How to do delay analysis by using Time Impact Analysis Technique .............................................................................. 2
1.2.
Navigating Delay Analysis: A Comprehensive Guide to Preparing Time Impact Analysis ............................................. 2
1.3.
Delving into Delay Analysis: A Comprehensive Guide to Time Impact Analysis (TIA) in Primavera P6 ....................... 2
1.4.
Unveiling Project Delays: A Comprehensive Guide to Time Impact Analysis in Primavera P6...................................... 2
1.5.
Demystifying Delay Analysis: A Step-by-Step Guide to Time Impact Analysis in Primavera P6 ................................... 2
1.6.
Advanced Guide to Precise Delay Analysis: Strategies for Time Impact Analysis Preparation .................................... 2
2.
WHAT YOU'LL LEARN: .............................................................................................................................................................. 2
2.1.
The fundamental principles and applications of Time Impact Analysis (TIA) .................................................................. 2
2.2.
Identifying the types of project delays and their causes ................................................................................................... 2
2.3.
Mastering the steps involved in conducting a comprehensive time impact analysis ..................................................... 2
2.4.
Constructing a network model of the impacted work using Primavera P6 / Utilizing Primavera P6 software to
streamline TIA preparation ................................................................................................................................................................. 2
2.5.
Analyzing the impact of delay events on project schedules and costs ............................................................................ 2
2.6.
Delving into Time Impact Analysis (TIA) and its applications ........................................................................................... 2
2.7.
Unveiling the key steps involved in preparing a comprehensive TIA ............................................................................... 2
2.8.
Calculating and quantifying the impact of delays on project schedules .......................................................................... 2
2.9.
Generating/preparation of comprehensive delay analysis reports ................................................................................... 2
2.10.
Complete Methodology to prepare time impact analysis ................................................................................................... 2
2.11.
Show the delays in Primavera p6 Gantt Chart with different colors for different types of delays. (Authority, Contractor
and Concurrent) ................................................................................................................................................................................... 3
3.
DESCRIPTION: ........................................................................................................................................................................... 3
4.
BENEFITS: .................................................................................................................................................................................. 3
5.
ADDITIONAL TIPS: ..................................................................................................................................................................... 4
6.
CONCLUSION: ............................................................................................................................................................................ 4
7.
TUTORIAL LINK: ........................................................................................................................................................................ 4
8.
DISCLAIMER: ............................................................................................................................................................................. 5
9.
ABOUT PLANNING-P6: .............................................................................................................................................................. 6
www.planningp6.com
1 of 6
PLANNING-P6
1. SEARCH TITLES:
1.1.
How to do delay analysis by using Time Impact Analysis Technique
1.2.
Navigating Delay Analysis: A Comprehensive Guide to Preparing Time
Impact Analysis
1.3.
Delving into Delay Analysis: A Comprehensive Guide to Time Impact
Analysis (TIA) in Primavera P6
1.4.
Unveiling Project Delays: A Comprehensive Guide to Time Impact
Analysis in Primavera P6
1.5.
Demystifying Delay Analysis: A Step-by-Step Guide to Time Impact
Analysis in Primavera P6
1.6.
Advanced Guide to Precise Delay Analysis: Strategies for Time Impact
Analysis Preparation
2. WHAT YOU'LL LEARN:
2.1.
The fundamental principles and applications of Time Impact Analysis
(TIA)
2.2.
Identifying the types of project delays and their causes
2.3.
Mastering the steps involved in conducting a comprehensive time impact
analysis
2.4.
Constructing a network model of the impacted work using Primavera P6
/ Utilizing Primavera P6 software to streamline TIA preparation
2.5.
Analyzing the impact of delay events on project schedules and costs
2.6.
Delving into Time Impact Analysis (TIA) and its applications
2.7.
Unveiling the key steps involved in preparing a comprehensive TIA
2.8.
Calculating and quantifying the impact of delays on project schedules
2.9.
