DEPARTMENT OF CIVIL ENGINEERING CVE 213: Site Organisational Studies I Introduction Eric Adjei 2023 1 CVE213 Site Organisational Studies I Introduction Introduction • Organisation is the systematic arrangement of work between individuals and groups wit the necessary allocation of duties and responsibilities among them to achieve specific objectives • Organisations have – Specific objectives – A formal structure of authority (leadership roles, subordinate roles, etc) – Division of work – A formal system of communications – A set of formal procedures and customs that distinguish them from other social entities CVE213 Site Organisational Studies I Introduction Introduction • In site organization, accomplishment of the specific goal in the most economical, efficient and effective manner within the constraints of time, budget and performance standards is the prime objective • Projects are to be delivered on time, within budget and with high quality CVE213 Site Organisational Studies I Outline • Site Management – – – – Site Organization Management of Plant, Materials and Human Resource Job Description Assignment of Tasks • Fundamentals of Organizational Behaviour – – – – Leadership and motivation Morale development and use Maintenance, Incentive, Supervision Leadership role and cultivation of team spirit • Graphic and Written Presentation – – – – Resumes Memoranda Progress reports Variation orders Introduction CVE213 Site Organisational Studies I Site Management and Leadership Site Management Planning • The aim of construction site management planning is to find solutions to build in the cheapest, fastest and safest way possible – Based on construction sketches and layouts, design and building standards and owner’s wishes • Planning of site management is based on knowledge of building technology and different methods of the time scheduling of construction work CVE213 Site Organisational Studies I Site Management and Leadership Site Management Planning • To fulfil the goal of site management planning, one must prepare – The budget of the construction expenses – The time schedule of construction works – The construction site layout(s) – The cost estimate for the set-up of temporary buildings and site management – List of risks • Alternatives solutions can be planned, from which, one can be selected CVE213 Site Organisational Studies I Site Management and Leadership Site Management Planning • The following evaluation criteria can be used in making a selection – The proportion of the cost of the temporary buildings in relation to the general cost of the building complex • Varies from 1.5 to 12% – The duration of the construction period – The bill of quantities for temporary buildings, including their proportion within the overall cost of temporary works – The quantity (length, area) of temporary construction and their cost by type of construction • Temporary roads, buildings, utility networks etc – Total labour used in building the temporary structures in man-days CVE213 Site Organisational Studies I Site Management and Leadership Construction Site Installation • Factors to be taken into consideration when installing a new construction site include: – Site layout – Site access – Storage – Plant – Site huts – Temporary services – Fencing CVE213 Site Organisational Studies I Site Management and Leadership Construction Site Installation - Site Layout • The purpose for planning an efficient site layout is to enable the flow of materials and work on site to be as free as possible from obstruction • Flow should be orderly and involve minimum movement of operators and materials • Before a site layout drawing is prepared, a list should be compiled of all accommodation and plant and material storage areas required CVE213 Site Organisational Studies I Site Management and Leadership Construction Site Installation - Site Layout • Site layouts may be prepared around five main points 1. Movement of personnel, plant and materials 2. Accommodation for administrators, operators, welfare (first aid, toilets, etc) 3. Work activity areas, eg. • • Repair and cleaning areas for formwork Steel reinforcing storage/work area 4. Site access – vehicle deliveries, etc 5. Control of site work activities CVE213 Site Organisational Studies I Site Management and Leadership Construction Site Installation - Site Layout • Location of accommodation – Administration offices are the information and control centre of the site – Should be situated so as to facilitate checking, supervision and security on site • Toilet facilities – Depends on the location (local or remote) and the number of operatives involved • Parking facilities – Should be located close to the site offices • Subcontractor accommodation – May provide their own accommodation or use the main contractor’s accommodation • Site clerk’s accommodation – Best situated near the entry of the site so the clerk can check and inspect deliveries and direct them to specified areas CVE213 Site Organisational Studies I Site Management and Leadership Construction Site Installation - Site Layout • Adequate protection for the public must be provided in the form of gantries, dust barriers, security gates, safety lighting, etc. • Other considerations include – Placing signs around the indicate entry, exit, directions and safety requirements – Space around the building for scaffolding and movement of plant and material – Special storage facilities for inflammable materials such as oil, paint and gas – Space for waste disposal container – Protection of adjoining properties CVE213 Site Organisational Studies I Site Management and Leadership Construction Site Installation - Site Layout CVE213 Site Organisational Studies I Site Management and Leadership Construction Site Installation - Site Layout • Important considerations in preparing a site layout include; – Analyzing the contract drawings and documents in detail – Finding out the restrictions on the use of the site by the permanent structures – Analyzing the construction methods to obtain the required space to be kept clear – Working out the area of the site which is left for temporary buildings, storage, etc CVE213 Site Organisational Studies I Site Management and Leadership Construction Site Layout – Site Access • Access has two separate aspects – The actual entrance from a highway to the site – Access within the site • Vehicles and plants entering or leaving the site or using the site should be considered in both cases • Position of the main access to the site must be practical and sensible but not just the most convenient – Should have good visibility and clear of instructions • Width of the access should be fixed considering the largest size of vehicle likely to visit the site CVE213 Site Organisational Studies I Site Management and Leadership Construction Site Layout – Site Access • Access within the site should be convenient for loading and unloading materials in storage points or work areas • Access roads should be made with suitable materials to avoid vehicles getting stuck • Car parks can be provided for small vehicles and vehicles not in use if the site is big enough CVE213 Site Organisational Studies I Site Management and Leadership Construction Site Installation - Storage • Storage involves the occupation of space by materials or goods • It is often wise to keep to a minimum the quantity of materials stored on site to prevent site congestion • Factors that may influence a contractor to store materials include the following – Economic buying of materials – buy in bulk to reduce costs – Changes in production programs – a revision of initially planned sequence of operations may require materials ordered to be stored until required – Late delivery from suppliers – to prevent last-minute delays – Limited period of availability of some materials CVE213 Site Organisational Studies I Site Management and Leadership Construction Site Installation - Storage • Valuable materials are stored in a locked room • All materials should be stored in the correct way – Aggregates should be stored on a clean, firm base, preferably concrete and no dirt or access of water allowed – Different sizes must be stored separately and near to the mixer • Bagged cement or lime should be kept in a dry, draught-free room or hut. – Not allowed to come in contact with moisture or moist air CVE213 Site Organisational Studies I Site Management and Leadership Construction Site Installation - Plant • The choice of plant depends primarily on the work to be done • A secondary consideration is the size and nature of the site • Adequate roadway is required within the site • Plant should be maintained regularly for high efficiency • For static plants, such as tower cranes, care must be taken to choose a correct sitting to suit the constructions CVE213 Site Organisational Studies I Site Management and Leadership Construction Site Installation – Site Huts • Temporary building for the duration of the construction work – Can be timber, concrete, shipping containers, etc • Used for the administrative purposes, storage, workshops, operations, laboratories, etc • Huts should be kept in groups according to their purpose • If possible, they are kept away from the actual construction areas to reduce the level of dust, noise and fumes CVE213 Site Organisational Studies I Site Management and Leadership Construction Site Installation • Temporary services such as electricity, water, telephone, drainage facility are needed as soon as the site is set up. • Site should be fenced for protection of the public and adjoining premises as well as security – Advantages of fencing should however be compared against the cost of implications. CVE213 Site Organisational Studies I Construction Site Installation Site Management and Leadership