Uploaded by Salman zaidi

assessment-guide

advertisement
lOMoARcPSD|39376716
Assessment Guide
Ece (Jawaharlal Nehru Technological University, Hyderabad)
Scan to open on Studocu
Studocu is not sponsored or endorsed by any college or university
Downloaded by Sam (zaidisaab11@gmail.com)
lOMoARcPSD|39376716
1Q. WHAT IS PTW SYSTEM?
A: (1) PTW SYSTEM IS AUTHORISED PEOPLE CONDUCT TO SPECIFIC PERSON AT SPECIFIC WORK AND TIME AT SPECIFIC
LOCATION.
(2) IT IS FORMAL AND LEGAL DOCUMENT
(3) ENSURE THAT MAINTAIN COMMUNICATION BETWEEN MANAGEMENT, SUPERVISOR, OPRATORS, WORK CREW.
2Q. WHY PTW SYSTEM?
A: PTW SYSTEM IN ENSURE THAT ALL NON-HAZARDIUOS WORKS CAN BE DONE IN SAFE MANNER.
3Q. WHO INVOLVE IN PTW SYSTEM? EXPLAIN AUTHORISATION LEVELS? EXPLAIN PTW LIFE CYCLE?
A: PTW APPLIED BY
PTW AUTHORISED BY
PTW AGREEMENT BY
PTW ACCEPT, SUSPENSION, CANCLE, COMPLETE BY
PTW VALID, CANCLE BY
ISO&DE ISO BY
PTW GAS TESTING BY
PTW AND ATTACHED DOCUMENTS QWALITY CHECKING
- PERMIT APPLICANT
- RESPONSIBLE SUPERVISOR
- OTHER AFFECTED COSTODION
-PERMIT HOLDER
-AREA AUTHORITY
-AREA AUTHORITY
-AUTHORISED GAS TESTER
- PTW COORDINATOR
4Q. TYPES OF PERMITS?
A: CLASS “A” TYPE PERMIT:
(1) 3 COPIES. 1st PINK WITH RED EDGE – WORK SITE
GREEN
- AREA AUTHORUTY (PERMIT ISSUE POINT)
WHITE
- RESPOSIBLE SUPERVISOR( FOR INFORMATION PURPOSE)
(2) NOTICE PERIOD 72 HOURS
(3) VALIDATION PERIOD 12 HOURS
(4) AUTHORISATION PERIOAD 14 DAYS
(5) ISSUE FOR HIGH RISK WORKS
(6) EX: CONFINED SPACE, HOT WORK IN PROCESS FACILITY,
CLASS “B” TYPE PERMIT:
(1) 3 COPIES. 1ST COPY BLUE COLOUR – WORK SITE
GREEN
- AREA AUTHORITY
WHITE
- RESPONSIBLE SUPERVISOR
(2) NOTICE PERIOD 24 HOURS
(3) VALIDATION PERIOD 12 HOURS
(4) AUTHORISATION PERIOAD 28 DAYS
(5) ISSUE FOR MIDIUM RISK WORKS
5Q. RESPONSIBILITIES OF PERMIT HOLDER:
A:
(1)UNDERSTAND THE WORK CONTENT AND REQUERMENTS OF JOB HSE PLAN.
(2) TELL TO WORK PARTY ABOUT THE WORK CONTENT AND REQUERMENTS OF JOB HSE PLAN
(3) ENSURE THAT ALL CREW MEMBERS UNDERSTAND THE JOB HSE PLAN AND WHAT IS REQUEREMENT
(4) ENSURE THAT PERMIT VALIDATION BEFORE STARTING THE WORK DAILY
(5) DISPLAY PTW AT SITE
(6) PREEPAIR TRIC AND CONDUCT TBT
Downloaded by Sam (zaidisaab11@gmail.com)
lOMoARcPSD|39376716
(7) TELL TO WORK PARTY ABOUT HARZARD AND CONTROLS OF THE WORK
(8) EXPLAIN ERP,ASSEMBLY POINT ,PRECAUTIONS
(9) CONDUCT PAUSE AND CHECK
(10)CONTINUESLY SUPERVISORING TO WORK CREW
RESPONSIBILITIES OF PERMIT APPLICANT:
(1) RECEIVE WORK SCOPE FROM THE PROJECT ENGINNER AND PLANNING ENGINEER
(2) MAKE A SITE VISIT TO UNDERSTAND THE SCOPE,LOCATION AND WHAT RESOURCES ARE NEEDED
(3) PREPARE THE PERMIT, INCLUDE THE JOB HSE PLAN, HRA PERMIT QUALITY, CHECK LIST,DRAWINGS AND
REQUIRED CERTIFICATE NEEDED FOR THE JOB
(4) AUTHORISE THE PERMIT FROM AREA RESPONSIBLE SUPERVISOR
(5) MAKE A STE VISIT ALONG WITH THE PERMIT HOLDER AND EXPLAIN THE CONTENT, HAZARDS ASSOCIATED WITH
THE JOB AND THE CONTROLS NEEDED IN PLACE
(6) MAKE PERIODIC SITE VISIT TO THE LOCATION WHICH YOU APPLIED A PERMIT FOR
(7) YOU OVERALL RESPONSIBLE FOR THE JOB FROM THE START TO END
CONDITIONS FOR CHANGE OVER THE PERMIT HOLDER:
(1) WHITHIN PROCESS FACILITY BOTH PERMT HOLDER MUST BE OBTAIN THE AREA AUTHORITY OPPROVAL TO
CHARGE AND THE OUTGOING PERMIT HOLDER WILL SOGN 10C AND WILL SUSPEND , NEW PERMIT HOLDER
WILL SIGN BOX 10B OF BOTH COPIES OF THE PERMIT OF ACCEPTANCE.
(2) AR REMOTE LOCATION WHERE HE IS UNABLE TO REACH AREA AUTHORITY SO THEY WILL CONTACT WITH AREA
AUTHORITY BY CELL PHONE AND TAKE APPROVAL THAN OUTGOING HOLDER WILL SIGN 10C AND WILL SUSPEND
(3) THE OUTGOING PERMIT HOLDER CANT LEAVE THE SITE WHEN EVER HAS FULLY BRIEFED THE CREW PERMIT
HOLDER AND THE NEW PERMIT HOLDER HAS SIGNED TO ACCEPT THE PERMIT IN HIS PRESENCE
6Q. PRINCIPLE OF PTW?
A: IT IS MANDOTARY DOCUMENT WHICH ALLOWS TO RESPONCIBLE SUPERVISOR, APPLICANT, TO USE OF A FRAME
WORK OF QUESTION TO IDENTIFY IF A PTW REQUERED
7Q. FACTORS OF PTW:
(1)
(2)
(3)
(4)
DETIFINATION OF PTW
SCOPE
OBJECTIVE
PRINCIPLE OF PTW
8Q. WHEN WE SUSPEND PTW?
A: (1)VALIDATION PERIOD EXPIRED
(2) ANY UNSAFE CONDITION DEVELOPS
(3) WORK WITH HIGHER PRIORITY THAN THIS WORK
(4) EMERGENCY EVACUATION
(5) DELAY WORK MORE TRAHN 4 HOURS
9Q. WHEN WE CANCLE THE PTW?
A: (1) AUTHORISATION PERIOD EXPIRED
(2) WORK COMPLETE
(3) WORK NOT COMPLETE
(4) WORK DISCRIPTION DIFFERENT THAN SITE SITUATION
Downloaded by Sam (zaidisaab11@gmail.com)
lOMoARcPSD|39376716
10Q. DOCUMENTS WITH PTW?
A: JOB SAFETY PALN, TRIC, HRA, PTW CHECK LIST, PAUSE AND CHECK, RELATED DRAWINGS
11Q. WHAT WILL YOU CHECK IN PTW?
A. PERMIT TYPE,DRAWING, DATES,SIGN,PERMIT NUMBER,LOCATION,WORK DESCRIPTION,ATTACHED
CERTIFICATES,JOB HSE PLAN,TRIC CARD,PROCRDURES.
12Q. WHEN PERMIT REQUIRED:
(1)
(2)
(3)
(4)
(5)
(6)
WORK WITHIN PROCESS FACILITY
WORK WITHIN EPZ
ELECTRICAL INSTALLATION
WORK WITHIN HYDRO CARBON AREA
WORK IS CONFINED SPACE
IS ADDITIONAL CERTIFICATES REQUIRED TO WORK
13Q. WHEN PTW NOT REQUIRED?
(1) FAMILIER TO WORK FORCE
(2) CONFITENTED SUPERVISOR
(3) WRITTEN PROCESSOR FOR WORK
1Q. WHAT IS H2S? AND PROPERTIES?
A:
(1) H2S MEANS HYDROGEN SULPHIDE, IS HIGHLY TOXIC GAS
(2) HEVIER THAN AIR
(3) EASILY MIX IN WATER
(4) CORROSIVE
(5) EXPLOSIVE AT 4.3% (6) COLOURLESS
(7) ROTTEN EGG SMELL
2Q. HOW WE CAN FIGHT WITH H2S?
A: WE CAN NOT FIGHT WITH H2S. BUT WE CAN ONLY ESCAPE FROM THIS GAS.
3Q. TOXIC GASES PROPERTIES:
H2S
1.HIGHLY TOXIC
2.COLOUR LESS
3. HEVIER THAN AIR
4.FLAMMEBLE @4.3%-46%
5.ROTTEN EGG SMELL @
0.13PPM)
6.EASILY MIX IN AIR
7.CORROSIVE
8.SOLUBLE IN WATER
EASILY
SO2
TOXIC
COLOUR LESS
HAVIER THAN AIR
PONGANT ODOUR
(GARLIC/VENIGAR)
CORROSIVE
-
CO
TOXIC
COLOUR LESS
LIGHTER THAN AIR
FLAMMABLE @12.5%-74%
-
CO2
SLIGHTLY TOXIC
COLOUR LESS
HAVIER THAN AIR
-
-
-
Downloaded by Sam (zaidisaab11@gmail.com)
lOMoARcPSD|39376716
4Q. TOXIC GASES LIMITS:
GAS
TVL (8HOURS)
H2S
SO2
CO
CO2
5 PPM
2PPM
35PPM
5000PPM
STEL (15MIN)
45MIN BREAK
10PPM
5PPM
50PPM
30000PPM
C CEILIONG VALUE
IDLH
200PPM
-
100PPM
100PPM
12,00PPM
40,000PPM
5Q. EFFECTS LEVELS OF H2S:
•
•
•
0.13 PPM: MINIMUM CONSENTRATION WHICH PRODUCE ODOUR
10 -20 PMM: EYES AND RESPIRATORY ITRACT IRRITATION
20-100 PPM: LOSS OF SENCE OF SMELL, BLISTERRING, INFLAMMATION AND OPACITY OF EYES, HADECHE,
NAUCIA,
100-500: RISPIRATORY DIFFICAULTY, RISPIRATORY DEPRESSION, IRRITATION.
500-700: CENTRAL NURVAS SYSTEM EFFECT, WEAKNESS, UNCONCIOUS, TERNOUS, NUMBNESS, CONFUSION.
700-1000: IMMIDIATELY (RAPIDLY) DEATH IF NOT PROMPTLY EMERGENCY ADMINISTRATED.
•
•
•
6Q. OXYGEN IN AIR
•
•
•
21% -OXYGEN
78%- NITROGEN
01%- OTHER GASES
7Q. MULTI GAS DETECTOR:
(1)
(2)
(3)
(4)
CHECK CALIBRATION DATE VAILATION
PHYSICAL DAMAGES
BATTERY CHARGE
FUNCTIONAL CHECK
GASES: (1) H2S (2) CO (3) LEL (4) OXYGE
8Q. TYPES OFALARM SOUND:
GAS - BREAKS/ INTERVALS
FIRE - CONTINUOUS
9Q. WORKSITE EXAMINATION:
