“Incident Free Starts With ME” Day 2 – JO 2010 Field Safety areas of Improvement © Chevron 2005 DOC ID PTW – Areas for improvement ( based on 154 field surveys) Permit approver not involved in PTW, 34 Gas testing not appropriate, 26 Improper permit filling, 104 Tools/ Equipment not proper, 43 Inadequate Hazard recognition & control, 46 © Chevron 2005 Proper PPE not used, 29 Controls are not in place, 56 2 Improvement Sought Permit Issuing • Complete site preparation section. • Write your name and contact number in addition to signature in Permit approval section. • Inspect the worksite before issuing the permit • Close the permit immediately after completion of the job. • Retain the 2nd & 3rd copies with the Permit Issue section © Chevron 2005 • Hazard Recognition 3 Improvement Sought Hazard Recognition & Control • Using the Hazard ID Tool. • Completing Field JSA at site. • Making JSA specific for task being conducted. • Involving the work crew to identify hazards at the site. • Provide PPE as identified in JSA © Chevron 2005 4 Improvement Sought Confined Space certificates • Perform the initial gas test (MUST be done by the Operations staff) and follow up test ( by Permit User representative) • An Entry(Safety) Watch MUST be assigned for working in a pit deeper than 1.2 meter. He MUST sign and MUST understand and execute his responsibilities. • Prepare Rescue Plan © Chevron 2005 5 Improvement Sought Hot Work Certificates • Initial gas test MUST be done by the Operations staff • A Fire Watch MUST be assigned, MUST sign and MUST understand and execute his responsibilities diligently. • Check the fire extinguisher condition and inspection tag before putting in service © Chevron 2005 6 Improvement Sought Excavation • Provide proper cave –in protection ( sloping/ benching/ shoring) • Identify the underground utilities (cables , pipes etc.) • Provide sufficient means of access/ egress © Chevron 2005 7 Improvement Sought Isolation of hazardous energy ( LO TO) • Complete Isolation check list. • Use P&IDs to verify isolation. • Contractor to verify the isolation before starting the work. © Chevron 2005 8 Improvement Sought Lifting & Rigging © Chevron 2005 • Prepare Lifting plan • Use pre-use inspection check list for crane • Reject the lifting equipment if found damaged( especially web slings) • Check the validity of third party certificates for lifting equipment • Barricade off swing radius 9 Improvement Sought Radiography • Suspend other work permits • Use calibrated survey meter for area survey and film badge for individuals © Chevron 2005 10 Improvement Sought Vehicles/ Equipment • Use pre use check list • Check ELCB( GFCI) condition before use. © Chevron 2005 11 Useful information on Field Safety • A “ Field Safety-Tools Webpage” containing over 54 necessary documents is available concerning Safe Work Practices, related JOSOPs, and Frequently asked questions. Link to the website http://jopweb.jop.chevrontexaco.net/MSW/ http://jopcontractors.chevron.com • © Chevron 2005 We have two full time Safety Trainers, regular safety training classes are being conducted in English and Arabic. Please check the jopweb page for regular updates on safety training and participate in this training. 12