PROJECT NAME: TDE DELTA PROJECT DOCUMENT TITLE: INSPECTION AND TEST PLAN ELECTRICAL PROJECT DOCUMENT: TDE - ZTE - RFA - ELECT – ITP - 001 INSPECTION AND TEST PLAN Project Title : TDE DELTA PROJECT Discipline/Works : ELECTRICAL Project Document : TDE-ZTE-RFA-ELECT-ITP-E001 Date : 06 December 2025 THIS INSPECTION AND TEST PLAN COMPRISES THE FOLLOWING DOCUMENTS AND IS APPROVED FOR USE: PART 1 INSPECTION & TEST PLAN PART 2 TDE-ZTE-RFA-ELECT-ITP-E001 (0.415kV CABLE INSTALLATION) TDE-ZTE-RFA-ELECT-ITP-E002 (20kV CABLE INSTALLATION) TDE-ZTE-RFA-ELECT-ITP-E003 (UPS INSTALLATION) TDE-ZTE-RFA-ELECT-ITP-E004 (POWER DISTRIBUTION CABINET INSTALLATION) TDE-ZTE-RFA-ELECT-ITP-E005 (BATTERY CABINET INSTALLATION) TDE-ZTE-RFA-ELECT-ITP-E006 (TRANSFORMER CABINET INSTALLATION) TDE-ZTE-RFA-ELECT-ITP-E007 (BUSDUCT INSTALLATION) TDE-ZTE-RFA-ELECT-ITP-E008 (FORM LIGHTING INSTALLATION) TDE-ZTE-RFA-ELECT-ITP-E009 (SOCKET & SWITCH INSTALLATION) TDE-ZTE-RFA-ELECT-ITP-E010 (GROUNDING BUSBAR INSTALLATION) TDE-ZTE-RFA-ELECT-ITP-E011 (LADER & TRAY INSTALLATION) TDE-ZTE-RFA-ELECT-ITP-E012 (CABLE CONTAINMENT SUPPORT INSTALLATION) Reference Documentation : - Client Spesification - Method of Statement - Material Approval - Manufacture's Data Sheet JOB CHECK LIST FORM 0.415kV CABLE INSTALLATION PROJECT : NEUTRA DATA CENTRE Date Report No Level/ Room Drawing No. Approval material MOS : : : No. : : : Not OK = ❌ OK = ✔ Consultant ZTE TDE Job Description Notes COMPELETE DATA 1 Shop drawing approval 2 Methode of statement 3 Approval Material 4 Factory Acepted Test 5 Incoming Material Check List ⬜ ⬜ ⬜ ⬜ ⬜ ⬜ ⬜ ⬜ ⬜ ⬜ ⬜ ⬜ ⬜ ⬜ ⬜ CHECKING 1 Check cable specification as approved on cable schedule/drawings. ⬜ ⬜ ⬜ 2 Check that preservation are in good conditions (no damage, no wounded, end cup installed etc.). ⬜ ⬜ ⬜ 3 Check that cable is correctly positioned, aligned, proper length and secured in accordance with approved cable schedule. ⬜ ⬜ ⬜ 4 Ensure there is no joint/splicing point on cable. ⬜ ⬜ ⬜ 5 Check that cable laying proper (phase squence, bending radius, tighting on tray .etc) ⬜ ⬜ ⬜ 6 Check that cable penetration on cabinet proper (tight gland, bending radius, no wonded, and torque if applicable) ⬜ ⬜ ⬜ 7 Check that cable termination proper (proper clamp, proper contact, fix terminal, lug isolated, tangging) ⬜ ⬜ ⬜ 8 Electric test required (indifidual electric test: Continuity test and IR Test) ⬜ ⬜ ⬜ 9 Check that equipment instaled with proper protection (from water, dust, humidity) ⬜ ⬜ ⬜ 10 Check that earthing cable connected in accordance with approved drawings. ⬜ ⬜ ⬜ 11 12 13 14 15 NOTE : ⬜ ⬜ A. Approved PT. ZTE INDONESIA Date: Name: Position: Consultant Sign ⬜ A. Complete Data Date: Name: Position: B. Not Approved PT. TELKOM DATA EKOSISTEM (TDE) Sign Date: Name: Position: Sign ⬜ B. Incomplete Data 1 JOB CHECK LIST FORM 20kV CABLE INSTALLATION PROJECT : NEUTRA DATA CENTRE Date Report No Level/ Room Drawing No. Approval material MOS : : : No. : : : Not OK = ❌ OK = ✔ Consultant