PTW Type
Examination by
Permit Applicant &
Responsible
Supervisor
Examination by Area Authority
Process Facility
Hydrocarbon Area
Before Authorization
First Day
Every Day
First Day
Every Day
CLASS A
YES*
YES
YES **
YES
NO***
CLASS B
NO
YES
NO
NO****
NO
Downloaded by Sam (zaidisaab11@gmail.com)
lOMoARcPSD|39376716
IMPORTANT POINTS:
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
PPM: PARTS PER MILLION 1% - 10,000PPM
0.01 – 1 PPM
HUMAN DEATH AT 650 PPM
HUMAN SAFE UPTO 10PPM
JUST HAVING PTW NOT ENGOUGH TOMAKE JOB SAFE, WE MUST COMPLY WITH REQUERMENTS OF THE JOB
HSE PLAN.
VALIDATION PERIOD OF PERMIT 12 HOURS
MUST SUSPEND PTW IF DELAY WORK MORE THAN 4 HOURS
RESPONSIBLE SUPERVISOR SEND DETAILS OF PERMITS THOSE PERMITS ONLY AREA AUTHORITY WILL VALIDATE.
WHILE WORKING IN SPZ AREA WTU PERSON ARE EFFECTED COSTODIAN PERSON
WHILE WORKING IN SPZ ALL CREW DEATAILS SHALL TAKE AREA AUTHORITY
NEED MINIMUM 2 SCBA PERSONS WITH 1 CREW (FOR 6 INCLUDE SCBA 2)
CAM LOCK/ RIG WALKER SHOULD BE WEAR WHILR WORKING IN SPZ WITH SCBA (2 PERSONS)
H2S MONITOR WILL ALERT AT 10 PPM
USE FILTER HOOD AT 10 PPM
SWITHING OPERATIONS CAN NOT BE CONDUT IN FACILITY AREA, SWITCH OFF FROM OUT SIDE AND ISOLATE
THEN TAKE OUT FROM FACILITY AREA, THEN PROCEED WORK
AREA AUTHORITY WITH AGT WILL CONDUCT GAS TEST OF FIRST DAY CLASS A PERMIT.
ALLOT WORKS TO CREW MEMBERS WHO COMPITENT THERE IN THAT
CHECK WORK DESCRIPTION, ACTIVITY NO., HAZARDIOUS AREA WITH DRAWING,
FIRE=FUEL+HEAT, IGNITION+OXYGEN
WHILE FIRE STOP-DROP-ROLL
ABOVE 2M HEIGHT WORK SHOULD WEAR SAFETY HARNESS AND MINIMUM TWO PEOPLE NEED.
ELECTRICAL SAFETY DOCUMENTS ARE NOT TRANSFERABLE, SHOULD CANCLE THE SUCH DOCUMENTS AND REISSUE TO THE ANOTHER CEP
JOB HSE PLAN -GENERIC
TRIC
- DYNAMIC
SAFETY EQUIPMENTS:
FIRE EXTINGUSHER,ESCAPE SET,BREATHING APPARATUS,
USING FIRE EXTINGUSHER:
•
•
•
•
PULL THE PIN
AIM THE NOZZLE
SQUEEZE THE HANDLE
SWEEP FROM SIDE TO SIDE
Downloaded by Sam (zaidisaab11@gmail.com)
lOMoARcPSD|39376716
1Q. HAZARD?
A. ANYTHING WITH POTENTIAL CAUSE HARM OR DAMAGE TO PEOPLE, ASSET, ENVIRONMENT
2Q. RISK?
A. ANYTHING WITH POTENTIAL LIKELY TO CAUSE OR DAMAGE.
3Q. CONSEQUENCE?
A. AMOUNT OF DAMAGE
4Q. DYNAMIC RISK REVIEW?
A. IT IS CONTINUEOS PROCESS FOR IDENTIFIEING HAZARDS AND RISK AND ACTION TAKEN TO BE ELIMINATE AND
REDUCE THEM.
B. PLANNED AND UNPLANNED
C. WHEN NEW PEOPLE ADDED,CONFLICTING ACTIVITY FROM ANOTHER WORK PARTY
D. WEATHER CHANGE
E. EMERGENCY HAPPENS
5Q. DYNAMIC RISK ASSESSMENT?
A. IT IS IDENTIFY THE HAZARD, PUT CONTROL AND ELEMINATE THE RISK.
6Q. JOB SAFETY PLAN (JSP)?
A. A DOCUMENT WHICH IS DESCRIBE ABOUT THE HAZARDS AND CONTROLS AND IT IS MANDOTERY DOCUMENT TO
ATTACH WITH EVERY PERMIT.
7Q. HEALTH RISK ASSESSMENT? (HRA)
A. IT IS PART OF THE HEMP, WHICH EXPLAIN HAZARD, CONTROLS AND RECOVERY MEASSURES RELATED TO THE
HEALTH.
8Q. (TRIC) TOOL BOX TALK AND RISK IDENTIFY CARD
A. IT IS A SITE RISK ASSESSMENT IN WHICH WE WILL FOCUS ON THE HAZARD AT THE WORK SITE WHEN CARRY OUT
THE WORK.
9Q. TYPES OF HAZARDS?
(1) UNSAFE ACT
(2) UNSAFE CONDITION
(3) HAZARD SUBSTANCE
(4) SOURCE OF ENERGY
(5) PHYSICAL HAZARD
10Q. WHAT IS HEMP?
(1) HAZARD EFFECT MANAGEMENT PROCESS
(2) IT IS A PROCESS WHICH IS USED TO EXPLAIN ABOUT HAZARDS AND THEIR CONTROLS, RECOVERY MEASURES.
I.
IDENTIFY: IDENTIFY THE RISK
II.
ACESS : THEN WE RECOGNIZE THE RISK IS IT AS LOW AS RESONABLY PRACTICABLE?
III.
CONTROL: MEASURES TAKEN TO ENSURE THAT WORK CAN BE DONE SAFELY
IV.
RECOVERY: TO BRING SITUAATION TO NORMAL AFTER ANY UNEXPECTED CONSEQUENCES.
11Q. WHAT ARE THE USES OF JOB HSE PLAN?
A.
B.
C.
D.
E.
IDENTIFY THE HAZARDS
CONTROLS OF APPLIED
IDENTIFY ANY OTHER ACTIVITIES THAT MAY CONFLICT WITH WORK
PERSONAL PROTECTIVE EQUIPMENT
RECOVERY
12Q. H2S FACILITIES CLASSIFICATION
A. SWEET: HAVING LESS THAN<100PMM (0-49PPM)
B. SOUR: HAVING MOR THAN >100 PPM WITH 5 BAR PARTIAL PRESSURE (50-499)
C. CRITICAL SOUR: HAVING MORE THAN >100 PPM WITH MORE THAN 5 BAR PARTIAL PRESSURE (500+PPM)
Downloaded by Sam (zaidisaab11@gmail.com)
lOMoARcPSD|39376716
13Q. WHAT DO YOU MEAN MY SIMOPS?
A. ANY SITUATION WERE TWO DIFFERENT ACTIVITIES ARE OCCURING CLOSE ENOUGH TO EACH OTHER THAT
THERE IS A RISK OF INTERFERENCE, CRASHING OR RISK TRANSFER.
SIMOPS INNER ZONE
SIMOPS OUTER ZONE
ALL WORKERS HAVE RECEIVED APPROVED VALID H2S
ALL WORKERS HAVE RECEIVED VALID H2S TRAINING
TRAINING CARD
CARD
SUPPLIED AIR RESPIRATORY EQUIPMENT TO BE CARRIED
FILTER ESCAPE HOOD
SELF- EXCAVATION TO BE DEMONSTRATED
SELF EVACUATION TO BE DEMONSTRATED
AGREEMENT WITH SITE ON RESCUE PROVISION
EITHR AGREEMENT ON SITE FOR RESCUE PROVISION
14Q. HAZARDIUOS ZONES CLASSIFICATIONS:
A. PROCESS FACILITY, HYDROCARBON AREA, NON HYDRO CARBON AREA, RED ZONE, YELLOW ZONE, EPZ, CONFINED
SPACE, TEZ, SPZ, ZONES (ZONE-0, ZONE-1, ZONE-2).
• PROCESS FACILITY: AN AREA WITHIN THE BOUNDARY FENCE OF ANT PROCESS FACILITY.
EX: PUMPING STATIONS, PROCESS UTILITY AREA, GATHERING STATIONS
PROCESS SAFETY MANAGEMENT:
ALL CONTROL WE ARE APPLYING TO SUSTAIN THE INTEGRETY OF AN ASSETS IS CALLED PROCESS SAFETY
MANAGEMENT
• HYDROCARBON AREA: AN AREA OUTSIDE OF THE BOUNDARY FENCE OF THE PROCESS FACILITY AREA.
(1) 50M FROM BOUNDARY FENCE OF PROCESS FACILITY, WELL PADS
(2) 50M FROM EXPOSED SECTION FLOW LINES
(3) 100M FROM DRILLING RIG
(4) 10M FROM INTERFIELD GAS PIPELINE
(5) 25M FROM SOGL
•
NON-HYDROCARBON AREA: AN AREA WHERE HYDROCARBONS HAVE BEEN PRESENCE AND WE CALLED AS
FREEN FIELD AREA.
EX: OFFICES, HOSPITALS, RESIDENTIALS,
• TEZ (TOTAL EXCLUSION ZONE) :
(1) AN AREA WITHIN 400M FROM FLARE TESTING POINT.
(2) ENTRY FOR ONLY WTU AUTHORISED PERSONALS.
(3) STRICTLY NOT ENTRY FOR CONSTRUCTION AND OPERATIONAL TEAMS
(4) ROADS WITHIN THIS ZONE ARE TO BE TEMPORARILY SEALED OFF BY WTU PERSONNEL
• SPZ (SPECIAL PRECAUTION ZONE):
(1) AN AREA WITHIN 1.4KM FROM FLARE TESTING POINT
(2) FOR ENTRY: EPZ WORKING REQUIRENTS + (1) CONTINUES GAS MONITORING
(2) POERTABLE WIND SOCK NEAR WORKING AERA
(3) COMMUNICATION WITH WTU PERSONS
(4) TAKE WTU SING IN PTW AS COSTODIAN
HAZRDIUOS ZONES:
ZONE-0: AN AREA WHERE EXPLOSIVE AND FLAMMABLE GASES ARE CONTINUOUSLY PRESSNCE FOR LONG PERIODS
HOT WORK CAN NOT BE DONE.
EX: VISSELS, STORAGE TANKS, FLARE POINT, FLANGE PIT
ZONE-1: AN AREA WHERE EXPLOSIVE AND FLAMMABLE GASES ARE LIKELY OCCURE IN NORMAL OPARATIONS
Downloaded by Sam (zaidisaab11@gmail.com)
lOMoARcPSD|39376716
HOT WORK CAN BE DONE, BUT NEED SPECIAL REQUIRMENTS (CONTINUOUSLY GAS TESING)
EX: NEAR COMPRESSORS, FLANGE JOINTS, NEAR VALVES, OUTSIDE THE STORAGE TANKS, VISSELS
ZONE-2: AN AREA WHERE EXPLOSIVE AND FLAMMABLE GASES ARE UNLIKELY OCCURE IN NORMAL OPERATION.
HOT WORK CAN BE DONE ANYTIME.
EX: NEAR PIPELINE WHICH HAVE NO FLANGED JOINTS AREA OUTSIDE.
RED ZONE
WHERE TOXIC GASES ARE CONTINUOUSLY PRESENCE
