A TECHNICAL REPORT ON STUDENT INDUSTRIAL WORK EXPERIENCE SCHEME (SIWES) UNDERTAKEN AT DATUMENERGY NIGERIA LIMITED (DNL) AVIATION ESTATE, IKEJA, LAGOS STATE. BY AKINRINADE, OPEYEMI DANIEL MATRIC NO: EES/16/17/0127 SIWES REPORT SUBMITTED TO THE DEPARTMENT OF MECHANICAL ENGINEERING FACULTY OF ENGINEERING OLABISI ONABANJO UNIVERSITY IN PARTIAL FULFILMENT OF THE REQUIREMENT FOR THE AWARD OF BACHELOR OF SCIENCE (B.Sc.) IN MECHANICAL ENGINEERING FROM MARCH 2020 TO FEBRUARY 2021 CERTIFICATION This is to certify that the Student Industrial Work Experience Scheme (SIWES) was carried out by Akinrinade Opeyemi Daniel with Matric Number - EES/16/17/0127 of Mechanical Engineering Department, Faculty of Engineering, Olabisi Onabanjo University, Ago – Iwoye , under my coordination. ____________________ Dr. Olatunde SIWES Co-ordinator ____________________ Date ____________________ Dr. H. O. Adeyemi Head of Department ____________________ Date DEDICATION This report is dedicated to my Fathers: God the Father who through the Holy Spirit guided me in choosing this career path and my earthly Father who has been supportive and also of guidance. ii ACKNOWLEDGEMENT My sincere and ultimate thanksgiving goes to the Almighty God, the one who sustain me throughout the course of my Industrial Training. I also appreciate and thank the Managing Director of DATUMNERGY Nigeria Limited Engr. Daniel Olaoluwa for giving me the opportunity to be trained under his establishment and supporting me throughout the training. My regards also goes to my Industrial Based Supervisor Mr. Adebayo Olubaye and all my lecturers in the department for their necessary supervision and useful information provided, Engr. Nwaokocha Collins for the advising that we should learn the use of CAD software’s, the Head of Department Dr. Adeyemi Hezekiah for taking is time and energy in teaching the Computer-Aided-Design course practically and SIWES coordinator Dr. Olatunde for the guidance. I cannot forget my loving and caring family, and all my brothers and sister for their support both spiritually and financially during my SIWES programme, may God bless you all. Time and space will not permit me to mention all the Individuals that contributed to the success of my SIWES in one way or other. I sincerely appreciate you all. iii ABSTRACT This report will take you through the journey of my SIWES which I did at Datumenergy Nigeria Limited, Ikeja, Lagos State. My training was on the design, fabrication and testing of different piping system ranging from fire hydrant piping, natural gas reticulation system and Air compressor piping with use of different pipe materials. During this period, I acquired practical knowledge on how to install and replace piping components like Pressure gauges, valves, gas filters and also providing the needed assistance to site supervisor, Non-Destructive Testing (NDT) inspectors, fitters and welders with the functionality they need. This report discussed the technical skills gained during the training period and justifying the relevance of the scheme in equipping students with needed technical competence to thrive in the real world. iv Contents TITLE PAGE CERTIFICATION ………………………………………………………………………………………………………………………………… i DEDICATION …………………………………………………………………………………………………………………………………… ii ACKNOWLEDGEMENT ……………………………………………………………………………………………………………………. iii ABSTRACT ……………………………………………………………………………………………………………………………………… iv TABLE OF CONTENT …………………………………………………………………………………………………………………….. v-vi CHAPTER ONE ......................................................................................................................................... 1 INTRODUCTION ................................................................................................................................... 1 OBJECTIVES OF SIWES ......................................................................................................................... 1 ABOUT INDUSTRIAL TRAINING I.T.F. ................................................................................................... 2 CHAPTER TWO ........................................................................................................................................ 3 COMPANY OVERVIEW ......................................................................................................................... 3 DNL SERVICES ...................................................................................................................................... 3 VISION STATEMENT ............................................................................................................................ 4 MISSION STATEMENT ......................................................................................................................... 4 QUALITY POLICY AND OBJECTIVES ...................................................................................................... 4 QUALITY POLICY .............................................................................................................................. 4 QUALITY OBJECTIVES ...................................................................................................................... 5 HEALTH SAFETY AND ENVIRONMENT ................................................................................................. 5 CHAPTER THREE ...................................................................................................................................... 6 INDUSTRIAL TRAINING EXPERIENCE ....................................................................................................... 