AOCM Presentation
Nov 30, 2011
Jim Strukalo – NAV CANADA Project Manager jim.strukalo@navcanada.ca
1
To maintain or enhance the level of safety within the new airspace system.
To renew the airspace and procedures in Alberta and update our systems in support of the new parallel runway in Calgary,
To update the NAV CANADA airspace system to take full advantage of current and planned technologies that will enable our customers to utilize the latest in flight deck technologies and
To complete the development and design of the project by May 2013 for implementation and opening of the new runway in May of 2014 .
2
Calgary Parallel Runway Ops – May 2014
CYEG
CYYC
4
Fully collaborative design process.
Technical Design Working Group established, to facilitate the design process
Customer technical representatives (Pilots), Air Traffic Controllers and Planning
Specialists
Additional consultation through individual and/or AASP group meetings:
Customers
Air Carriers
Oil Sands and Additional Corporate
Flight Training and Recreational
Airport Authorities
Calgary, Edmonton
Additional Stakeholders
Adjacent Facilities – WG, VR, FAA (SEA, SLC)
TC
NAV CANADA Departments – AIS, Airspace Design Specialists, Procedures, Simulators
Communities
55
Business Case – nearing completion
4 Options Developed – based on bedpost design
STARs for the 4 options in draft
Circulated amongst Design Working Group
Upcoming design meeting to get feedback on STARs
Enroute phase of flight - designs work in progress
6
Meet with Design Working Group to review YC terminal designs.
Finalize Option Cases – (4)
Fast Time simulation of Option Cases to evaluate efficiencies to Base Case.
Narrow the design to 1 or 2 and focus on these for final efficiency determination.
Further business case analysis.
Finalize Enroute portions of plans.
7
' 11
6/1/11
6/1/11
AASP Project Kickoff
6/1/11
Stakeholder Meeting
6/23/11
Stakeholder/DWG Meeting
8/24/11
2011
Jun
9/12/11
10/1/11
10/3/11
Oct
Today
2012
Feb
Final Bedpost Location
5/31/12
2013
Jun Oct Feb
Design Complete/Lockdown
5/31/13
AIS Submission
6/3/13
Jun Oct
2014
Feb
Design Development 5/31/13
SMS
Communications Planning
Aero Studies 2/28/13
Staff Planning TCU & Twr
6/30/14
5/30/14
5/30/14
1/1/13
4/1/13
Procedures Design 12/31/13
AIS Management & Q.C.
5/29/14
9/1/13 Training Design 4/30/14
1/1/14 Training Delivery 5/29/14
Runway Opening
5/29/14
30 Day SMS Review
6/30/14
60 Day SMS Review
7/31/14
Jun
' 14
Timelines - driven by CYXD and CZVL milestones.
Current Project Activities
Stakeholder Identification
Review of current airspace structure
Identification of operational opportunities for both Customers and ANSP
Areas of Initial Consideration
A review of the utilization of the airspace to the North and Northeast of CYXD; since RWY
16-34 has been closed.
A feasibility review of resizing the size of Class C airspace, with the closure of CYXD, and a goal of increased access to this airspace. i.e. the Chipman Soaring Area
Assurance that any new approaches are kept within controlled airspace and the impact this will have on future designs.
Collaborative Approach
To determine requirements and constraints of Stakeholders.
Communication and coordination for customer feedback is a project requirement.
9
Time to Update the System?
10