NEED SPECIAL TRAINING TO ENTER RED ZONE
CAN NOT PERFORM WORK INSIDE
B.A.SET TO BE WEAR AND HOSE PIPE TO BE CONNECT
WITH FIXED AIR BREATHING SYSTEM DURATION OF
WORKING.
PERMISSIONS AND SPECIAL PRECAUSIONS TO TAKEN TO
ENTER, PORTABLE WIND SOCK,CCTV
MONITORING,NEAREST ESCAPE GATE
EXPECTED MORETHAN 650 PPM
YELLOW ZONE
WHERE TOXIC GASES ARE LIKELY PRESENCE
ANYBODY CAN ENTER WHO HAVING VALID H2S CARD
WITH TRAING
WORK CAN BE CARRYIED OUT
WEAR B.A. SET AND USE TO ESCAPE PURPOSE ONLY
CAN ENTER WITH VALID H2S CARD AND INDUCTION TO
BRE NEED
EXPECTED 100PMM AND ABOVE
EPZ (EMEGENCY PLANNING ZONE):
GEOGRAPHICAL AREA AROUND THE WELL HEADS, FLOW LINES, FACILITIES CONTAINS HIGH LEVEL OF H2S AND ITS
BOUNDARY AREA HAVING 100PPM CONSENTRATION OF H2S IF ANY ACCEDENTICAL LEAK.
REQUERMENTS OF EPZ ENTRY:
(1) VALID H2S CARD WITH TRAINING
- H2S TRAINING
(2) H2S MONITOR
-DETECTION
(3) COMMUNICATION SET (EX. PROF)
-COMMUNICATION
(4) ESCAPE SET / BREATHING APPARATUS - PROTECTION
(5) STAND BY VEHICLE (WITHIN 400M)
-EVEACUATION
REQUERMENTS FOR WORK IN EPZ:
ALL EPZ ENTRY REQUIREMENTS + (6)
NEED TO AWARE OF EPZ:
(1) CONSIDER CHANGES IN CONDITION
(2) TRAINING RESCUE PERSONNEL
(3) RISK ASSESSMENT
(4) MUSTER AREA OR ASSEMBLY POINT
(5) IMMIDIATE ACTION/ EVACUATION/EMERGENCY RSPONCE PROCESSOR
RANGE / DISTANCE OF EPZ:
AROUND WELL HEAD
-1.5KM
AROUND LIVE LINE / FLOW LINE -4.4KM
HMPS STATION
-13KMBIRBA STATION
-7KM
AL NOOR
- 5KM
DRILLING RIG
-1.5KM
ISOLATION BOUNDARY: SIMILAR DEVICES USED TO ESTABLISH AN AREA SAFE FROM HAZARDS FLIUD,THE SET OF VALVES
ELECTRICAL SWITH GEARS
Downloaded by Sam (zaidisaab11@gmail.com)
lOMoARcPSD|39376716
EVACUATION DRILL PROCESS:
THE EVACUATION DRILL IS PERFOMED BY STATION OR BUILDING INCHARGE TO CHECK THE READINEDD AND AWARNESS
OF PEOPLE ABOUT THE EMERGENCY RESPONSE, ALL SHOULD EVECUATE THE PLACE IMMIDIATLY AFTER HEARING ANY
EMEGENCY ALARM AND REACH TO THE DESIGNATED ASSEMBLY POINT. THEY SHOULD NOT RE ENTER THE BUILDING
UNTILL ALL CLEAR ANNOUNCEMENT BY THE INCHARGE.
CONFINED SPACE:
AN AREA WITH LIFE THRETENING CONDITION AND RESTICTED ENTRIES AND EXITS IS CAN BE CALLED AS CONFINED
SPACE.
HAVING MORE THAN 1.5M DEEP.
WHY REQUERED CONFINED SPACE ENTRY CERTIFICATE:
IN CONFINED SPACE THERE MAY BE PRESENT TOXIC AND POISONOUS GASES OXYGEN DEFFICIENCY ENVIRONMENT OR
PRESENCE OF FLAMMEBLE GASES.
PRECAUTIONS TO ENTER AND WORKING IN CONFINED SPACE:
• CONTINUOUS GAS TESYTING
• VISIBLE SUPERVISION NEEDED
• NEED HIAB/ CRANE AT THE TIME OF WORK WITH CONFINED SPACE
• MINIMUM 2 VEHICLES FOR ESCAPE
• SAFETY HARNESS SHALL BE WEAR
• SHOULD APPLY BUDDY SYSTEM
• WORK TURN BY TURN AFTER 30MIN, (MAX 30 MIN IN CONFINED SPACE)
• WRITE DOWN TIMING ENTRIED AND EXITS.
CONFINED SPACE HAZARDS AND CONTROLS:
HAZARDS
OXYGEN DEFFIANCY
POOR COMMUNICATION
TOXIC / EXPLOSIVE/FLAMMABLE GASES
CONTROLS
CONFINED SPACE CERTIFICATE
BUDDY SYSTEM FOR CONTINUOUS MONITORING
AND COMMUNICATING WITH ANOTHER
GAS TESING IN 3 STEPS (TOP- C0/CH4,MIDDLECO2,BUTTOM-H2S,SO2)
PROPER PPE
SUFFIETIANT LIGHTING
MAX 30MIN AFTER CHAGE ANOTHER PERSON
PUT SIGN BOARDS
WEAR PROPER PPE
PREPARE PROPER ENTRIES AND EXITS
MAKE AS COMFARTABLE AS POSSIBLE
BIOLOGICAL HAZARDS
POOR LIGHTING/VISIBILITY
TEMPERATURE CHANGES
UN EVEN/ SLIPPERY SUFACE,
SHARP EDGES
UNPROPER ENTRIES AND EXITS
CONGESTED PLACE
EMERGENCY TYPES:
(1) ELECTRICAL EMEGENCY (2) FIRE EMERGENCY (3) H2S LEAK (4) MEDICAL EMERGENCY
H2S LEAK EMERGENCY RESPONSE:(ISBL, STATIONS)
STEPS: (1) STOP THE WORK (2) HOLD THE BREATH (3) WEAR CAM LOCK/ RIG WALKER (20MIN FOR ESCAPE PURPOSE
ONLY) (4) CHECK WIND DIRECTION
FOR AROUD THE TSR CREW-(5) MOVE TO TSR-2 ACREOSS THE WIND DIRECTION,(6) REVERSE H2S CARD,(7)COUNT
HEADS (8) STAND IN POSITION, (9) AND FOLLOW INSTRUCTIONS FROM MUSTER.
Downloaded by Sam (zaidisaab11@gmail.com)
lOMoARcPSD|39376716
FOR OTHERS-(5)GO TO NEAREST ASSEMBLY POINT THROUGH ESCAPE GATE (6)COUNT HEADS (7) INFORM TO AREA
AUTHORITY (8) FOLLOW MUSTER CHECKER INSTRUCTIONS.
H2S LEAK EMERGENCY RESPONSE:(OSBL):
(1) STOP THE WORK (2)HOLD BREATH (3) WEAR FILTER HOOD(4) CHECK WIND DIRECTION (5) GO TO FIRST
ASSEMBLY POINT ACROSS THE WIND DIRECTION (VEHICLE/OTHER ) (6) COUNT HEADS (7) INFORM TO AREA
ATHOURITY(8) MOVE TO SECONDARY ASSEMBLY POINT( T- JUNTION FOOD BALL COURT)
LIFE SAVING RULES:
(1) VALID PTW,
(2) ISOLATION,
(3) GAS TESTING,
(4) SYSTEM OVEERRIDE,
(5) SUSPENDED LOAD,
(6) WORK AT HIGHT,
(7) BUDDY SYSTEM – CONFINED SPACE,
(8) JOURNEY PLAN,
(9) SEAT BELT,
(10)NO MOBILE USE WHILE DRIVING,
(11)DRUGS & ALCHOHOL,
(12)OVER SPEED
HOUSE SAVING RULES:
(1)
(2)
(3)
(4)
(5)
(6)
(7)
(2)
STOP THE WORK WHEN I FEEL UNSAFE
HOLD HANDRAIL WHILE USING THE STAIR
DO USE SEAT BELTAND DO NOT USE MOBILE WHILE DRIVING
WEAR PROPER PPE
KEEP WORKING AREA DRY AND CLEAN, GOOD HOUSE KEEPING
UNDERSTAND THE RULES FOR JOB
REDUCE THE SOURCES OF WASTE
USE THE RIGHT TOOL FOR THE RIGHT JOB
ELECTRICAL HARZARDS AND CONTROLS
HAZARDS
CONTROLS
ELECTRICAL SHOCK
HIGH VOLTAGE. / LOW VOLTAGE MAINTANANCE
EARTHING
ENERGY STORED CAPACITORS
POOR CABLE CONDITION
INSULATION DAMAGE
LOOSE TERMINATION
OVER LOAD
SHORT CIRCUIT
DAMAGED POWER TOOLS
OHL CONDUCTORS,POLES
LIVE LINE WASHING
REVERSE POWER
CAUTION NOTICE, DANGER BOARD
ISOLATION, PPM
APPLY CME, AE
USE FUSE EXTRACTOR
SPARKS
MAINTANANCE WITH EQUIPMENTS
CEP,FOLLOW ESR,ESOP
ISOLATION, DISPLAY MONITORS
INSULATION RESISTANCE TEST , KEEP SAFE
TIGHTNESS WITH CALIBRATED TORQUE WRENCH
LOAD BALANCING
CONNECT EARTH AND DISCHARGE BEFORE OPERATE
CALIBRATED AND FULL INSULATION TOOLS
SAFETY DISTANCE
LIMITATION OF ACCESS LOA
VOLTAGE TESTER
Downloaded by Sam (zaidisaab11@gmail.com)
lOMoARcPSD|39376716
Electrical Isolation Keys:
A Key Safe shall be employed to control all the Safety Padlock keys used to secure an Isolation. The Key Safe shall be
fitted with at least two unique locks with associated keys. Where the electrical isolation requires the use of a Key
Safe then the Key Safe keys should be distributed as follows:
Key 1 – Permit Holder
Key 2 – Senior or Authorized Electrical Person (SAEP or AEP)
Key 3 (If fitted) – Area Authority or SAEP/AEP
•
•
•
Overhead line clearance:
•
PR-1242 – Activities in the Vicinity of Overhead Power Lines gives required horizontal & vertical clearances
(Typically, 3m both horizontally and vertically)
•
•
A clearance certificate is required to be authorised by the Asset Custodian.
An 'Overhead Line Clearance ', is required for passing by or under an overhead line. A PTW is required as this
is not an Electrical Safety document.
If work is to be conducted under or near an Overhead Line a 'Limitation of Access' with supervision by a
Competent Electrical Person may be required.
If machinery could possibly come into contact with the Overhead Line, a PTW is required (Activity 9.1).
•
•
Electrical safety rules and PTW interfaces:
:Electrical safety documents
There are five electrical safety documents:
1. Electrical PTW - For HV work or LV with Circuit Main Earth (CME)
2. Sanction for Test - For HV work
3. Limitation of Access - For HV and LV work
4. Electrical Isolation / De-Isolation Certificate - For HV and LV work
5. Electrical Immobilisation Certificate - LV isolation for Non-Electrical work
The Electrical Safety Document highlights the electrical hazards of the relevant electrical work but additionally
the work also requires a Class A or B PTW relevant to the activity when the work interfaces with other
work/operations. This is to control the additional hazard at the interface.
Types of electrical work:
Work in electrical areas of a production asset
The work shall be authorised by the Area Electrical Supervisor (licensed as a Responsible Supervisor) and agreed
by the Production Responsible Supervisor as the Other Affected Custodian and validated by the Electrical Area
Authority. If however the work extends or affects equipment outside the substation then a PTW authorised by
the Production Responsible Supervisor is required.
This includes work in sub-stations and switchyards located in production assets.
Electrical work on electrical assets controlled by power systems operations
The work shall be authorised by the Infrastructure Electrical Supervisor (licensed as a Responsible Supervisor), no
other Affected Custodian and validated by the Electrical Area Authority.
Non electrical work on electrical assets controlled by power systems operations
The work shall be authorised by the Infrastructure Electrical Supervisor (licensed as a Responsible Supervisor), no
other Affected Custodian and validated by the Electrical Area Authority, or he is not available validated by a
Production Area Authority who is an Electrically Appointed person.
Live line washing
Requires only a Limitation of Access (LOA) unless the live lines pass through a hazardous zone (1 or 2) where it
needs a Class B PTW.
The Electrical Supervisor shall ensure that the auto-reclose facility is disabled.
Downloaded by Sam (zaidisaab11@gmail.com)
lOMoARcPSD|39376716
Work at remote electrical assets controlled by power systems operations
•
•
•
•
•
•
Electrical work will have a suitably qualified electrical person in the work party to validate the PTW.
Non-electrical work - e.g. work on gas turbine prime mover is covered by 11.9.2 above, unless
circumstances prevent the PDO Electrical Area Authority from validating in which case the PTW can be
validated by a suitably qualified Production Area Authority from the local area. This requires agreement
from the asset teams and a familiarisation briefing for the Area Authorities.
• If the asset team or project team working within an Asset wish to maintain construct or commission
plant under custodianship of UIE3 then they need to do so under the PDO PTW system. If asset
operations wish to carry out work on utility equipment inside a power station fence the following shall
be followed:
Operations Responsible Supervisor shall authorise the PTW.
The PTW Applicant shall fax a copy of the PTW to the relevant Power System Responsible Supervisor in Yibal,
who will sign the faxed copy as Affected Custodian.
The PTW shall be faxed back to the PTW Applicant for him to arrange for the Operations Responsible
Supervisor to sign the actual PTW in box 5, by writing the words “signed on behalf of” and writing in the
name of the Affected Custodian.
The signed fax copy should be attached to the worksite copy of the actual PTW as an auditable record of the
agreement.
When Power Systems wish to carry out any physical work within the fenced area, a PTW should be raised by the
Power Systems Responsible Supervisor and countersigned by the Operations Responsible Supervisor as Affected
Custodian.
For daily validation within an area under the control of Power Systems this can be completed by fax under strict
adherence to the following conditions.
•
•
The Power Systems Area Authority shall visit the site for the first validation and at least once per week for
ongoing activities where the task or risks have not changed.
Subsequent validations can be completed by fax in the following way.
o
o
o
o
o
o
1.1.1
The Permit Holder emails/faxes the PTW to the Area Authority, who signs the scanned copy in box 10,
and returns it to the Permit Holder by email or fax.
The Permit Holder attaches the signed copy to the worksite copy.
On suspension of the activity on a daily basis, the Permit Holder emails/faxes the suspension in box 10
to the Area Authority.
The process is repeated when validation is again required.
The worksite copy of the PTW will therefore contain a signed copy of box 10 for each day the PTW was
validated.
On completion or cancellation, the PTW is emailed/faxed to the Area Authority who shall visit the site
with the Permit Holder and check the worksite has been left safe and tidy and close/cancel the PTW.
Electrical isolation (low voltage)
Controls for this work are covered in the Electrical Safety rules. An electrical isolation / de-isolation certificate
shall be issued by a responsible member of the custodian department to a third party who is to carry out nonelectrical work on equipment that needs isolating before work commences.
1.2
PTWs for ESP activities
This includes work on ESPs, ESPCPs & PCPs and there is a standard approach for requirements for a vendor’s use
of our PDO PTW system.
Downloaded by Sam (zaidisaab11@gmail.com)
lOMoARcPSD|39376716
1.2.1
Pre-requisites for ESP activities
The following shall be in place:
•
•
•
•
•
The Contract Holder (CH) shall ensure the competency of vendor engineers assuring their competency
credentials and certificates.
The Contract Site Rep (CSR) shall ensure that all controls in the HEMP exercise and the Job HSE plan in place.
The CH shall ensure every activity has a robust safe execution procedure.
The CSR with the Production Coordinator and vendor shall establish Job HSE Plans for every specific activity
for ESPs, ESPCPs & PCPs in their area using the Online Job HSE Plan system as baseline.
The Job HSE Plans shall be readily available to the CSR, Production Coordinator/Supervisor and vendor.
The following steps shall be adhered to for all ESPs, ESPCPs & PCPs activities:
1. The Responsible Supervisor requests the CSR to attend job.
2. The CSR instructs the vendor engineer to carry out the work (this does not have to be face to face) and to
refer to relevant Job HSE Plan for the activity and verify all controls are in place.
3. Vendor engineer informs CCR when the job is started.
4. The CCR Operator logs the work details and start time in the “Station Log Book” and reports the status to the