6 PIPING SYSTEM ................................................................................................................................... 7 COMPONENTS OF PIPING SYSTEM ..................................................................................................... 8 PIPES................................................................................................................................................ 8 PIPE FITTINGS ................................................................................................................................ 10 Flanges Gaskets and Bolting ......................................................................................................... 14 Types of flanges based on flange facing ....................................................................................... 17 Types of Flange based on Pressure-Temperature Class (Service Rating) ..................................... 18 Types of Flange based on Material ............................................................................................... 18 GASKET .............................................................................................................................................. 18 Types of Gasket ............................................................................................................................. 19 BOLTS ................................................................................................................................................ 20 v PROCEDURE FOR APPLICATION OF BOLT TORQUE ON FLANGED JOINTS .................................... 21 VALVES .......................................................................................................................................... 22 PRESSURE GAUGE ......................................................................................................................... 26 NON-DESTRUCTIVE TESTING (NDT) OF PIPING SYSTEM ................................................................... 27 HYDROSTATIC TESTING OF PRESSURE PIPING SYSTEM ................................................................ 27 FABRICATION AND INSTALLATION OF PIPING SYSTEM .................................................................... 30 Types of Pipe-Weld Joint............................................................................................................... 30 DRAWING .......................................................................................................................................... 32 PAINTING OF FABRICATED PIPING .................................................................................................... 37 CHAPTER FOUR ..................................................................................................................................... 38 NEW SKILLS ACQUIRED AND CHALLENGES ENCOUNTERED ................................................................. 38 CHAPTER FIVE ....................................................................................................................................... 40 CONCLUSION AND RECOMMENDATIONS............................................................................................. 40 REFERENCES .......................................................................................................................................... 41 vi CHAPTER ONE INTRODUCTION The Student Industrial Work Experience Scheme (SIWES) was initiated in October 8, 1973 by the Industrial Training Fund (ITF), the Student Industrial Work Experience (SIWES) gives opportunity for students to go on a Skill Acquisition or Work Experience program in an Industry that relate to their field of study in order to update practical knowledge of students in the Universities, Polytechnics and Colleges of Technology. It was aimed at bridging the gap between the theoretical knowledge acquired in classes and technical knowledge in the industry by providing students with the opportunities to apply their educational knowledge in real work situations. With the primary purpose of gaining relevant skills required from an engineering graduate and to secondary purpose of fulfilling the major requirement for the award of Bachelor of Science degree, I undertook my SIWES at Datumenergy Nigeria Limited which is located at Aviation Estate, Ikeja, Lagos from MARCH 2020 to FEBRUARY 2021. OBJECTIVES OF SIWES The Industrial Training Fund’s Policy Document No. 1 of 1973 which established SIWES outlined the objectives of the scheme. The objectives of the Students Industrial Work Experience Scheme (SIWES) are: Provide an avenue for students in institutions of higher learning to acquire industrial skills and experience during their courses of study; Prepare students for industrial work situations that they are likely to meet after graduation; Expose students to work methods and techniques in handling equipment and machinery that may not be available in their institutions; Make the transition from school to the world of work easier and enhance students’ contacts for later job placements; Provide students with the opportunities to apply their educational knowledge in real work situations, thereby bridging the gap between theory and practice; 1 Enlist and strengthen employers’ involvement in the entire educational process through SIWES. ABOUT INDUSTRIAL TRAINING I.T.F. The objective for which the Fund was established has been pursued vigorously and efficaciously. In the four decades of its existence, the ITF has not only raised training consciousness in the