CVE213 Site Organisational Studies I Construction Site Installation Site Management and Leadership CVE213 Site Organisational Studies I Site Management and Leadership Site Organisation • A good contractor always tries to keep site staff to a minimum for economic construction • The right type of employees must therefore be used – They must be given freedom and responsibility to act on their own initiative – They must have quick communication with each other – Their areas of action must be clearly defined CVE213 Site Organisational Studies I Site Management and Leadership Site Organisation • Key site personnel for a contractor include – – – – – – Project Manager Site engineer Office manager General foreman Plant manger(s) Contract manager on large jobs • For small jobs, the duties of the agent and the site engineer may be combined and the general foreman may also be the plant foreman • On large jobs, the Contract Manager may be appointed over the agent CVE213 Site Organisational Studies I Site Management and Leadership Site Organisation – Project Manager • The project manager is responsible for directing and controlling the whole of the construction work on site • They have the powers to employ, hire machinery and equipment, purchase materials and employ sub-contractors – The power to do these without consulting main firm office may depend on the size of the job, policy adopted and standing in the firm. • May also be called the site manager, construction manager or agent CVE213 Site Organisational Studies I Site Management and Leadership Site Organisation - Agent • The agent should be a person with skills including – Knowledge in the civil engineering construction – Ability to command men – Be a good organizer and administrator – Have sound business sense • Job is not just to build properly to the satisfaction of the engineer but also to make profit for the contractor CVE213 Site Organisational Studies I Site Management and Leadership Site Organisation – Site Engineer • The site engineer is responsible for making sure that the work is constructed to the right standards • They may also advise the project manager on all design and engineering matters • Duties of a site engineer will include; – – – – – Taking site levels Planning temporary access, roads and bridges Concrete batching, plant foundation Keeping records of progress and quality Prepare reports as directed by the project manager CVE213 Site Organisational Studies I Site Management and Leadership Site Organisation – Office Manager • Within the site office, the project manager’s principal administrator is the office manager • Responsibilities include; – Carrying out most of the paper workscorrespondence – Issuing of orders for materials, receiving and checking – Checking accounts, making up pay sheets etc • Normally have other persons working under him/her such as accountant, order clerk, etc CVE213 Site Organisational Studies I Site Management and Leadership Site Organisation – General Foreman • The general foreman is the project manager’s righthand man for the execution of the works in the field • Responsible for keeping the work moving ahead on a daily basis as the project manager has planned it. • Has to have wide practical knowledge and experience • Must be able to read the engineer’s drawings • Has to be a leader of the working group • Must possess foresight and planning ability CVE213 Site Organisational Studies I Site Management and Leadership Site Organisation – Plant Manager • Job is to maintain and service the plant and to have it available as required • Advised by the project manager in long-term planning and by the general foreman for day to day planning • Has to maintain power supply to the site – Thus to run the site generator if need be CVE213 Site Organisational Studies I Site Management and Leadership Site Organisation – Resident Engineer • The resident engineer is the consultant’s representative on site • Primary job of the site engineer is to make sure the project is executed as designed and instructed by the consultant • Only responsible to the engineering consulting firm, even though he/she may be paid by the client or employer CVE213 Site Organisational Studies I Site Management and Leadership Site Organisation – Resident Engineer • The resident engineer is expected to; – Coordinate the work of various contractors – Check that all the materials are ordered in good time and all necessary permits obtained – Check that the materials and workmanship are up to standards – Watch for faulty workmanship or material and issue instructions for remedying such faults – Check the project set-out conforms with the drawings – Measure amount of work done for the purpose of payment and to calculate such payments – Keep records of all measurements and test – Act as a channel for all claims and disputes’ – Report regularly to the engineering consulting firm CVE213 Site Organisational Studies I Site Management and Leadership Construction Equipment Management • Good project management in construction must pursue the efficient use of labour, material and equipment • The use of new equipment and innovative methods has made possible wholesale changes in construction technologies • The selection of the appropriate type and size of construction equipment often affects the required amount of time and effort and thus the job-site productivity of a project • Site managers should therefore be familiar with the characteristics of major types of equipment most commonly used in construction CVE213 Site Organisational Studies I Site Management and Leadership Construction Equipment Management • Advantages of utilizing construction equipment include; – Increase in rate of output – Reduction in overall construction costs, especially for large contracts – Carrying out activities which cannot be done manually or to do them more economically and faster – Eliminate the heavy manual work by human, thus reducing fatigue and other hazards and health issues – Maintain high quality standards often required by present day design and specifications CVE213 Site Organisational Studies I Site Management and Leadership Construction Equipment Management • Factors that influence construction equipment selection include; – Economic consideration • • • • Owning costs, operating labour cost, operating fuel cost Resale value Replacement cost of existing equipment Salvage value – Company specific • Company’s policy on ‘owning’ or ‘renting’ equipment – Site conditions • Ground conditions • Climatic conditions CVE213 Site Organisational Studies I Site Management and Leadership Construction Equipment Management • Factors that influence construction equipment selection include; – Equipment specific • Should we go with equipment with low initial cost or for standard equipment? – Site specific • Site conditions, both ground and climatic conditions may affect the equipment selection – Client and project specification • Owner may have certain preferences as far as equipment procurement are concerned • Schedule, quality and safety requirements demanded for a particular project may also influence choice of equipment – Manufacturer specific • A construction company may prefer to buy equipment from the same manufacturer over and again – Labour consideration CVE213 Site Organisational Studies I Site Management and Leadership Construction Equipment Management • Types of construction equipments and their selection criteria – Earthwork equipments • Backhoe, front shovel, dragline, clamshell, dozers, roller compactor, scraper, dumper, grader – Concreting equipments • Concrete batching and mixing plant; concrete mixers, concrete transit mixers, concrete pumps – Hoisting equipments CVE213 Site Organisational Studies I Site Management and Leadership Construction Equipment Management – Earthwork Equipment • Earthworking equipments may either move on tracks or tires • Tracked equipment is designed for work activities requiring high tractive effort or the ability to move and remain stable on uneven or unstable surfaces – Tasks such as pushing over tree, removing tree stumps, moving broken concrete flatwork • Tracks can be wide or narrow – Wider tracks have greater floatation on the work surface – Narrow track shoes are better for harsh irregular hard work surfaces CVE213 Site Organisational Studies I Site Management and Leadership Construction Equipment Management – Earthwork Equipment • Tired equipment is more mobile and maneuverable than tracked equipment – Better for hauling – Pulling ability is reduced to reach a higher speed CVE213 Site Organisational Studies I Site Management and Leadership Construction Equipment Management – Earthwork Equipment • Earthwork moving equipment usually have buckets and/or blades • Buckets come in many shapes and sizes • The shape of the bucket and the teeth or penetration edge is greatly influenced by the material that is to be excavated or moved • As materials to be worked becomes harder, buckets typically become slimmer and elongated • Buckets can have jaws or apparatus for grasping irregular shaped loads such as concrete chunks CVE213 Site Organisational Studies I Site Management and Leadership Construction Equipment Management – Earthwork Equipment CVE213 Site Organisational Studies I Site Management and Leadership Construction Equipment Management – Earthwork Equipment • A typical blade configuration is like a “C” from top to bottom – As the blade is moved forward and tilted, the bottom of the blade acts as a cutting edge and the top edge rolls the materials forward • Blade configurations include – A blade – C blade – U blade – S blade CVE213 Site Organisational Studies I Site Management and Leadership Construction Equipment Management – Earthwork Equipment • Angle (A) – can be