ZTE TDE Job Description Notes COMPELETE DATA 1 Shop drawing approval 2 Methode of statement 3 Approval Material 4 Factory Acepted Test 5 Incoming Material Check List ⬜ ⬜ ⬜ ⬜ ⬜ ⬜ ⬜ ⬜ ⬜ ⬜ ⬜ ⬜ ⬜ ⬜ ⬜ CHECKING 1 Check cable specification as approved on cable schedule/drawings. ⬜ ⬜ ⬜ 2 Check that preservation are in good conditions (no damage, no wounded, end cup installed etc.). ⬜ ⬜ ⬜ 3 Check that cable is correctly positioned, aligned, proper length and secured in accordance with approved cable schedule. ⬜ ⬜ ⬜ 4 Ensure there is no joint/splicing point on cable. ⬜ ⬜ ⬜ 5 Check that cable penetration on cabinet proper (tight gland, bending radius, no wonded) ⬜ ⬜ ⬜ 6 Check that cable termination proper (proper clamp, proper contact, fix terminal, lug isolated, tangging, torque, and supported without stressed to cable) ⬜ ⬜ ⬜ 7 Check that cable laying proper (phase squence, bending radius, tighting on tray .etc) ⬜ ⬜ ⬜ 8 Electric test required (indifidual electric test: Continuity test, IR Test, and Hi-Pot Test) ⬜ ⬜ ⬜ 9 Check that equipment instaled protect proper (from water, dust, humidity) ⬜ ⬜ ⬜ 10 Check that armored cable as earthing cable connected in accordance with approved drawings. ⬜ ⬜ ⬜ 11 Inspect stress relief sleeving and cone installation as per standard ⬜ ⬜ ⬜ 12 13 14 15 NOTE : ⬜ ⬜ A. Approved PT. ZTE INDONESIA Consultant Sign Date: Name: Position: ⬜ A. Complete Data Date: Name: Position: B. Not Approved PT. TELKOM DATA EKOSISTEM (TDE) Sign Sign Date: Name: Position: ⬜ B. Incomplete Data 2 JOB CHECK LIST FORM UPS INSTALLATION PROJECT : NEUTRA DATA CENTRE Date Report No Level/ Room Drawing No. Approval material MOS : : : No. : : : Not OK = ❌ OK = ✔ Consultant ZTE TDE Job Description Notes COMPELETE DATA 1 Shop drawing approval 2 Methode of statement 3 Approval Material 4 Factory Acepted Test 5 Incoming Material Check List ⬜ ⬜ ⬜ ⬜ ⬜ ⬜ ⬜ ⬜ ⬜ ⬜ ⬜ ⬜ ⬜ ⬜ ⬜ CHECKING 1 Compare Equipment Indentification with approved documents/drawings and confirm no deviation. ⬜ ⬜ ⬜ 2 Check that preservation are in good conditions (no damage, no rust, no undue accumulation of dust and dirt, no condensation etc.). ⬜ ⬜ ⬜ 3 Check that equipment is correctly positioned, aligned, leveled, rigid and secured in accordance with approved vendor drawings and construction drawings. ⬜ ⬜ ⬜ 4 Check all Equipment mounted devices in accordance with approved drawings (lock, torque, etc.) ⬜ ⬜ ⬜ 5 Check all Accesories proper installations in accordance (indicator, display .etc) ⬜ ⬜ ⬜ 6 Check all earthing and bonding has been connected in accordance with approved construction drawings. ⬜ ⬜ ⬜ 7 Check that power cables proper connections (no damage, within allowed cable bending radius, proper cable supports, cable gland tightness, proper terminating, corect color, tagging). ⬜ ⬜ ⬜ 8 Electric test required (individual electric test) ⬜ ⬜ ⬜ 9 Check that equipment instaled protect proper (from water, dust, humidity) ⬜ ⬜ ⬜ 10 Check all internal cabling/wiring includes identification, which