Florida Citrus Bowl Re-Construction

advertisement
Florida Citrus Bowl
Re-Construction
February 12, 2013
Project Topics
 Citrus Bowl History & Events
 Target Accomplishments
 Reconstruction Highlights
 Project Team
 Project Status/ Schedule
 Plans & Renderings
 Q&A
Citrus Bowl History
 Originally call Orlando Stadium and constructed as a Works Project
Administration project during Franklin Roosevelt’s administration in
1936 with a capacity of 8,900
 The stadium was renamed the Tangerine Bowl during a renovation
in 1947 adding 2,000 seats
 5,000 more seats were added in 1968, along with the first press
box.
 The stadium underwent an expansion from 1974 to 1976, to bring
the total seating capacity to 50,000
 After re-naming the stadium in 1983 to the Florida Citrus Bowl, a
capacity of 65,438 was established in 1989, after a $38 million
renovation that added the upper decks.
 1999-2002 improvements included escalators, seat bottoms and a
new video board.
 AstroTurf added in 2010 during a $10M renovation
 Current Capacity is 70,000
Florida Citrus Bowl Major Events
 Four major events held each year from early November
to late January
 Florida Classic between Bethune-Cookman University
and Florida A&M University
 Russel Athletic Bowl
 Capital One Bowl (New Years Day)
 Monster Jam (Monster Truck Event)
Why Renovate?
 City of Orlando and Florida Citrus Sports officials expect
the reconstruction to generate a $300 million annual
economic impact from new events
 Reconstruction will allow the stadium to host college and
pre-season NFL neutral site football games, international
soccer games, WrestleMania, monster truck and
motocross events, music festivals, state football
championships, band competitions and lacrosse
tournaments
 Rebranding of the stadium’s regional and national image
 Funding approved as part of $1.1 Billion Downtown
Orlando Centroplex Program
Renovation Highlights
 The stadium will undergo a $178 million reconstruction
project, set to be complete in March/ April 2015
 Under the reconstruction plan, 80% of the existing
stadium will be demolished and reconstructed
 New 360-degree Main Concourse with wide concourse
and improved que-ing areas
 New stadium seating in lower bowl including individual
seats on sidelines and bleachers with backs in endzones
 Six more inches of leg-room in bowl lower and club level
seating bowls
 New team Facilities and Operations areas on Main
Concourse
Renovation Highlights (Cont.)
 New 360-degree Club Level with Clubs on east and west
sidelines, party deck in north endzone
 Updated Suites and Press boxes
 10 new suites and potential “Super-Suite” on west side
 New waterproofing on Upper seating bowl and concourse
to protect finishes below
 New vertical Circulation
 New exterior façade with decorative metal panels
 Update Sound System
 New Video Displays
 Site improvements with new entries
Project Team
 HNTB Corporation (Kansas City) has been Contracted by
the City for Design Services. Firm has almost 100 years
and multiple stadiums of experience (including recent
similar renovations)
 City has aquired SC Advisors as the Owner’s Rep (SCAdvisors also served as Owner’s Rep for the Orlando
Magic on Amway center)
 Program Manager procurement took place in January
with City Council approval on February 5th to negotiate
with Firms in order of Ranking
Project Team (Continued)
 Construction Manager Procurement will consist of a twopart RFQ/ RFP Process (similar to Amway and DPAC
Projects)
 RFQ/ RFP will be advertised on February 24th and
available for download on February 25th
 RFQ will be due in let March with shortlisting shortly
following
 Rankings are projected to be presented to City Council
on May 5th
Design/ Procurement Status
 The design for the re-construction is in the Schematic
Design Phase.
 Early packages are expected to be released in July timeframe including the following:
 Underground Utilities
 Foundations
 Steel and Concrete structures
 Pre-cast Stadia
 Vertical Transportation
 Procurement of these packages anticipated in August/
September
 Possible Design Assist packages for MEP
 Balance of Design anticipated to be complete at end of
2013 with Procurement immediately following
Project Strategy
 Complete as much work as possible prior to and during
the November 2013 – January 2014 events
 Decommissioning and demolition of lower two seating
bowls begins immediately following Monster Jam in
January 2014
 Two crews working on structure and seating bowls
 Finish work where possible during demo/ structural work
 Outbuildings, operations and team facilities work
following structure/ seating bowl
 Majority of work to be completed by November 2014
with final completion in the January 2015 – March 2015
timeframe
Main Concourse Base Plan
Main Concourse Base Plan
Main Concourse Base Plan
Main Concourse Base Plan
Main Concourse Base Plan
Main Concourse Base Plan
Exterior (NE Corner) Rendering
New Upper Concourse Access
New Vertical Transportation
Main Concourse Base Plan
Alternate Rendering
Q&A
Download