swimming Pool Cunningham Intermediate School Gaston Primary School Fitness Center McNeel Aldrich Memorial Update as of January 29, 2014 Architect Renderings North-East Exterior Front View North-West Exterior Front View Architect Renderings West Exterior View South-West Exterior View Architect Renderings South-East Exterior View North-East Exterior View Site Layout Sidewalk Storage Building 16 x 16 4-6 Entrance Plaza 7/8 Entrance Dumpster Enclosure Hard Surface Play Site Plan First Floor First Floor= 70,242 SF Second Floor= 30,214 SF Total= 100,456 SF Second Floor First Floor= 70,242 SF Second Floor= 30,214 SF Total= 100,456 SF Site Clearing/Demolition: March/April 2014 Bid Date: April 17, 2014 Construction Start: April 30, 2014 Construction Complete: July 31, 2015 Tennis Courts Big Field between 6th and 4th Scoreboards New Storage for Football Propane Tank outside of Swimming Pool