installed at site as par drawings, if applicable ⬜ ⬜ ⬜ 11 Check cleanliness inside cable terminal box and panel ⬜ ⬜ ⬜ 12 13 14 15 NOTE : ⬜ ⬜ A. Approved PT. ZTE INDONESIA Consultant Sign Date: Name: Position: ⬜ A. Complete Data Date: Name: Position: B. Not Approved PT. TELKOM DATA EKOSISTEM (TDE) Sign Sign Date: Name: Position: ⬜ B. Incomplete Data 3 JOB CHECK LIST FORM POWER DISTRIBUTION CABINET INSTALLATION PROJECT : NEUTRA DATA CENTRE Date Report No Level/ Room Drawing No. Approval material MOS : : : No. : : : Not OK = ❌ OK = ✔ ZTE Consultant TDE Job Description Notes COMPELETE DATA 1 Shop drawing approval 2 Methode of statement 3 Approval Material 4 Factory Acepted Test 5 Incoming Material Check List ⬜ ⬜ ⬜ ⬜ ⬜ ⬜ ⬜ ⬜ ⬜ ⬜ ⬜ ⬜ ⬜ ⬜ ⬜ CHECKING 1 Compare Equipment Indentification with approved documents/drawings and confirm no deviation. ⬜ ⬜ ⬜ 2 Check that preservation are in good conditions (no damage, no rust, no undue accumulation of dust and dirt, no condensation etc.). ⬜ ⬜ ⬜ 3 Check that equipment is correctly positioned, aligned, leveled, rigid and secured in accordance with approved vendor drawings and construction drawings. ⬜ ⬜ ⬜ 4 Check all equipment mounted devices in accordance with approved drawings (Busbar, lock, torque, etc.) ⬜ ⬜ ⬜ 5 Check all accesories proper installations in accordance (indicator, front switch, tagging) ⬜ ⬜ ⬜ 6 Check all earthing and bonding has been connected in accordance with approved construction drawings. ⬜ ⬜ ⬜ 7 Check that power cables proper connections (no damage, within allowed cable bending radius, proper cable supports, cable gland tightness, proper terminating, corect color, tagging). ⬜ ⬜ ⬜ 8 Check no loose connection for all internal wires. ⬜ ⬜ ⬜ 9 Check that equipment instaled protect proper (from water, dust, humidity) ⬜ ⬜ ⬜ 10 Electric test required (individual electric test) ⬜ ⬜ ⬜ 11 Check circuit diagram hard copy placed in cabinet, if applicable ⬜ ⬜ ⬜ 12 Check ratings (voltage, current) for breaker, contactor and fuse as per drawing. ⬜ ⬜ ⬜ 13 Check all unused holes are sealed, installed certified blind plug. ⬜ ⬜ ⬜ 14 15 NOTE : ⬜ ⬜ A. Approved PT. ZTE INDONESIA Consultant Sign Date: Name: Position: ⬜ A. Complete Data Date: Name: Position: B. Not Approved PT. TELKOM DATA EKOSISTEM (TDE) Sign Sign Date: Name: Position: ⬜ B. Incomplete Data 4 JOB CHECK LIST FORM BATTERY CABINET INSTALLATION PROJECT : NEUTRA DATA CENTRE Date Report No Level/ Room Drawing No. Approval material MOS : : : No. : : : Not OK = ❌ OK = ✔ ZTE Consultant TDE Job Description Notes COMPELETE DATA 1 Shop drawing approval 2 Methode of statement 3 Approval Material 4 Factory Acepted Test 5 Incoming Material Check List ⬜ ⬜ ⬜ ⬜ ⬜ ⬜ ⬜ ⬜ ⬜ ⬜ ⬜ ⬜ ⬜ ⬜ ⬜ CHECKING 1 Compare Equipment Indentification with approved documents/drawings and confirm no deviation. ⬜ ⬜ ⬜ 2 Check that preservation are in good conditions (no damage, no rust, no undue accumulation of dust and dirt, no condensation etc.). ⬜ ⬜ ⬜ 3 Check that equipment is