Responsible Supervisor.
5. Vendor engineer informs CCR when the job is completed.
6. The CCR Operator logs the work details in the “Station Log Book” including the completion time and reports
the status to the Responsible Supervisor.
7. Vendor engineer submits Job HSE Plans for all completed jobs to the CSR for documentation and assurance
on return to the base.
1.2.2
PTW requirements for ESP activities
*Activities requiring PTW system:
Activities requiring only Job HSE plan:
Activities requiring Access Authorisation
Form:
Commissioning of ESP, ESPCP & PCP
Working on ESP, ESPCP & PCP
panel/Troubleshooting
Data Collection including download data
from ESP by using DH sensor
Fluid Shot
Program software (adjustment to
controller) if controller is inside the ESP
Panel
Program software (adjustment to
controller) if controller is outside ESP
Panel
ESP etc powered by Generator
Replacing pigtail at Wellhead (Isolated)
Assist to restart ESP, ESPCP & PCP after
STN S/D. (In this case if vendor engineer
is in remote area “Access Permit” can be
obtained by any means of
communication and sign off the Access
Authorisation Form on return for
documentation and assurance)
Visual Inspection of ESP Panel
*Note: The Electrical Supervisor shall sign as the Affected Custodian with direct liaison with the ESP-CSR and the
Production Supervisor to sign as the Responsible Supervisor.
(8)
Downloaded by Sam (zaidisaab11@gmail.com)
lOMoARcPSD|39376716
Downloaded by Sam (zaidisaab11@gmail.com)
lOMoARcPSD|39376716
NO PERMIT JOB
Number:
Work Description:
Location:
A. Questions Regarding Hazardous Areas
1. Is the work within the facilities?
YES
NO
2. Is the work within a hydrocarbon area?
YES
NO
3. Is the work in/ on electrical installations?
YES
NO
4. Is the work in a confined space?
YES
NO
5. Is a supplementary certificate required for the work?
YES
NO
6. Is the work within Emergency Planning Zone of a Critical Sour Area
YES
NO
If any of the questions above has a YES answer then a Permit to Work is required
B. Questions Regarding Type of Work to be Done
1. Is the work familiar to the work force?
YES
NO
2. Is the work going to be undertaken by competent staff?
YES
NO
3. Is there a written procedure for the work?
YES
NO
If any of the questions above has a NO answer then a Permit to Work is required
C. No Permit Job Requirements
1. Job HSE Plan been written for the work
YES
2. Work Site Supervisor appointed for the work
YES
Name of appointed Supervisor
NO
NO
If a Job HSE Plan has not been written or a Supervisor is not named, then a Permit to Work is required.
Work Site Supervisor
Responsible Supervisor
Name:
Name:
Date:
Date:
Agreed duration and review date
Duration:
Approved:
Approved:
Review Date:
NO PERMIT JOB can only start when the above have been completed and signed by all parties
Downloaded by Sam (zaidisaab11@gmail.com)
lOMoARcPSD|39376716
CLASS A
PERMIT
PETROLEUM
DEVELOPMENT
OMAN
PERMIT No.
Work Order Title:
7. VEHICLE ACCESS to restricted Area
1. APPLICATION AND DESCRIPTION (by Applicant)
Location:
Work Site
Vehicle Access Route Plan prepared and approved
YES
PERMIT No.
Permission is given to the Permit Holder to take the following vehicle(s) of the following type(s) to the work site/location:
Vehicle types:
Location:
Vehicle Access is subject to a satisfactory gas test being carried out on each occasion, with the result recorded in Box 8.
A
A
8. GAS TEST RECORD - results for Confined Space Entry to be recorded on Certificate, NOT HERE.
Copies: Pink - Worksite, Green - Permit Control, White - Information
Hazardous Area Classification
Date
Time
Result
Signature Auth. No.
Date
Time
Result
Signature Auth. No.
Date
Time
Result
Signature Auth. No.
HAZARDOUS ZONE 0
HAZARDOUS ZONE 1
No. in Work Party
HAZARDOUS ZONE 2
Work Description
NON-HAZARDOUS
NORM Contaminated Area
YES
NO
9. SAFETY COORDINATION
Any conflicting work identified will be Suspended or Cancelled before first Validation. Worksite preparations specified in Box 2 may proceed.
Mercury Potential
YES
YES
NONO
Name :
10a. VALIDATION
Expected Max ppm
To be signed by the Area Authority at the start of each
work period.
Vehicle Entry Required?
Yes
No
Hydrocarbon Area
Time:
Date:
10b. ACCEPTANCE
10c. SUSPENSION
To be signed by the oncoming Permit Holder whenever
the permit is validated or whenever responsibility
passes from one Permit Holder to another.
I am satified that the conditions at the worksite are safe I have been fully briefed by the Applicant on the work
and necessary precautions. I am satisfied that the
for the work specified. I validate the Permit for the
worksite is safe for work to start. I will brief the work
period stated, provided the work party adhere to the
party and supervise the work. I will stop the work if the
permit requirements. Work must stop if the permit
requirements cannot be met.
permit requirments cannot be met.
Activity Nos. ( Refer to PTW System Manual Section 3.5.4)
Process Facility
Signature:
H2S Facility Classification
HIGH
LOW
NON
Non Hydrocarbon Area
To be signed by the offgoing Permit Holder whenever
work stops for more than 4 hours.
I have examined the worksite. It has been left in a clear
and safe condition.
Associated Permit Nos.
Planner Agrees
In Frozen Plan
Work Order / EWP No
Y
2. CERTIFICATES ATTACHED TO THIS PERMIT
√
Certificate
Validated
Time
Time
From
To
N
3. GAS TESTING REQUIREMENTS
Certificate Number(s)
Gases to be tested for:
Gas test
to be
repeated
at
intervals
of:
Electrical Isolation/De-isolation
Date
Continuous gas monitoring
required during execution of
the work
Name
Initials
Name
PDO Ind/
Contractor
Date
Signature
Time
Date
Signature
Hydrocarbons
H2S
Oxygen
Other
Yes
No
(Specify)
hrs
3a. WORKSITE EXAMINATION required by Area Authority
Mechanical Isolation
Mechanical Isolation Continuation
Excavation
Overhead Line Clearance
Electrical Safety Document
Elec. Immobilisation/Mobilisation
Radiography
Safeguarding Isolation
Worksite Examination 1st day
Yes
No
By Validator required
Yes
No
Confined Space Entry
√
TRIC Required
Everyday
4. APPLICATION BY APPLICANT
I have reviewed the task and am satisfied that the information in this Application and in the Job HSE Plan is adequate and correct
Name:
Position/Ind.
Signed:
CANCELLATION
11. WORK COMPLETED
a. Permit Return by Permit Holder
12. WORK NOT COMPLETED
a. Permit Return by Permit Holder
Contractor:
Tel. No:
Date:
Work Complete. Worksite and equipment affected left in a safe condition.
Work not complete. Worksite and equipment affected left in a safe condition.
Duration Requested
FROM: Date:
Time:
TO:
Name:
Date:
Post:
Time:
*Work is continuing under Permit No:
Date:
* Delete as appropriate
A JOB SAFETY PLAN MUST BE ATTACHED TO THIS PERMIT