mounted to the bulldozer in the center of the panel and can be angled about 30o left or right – Used primarily for pushing material off to the side – Excellent for drainage ditch excavation – Used for grading and surface removal – Not recommended for rock or hard digging surfaces CVE213 Site Organisational Studies I Site Management and Leadership Construction Equipment Management – Earthwork Equipment • Cushion (C) – Used primarily with scrapers for ‘on the go’ push loading – Can be used for lighter excavation and other general tasks CVE213 Site Organisational Studies I Site Management and Leadership Construction Equipment Management – Earthwork Equipment • Universal (U) – Used for moving big loads over longer distances – Curved shape with side and top extensions to reduce spillage of loose material – Best suited for lighter materials CVE213 Site Organisational Studies I Site Management and Leadership Construction Equipment Management – Earthwork Equipment • Straight (S) – Used primarily for shallow surface removal, land clearing – Designed to push earth for short distances – Versatile, lightweight and maneuverable – Handles a wide range of materials CVE213 Site Organisational Studies I Site Management and Leadership Construction Equipment Management – Earthwork Equipment • Backhoes are mainly used to clean up construction areas, to dig holes in the ground, to smooth uneven ground, to make trenches, ditches and help to remove deep roots from trees CVE213 Site Organisational Studies I Site Management and Leadership Construction Equipment Management – Earthwork Equipment • Front shovels are used for excavation purposes above its own track or wheel level • They are suitable for heavy positive cutting in all types of dry soils CVE213 Site Organisational Studies I Site Management and Leadership Construction Equipment Management – Earthwork Equipment • Dragline is used for bulk excavation below its track level in loose soils, marshy land and areas containing water CVE213 Site Organisational Studies I Site Management and Leadership Construction Equipment Management – Earthwork Equipment • Clamshell consist of hydraulically controlled bucket suspended from a lifting arm • It is mainly used for deep confined cuttings in pits and trenches CVE213 Site Organisational Studies I Site Management and Leadership Construction Equipment Management – Earthwork Equipment • Dozers are used for moving earth up to a distance of about 100m and act as a towing tractor and pusher to scraper machines • They can be track-mounted or wheel-mounted CVE213 Site Organisational Studies I Site Management and Leadership Construction Equipment Management – Earthwork Equipment • Roller compactor is mainly used for compaction of earth and other materials in large works of highways, canals and airports CVE213 Site Organisational Studies I Site Management and Leadership Construction Equipment Management – Earthwork Equipment • Scrapers are used for site levelling, loading, hauling over distances between 150m – 900m. • They may be towed, two-axle or three-axle type CVE213 Site Organisational Studies I Site Management and Leadership Construction Equipment Management – Earthwork Equipment • Dumpers are used for horizontal transportation of materials on and off sites • Large capacity dumpers are used in mines and quarries CVE213 Site Organisational Studies I Site Management and Leadership Construction Equipment Management – Earthwork Equipment • Graders are used for grading and finishing the upper surface of the earthen formations and embankments • They usually operate in the forward direction CVE213 Site Organisational Studies I Site Management and Leadership Construction Equipment Management – Earthwork Equipment • The selection of earthwork equipments mainly depends on; – Quantities of materials to be moved – The available time to complete the work – The prevailing soil types, the swell and compaction factors, etc. – The job conditions including factors such as availability of loading and dumping area, accessibility of site, traffic flows and weather conditions at site CVE213 Site Organisational Studies I Site Management and Leadership Construction Equipment Management – Earthwork Equipment • In order to determine the number of earthwork equipment needed, the planner needs to determine the following – The suitable class of equipment for earthwork • E.g. if the soil to be excavated is loose or marshy, and bulk excavation is involved in the project, one may opt for a dragline – The appropriate model of equipment based on different characteristics such as payload of bucket and speeds required • E.g. draglines come in different capacities, ranging from 0.38 cum to 3.06 cum; • Scrapers range from 8 cum to 50cum, etc – The number of equipment needed for the project to carry out the given quantity – The number of associated equipment required to support the main equipment CVE213 Site Organisational Studies I Site Management and Leadership Construction Equipment Management – Concrete Equipment • Concrete batching and mixing plant are mainly used for weighing and mixing large quantity of concrete materials – 20cum/hr t0 250 cum/hr CVE213 Site Organisational Studies I Site Management and Leadership Construction Equipment Management – Concrete Equipment • Concrete mixers are mainly used for mixing small quantities of concrete – 200l/batch for small mixers – 200 – 750l/batch for large mixers CVE213 Site Organisational Studies I Site Management and Leadership Construction Equipment Management – Concrete Equipment • Concrete transit mixers are used for transporting concrete from batching point (3cum – 9cum) CVE213 Site Organisational Studies I Site Management and Leadership Construction Equipment Management – Concrete Equipment • Concrete pumps are used for horizontal and vertical transportation of large volumes of concrete in short duration (30cum/hr – 120 cum/hr) CVE213 Site Organisational Studies I Site Management and Leadership Construction Equipment Management – Concrete Equipment • Factors considered during concreting equipment selection include; – Site characteristics such as boundary conditions, noise limitation and other restrictions – Equipment availability – local availability of equipments, whether the contractor owns that equipment – Continuity of operation – Effect of permanent work – Weather conditions – Temporary works – Time restrictions – Concrete specifications CVE213 Site Organisational Studies I Site Management and Leadership Construction Equipment Management – Concrete Equipment • Concrete-mixing equipment selection depends on factors such as – Maximum and the total output required in a given time frame – The method of transporting the mixed concrete – The requirement of discharge height of the mixer CVE213 Site Organisational Studies I Site Management and Leadership Construction Equipment Management – Concrete Equipment • Concrete placement equipment selection depends on factors such as – Capacity of the vehicle – The output of the vehicle – The site characteristics – The weather conditions – The rental costs, the temporary haul roads CVE213 Site Organisational Studies I Site Management and Leadership Construction Equipment Management – Hoisting Equipment • Hoisting equipments are used mainly for lifting or lowering of unit load and others • Hoisting equipment can be classified into two main groups – Hoists • Boom hoists, Chain hoists, Electric hoists – Cranes • Derrick crane, Mobile crane, Tower crane CVE213 Site Organisational Studies I Site Management and Leadership Construction Equipment Management – Hoisting Equipment • Boom hoists are used to lift weights on the hooks that are attached to the special metal ropes designed to bear maximum loads • Mostly used as industrial machine where it loads the weight on containers CVE213 Site Organisational Studies I Site Management and Leadership Construction Equipment Management – Hoisting Equipment • Chain hoists consist of chain rope and pulley that is used to move the load from up to down CVE213 Site Organisational Studies I Site Management and Leadership Construction Equipment Management – Hoisting Equipment • Electric hoists are modernized form of chain and boom hoist mostly used in the industries for fast working • Popular in material handling industries because it saves labour costs by handling maximum loads at a time with no damage threats CVE213 Site Organisational Studies I Site Management and Leadership Construction Equipment Management – Hoisting Equipment • Tractor hoist consist of a boom that is attached with base of tractor and a hook with rope is installed on this boom that can operate through driver controls CVE213 Site Organisational Studies I Site Management and Leadership Construction Equipment Management – Hoisting Equipment • Cranes are considered to be one of the most important equipment used in construction due to their key role in performing lifting tasks all over the construction site • Plenty of crane models are available in different shapes and sizes • They fall into three categories – Derick Cranes – Mobile Cranes – Tower Cranes CVE213 Site Organisational Studies I Site Management and Leadership Construction Equipment Management – Hoisting Equipment • Factors influencing the selection of cranes include – Building design • Building height, project duration – Capability • Power supply, load lifting frequency, operators visibility – Safety • Initial planning and engineering – Economy • Cost of move in, setup, and move out, cost for rent, productivity – Site Conditions • Soil stability and ground conditions, access road requirements and accessibility CVE213 Site Organisational Studies I Site Management and Leadership Construction Equipment Management – Hoisting Equipment • Mobile cranes – Adequate for all types of structures (up to 107m) – Used for shorter project duration (less than 4 months) – Not considered to be very safe due to lack of safety devices and limited switches to prevent overloading – Can operate in muddy terrain but requires good ground conditions – Needs adequate operating clearance CVE213 Site Organisational Studies I Site Management and Leadership Construction Equipment Management – Hoisting Equipment • Tower Cranes – Preferable for high rise (over 107m) – Used for longer project duration – Considered to be very safe due to the presence of limit switches – Can operate where ground conditions are poor – Does not need adequate operating clearance CVE213 Site Organisational Studies I Site Management and Leadership Construction Equipment Management – Hoisting Equipment • Derrick Cranes – Preferable for high-rise and apartment buildings – Can be used for both long term and short term projects – Cheaper than mobile and tower cranes – Not considered to be safe – Used when clearance is inadequate for the other units and sufficient space is unavailable for the erection of a tower foundation CVE213 Site Organisational Studies I Site Management and Leadership Construction Equipment Management – Hoisting Equipment • Derrick Cranes CVE213 Site Organisational Studies I Site Management and Leadership Construction Equipment Management – Productivity • Productivity is the unit output per hour – An accurate prediction of the productivity of construction equipment is critical for construction management – Peak productivity – is the theoretical productivity governed by design limitations only – Actual productivity – productivity after taking care of effective working hours and job management factor on peak productivity • Equipments can be broadly classified into two based on equipment productivity concepts – Cyclic Operating equipment – Continuously Operating equipment CVE213 Site Organisational Studies I Site Management and Leadership Construction Equipment Management – Productivity • Cyclic operating equipments – are machines which are intentionally or unintentionally influenced by their operators 𝑄𝑎 = 𝑉𝑛 × 𝑛𝑜 × η 𝑛𝑜 = Where Qa = Actual Productivity (Bm3/hr) Vn = Volume per cycle (Bm3) 𝛈 = Efficiency of the equipment no = number of cycle/unit time (usually in hours). To = theoretical cycle time 60 𝑇𝑜 CVE213 Site Organisational Studies I Site Management and Leadership Construction Equipment Management – Productivity • Continuously operating equipments – are machines that continuously operate – E.g. pumps, conveyor belts, etc 𝑄𝑎 = 𝑉𝑛 × 𝑎 × 𝑛𝑜 × 60 × η Where Qa = Actual Productivity (Bm3/hr) Vn = Volume per bucket (Bm3) a = Number of buckets 𝛈 = Efficiency of the equipment no = number of cycle/unit time (usually in hours). CVE213 Site Organisational Studies I Site Management and Leadership Construction Equipment Management – Productivity • Productivity of bull dozers are calculated based on their blade load 𝐵𝑙𝑎𝑑𝑒 𝐿𝑜𝑎𝑑 (𝑙𝑐𝑚) = 0.375 × 𝑊𝐻𝐿 Where W = Average width of pile cut by the blade H = Average height of the pile cut by the blade L = Greatest length of the pile cut by the blade CVE213 Site Organisational Studies I Site Management and Leadership Construction Equipment Management – Productivity • A Case 750K bulldozer with a 2.5m blade is to be used to excavate and push fairly loose earth material. According to the soils report, the soil to be moved has a 23% swell factor. When the bulldozer is hauled to the site, a couple of blade loads are excavated to estimate a typical load. The average height of a load was 1.2m, with average load width of 1.8m and load length of 2.7m. The load time suggested by the manufacturer is about 0.08min. The earth material is pushed about 60m with an average speed of about 4.2km/h. Backtrack distance is about 75m with a speed of about 5.2km/hr. Once back to the hole, the bulldozer takes about 0.06min to reposition. An operating cost of GhC250/h is determined with labour cost of GhC150/hr. – What is the unit cost for the work, if there is about 920 bcm of surface material that must be moved by the 750K bulldozer and the operator works 50min per 60-min hour. CVE213 Site Organisational Studies I Site Management and Leadership Construction Equipment Management – Productivity First calculate the volume of material to be moved in one production cycle 𝐵𝑙𝑎𝑑𝑒 𝐿𝑜𝑎𝑑 𝑙𝑐𝑚 𝑉𝑜𝑙𝑢𝑚𝑒 = 0.375 × 1.8 × 1.2 × 2.7 = 𝟐. 𝟏𝟖𝟕𝒎𝟑 Calculate how much earth in the bank state to be moved in one production cycle by factoring in the swell factor 𝐵𝑎𝑛𝑘 𝑉𝑜𝑙𝑢𝑚𝑒(𝑏𝑐𝑚) = 2.187 = 𝟏. 𝟕𝟕𝟖𝒎𝟑 1.23 Calculate the cycle time for one production cycle 60 𝐻𝑎𝑢𝑙 𝑡𝑖𝑚𝑒 = 1000 = 𝟎. 𝟎𝟏𝟒𝟑𝒉𝒓𝒔 = 𝟎. 𝟖𝟓𝟕𝒎𝒊𝒏 4.2 75 𝐵𝑎𝑐𝑘 𝑇𝑟𝑎𝑐𝑘 𝑡𝑖𝑚𝑒 = 1000 = 𝟎. 𝟎𝟏𝟒𝟒𝒉𝒓𝒔 = 𝟎. 𝟖𝟔𝟓𝒎𝒊𝒏 5.2 𝐶𝑦𝑐𝑙𝑒 𝑡𝑖𝑚𝑒 = 𝑙𝑜𝑎𝑑 + ℎ𝑎𝑢𝑙 + 𝑏𝑎𝑐𝑘𝑡𝑟𝑎𝑐𝑘 + 𝑟𝑒𝑝𝑜𝑠𝑖𝑡𝑖𝑜𝑛 𝐶𝑦𝑐𝑙𝑒 𝑡𝑖𝑚𝑒 = 0.08 + 0.857 + 0.865 + 0.06 = 𝟏. 𝟖𝟔𝟐𝒎𝒊𝒏 CVE213 Site Organisational Studies I Site Management and Leadership Construction Equipment Management – Productivity Calculate the work hour productivity if the operator works 50min per 60-min hour 𝑃𝑟𝑜𝑑𝑢𝑐𝑡𝑖𝑣𝑒 𝑤𝑜𝑟𝑘𝑖𝑛𝑔 ℎ𝑜𝑢𝑟𝑠 𝑊𝑜𝑟𝑘 ℎ𝑜𝑢𝑟 𝑝𝑟𝑜𝑑𝑢𝑐𝑡𝑖𝑣𝑖𝑡𝑦 = × 𝐵𝑙𝑎𝑑𝑒 𝑙𝑜𝑎𝑑 (𝑏𝑐𝑚) 𝐶𝑦𝑐𝑙𝑒 𝑡𝑖𝑚𝑒 50 𝑊𝑜𝑟𝑘 ℎ𝑜𝑢𝑟 𝑝𝑟𝑜𝑑𝑢𝑐𝑡𝑖𝑣𝑖𝑡𝑦 = × 1.778 = 𝟒𝟕. 𝟕𝟒 𝒃𝒄𝒎/𝒘𝒐𝒓𝒌𝒉𝒐𝒖𝒓 1.862 Calculate how long it will take to move the 920 bcm 920 𝑇𝑜𝑡𝑎𝑙 𝑤𝑜𝑟𝑘𝑖𝑛𝑔 𝑡𝑖𝑚𝑒 = = 𝟏𝟗. 𝟐𝟕𝒉𝒓 ≈ 𝟏𝟗. 𝟓𝒉𝒓 47.74 Calculate how much it will cost in total 𝑇𝑜𝑡𝑎𝑙 𝑐𝑜𝑠𝑡 = 250 + 150 × 19.5 = 𝑮𝒉𝑪 𝟕, 𝟖𝟎𝟎 Calculate the unit cost to perform the work 7,800 𝑈𝑛𝑖𝑡 𝑐𝑜𝑠𝑡 = = 𝑮𝒉𝑪 𝟖. 𝟒𝟕 𝒃𝒄𝒎 𝒕𝒐 𝒎𝒐𝒗𝒆 𝒆𝒂𝒓𝒕𝒉 920 CVE213 Site Organisational Studies I Site Management and Leadership Labour Productivity • Productivity in construction is often broadly defined as output per labour hour • Labour constitutes a large part of the construction cost • The quantity of labour hours in performing a task in construction is more susceptible to the influence of management than are materials or capital • The measure of productivity is often referred to as labour productivity CVE213 Site Organisational Studies I Site Management and Leadership Labour Productivity • Labour productivity is a measure of the overall effectiveness of an operating system in utilizing labour, equipment and capital to convert labour efforts into useful output – It is not a measure of capabilities of labour alone – Investing in a new equipment to perform certain tasks in construction may increase output – thus higher labour productivity CVE213 Site Organisational Studies I Site Management and Leadership Labour Productivity • Factors affecting job-site productivity may be categorized into three – Labour characteristics • Age, skill, workforce experience, leadership and motivation – Project work conditions • Job size and complexity, site accessibility, labour availability, equipment utilization, climate – Non-productive activities CVE213 Site Organisational Studies I Site Management and Leadership Labour Productivity • Non-productive activities associated with a project may or may not be paid by the owner – They however take up potential labour resources • The non-productive activities include; – Indirect labour required to maintain the progress of the project – Rework for correcting unsatisfactory work – Temporary work stoppage due to inclement weather or material shortage – Time off for union activities – Absentee time, including late start and early quits – Non-working holidays – Strikes CVE213 Site Organisational Studies I Site Management and Leadership Labour Productivity • Factors that may be used in evaluating labour characteristics include – Quality of work – caliber of work produced or accomplished – Quantity of work – volume of acceptable work – Job knowledge – demonstrated knowledge of requirements, methods, techniques and skils – Related work knowledge – knowledge of effect of work upon other areas and knowledge of related areas which have influence on assigned work – Resource utilization – ability to delineate project needs and locate, plan and effectively use all resources available – Dependability – reliability in assuming and carrying our commitments and obligations CVE213 Site Organisational Studies I Site Management and Leadership Labour Productivity • Factors cont. – Analytical ability – effectiveness in thinking through a problem and reaching sound conclusions – Communicative ability – effectiveness in using oral and written communications and in keeping subordinates, associates, superiors and others adequately informed – Interpersonal skills – effectiveness in relating in an appropriate and productive manner to others – Ability to work under pressure – ability to meet tight deadlines and adapt to changes – Security sensitivity – ability to handle confidential information appropriately and to exercise care in safeguarding sensitive information CVE213 Site Organisational Studies I Site Management and Leadership Labour Productivity • Factors cont. – Safety consciousness – has knowledge of good safety practices and demonstrate awareness of own personal safety and the safety of others – Profit and Cost Sensitivity – ability to seek out, generate and implement profit-making ideas – Planning effectiveness – ability to anticipate needs, forecast conditions, set goals and standards, plan and schedule work and measure results – Leadership – ability to develop in others the willingness and desire to work towards common objectives – Delegating – effectiveness in delegating work appropriately – Development of people – ability to select, train and appraise personnel, set standards of performance, and provide motivation to grow their capacity CVE213 Site Organisational Studies I Site Management and Leadership Materials Management • Materials management is an important element in project planning and control – It represent a major expense in construction – Minimizing procurement or purchase costs presents important