correctly positioned, aligned, leveled, rigid and secured in accordance with approved vendor drawings and construction drawings. ⬜ ⬜ ⬜ 4 Check all Equipment mounted devices in accordance with approved drawings (lock, torque, battery cell sequence, etc.) ⬜ ⬜ ⬜ 5 Check all Accesories proper installations in accordance (indicator, display .etc) ⬜ ⬜ ⬜ 6 Check all earthing and bonding has been connected in accordance with approved construction drawings. ⬜ ⬜ ⬜ 7 Check that battery module on proper condition (no lakage, fix, isolated) ⬜ ⬜ ⬜ 8 Check that Power cables proper connections (no damage, within allowed cable bending radius, proper cable supports, cable gland tightness, proper terminating, corect color, tagging). ⬜ ⬜ ⬜ 9 Electric test required (individual electric test) ⬜ ⬜ ⬜ 10 Check that breaker on Off position (durring inspection) ⬜ ⬜ ⬜ 11 Check that equipment instaled protect proper (from water, dust, humidity) ⬜ ⬜ ⬜ 12 Check all unused holes are sealed, installed certified blind plug, and unused terminal pole is attached with plug. ⬜ ⬜ ⬜ 13 14 15 NOTE : ⬜ ⬜ A. Approved PT. ZTE INDONESIA Consultant Sign Date: Name: Position: ⬜ A. Complete Data Date: Name: Position: B. Not Approved PT. TELKOM DATA EKOSISTEM (TDE) Sign Sign Date: Name: Position: ⬜ B. Incomplete Data 5 JOB CHECK LIST FORM TRANSFORMER CABINET INSTALLATION PROJECT : NEUTRA DATA CENTRE Date Report No Level/ Room Drawing No. Approval material MOS : : : No. : : : Not OK = ❌ OK = ✔ ZTE Consultant TDE Job Description Notes COMPELETE DATA 1 Shop drawing approval 2 Methode of statement 3 Approval Material 4 Factory Acepted Test 5 Incoming Material Check List ⬜ ⬜ ⬜ ⬜ ⬜ ⬜ ⬜ ⬜ ⬜ ⬜ ⬜ ⬜ ⬜ ⬜ ⬜ CHECKING 1 Compare Equipment Indentification with approved documents/drawings and confirm no deviation. ⬜ ⬜ ⬜ 2 Check that preservation are in good conditions (no damage, no rust, no undue accumulation of dust and dirt, no condensation etc.). ⬜ ⬜ ⬜ 3 Check that equipment is correctly positioned, aligned, leveled, rigid and secured in accordance with approved vendor drawings and construction drawings. ⬜ ⬜ ⬜ 4 Check all Equipment mounted devices in accordance with approved drawings (lock, torque, etc.) ⬜ ⬜ ⬜ 5 Check all Accesories installation matched as per approved drawing (enclosure, display .etc) ⬜ ⬜ ⬜ 6 Check all earthing and bonding in accordance with approved construction drawings. ⬜ ⬜ ⬜ 7 Check that MV Power side proper connections (no damage, within allowed cable bending radius, proper cable supports, cable gland tightness, proper terminating, corect color, tagging). ⬜ ⬜ ⬜ 8 Check that LV Power side proper connections (no damage, proper supports, proper insulated, proper terminating, corect color, tagging). ⬜ ⬜ ⬜ 9 Electric test required (individual electric test) ⬜ ⬜ ⬜ 10 Check that equipment instaled protect proper (from water, dust, humidity) ⬜ ⬜ ⬜ 11 Check cleanliness inside cable terminal box and panel. ⬜ ⬜ ⬜ 12 Check caution & danger notices and instruction plates provided. ⬜ ⬜ ⬜ 13 