Generating/preparation of comprehensive delay analysis reports
2.10. Complete Methodology to prepare time impact analysis
www.planningp6.com
2 of 6
PLANNING-P6
2.11. Show the delays in Primavera p6 Gantt Chart with different colors for
different types of delays. (Authority, Contractor and Concurrent)
3. DESCRIPTION:
In the intricate world of project management, delays can pose significant challenges,
affecting project schedules, budgets, and overall success. Delay analysis, particularly
Time Impact Analysis (TIA), emerges as a crucial tool for understanding the causes and
effects of delays, enabling informed decision-making and potential claims management.
In this comprehensive video tutorial, we'll embark on a journey to master the art of delay
analysis, specifically focusing on Time Impact Analysis. We'll guide you through the
intricate steps involved in preparing a thorough and effective TIA, empowering you to
navigate the complexities of delay analysis with confidence.
Through real-life examples and practical tips, this tutorial equips you with the knowledge
needed to minimize disruptions and effectively communicate the impact of delays using
powerful techniques/tools.
Get ready to elevate your proficiency as you embark on this enlightening journey
towards mastering delay analysis and honing your time impact analysis skills. Join us
now and strengthen your command over accurate delay assessment.
4. BENEFITS:
❖ Effectively identify and quantify project delays
❖ Determine the impact of delays on project schedule and costs
❖ Develop strategies to mitigate delays and prevent future occurrences
❖ Enhance project management decision-making based on accurate delay analysis
❖ Strengthen project communication and accountability
❖ Substantiated claims management and dispute resolution
❖ Streamlined project communication and stakeholder engagement
❖ Elevated project management skills and expertise
www.planningp6.com
3 of 6
PLANNING-P6
5. ADDITIONAL TIPS:
❖ Consult industry standards and best practices for conducting delay analysis.
❖ Familiarize yourself with relevant contract clauses and legal considerations
related to delay analysis.
❖ Seek guidance from experienced project professionals or delay analysis experts
if necessary.
❖ Maintain detailed project documentation to facilitate accurate delay analysis.
❖ Stay updated on the latest TIA techniques and software advancements.
6. CONCLUSION:
We encourage you to apply the skills and knowledge gained from this tutorial to your
current and future projects.
By mastering the art of time impact analysis, you'll empower yourself to effectively
address project delays, minimize their impact, and contribute to the overall success of
your projects. This valuable skill will undoubtedly elevate your project management
expertise and enhance your ability to navigate the challenges of project delays.
Thank you for joining us on this journey to understanding delay analysis and TIA.
Remember, effective project management is a continuous learning process, and we
encourage you to explore further resources and seek guidance from experienced
professionals to refine your skills and stay ahead of the curve.
7. TUTORIAL LINK:
Click
on the
Picture
www.planningp6.com
4 of 6
PLANNING-P6
8. DISCLAIMER:
This channel does not promote or encourage any illegal activities and all content
provided by this channel is meant for EDUCATIONAL purposes only.
Copyright Disclaimer: Under section 107 of the Copyright Act 1976, allowance is made
for FAIR USE for purposes such as criticism, comment, news reporting, teaching,
scholarship, and research. Fair use is a use permitted by copyright statutes that might
otherwise be infringing. Non-profit, educational, or personal use tips the balance in favor
of FAIR USE.
www.planningp6.com
5 of 6
PLANNING-P6
9. ABOUT PLANNING-P6:
Planning-P6 is a deeply versatile and exceptionally experienced firm, offering an
extensive array of services encompassing project management, project controls, quality
management, environmental management, occupational health and safety
management, as well as auditing. Bolstered by an unwavering commitment to adhering
to industry best practices, Planning-P6 proudly serves as a go-to resource for premium
freelance consultancy and project management services across global built and natural
environments.
SERVICES OFFERED
Planning & Project Controls
Trainings
Job Assistance
Project management
Project controls
Online audits
Documentation preparation
Delay analysis
Impact assessments
Reporting
Key stage reports
Project schedules (Primavera P6)
ISO Certifications
Trainings
Online audits
Documentation preparation
Quality management system (ISO 9001:2015)