opportunity to cut down costs • Poor materials management can result in large and avoidable costs during construction – Capital may be tied up along with interest charges if materials are purchased early – Materials may deteriorate during storage or be stolen if care is not taken – Delays and extra expenses may be incurred if materials required for particular activities are not available • Ensuring timely flow of materials is therefore of important concern to project managers CVE213 Site Organisational Studies I Site Management and Leadership Materials Management • Decisions about material procurement may be required during the initial planning and scheduling stages and not just during the monitoring stage • Availability of materials may greatly influence the schedule in projects with a fast track or very tight time schedule – Sufficient time for obtaining necessary materials must be allowed CVE213 Site Organisational Studies I Site Management and Leadership Materials Management – Procurement and Delivery • Materials for delivery to and from a construction site may be broadly classified as – Bulk materials – Standard off-the-shelf materials – Fabricated members or units • The process of delivery, including transportation, field storage and installation will be different for these classes of materials • Equipment needed to handle and haul these classes of materials will also be different CVE213 Site Organisational Studies I Site Management and Leadership Materials Management – Procurement and Delivery • Bulk materials – refer to materials in their natural or semi-processed state – E.g. earthwork to be excavated, wet concrete mix, etc – Usually encountered in large quantities in construction • Some bulk materials such as earthwork or gravels may be measured in bank (solid in-situ) volume • Quantities of materials for delivery may be substantially different when expressed in different measures of volume depending on the characteristics of such materials CVE213 Site Organisational Studies I Site Management and Leadership Materials Management – Procurement and Delivery • Standard off-the-shelf materials are used extensively in the chemical process industry – E.g. pipes, valves, etc – They can be stockpiled, making their delivery process relatively simple • Fabricated members are pre-processed in a shop to simplify the field installation procedures – E.g. steel beams, columns, precast beams, prestressed beams, etc. – If work can be done in the shop where working conditions can be better controlled, then it is advisable to do so, provided the fabricated member or unit can be shipped to the construction site in a satisfactory manner at a reasonable cost CVE213 Site Organisational Studies I Site Management and Leadership Materials Management – Inventory Control • Goods purchased represent an inventory used during the construction process • Main aim of inventory control is to minimize the total cost of keeping the inventory while making tradeoffs among major categories of costs – Purchase cost – Order cost – Holding cost – Unavailable cost CVE213 Site Organisational Studies I Site Management and Leadership Materials Management – Inventory Control • Purchase cost – is the unit purchase price from an external source including transportation and freight costs – Common to receive discounts for bulk purchases for construction materials – Unit purchase cost therefore declines as quantity increases – Reductions may reflect manufacturers’ marketing policies, economies of scale in the material production, or scale economies in transportation – There may also be advantages in having homogeneous materials • E.g. a bulk order to ensure the same colour or size of items CVE213 Site Organisational Studies I Site Management and Leadership Materials Management – Inventory Control • Factors affecting unit costs of materials may depend on – Bargaining leverage – Quantities – Delivery time • Organisations with potential for long-term purchase volume can command better bargaining leverage • While orders in large quantities may result in lower unit prices, they may also increase holding costs – Thus causing problems in cash flow • Design characteristics which include items of odd sizes or shapes should be avoided – Normally not available in standard stockpile and can increase prices CVE213 Site Organisational Studies I Site Management and Leadership Materials Management – Inventory Control • Transportation costs are affected by shipment sizes • Shipment by the full load of a carrier often reduces prices and assures quicker delivery – Carrier can travel from the origin to the destination of the full load without having to stop for delivering part of the cargo at other stations • Avoiding transshipment also help in reducing shipping cost – Transshipment is shipment of goods to an intermediate destination, then to another destination • Requirement of delicate handling of some items may favour a more expensive mode of transportation to avoid breakage and replacement cost CVE213 Site Organisational Studies I Site Management and Leadership Materials Management – Inventory Control • Order cost reflect the administrative expense of issuing a purchase order to an outside supplier • Order costs include; – – – – – – – Expenses of making requisitions Analysing alternative vendors Writing purchase orders Receiving materials Inspecting materials Checking on orders Maintaining records of the entire process • Order costs are usually only a small portion of total costs of material management in construction projects CVE213 Site Organisational Studies I Site Management and Leadership Materials Management – Inventory Control • Holding or carrying costs are primarily the result of capital costs, handling, storage, obsolescence, shrinkage and deterioration • Capital cost results from the opportunity cost or financial expense of capital tied up in inventory • Once payment for goods is made, borrowing costs are incurred – Consequently, a capital carrying cost is incurred which is equal to the value of the inventory during the period multiplied by the interest rate obtainable or paid during that period • Capital costs only accumulate when payment of materials actually occurs – Many organisations attempt to delay payments as long as possible to minimize such costs. CVE213 Site Organisational Studies I Site Management and Leadership Materials Management – Inventory Control • Handling and storage represent the movement and protection charges incurred for materials • Storage costs also include the disruption caused to other project activities by large inventories of materials that get in the way • Obsolescence is the risk that an item will lose value because of changes in specifications • Shrinkage is the decrease in inventory over time due to theft or loss • Deterioration reflects a change in material quality due to age or environmental degradation CVE213 Site Organisational Studies I Site Management and Leadership Materials Management – Inventory Control • Unavailability cost is incurred when a desired material is not available at the desired time • Shortages may delay work, thereby wasting labour resources or delaying the completion of the entire project • Cost associated with shortage may be difficult to assess – If the material used for one activity is not available, it may be possible to assign workers to other activities – Depending on which activities are critical, the project may not be delayed CVE213 Site Organisational Studies I Site Management and Leadership Materials Management – Control System • Objectives of adopting a material control system include – To assess material requirements so as to allow for periods of manufacture, distribution and delivery appropriate to the construction situation – To facilitate forward planning, thus enabling material supplies and prices to be fully evaluated – To enable checks to be made on material utilization with the objective of controlling or reducing waste – To enable key materials which affect the construction progress to be incorporated into the contract programme – To take advantage of favourable trading conditions, and where applicable, bulk buying facilities – To enable site management to assess the influence of materials on planning procedures and site layout – To incorporate materials requirement into the planning process CVE213 Site Organisational Studies I Site Management and Leadership Stores Management • Stores management is concerned with ensuring that all the activities involved in storekeeping and stock control are carried out efficiently and economically by those employed in the store • Objectives of site stores management is to – ensure stores staff correctly issue and charge items – Maintain stock records to ensure accurate stock taking procedures – Assist operatives to acquire materials, items and equipment from stores CVE213 Site Organisational Studies I Site Management and Leadership Stores Management • Functions of a properly organized stores system include; – Completing a purchase requisition for each purchase order. Purchasing officer will be responsible for the placement of stores purchase orders – Availability of goods inwards inspector to check or test incoming materials to ensure that they conform to requirements and are fit to pass into stores for subsequent project use – Goods inwards receipt notes to be issued by goods inwards inspectors when they are satisfied that goods comply with purchase order needs • One copy will accompany the materials into stores – Reject notes are produced by inspectors when deliveries are deficient or damaged or unacceptable. • They ensure that replacement materials are obtained quickly CVE213 Site Organisational Studies I Site Management and Leadership Stores Management – Shortage list are compiled by store men to highlight any stock deficiencies. – Stock control procedures to govern the procurement and stockholding levels of materials – Requisitions for stores issues – store requisition authorize the release of materials from stores and charged to a particular job. • Form contains items like job number, department, description of material, quantity, unit and cost if necessary – Stores issues – issues require the authority of project management staff. The usual procedure for the release of material from stock is that the person requiring the materials presents a properly authorized stores requisition to the store man – Surplus materials – at the end of the project, an inventory should be made of the remaining materials in stock and arrange for disposal as directed by the Project manager. CVE213 Site Organisational Studies I Site Management and Leadership Stores Management • Stock control comprises mainly the clerical and administrative functions of stores work • It includes; – Ensuring that the right types and qualities of materials needed for work, are always available when required – Ensuring that stock is issued in the correct sequence, that is, first in first out, so that “older” stock is not allowed to deteriorate by being kept too long in the store – Maintaining records showing the “movement” of items into and out of the store – Ensuring that the correct ‘stock levels’ of the various items are set and are maintained, that orders and reorders are made in good time, and that what is ordered is received – Checking, counting or measuring stock to ensure that records are accurate and that no losses are occurring due to pilfering, theft, damage or poor storage – Pricing and valuing that items in the store CVE213 Site Organisational Studies I Organisational Behaviour Fundamentals of Organisational Behaviour • Organisational behaviour is the study and application of knowledge about how individuals and groups act in organisations • All three components of organizational behaviour needs to be studied – Individual – The Group – The organisation • The main objective of any organisation is to achieve results effectively and efficiently – Effectiveness means producing the intended or expected results – Efficiency borders on competency in performance and use of resources CVE213 Site Organisational Studies I Organisational Behaviour Fundamentals of Organisational Behaviour • Whenever people interact, may factors come into play – Constructive, destructive, positive, negative, etc. • Organisational behaviour looks at work behaviour – What people do in an organisation – How that behaviour affects the performance of the organisation • Organisational behaviour is interested in understanding, predicting and controlling overt behaviour at work CVE213 Site Organisational Studies I Organisational Behaviour Fundamentals of Organisational Behaviour • The three levels of analysis (individual, group and organisation) tend to correspond closely to the levels of a manager’s responsibility • Individuals bring a complex set of characteristics, experiences, skills, value and attitudes to the workplace – They have an impact on their level of performance • Managers can have impact on employee behaviour through motivation, counselling, training, communication, vision sharing and job satisfaction CVE213 Site Organisational Studies I Organisational Behaviour Fundamentals of Organisational Behaviour • Work groups are created within organisations to enable individuals to interact and contribute to an organisation’s production purpose – People behave differently when working in a group – Communication patterns and levels of conflict will affect group behaviour • Communication is the way in which information is transmitted between the individual and the group – it is an essential link between the three levels • The group and the organisation are in turn linked through leadership and the authority conveyed through the organisational structure CVE213 Site Organisational Studies I Organisational Behaviour Fundamentals of Organisational Behaviour • Changing and developing employee behaviour is a key factor in organisational behaviour – Organisation’s human resources practices (e.g. selection processes, training programmes, performance appraisals, etc) influence employee’s productivity, absenteeism, high turnover and job satisfaction • Managers are responsible for the performance of one or more subordinates • Manager’s immediate concerns are – Task performance (quality and quantity of work produced) – Human resource maintenance • Absenteeism, grievances, turnover, performance, etc CVE213 Site Organisational Studies I Organisational Behaviour Fundamentals of Organisational Behaviour • Organisational behaviour study helps to develop the ability to solve problems and prevent them from occurring • Good managers are problem solvers • It is important for managers to have some idea of why people do what they do in an organisation • Examples of problem indicators include – Absenteeism, high turnover, negative attitudes, poor quality work, declining work quantity CVE213 Site Organisational Studies I Organisational Behaviour Conflict Management • Conflicts among team members on projects are inevitable due to its dynamic nature • Conflict is a disagreement between people caused by personality differences, miscommunication, or technical and administrative issues • Conflict is beneficial when it pushes people to higher levels of performance or when it results in the development of new information that enhances the decision-making process • Conflict is detrimental when it impedes project objectives with no positive consequences CVE213 Site Organisational Studies I Organisational Behaviour Conflict Management • Little or no conflict decreases effectiveness in the organisation – It produces apathy, stagnation, and lack of new ideas • High level of conflict also decreases effectiveness in the organisation – It creates disruption, chaos and lack of cooperation • An optimal level of conflict increases organisational effectives – It produces self-evaluation and innovation • Managers, therefore should not try to eliminate conflict but manage it. CVE213 Site Organisational Studies I Organisational Behaviour Conflict Management • Conflicts can arise over the following – The distribution of resources – Access to information – Disagreement about decisions – The perception by an individual that he or she is not respected or fully part of the team – Different agenda among team members • Conflicts can have a negative influence by fostering interpersonal hostility, reduced performance and dissension in the team CVE213 Site Organisational Studies I Organisational Behaviour Conflict Management • On a construction site, some of the things that lead to conflicts may include – Modification of drawings – Reassignment of team members – Changes in meeting dates that are not communicated to other team members • Ways of managing conflicts include; – – – – – Withdrawal Smoothing Compromising Confronting Forcing CVE213 Site Organisational Studies I Organisational Behaviour Conflict Management • Withdrawal means giving up or retreating from the conflict issue • The person purposely ignores the conflict because he wants to avoid causing problems, or out of fear, or feeling inadequate to resolve the issue – It is a poor way of managing conflicts – It is a stopgap attempt to resolve conflicts and does not solve the problem – It is a passive approach to solving a problem and only temporarily delays the inevitable future reoccurrence of the problem CVE213 Site Organisational Studies I Organisational Behaviour Conflict Management • Smoothing seeks to maintain friendly relations by emphasizing common areas of agreement and deemphasizing areas of differences • Smoothing is a more active technique to managing conflicts • However, it only avoid the conflict temporarily by appeasing one or more of the parties involved in the conflict • It may not address the real issues – It may be effective because identifying areas of agreement may put the disagreement into clearer perspective – Project work can therefore continue in areas where there is agreement CVE213 Site Organisational Studies I Organisational Behaviour Conflict Management • Compromising involves bargaining between the disputing parties to reach an acceptable agreement • Disputing parties make trade-offs that often fall short of idea solutions • Compromising does not result in a definitive resolution – Leaving opportunities for a reoccurrence of the conflicts CVE213 Site Organisational Studies I Organisational Behaviour Conflict Management • Confronting is a method of resolving conflicts that requires participation by all parties involved in the conflict • Requires an open dialogue to identify the root problems and a joint effort to resolving the conflict • Potential to find final, mutually acceptable solutions is usually higher • For some situations, it may be necessary for the project manager to exercise authority to force a resolution of the conflict • Forcing a resolution may create resentment or other adverse reactions that can affect the team’s future performance CVE213 Site Organisational Studies I Organisational Behaviour Conflict Management • Forcing involves a straightforward use of authority power in resolving the conflict by exerting one’s viewpoint over the others • Should be used only as a last resort or in urgent situations • It may cause resentment and deterioration of the work climate CVE213 Site Organisational Studies I Organisational Behaviour Leadership and Motivation • Motivation involves providing leadership for subordinates – Requires the ability to inspire them to give of their best in achieving the