Check cooling fans installed (rotation, support etc.) as per drawing, if applicable. ⬜ ⬜ ⬜ 14 Check all internal cabling/wiring includes identification, which installed at site as par drawings, if applicable. And there is no lose connections. ⬜ ⬜ ⬜ 15 NOTE : ⬜ ⬜ A. Approved PT. ZTE INDONESIA Consultant Sign Date: Name: Position: ⬜ A. Complete Data Date: Name: Position: B. Not Approved PT. TELKOM DATA EKOSISTEM (TDE) Sign Sign Date: Name: Position: ⬜ B. Incomplete Data 6 JOB CHECK LIST FORM TRANSFORMER CABINET INSTALLATION PROJECT : NEUTRA DATA CENTRE : : : Date Report No Level/ Room No. Drawing No. Approval material MOS : : : Not OK = ❌ OK = ✔ Consultant ZTE TDE Job Description Notes COMPELETE DATA 1 Shop drawing approval 2 Methode of statement 3 Approval Material 4 Factory Acepted Test 5 Incoming Material Check List ⬜ ⬜ ⬜ ⬜ ⬜ ⬜ ⬜ ⬜ ⬜ ⬜ ⬜ ⬜ ⬜ ⬜ ⬜ CHECKING 1 Compare Busbar Indentification with approved documents/drawings and confirm no deviation. ⬜ ⬜ ⬜ 2 Check that preservation are in good conditions (no damage, no wounded, end cover installed etc.). ⬜ ⬜ ⬜ 3 Electric test before installation (Insulation Resistance test) ⬜ ⬜ ⬜ 4 Check that busbar laying in correctly positioned, aligned and secured in accordance with approved drawing. ⬜ ⬜ ⬜ 5 Check that busbar jointing proper (phase squence, contact survace, torque .etc) ⬜ ⬜ ⬜ 6 Check that outdoor busbar isolation at jointing proper (thickness, clearance .etc) ⬜ ⬜ ⬜ 7 Check that busbar penetration on cabinet proper (cover, phase sequence, tighted, color indentification) ⬜ ⬜ ⬜ 8 Electric test required (IR and CR test) ⬜ ⬜ ⬜ 9 Check that equipment instaled protected with proper (from water, dust, humidity) ⬜ ⬜ ⬜ 10 Ensure busbar specification matched as per approved drawing and specification. ⬜ ⬜ ⬜ 11 Busduct installation supported well following as per specification and approved drawing. ⬜ ⬜ ⬜ 12 check there is no strains and stresses on the bus bars and housings. ⬜ ⬜ ⬜ 13 14 15 NOTE : ⬜ ⬜ A. Approved PT. ZTE INDONESIA Consultant Sign Date: Name: Position: ⬜ A. Complete Data Date: Name: Position: B. Not Approved PT. TELKOM DATA EKOSISTEM (TDE) Sign Sign Date: Name: Position: ⬜ B. Incomplete Data 7 JOB CHECK LIST FORM LIGHTING INSTALLATION PROJECT : NEUTRA DATA CENTRE Date Report No Level/ Room Drawing No. Approval material MOS : : : No. : : : Not OK = ❌ OK = ✔ Consultant ZTE TDE Job Description Notes COMPELETE DATA 1 Shop drawing approval 2 Methode of statement 3 Approval Material 4 Factory Acepted Test 5 Incoming Material Check List ⬜ ⬜ ⬜ ⬜ ⬜ ⬜ ⬜ ⬜ ⬜ ⬜ ⬜ ⬜ ⬜ ⬜ ⬜ CHECKING 1 Compare lamp Indentification with approved documents/drawings and confirm no deviation. ⬜ ⬜ ⬜ 2 Check that preservation are in good conditions (no damage, no scratches, end dry condition etc.). ⬜ ⬜ ⬜ 3 Check that lighting fixture type is correctly positioned, aligned, level, tighted and secured in accordance with approved drawing. ⬜ ⬜ ⬜ 4 Check that lighting group proper (phase group, connection point, tagging .etc). ⬜ ⬜ ⬜ 5 Check that lighting sensor on proper position (level, direction, connection). ⬜ ⬜ ⬜ 6 Check that lighting body part connected to ground. ⬜ ⬜ ⬜ 7 Electric test required (individual electric test). ⬜ ⬜ ⬜ 8 Check that equipment instaled protect proper (from water, dust, humidity). ⬜ ⬜ ⬜ 9 Check termination kit and materials are installed in accordance with project specification. ⬜ ⬜ ⬜ 10 Ensure cable route is comply with specification and as per approved drawing. ⬜ ⬜ ⬜ 11 No hazards from other equipment (e.g. moving parts, hot surface etc.). ⬜ ⬜ ⬜ 12 13 14 15 NOTE : ⬜ ⬜ A. Approved PT. ZTE INDONESIA Consultant Sign Date: Name: Position: ⬜ A. Complete Data Date: Name: Position: B. Not Approved PT. TELKOM DATA EKOSISTEM (TDE) Sign Sign Date: Name: Position: ⬜ B. Incomplete Data 8 JOB CHECK LIST FORM SOCKET & SWITCH INSTALLATION PROJECT : NEUTRA DATA CENTRE Date Report No Level/ Room Drawing No. Approval material MOS : : : No. : : : Not OK = ❌ OK = ✔ Consultant ZTE TDE Job Description Notes COMPELETE DATA 1 Shop drawing approval 2 Methode of statement 3 Approval Material 4 Factory Acepted Test 5 Incoming Material Check List ⬜ ⬜ ⬜ ⬜ ⬜ ⬜ ⬜ ⬜ ⬜ ⬜ ⬜ ⬜ ⬜ ⬜ ⬜ CHECKING 1 Compare socket & switch Indentification and specification with approved documents/drawings and confirm no deviation. ⬜ ⬜ ⬜ 2 Check that preservation are in good conditions (no damage, no scratches, dry condition etc.). ⬜ ⬜ ⬜ 3 Check that socket & switch type is correctly positioned, aligned, level, fixed and secured in accordance with approved drawing. ⬜ ⬜ ⬜ 4 Check that socket & switch group proper (phase group, connection point, tagging .etc) ⬜ ⬜ ⬜ 5 Check that socket & switch body part connected to ground. ⬜ ⬜ ⬜ 6 Electric test requiret (indifidual electric test) ⬜ ⬜ ⬜ 7 Check that equipment instaled protect proper (from water, dust, humidity) ⬜ ⬜ ⬜ 8 9 10 11 12 13 14 15 NOTE : ⬜ ⬜ A. Approved PT. ZTE INDONESIA Consultant Sign Date: Name: Position: ⬜ A. Complete Data Date: Name: Position: B. Not Approved PT. TELKOM DATA EKOSISTEM (TDE) Sign Sign Date: Name: Position: ⬜ B. Incomplete Data 9 JOB CHECK LIST FORM GROUNDING BUSBAR INSTALLATION PROJECT : NEUTRA DATA CENTRE Date Report No Level/ Room Drawing No. Approval material MOS : : : No. : : : Not OK = ❌ OK = ✔ Consultant ZTE TDE Job Description Notes COMPELETE DATA 1 Shop drawing approval 2 Methode of statement 3 Approval Material 4 Factory Acepted Test 5 Incoming Material Check List ⬜ ⬜ ⬜ ⬜ ⬜ ⬜ ⬜ ⬜ ⬜ ⬜ ⬜ ⬜ ⬜ ⬜ ⬜ CHECKING 1 Compare grounding busbar Indentification with approved documents/drawings and confirm no deviation. ⬜ ⬜ ⬜ 2 Check that preservation are in good conditions (no damage, no scratches, dry condition etc.). ⬜ ⬜ ⬜ 3 Check that grounding busbar is correctly positioned, aligned, level, fixed and secured in accordance with approved drawing. ⬜ ⬜ ⬜ 4 Check that accesories install proper (isolator, bolt & nut, tagging .etc) ⬜ ⬜ ⬜ 5 Check that grounding group connecting proper. ⬜ ⬜ ⬜ 6 Electric test required (indifidual