* Isolations retained under Isolation Certificate No:
5. AGREEMENT by Other Affected Custodian
6. AUTHORISATION by Responsible Supervisor
I agree that the work described may be carried out
during the proposed period:
I have examined the Permit and Job Safety Plan. The work described in
this Permit and attached Job safety Plan is authorised for this period:
Daily Pre-Validation Allowed?
NO
YES
NO
24 Hour Validation Allowed?
YES
FROM: Date:
Time:
TO:
Date:
Time:
Name
Signed
Ref Ind:
Time
Date
Signed:
b. Permit Cancellation by Area Authority
Name:
Worksite checked, clear and safe (Process Facility only)
Signed
Ref Ind:
6a Production Co-ordinator
Date
Time:
Signed:
b. Permit Cancellation by Area Authority
* Delete as appropriate
Name
Post:
*Reinstatements/De-isolations Complete.
Isolations retained under Cert No:
Date:
Worksite checked, clear and safe (Process Facility only)
Time
Name:
Ind:
Time:
Name:
Date:
Signed:
Name:
Signed:
Ind:
Time:
6b. EXTENSION AUTHORISATION by Responsible Supervisor
Name
Ref Ind:
Extension valid until: Date
Signed
Date
Name:
Signed:
13. REGISTRATION OF CANCELLATION
Ref Ind:
Sign:
CLASS B
PERMIT
PETROLEUM
DEVELOPMENT
OMAN
Time:
1. APPLICATION AND DESCRIPTION (by Applicant)
Location:
Work Site
All necessary documentation collected and retained in PCF
PERMIT No.
Work Order Title:
7. VEHICLE ACCESS to restricted Area
Date:
Time:
PC
Date:
Class A Rev 8 SAP 1000066565
Vehicle Access Route Plan prepared and approved
YES
PERMIT No.
Permission is given to the Permit Holder to take the following vehicle(s) of the following type(s) to the work site/location:
Vehicle type and Reg'n No:
Location:
Vehicle Access is subject to a satisfactory gas test being carried out on each occasion, with the result recorded in Box 8.
B
Copies: Blue - Worksite, Green - Permit Control, White - Information
Hazardous Area Classification
B
8. GAS TEST RECORD - results for Confined Space Entry to be recorded on Certificate, NOT HERE.
Date
Time
Result
Signature Auth. No.
Date
Time
Result
Signature Auth. No.
Date
Time
Result
Signature Auth. No.
HAZARDOUS ZONE 0
HAZARDOUS ZONE 1
No. in Work Party
HAZARDOUS ZONE 2
Work Description
NON-HAZARDOUS
NORM Restricted Area
YES
NO
9. SAFETY COORDINATION
Any conflicting work identified will be Suspended or Cancelled before first Validation. Worksite preparations specified in Box 2 may proceed.
Mercury Potential
YES
YES
NONO
Name :
Date:
10b. ACCEPTANCE
10c. SUSPENSION
Expected Max ppm
To be signed by the Area Authority at the start of each
work period.
To be signed by the oncoming Permit Holder whenever
the permit is validated or whenever responsibility
passes from one Permit Holder to another.
I have been fully briefed by the Applicant on the work
and necessary precautions. I am satisfied that the
worksite is safe for work to start. I will brief the work
party and supervise the work. I will stop the work if the
permit requirments cannot be met.
To be signed by the offgoing Permit Holder whenever
work stops for more than 4 hours.
Vehicle Entry Required?
Yes
No
Hydrocarbon Area
Time:
10a. VALIDATION
Activity Nos. ( Refer to PTW System Manual Section 3.5.4)
Process Facility
Signature:
H2S Facility Classification
HIGH
LOW
NON
Non Hydrocarbon Area
I am satified that the conditions at the worksite are safe
for the work specified. I validate the Permit for the
period stated, provided the work party adhere to the
permit requirements. Work must stop if the permit
requirements cannot be met.
I have examined the worksite. It has been left in a clear
and safe condition.
Associated Permit Nos.
Planner Agrees
In Frozen Plan
Work Order / EWP No
Y
2. CERTIFICATES ATTACHED TO THIS PERMIT
√
Certificate
N
3. GAS TESTING REQUIREMENTS
Certificate Number(s)
Gases to be tested for:
Gas test Continuous gas monitoring
to be
required during execution of
repeated
the work
at
intervals
of:
Electrical Isolation/De-isolation
Date
Validated
Time
Time
From
To
Name
Initials
Name
PDO Ind/
Contractor
Date
Signature
Time
Date
Signature
Hydrocarbons
H2S
Oxygen
Other
Yes
No
(Specify)
hrs
3a. WORKSITE EXAMINATION required by Area Authority
Mechanical Isolation
Mechanical Isolation Continuation
Excavation
Overhead Line Clearance
Electrical Safety Document
Elec. Immobilisation/Mobilisation
Radiography
Safeguarding Isolation
Worksite Examination 1st day
Yes
No
Yes
No
Confined Space Entry
TRIC Required
√
By Validator required
Everyday
4. APPLICATION BY APPLICANT
I have reviewed the task and am satisfied that the information in this Application and in the Job HSE Plan is adequate and correct
Name:
Position/Ind.
Signed:
CANCELLATION
11. WORK COMPLETED
a. Permit Return by Permit Holder
12. WORK NOT COMPLETED
a. Permit Return by Permit Holder
Contractor:
Tel. No:
Date:
Work Complete. Worksite and equipment affected left in a safe condition.
Work not complete. Worksite and equipment affected left in a safe condition.
Duration Requested
FROM: Date:
Time:
TO:
Name:
Date:
Post:
Time:
*Work is continuing under Permit No:
Date:
* Delete as appropriate
A JOB SAFETY PLAN MUST BE ATTACHED TO THIS PERMIT
* Isolations retained under Isolation Certificate No:
5. AGREEMENT by Other Affected Custodian
6. AUTHORISATION by Responsible Supervisor
I agree that the work described may be carried out
during the proposed period:
I have examined the Permit and Job Safety Plan. The work described in
this Permit and attached Job safety Plan is authorised for this period:
NO
Daily Pre-Validation Allowed?
YES
24 Hour Validation Allowed?
NO
YES
FROM: Date:
Time:
TO:
Date:
Time:
Name
Signed
Ref Ind:
Worksite checked, clear and safe (Process Facility only)
Name:
Post:
Time:
*Reinstatements/De-isolations Complete.
Signed:
b. Permit Cancellation by Area Authority
Isolations retained under Cert No:
* Delete as appropriate
Name
Time
Signed:
b. Permit Cancellation by Area Authority
Signed
Date:
Worksite checked, clear and safe (Process Facility only)
Date
Ref Ind:
6a Production Co-ordinator (if Required)
Date
Time
Name:
Ind:
Time:
Name:
Date:
Signed:
Name:
Signed:
Ind:
Time:
6b. EXTENSION AUTHORISATION by Responsible Supervisor
Name
Ref Ind:
Extension valid until: Date
Signed
Date
Name:
Time:
Sign:
Ref Ind:
Signed:
13. REGISTRATION OF CANCELLATION
All necessary documentation collected and retained in PCF
Downloaded by Sam (zaidisaab11@gmail.com)
Date:
Time:
PC
Date:
Class B Rev 8 SAP 1000066566
lOMoARcPSD|39376716
Downloaded by Sam (zaidisaab11@gmail.com)
lOMoARcPSD|39376716
Appendix 1 – PTW type and controls for activities in each type of work area
Class A PTW required
Class B PTW required
No permit document (HSE Plan) required
Gas Test required before starting work each day and after being away for over an hour

