5th International Engineering Symposium (IES 2016), 2 - 4 March 2016, Kumamoto University, Japan A CASE STUDY ON DELAY ANALYSIS OF STADIUM CONSTRUCTION PROJECT USING IMPACTED AS-PLANNED METHOD Deepak Koshy Mathew1, Rajasekaran, C. 2 and Shree Vidhya, R.3 1 Former Post Graduate Student, Department of Civil Engineering, National Institute of Technology Karnataka, Surathkal, India. Email: deepakkoshymathew@gmail.com 2 Assistant Professor, Department of Civil Engineering, National Institute of Technology Karnataka, Surathkal, India. Email: bcrajasekaran@gmail.com 3 Assistant Lecturer, Department of Civil Engineering, National Institute of Technology Karnataka, Surathkal, India. Email: shreevidhyaramamoorthy@gmail.com ABSTRACT Construction projects are subjected to various uncertainties and frequently cause delays, resulting in unanticipated extra costs being incurred by both contractors and clients. The research to date suggests that the costs caused by delays are highly significant. Hence, it is in the interests of all parties that delays, or their effects, are reduced. Various techniques for analyzing delay have been developed over the years. Although delay techniques have been very useful, they have wide differences as to their capabilities and the accuracy of the results produced. The Time Impact Analysis or Impacted as-planned method has evolved as the preferable technique to resolve complex disputes related to delay and compensation for delays. The main purpose of this study is to investigate the causes of construction schedule delays and the methods of schedule delay analyses. In this context, construction works of an international stadium project in Kerala, India was chosen and Impacted as-planned method was applied to the case study project in order to determine the construction schedule delays; to measure the impacts of these delays on the project completion duration; and to allocate responsibility amongst the project participants for preventing delay claims. These delays were caused due to organizational deficiencies of the owner, owner caused delays, the bureaucracy of the provincial municipality, lack of consensus within governmental organisations, contractor’s financial difficulties, problems in material procurement, shortages of labour and. unforeseeable weather conditions. After the application of the delay analysis it was observed that the delays in the critical activities extended the project duration by 101 days in total i.e. by 11.8% of the estimated construction period. Keywords: Construction management in India, Project management, Time Impact Analysis, Schedule Delays