objectives as well as in their own best interest – Can be done by creating a good morale or working spirit amongst all employees • A person’s motivation is a combination of desire and energy directed at achieving a goal • Influencing someone’s motivation means getting them to want to do what you know must be done • Supervisors want to motivate employees because it gets more work down from them with less effort on the part of the organisation • As a leader, you have the power to influence motivation CVE213 Site Organisational Studies I Organisational Behaviour Leadership and Motivation • Objectives of an organisation can be achieved only through the efforts of people – They need to be motivated (induced, persuaded) to give off their best – What motivates one person or group of people might not motivate another – A manager should therefore get to know something about each of their subordinates as much as possible • Financial rewards are more of an incentive than a motivation to many people • Many employees today are interested in gaining more from their employment than just money – Job satisfaction – doing jobs which they enjoy CVE213 Site Organisational Studies I Organisational Behaviour Leadership and Motivation • In the early 1950s, A. H. Maslow developed a theory of motivation called the hierarchy of needs • The theory has been used to – Understand why people behave they way they do – Motivate them – Enlist their commitment • Maslow proposed that humans are wanting animals and their wants become needs – The quest to satisfy their needs drives or motivates people CVE213 Site Organisational Studies I Organisational Behaviour Leadership and Motivation • The needs include basic physical and psychological needs, which are perceived in the human mind and satisfied by material things • Maslow proposed that the needs of humans follow a hierarchy, beginning with comfort and basic survival – Food, clothing and shelter • Once this first need is satisfied, humans seek to satisfy the next higher level of need – Belonging, ego, and finally self-fulfilment CVE213 Site Organisational Studies I Leadership and Motivation Organisational Behaviour CVE213 Site Organisational Studies I Organisational Behaviour Leadership and Motivation • Determining the needs of people is not easy to accomplish in the day-to-day work environment – It may be necessary to spend time in an informal setting to build a relationship that provides understanding of what is important to a team member • E.g a team member may be concerned about having adequate time to attend a child’s school function or care for an ill family member. Such a member may be motivated by being allowed flexible work hours with the understanding that the time will be made up at nights or on week-ends – Needs of people may also change CVE213 Site Organisational Studies I Organisational Behaviour Leadership and Motivation – Ways of Motivating a Team • Allow the needs of your team to coincide with the needs of your organisation – Needs of job security, promotion, raises – People are also influenced by internal forces such as values, morals, ethics – Ensure team is trained, encouraged and have opportunity to advance • Reward good behaviour – Certificates, letter, a thank you note may seem small and insignificant, but can be powerful motivation tools – Rewards should be specific and prompt, citing the specific action that made the person receive the award CVE213 Site Organisational Studies I Organisational Behaviour Leadership and Motivation – Ways of Motivating a Team • Set an example – The leader must be a role model that wants others to grow into • Allow your team to be part of the planning and problem solving process – It helps in their development and allows employers to coach employees – It gives them a personal interest in seeing to a successful implementation of the plan – Communication is clearer as everyone has a better understanding of what role they must play as part of the team – Creates an open trusting communication bond CVE213 Site Organisational Studies I Organisational Behaviour Leadership and Motivation – Ways of Motivating a Team • Look out for your team – You must show concern for your team members even though you do not have control over their personal lives • Keep them informed – It allow members to have a sense of control over their lives • Counsel people who behave in a way that is counter to the company’s goals – Let people who are not performing to an acceptable standard know of them – Protect people when needed • Trust and respect – Give people the trust and respect they deserve and they will respond to requests much more favourably CVE213 Site Organisational Studies I Organisational Behaviour Leadership and Motivation – Morale Development • Morale is the mental, emotional and spiritual state of a person • Ethics are the morale principles that control or influences a person’s behaviour • An employer is to accept certain rights of the employees – Right of conscientious refusal – it is the right of the employee to refuse to engage in unethical behaviour and to refuse to do so solely because one views it as unethical CVE213 Site Organisational Studies I Organisational Behaviour Leadership and Motivation – Morale Development – Right to whistle blowing – whistle blowing is alerting relevant persons to some immoral or illegal act in the organisation by an employee • There are two major whistle blowing – internal and external – Right to pursue non-work activities of choice – employees should be permitted to join any society or movement and pursue its activities outside their duty hours • they however cannot sabotage the employer’s interest during off-hours – Right to privacy off the job – employees have the right to lead their private lives according to their choice and employers should not interfere into this CVE213 Site Organisational Studies I Organisational Behaviour Leadership and Motivation – Morale Development – Right to equal treatment while on the job – equal work equal pay should be the slogan followed by any employer • Avoiding discrimination leads to happy employees and high morale – Right for protection against sexual harassment – employer should be always monitoring whether there is any sexual harassment in his organization • an effective grievance redressal mechanism will improve the morale of employees CVE213 Site Organisational Studies I Organisational Behaviour Leadership and Motivation – Cultivating Team Spirit • Team spirit is the catalytic agent to performance • Strategic plans, technology and capital investments are important in construction projects, but emotional commitment of the employees executing the plans will determine if they succeed or sink CVE213 Site Organisational Studies I Organisational Behaviour Leadership and Motivation – Cultivating Team Spirit • Ways of cultivating team spirit include – Wall of fame – display awards, trophies, certificates or other professional or personal success on a shelf in the office dedicated to showing off individual or team achievements – Peer pats - send message to team, acknowledging a worker of an award or a good job done. • Do now wait for management to recognize them – Personal messages – encourage team members to create some sort of personal message or information • Accolades, hobbies, greatest achievement, holiday retreats – Brain power inventory – hold social events involving team members to have people show off the skills and interests • Musicians, instrumentalist, artists, sportsmen etc – Plan to attend sporting events, concerts, movies, etc as a group – rent a bus and ride together – Recognise and celebrate significant achievement and milestones reached CVE213 Site Organisational Studies I Site Supervision Site Supervision • Effective supervision is concerned with – – – – – Monitoring work in hand Reviewing progress against work plans Discussing problems Developing solutions Delegating new tasks and projects • Effective supervision should maximize learning on the job and support the individual in a way which is appropriate to their stage of development • Effective supervision is a vital tool in helping ensure peak performance from employees – It ensure everyone is working together towards a common goal CVE213 Site Organisational Studies I Site Supervision Site Supervision – Monitoring and Control • Monitoring serves two main purposes – Check the quality and quantity of work being done – Provides data that can be used to improve future operations • There are two aspects of monitoring – Site visits and inspections – Desk review CVE213 Site Organisational Studies I Site Supervision Site Supervision – Monitoring and Control • Site visits enable the site manager to get familiar with site conditions and to gain first hand knowledge of the extent and quality of work done • The manager can advice on problems as they arise • Seeing the manager on site also boost the morale of workers and improve their standard of work and output CVE213 Site Organisational Studies I Site Supervision Site Supervision – Monitoring and Control • Desk review is an office task which involves reviewing all the documentation so as to assess the performance of the programme – Inspection reports – Resource requirement forms – Work schedules – Completed worksheets • It provides an opportunity to check that adequate resources were allocated to each task CVE213 Site Organisational Studies I Site Supervision Site Supervision – Monitoring and Control • Progress of work is tracked by comparing actual work done with that planned – Cost estimates can be compared with expenditure – Variances or shortfalls are noted • Variances in schedule may result from inadequate assignment of resources, poor control over the work, lower productivity etc • Weekly