Gas Test required every two hours where significant quantities of gas may be present

Activity.
Location of Work
Process Facility
Hydrocarbon Area
1.
Burning, Welding and Grinding
1.1
Welding (Gas) / Oxy-Acetylene cutting (Hot Work)

+
Continuous
monitoring

1.2
Welding (Arc) (Hot Work) (See 15.6.1)

+
Continuous
monitoring

1.3
Grinding (Hot Work)

+
Continuous
monitoring

2.
Confined Space Work
2.1
Confined Space Entry, except for Well Cellars and Casasco pits,

and excavations below 1.5m. Note-Gas testing in accordance
+
with PDO policy is required. (See 3.5.1)
Entry into Well Cellars (See 12.6.3) and Casasco Pits (See

12.5.2) and excavations below 1.5m.
2.3 Entry into Well Cellars or Casasco pits by Area Authority to carry 
out Operational Tasks to an approved procedure.
+
 Continuous
Continuous
monitoring
monitoring
+

2.2
3.
Electrical Work and Work in Electrical Areas (See Section 15.9)
3.1
Work requiring an electrical safety document as specified in
Electrical Safety Rules (ESRs)
3.2
The opening of live electrical junction boxes by Electrical
Authorised Persons
4.
Handling Hazardous Substances
4.1
Handling substances hazardous to health, e.g. toxic chemicals
or asbestos
4.2
Use of Radioactive sources (See 15.6.8)
4.3
Contamination with Naturally Occurring Radiation Material
(NORM)
4.4
Working with Pyrophoric Scale (except for scale encountered
during pigging operations)
5.
Work on Safety Systems (See 15.6.1)
5.1
Work that affects the availability of ESD & F&G Systems
5.2
Work that affects the availability of Process and Machinery
Continuous
monitoring



Downloaded by Sam (zaidisaab11@gmail.com)

N/A
N/A
lOMoARcPSD|39376716
control systems
6.
Mechanical Maintenance Activities (See Section 15.6)
6.1 Work that involves cold cutting pipe on systems containing 
hydrocarbons or hazardous fluids
Continuous
monitoring
+
6.2
Work that involves unbolting flanges on systems containing
hydrocarbons or hazardous fluids
6.3
Grit Blasting (Hot Work)

6.4
Power/hand tools (except grinders) that may create a spark
between surface and tool

6.5
High Pressure (HP) water jetting
6.6
Painting (hand and spray) (See 15.6.17)
6.7
Engineering and routine/corrective maintenance work which
does not involve unbolting flanges or cutting into systems
which have contained hydrocarbons or hazardous fluids.
6.8
Work in authorised workshops located in non-hazardous
areas.
6.9
Leak clamping of oil/gas flowlines
6.10
Beam pump/PCP maintenance activities (See 15.6.2)
6.11
Polyethylene lining of pipelines and flowlines

