MINERVA VERITAS DATA CENTRE PROJECT
DRAWING SUBMISSION AND PEER REVIEW WORKFLOW
Submission of
drawing/ document to
PMC
S. No.
Transmitting of
drawings/documents
for stakeholders
review by PMC
Drawing/ Document
review by Peer
Reviewer
Drawing/ Document
review by PMC
Drawing/ Document
review by Client
Sharing of comments
to D&B Vendor by
PMC
Yes
Revision &
Resubmission
Required?
No
Implementation of
comments in the
drawing by D&B
vendor
Description
Timeline
1
Submission of drawings to peer
Reviewer from PMC
Within 24 Hrs
2A
Drawing Review by stakeholders
7 to 10 Days
2B
Documents (i.e.,TDS, calculations,
Mock-up etc.,) by stakeholders
3 Days
3
Resubmission of revised drawings/ TDS
by D&B vendor (Revision 1)
5 Days
4
Submission of hard copy drawings by
D&B vendor
7 Days
5
Issue of drawings to site team on
revision or Amendment
Immediate on approval
Note:
Updating drawing
register
Submission of hard
copy drawings by D&B
Vendor
Drawing Seal & Sign by
Peer Reviewer & Client
Issue of drawings to
site team for
execution by D&B
vendor
1. While submission of hard copies, relevant calculations, data sheets and
supporting documents needs to be submitted proactively for validation of
the drawings.
2. Vendor to submit 4 sets of the drawing within 7 days as per the tender.
3. No works to commence at the site, without recent signed copy of the
drawings.