electric test) ⬜ ⬜ ⬜ 7 Check that equipment instaled protect proper (from water, dust, humidity) ⬜ ⬜ ⬜ 8 9 10 11 12 13 14 15 NOTE : ⬜ ⬜ A. Approved PT. ZTE INDONESIA Consultant Sign Date: Name: Position: ⬜ A. Complete Data Date: Name: Position: B. Not Approved PT. TELKOM DATA EKOSISTEM (TDE) Sign Sign Date: Name: Position: ⬜ B. Incomplete Data 10 JOB CHECK LIST FORM LADER & TRAY INSTALLATION PROJECT : NEUTRA DATA CENTRE Date Report No Level/ Room Drawing No. Approval material MOS : : : No. : : : Not OK = ❌ OK = ✔ Consultant ZTE TDE Job Description Notes COMPELETE DATA 1 Shop drawing approval 2 Methode of statement 3 Approval Material 4 Factory Acepted Test 5 Incoming Material Check List ⬜ ⬜ ⬜ ⬜ ⬜ ⬜ ⬜ ⬜ ⬜ ⬜ ⬜ ⬜ ⬜ ⬜ ⬜ CHECKING 1 Ensure that the cable route is comppleted and the tray route is free from any obstructions. ⬜ ⬜ ⬜ 2 Check that preservation are in good conditions (no damage, no scratches, dry condition etc.). ⬜ ⬜ ⬜ 3 Check that ladder & tray is correctly positioned, aligned, level, fixed and secured in accordance with approved drawing. ⬜ ⬜ ⬜ 4 Check that accesories install proper (jointing, bonding jumper .etc). ⬜ ⬜ ⬜ 5 Check that earth bonding of ladder & tray connected to ground. ⬜ ⬜ ⬜ 6 Check there is no sharp edges. ⬜ ⬜ ⬜ 7 Check all wall penetrations are sealed where necessary. ⬜ ⬜ ⬜ 8 Check fireproofing is installed as per drawings, if required. ⬜ ⬜ ⬜ 9 Check support is installed as per drawings. ⬜ ⬜ ⬜ 10 Check cable segregation and/or separator installation is meet with specification or drawings. ⬜ ⬜ ⬜ 11 Ensure cable tray & ladder is clean and there is no debris. ⬜ ⬜ ⬜ 12 Check cable tray support and touch up paint completed. ⬜ ⬜ ⬜ 13 14 15 NOTE : ⬜ ⬜ A. Approved PT. ZTE INDONESIA Consultant Sign Date: Name: Position: ⬜ A. Complete Data Date: Name: Position: B. Not Approved PT. TELKOM DATA EKOSISTEM (TDE) Sign Sign Date: Name: Position: ⬜ B. Incomplete Data 11 JOB CHECK LIST FORM CABLE CONTAINMENT SUPPORT INSTALLATION PROJECT : NEUTRA DATA CENTRE Date Report No Level/ Room Drawing No. Approval material MOS : : : No. : : : Not OK = ❌ OK = ✔ Consultant ZTE TDE Job Description Notes COMPELETE DATA 1 Shop drawing approval 2 Methode of statement 3 Approval Material 4 Factory Acepted Test 5 Incoming Material Check List ⬜ ⬜ ⬜ ⬜ ⬜ ⬜ ⬜ ⬜ ⬜ ⬜ ⬜ ⬜ ⬜ ⬜ ⬜ CHECKING 1 Cable containment support type are installed as per approved drawing and specification. ⬜ ⬜ ⬜ 2 Cable containment support location, dimmension, and level are installed as per approved drawing. ⬜ ⬜ ⬜ 3 Support accessories has been installed completely as per project specification. ⬜ ⬜ ⬜ 4 Ensure installed support is clean and touch-up pain has been applied, if required. ⬜ ⬜ ⬜ 5 Check all bolt and nut has been tightned. ⬜ ⬜ ⬜ 6 7 8 9 10 11 12 13 14 15 NOTE : ⬜ ⬜ A. Approved PT. ZTE INDONESIA Consultant Sign Date: Name: Position: ⬜ A. Complete Data Date: Name: Position: B. Not Approved PT. TELKOM DATA EKOSISTEM (TDE) Sign Sign Date: Name: Position: ⬜ B. Incomplete Data 12