Continuous
monitoring



6.12 Vacuum tanker discharge inside a process area. (See 15.6.6)

+
Continuous
monitoring
6.13
Suction tanker operations inside a process area. (See 15.6.6

+
Continuous
monitoring
6.14
Engineering and routine/corrective maintenance work which
involves the use of lifting equipment
7.
Work at Height
7.1
Working where a person may fall more than 2 metres, except
on approved walkways and scaffolds
8.
Scaffolding Activities
8.1
Erection or dismantling of scaffolding
9.
Operations using Cranes and other Heavy Machinery
9.1
Operations where heavy machinery e.g. cranes/crane loads,
mechanical excavators, trucks etc. could pass over, or come
into contact with, live hydrocarbon, high pressure steam or
chemical systems or overhead power lines Gas testing
requirements for any diesel engine used is as per 11.1
10.
Systems and Equipment Testing and Commissioning /
Decommissioning
10.1
Pressure testing of plant and equipment
10.2
Commissioning Systems and Equipment
10.3
11.
Decommissioning
Use of non-certified equipment in Hazardous Areas
11.1
Use of Temporary Diesel Engines in hazardous areas
(including vehicle access, and the use of a mobile crane)
(Including refuel operations)

+
Continuous
monitoring

11.2
Use of non-Intrinsically Safe equipment

Continuous

Downloaded by Sam (zaidisaab11@gmail.com)
lOMoARcPSD|39376716
monitoring
11.3
Use of Intrinsically Safe test / portable equipment
11.4
Use of cameras. Providing a gas detector is carried by an
individual who has been briefed in its use, and is able to
demonstrate an understanding of the detector operation and
actions to be taken on alarm activation. Flash requirements to
be included on the access authorisation form
11.5 Mobile diesel powered cleaning units used only by Area
Authority for external cleaning of water injection plant,
equipment and pipework.
Continuous
monitoring

+
Continuous
monitoring
Process Facility
11.6 Use of GPS equipment that is Non I.S. on a well pad. Providing a
gas detector is carried by an individual who has been briefed
in its use, and is able to demonstrate an understanding of the
detector operation and actions to be taken on alarm
activation

+
Continuous
monitoring
When GPS equipment used in a fenced Process area, 11.2
applies

+
Continuous
monitoring
12.
Civil Works
12.1
Excavation. (Hand excavation to 300 mm depth is required in
areas where pipes or cables may be present) (See 15.6.7)
Hydrocarbon Area
12.2 Rebar cutting, bending and shuttering (form work) and concrete
pouring
12.3
Engineering construction activities, not involving welding,
burning or grinding (See Section15.2.)
13.
Operational Activities
13.1
Production operations including routine checks and visual
inspections by the Area Authority which require blowing down
or sampling of hydrocarbons (providing an approved
Operating Procedure is being followed)
13.2
Routine, documented drilling activities. (See Section15.11)
13.3
Well Services operations at locations where well site
custodianship has not been transferred to the Well Services
department. (See 15.6.16)
13.4
Drilling Water Services activities listed in Procedure DWSOP
No P033
13.5
Pipeline pigging operations covered by authorised procedures
& listed in approved programme, including vehicle access to
pig trap area.
Operation of permanently installed approved equipment
which produced an ignition source or open flame when it
operates.
13.6
13.7
Seismic exploration activities. (See Section 15.3)
N/A
Hydrocarbon Area
requirements may apply See
3.3.2
Use Pigging Authorisation
Form
Use Pigging Authorisation
Form


See Section 15.7
13.8 Terminal Operations.
13.9 Government Gas Operations.
See Section 15.8
13.10 Geomatic Survey (See Section 15.4)
13.11 Sampling of Process fluids where the fluids are classed as low,
high, or very high risk sour service, or are not yet classified
and the sampling is carried out using approved Production
Chemistry procedures.

 + Continuous

monitoring
Downloaded by Sam (zaidisaab11@gmail.com)
+ Continuous
Monitoring
lOMoARcPSD|39376716
13.12 Sampling of Process fluids where the fluids are classed as
sweet, and the sampling is carried out using approved
Production Chemistry procedures.
13.13 Use of Flushby Unit following dedicated contractors
procedures approved by PDO. See Section 15.12

13.14 Use of Flare Ignition Gun by authorised Operations Personnel,
providing Operating Procedure PR-1097 is being followed, the
user is an AGT, and a gas test is carried out

14.
Inspection Work
14.1
Entry to Restricted Areas, for viewing purposes only, by
personnel not on the access list for that Area.
15.
Roadway Work
15.1
Levelling and grading using machinery
16.
Faultfinding
16.1
Minor Fault finding work. This may include the controlled
isolation and de-isolation of valves, the removal of
instruments for calibration, blowing through of pneumatic
relays or other routine minor activities. (See 15.1)
17
+ Continuous
monitoring
+ Continuous
monitoring
No PTW Required.
Use Access authorisation
Form
N/A
Hydrocarbon Area requirements may
apply See 3.3.2
ESP Activities
17.1 Meggar Testing HV – See E1.1
Hazardous Area
(Zone 1 or 2)
Non Hazardous Area
Intrinsically safe
Equipment to be used
No PTW Required.
Controlled by ESR’s
N/A
17.2 Replacing Pig Tail at Wellhead (Isolated)
N/A
17.3 Fluid Shot
Activity Controlled by ESRs
17.4 Electrical Isolation - HV
17.5 Commissioning ESP, ESPCP & PCP (Will require gas test if
breaking hydrocarbon envelope)
17.6 Trouble shooting ESP, ESPCP, & PCP (Controlled under ESRs. See
E1.1 No Permit Job to be signed by Electrical Supervisor)
No PTW Required.
Controlled by ESR’s
17.7 ESP Powered by Generator (Controlled by ESRs See E1.1)
Downloaded by Sam (zaidisaab11@gmail.com)
No PTW Required.
Controlled by ESR’s
No PTW Required.
Controlled by ESR’s
lOMoARcPSD|39376716
Appendix 2 – PTW type and controls for activities in PDO electrical
installations
Activity.
Location of Work
Hazardous Area
(Zone 1 or 2)
E1.
Non Hazardous Area
Work in Electrical Installations (See Section15.8)
E1.1 Work requiring an electrical safety document as
specified in Electrical Safety Rules (ESRs)
(Activity 3.1)
No PTW Required.
Controlled by ESR’s
E1.2. Periodic Electrical inspections at unmanned
substations and power stations as per ESRs and
Electrical Safety Operating Procedures (ESOPs),
carried out by Power Systems Operations own
contractor staff.
E1.3. All construction activity such as excavation work, civil
and electrical work, lifting operations using crane,
shot blasting and painting etc. by third party or PDO
supervision. (Use equivalent Activities from
No PTW Required.
Controlled by ESR’s

No PTW Required.
Controlled by ESR’s

Appendix 1)
E1.4. Third party periodic visits to electrical substations and
power stations e.g. Telecoms/SCADA, Area Services
for routine electrical work.
E1.5. Live Line Washing on overhead lines to process field
facilities with or without auto-reclosers.

No PTW Required.
Use Limitation of Access (LOA)
E1.6 The Opening of Live Electrical Junction Boxes by
Electrical Authorised Persons (Hot Work) (Activity
3.2)

No PTW Required.
Controlled by ESR’s
E1.7. Low Voltage (LV) work requiring an electrical safety
document as specified in ESRs

No PTW Required.
Controlled by ESR’s
E1.8

No PTW Required.
Use Limitation of Access (LOA)
E1.10 Electrical Maintenance Activities at unmanned
substations and power stations as per ESRs and
ESOPs, carried out by Power Systems Operations
own and contractor staff.

No PTW Required.
Controlled by ESR’s
E1.11 Non-routine electrical work in power stations and
substations, carried out by Power Systems
Operations own contractor staff.

Non electrical work in electrical switchrooms, power
stations or near overhead lines
E1.9 Electrical Switching controlled by ESOPs and ESRs.
E1.12 Non electrical work in power stations and substations,

carried out by Power Systems Operations own
contractor staff.
Downloaded by Sam (zaidisaab11@gmail.com)
Download