site meeting are organised to discuss results of review work and find ways of correcting any variances • Introducing incentives for achieving the programme of work may motivate workers CVE213 Site Organisational Studies I Site Supervision Site Supervision – Monitoring and Control • Variation order is an instruction that is given to the contractor concerning any addition or subtraction to the original contract • The engineer/architect is authorized to order the contractor to – Carry out extra works – Omit an item of work – Make changes to the design of the project – Alters the amount specified in the contract CVE213 Site Organisational Studies I Site Supervision Variation Order Example • A road rehabilitation project has a contract sum of GhC 500,000. The resident engineer authorized the following variations and the contractors executed them on site: 3.4 A change from 450mm U-drain costing GhC 65,600 to 600mm U-drain costing GhC 88,400 3.5 A reduction in the area of granular roadbase from 24,000m2 to 22,800m2 at a bill rate of GhC 2.50 per m2 3.3 Addition of 2 No. inspection chambers, each costing GhC 904 3.8 GhC 6540 extra cost of bridge works – Prepare a variation order and determine the new contract sum CVE213 Site Organisational Studies I Site Supervision Variation Order Example VARIATION ORDER NO. 1 Add GhC 3.3 2 No. inspection chambers (2 @ 904) 1 808 3.4 600mm U-drain 88 400 3.5 Granular road based (22,800m2 @ 2.5) 57 000 3.8 Bridge works 6 540 Total 153 748 Omit GhC 3.4 450mm U-drain 65 500 3.5 Granular road based (24,000m2 @ 2.5) 60 000 Total 125 500 Variation Order No. 1 (Net Addition) 28 248 Old Contract Sum 500 000 New Contract Sum 528 248 CVE213 Site Organisational Studies I Site Supervision Site Instructions • A site instruction is a formal written order given to contractors or sub-contractors on specific project issues by the head of the project or consultant • Issues may include – – – – – – Delay in progress Defective work or materials Guidance on how to carry out a specific item of work Permission to proceed with an item of work Amendments to procedure General project challenges, etc • Site instructions are formal documents and can be presented during disputes, claims, variations, arbitration CVE213 Site Organisational Studies I Site Supervision Site Instructions • A good site instruction must contain the following – The name of the firm and the individual issue the instruction – The name of the firm and the individual receiving the instruction – The place, date and time that the instruction was issued – The team that issued the instruction and the head of the team – The current observation on site for the item of work for which instruction is being issued – The instruction on what is to be done (with sketches if applicable) – The signatures of the person issuing and receiving the instruction CVE213 Site Organisational Studies I Site Instructions Site Supervision CVE213 Site Organisational Studies I Site Supervision Site Instructions – 7 Day Rule • All instructions issued by the consultant shall be issued in writing – Any verbal instructions, direction or explanations involving a variation shall be confirmed in writing by the contractor to the consultant within seven days – If not dissented from in writing by the consultant to the contractor within a further seven days, then it shall be deemed to be consultant’s instructions • If the contractors does not comply within seven days after receipt of a written notice from the consultant, the employer may employ and pay other persons to execute any work which may be necessary to give effect to such instructions – Costs incurred shall be deducted from the contractor’s next payment certificate CVE213 Site Organisational Studies I Site Supervision Dayworks • Bill of Quantities normally contain list of dayworks – That is the contractor’s hourly daily rates for various types of labourers and equipment • Dayworks is payment to a contractor based on cost of materials, equipment and wages plus a percentage for overheads and profit • The Resident Engineer may order the contractor to carry out minor work for which there are no unit rates in the bill of quantities as dayworks – Such orders are done in writing – Works are paid according to the rates given by the contractor in their tender for equipment and labourers – Materials are paid for as the purchase price (verified by receipts) plus a certain mark-up(30-40%) to cover overheads and profit – Account of men, machines and materials used are submitted by the contractor each day for approval and payment • Dayworks are for minor works only CVE213 Site Organisational Studies I Site Supervision Project Reports • The project manager (contractor) and resident engineer (consultant) are responsible for submitting regular report on the project’s progress • Type of project reports incude – Progress report – to be submitted regularly during the implementation of the project – Final/Completion report – to be submitted when the project is done – Project evaluation report – to be carried out sometime after the project is completed CVE213 Site Organisational Studies I Site Supervision Project Reports • Progress report enable the consultant to monitor work done on the project – Describe the operations, activities and finances for each report period (usually monthly) • Final report describe the entire project – A qualitative summary of the project as a whole – Should contain the relevant information for the financiers of the project as well as other organisations that can have an interest of or benefit form the experiences and results of the project CVE213 Site Organisational Studies I Site Supervision Project Reports • Evaluation report assesses the appropriateness of the objectives, the rate of achievement of objectives, effectiveness and sustainability – Results of an evaluation must be trustworthy and in a form that makes the findings useful to be incorporated in the decision processes of new projects • Evaluation report is the most important single feedback document in development work • It is undertaken as a combination of desk and field study CVE213 Site Organisational Studies I Site Supervision Project Reports – Weekly Progress • Weekly reports are done by the site manager and submitted to the contractor’s head office • The contract manager is responsible for analysing the weekly information received and implementing the appropriate action • Purpose of weekly reports to the contractor include; – Keeping the head office informed of the current progress – Providing a detailed record of contract resources including labour, material, and plant utilisation – Reporting problem areas relating to labour, material and plant requirement which are likely to affect future progress – Monitoring key dates relating to the receipt of information at site management level – Summarise major instructions received from the engineer in the form of verbal or written instructions CVE213 Site Organisational Studies I Site Supervision Project Reports – Weekly Progress • Many companies use standard weekly progress report designed to collect data relative to the company’s individual requirements • Information contained in the weekly report include; – Contract information – name of project, name of site manager, date and current week number, contract start and end dates – Current progress – the percentage completion of each activity along with an assessment of the completion date. – Future progress – a review of activities to be undertaken in the following week CVE213 Site Organisational Studies I Site Supervision Project Reports – Weekly Progress – Labour summary – all labour employed on the project including both domestic and nominated subcontractors – Plant – summary of plant currently being used on site together with any urgent requirements for the immediate period • Plants to be sent to head office or hirer should be listed together with instructions for collection or return – Drawings received – summary of all new and revised drawings issued – Weather conditions – summary of weather conditions over the past week • It enables lost time to be assessed due to the inclement weather and may later be used to formulate an application for an extension of time – Urgent requirements – major areas requiring immediate action by the head office – Other relevant information – may contain details of visitors to site, accidents recorded etc CVE213 Site Organisational Studies I Site Supervision Memorandum (Memo) • Memos are brief printed documents traditionally used for routine, day-to-day communication within an organisation – They are used to convey decisions, meeting agendas, policies, internal report and short proposals • Engineers and scientist use memos to make requests, give announcements and to communicate reports • Sentences and paragraph lengths in memos should be kept relatively short • Memos should not be more than one page long CVE213 Site Organisational Studies I Site Supervision Memorandum (Memo) • A memo should have the following; – document title, indicating the word “Memo” or “Memorandum” – a heading section which indicate who recipient of the memo, who it writing the memo, the date and the subject • Subject line should be specific and in a few words – Message section to convey the message CVE213 Site Organisational Studies I Site Supervision Memorandum (Memo) • The message section should have the following – Memo Opening – explains the reason for the correspondence (the problem or need for the memo) – Brief discussion – gives details about the problem, need or announcement. • Should be kept short and straight to the point – Closing – states clearly the action you expect the recipient to take, or what you will do for them • Include attachments if any