economy, but has also helped in generating a corps of skilled indigenous manpower which has been manning and managing various sectors of the national economy. Over the years, pursuant to its statutory responsibility, the ITF has expanded its structures, developed training programmes, reviewed its strategies, operations and services in order to meet the expanding, and changing demands for skilled manpower in the economy As part of its responsibilities, the ITF provides Direct Training, Vocational and Apprentice Training, Research and Consultancy Service, Reimbursement of up to 50% Levy paid by employers of labour registered with it, and administers the Students Industrial Work Experience Scheme (SIWES). It also provides human resource development information and training technology service to industry and commerce to enhance their manpower capacity and in-house training delivery effort. 2 CHAPTER TWO COMPANY OVERVIEW DATUMENERGY LIMITED (DNL) is a wholly indigenous engineering company incorporated since 2003 to provide needed engineering services for Industrial and Oil & Gas Companies The company is comprised of highly experienced indigenous engineers of different engineering disciplines. Experienced gained over the years of active engineering practice in various companies is being put together to form a formidable corporate body to the best advantage of our various clients. The merging of the expertise in their various fields has allowed the development of an innovative Engineering culture providing our firm with interesting areas of operation. The company over the years has been very successful in possessing various types of machinery’s in its workshop for use on various projects. The permanent office located at 116, Ewu Road, Aviation Estate Lagos State. This office in Lagos is presently the control center for all our activities Nationwide. While the workshop is located within the perimeter-fenced office. It is at the back of administrative building. This workshop in Lagos is presently the fabrication yard for all our activities. The workshop is equipped to meet all fabrication, welding and insulation fabrication works. DNL SERVICES Oil & Gas and industrial pipes welding Non Destructive Testing (NDT ) Insulation and cladding of industrial pipes and fittings Cement Kiln installation and welding Fire hydrant installation and pump sizing TIG (argon) welding for stainless steel pipes PRMS assembling and installation Structural design, welding and construction Civil work ( insitu casting, pre-casting and reinforcement) Plant/storage Tank erection 3 Detailed engineering and front end design Procurement (gas flow metre, diesel flow metre , regulators, filters, valves, PRMS, pipes, etc.) Pipeline Maintenance Services Liquefied Petroleum Gas (LPG) Compressed gas (nitrogen gas, acetylene, oxygen, argon gas, etc.) VISION STATEMENT “To be a leading operator in project management, engineering consulting services in the industrial environment. We draw our strength from our experience, integrity, unique packaging of service and excellence of the people we engage. We shall demonstrate our our leadership position with great passion, rigour and total commitment to providing our customers with concise solutions to their problems always meeting and exceeding, where possible, customer’s need and expectations. ” MISSION STATEMENT To passionately provide engineering solutions that exceeds customers’ expectations. We shall this through: Building and developing well trained professionals that are proud of their work and working environment and committed to continuous improvement. Ensure that all employees are treated well, working as an “intelligent army” Give future to our employees towards individual actualization. QUALITY POLICY AND OBJECTIVES QUALITY POLICY DNL shall operate a quality Assurance system. We are keen on excellence to our customer’s service deliverables which must consistently be of the highest quality obtainable. We ensure that our customers’ needs are met and exceeded, where possible demonstrating our professionalism and experience in our areas of operations. We shall achieve this through: Prompt provision of information Priority attention to customers’ satisfaction, through articulated consideration and customers’ needs and expectation. 4 Making everyone committed to attainable, define quality requirements. Therefore, management shall create a conducive working environment for employees through mutual trust, respect and love, teamwork, continuous improvement, compliance with national and international standards recognition and celebration of individual or team achievements. We will measure the efficiency of our activities and ability to meet our customer’s requirements and expectations. Identify shortcomings and take necessary actions promptly. Adequate communication interface with customers to identify complaints before they become problems and most importantly, DATUMENERGY will treat our customers as partners in our business. QUALITY OBJECTIVES Provide a service that consistently meets the needs and expectations of our customers and indeed exceed them. Targets shall be compliance to regulatory and contractual requirements. To be seen and perceived by our customers as being better than the competition. Achieving an optional level of employee satisfaction and competence and cooperation. Targets shall be defined through periodic evaluation process Delivering service with improved results as evident of continuous process improvement activities Ensure that all works are performed correctly at the first time for cost effectiveness and efficiency. HEALTH SAFETY AND ENVIRONMENT Successfully managing HSE issues is an essential component of our business strategy through the encouragement of our HSE policy and program. Our goal is to minimize impact to the environment and prevent harm to those who could be affected by our operations. DNL is solely committed to personnel safety; environmental safety, equipment safety, quality and when these concerns are met objectives can be focused on profit. We take safety as our priority. …Safety first and safety always 5 CHAPTER THREE INDUSTRIAL TRAINING EXPERIENCE During my industrial I worked in several departments/sections in the company where I was trained, assisted and carried out several duties and assignments. Basic Work activities and job assigned to me in the office and workshop: Preparation of waybills and moving materials to site Design and drafting of piping isometric drawings Acknowledgement of waybill and invoice from suppliers Taking inventory of materials and tools Assisting in office activities such as printing, photocopying and editing document such as work permits, invoices and waybills Maintenance of workshop tools and machines Observation of all engineering related work going-on in the workshop. Identification and training on how to use different tools and equipment like wrench, steel square, spirit level, grinding and cutting machines Carry out routine inspection of materials, tools and equipment. I also visited and worked on different sites during my industrial training which include; Josefdam Port Services,Apapa VIK industries Ajao Estate Reco plastics Ajao Estate National Salt Company (NASCON) Allied Industries Plc. Apapa NASCON Oregun Ikeja Pardee Foods Nigeria Limited Sango-Otta Fareast Mercantile Company Limited (FMCL) Mushin 6 Ro-Manrong Nigeria Limited Amuwo Odofin Industrial Estate Basic work activities in various site: Participated in site survey and drafting of piping isometric drawings piping plan drawings and Piping and Instrumentation Diagrams(P&ID) Moving of working tools and equipment’s(welding machine, extension box, grinding machine measuring tape) on and off site Delivery of materials to the site Collection of site PTW( Permit-To-Work) Participation in Nitrogen purging of pipelines Installation of equipment like pressure gauges, gas filters, ball valves and bolting of valves to flanges Pneumatic pressure testing Leakage test(bubble test) I also worked on two different residential building acting as the supervisor and ensure all plumbing works are done to standard. PIPING SYSTEM Piping includes pipe, flanges, fittings, bolting, gaskets, valves, and the pressure containing portions of other piping components. It also includes pipe hangers and supports and other items necessary to prevent over-pressurization and overstressing of the pressure-containing components. It is evident that pipe is one element or a part of piping. Therefore, pipe sections when joined with fittings, valves, and other mechanical equipment and properly supported by hangers and supports, are called piping. Piping covers very large part of any process plant. If you look at Oil Exploration platform, Refinery and Petrochemical complex one thing that catches the attention is a complex network of piping. Piping is used to transport various process materials from one equipment to another. During my industrial training we fabricated different piping system like Water system(fire hydrant piping) natural gas piping system of different working pressure and pipe sizes Air compressor system piping system(stainless steel pipe and socket weld joint) Domestic plumbing. 7 COMPONENTS OF PIPING SYSTEM Piping components are mechanical elements suitable for joining or assembly into pressuretight fluid containing piping system. Piping system components include: Pipes Fittings (e.g. elbows, reducers, branch connections, etc.) Flanges, gaskets and bolting Valves Instruments for pressure temperature and flow measurement Pipe supports PIPES Pipe is a straight pressure tight cylindrical hollow, used in the piping system to transport liquid, gas and sometimes solids. A pipeline conveys a fluid from one given point of the plant called inlet point of the line, to another part of the plant called outlets point of the line. TYPES OF PIPES Different types of pipes used in different design conditions, considering technical and commercial parameters. Types of pipes include: 1. Seamless Pipe: Seamless pipe is Strongest amongst all pipes type as it has a Homogenous structure throughout pipe length. It is manufactured in variety of size. However, there is a Restriction on the manufacturing of large diameter pipe. Throughout my Industrial training seamless pipe was used for the piping system I worked with due to the working pressure of these piping systems. Different manufacturing processes used for producing seamless pipes are milling, forging and extrusion 2. Welded Pipe: Welded Pipes are manufactured from Plate or continues Coil or strips. To manufactured welded pipe, first plate or coil is rolled in the circular section with the help of plate bending machine or by a roller in the case of continues process. Once the circular section is rolled from the plate, the pipe can be welded with or without filler material. Welded pipe can be manufactured in large size without any upper restriction. Welded pipe with filler material can be used in the manufacturing of long radius bends and elbow. Welded pipes are cheaper with compared to the seamless 8 pipe and also Weak due to the weld joint. There are different methods used to weld pipes. Which are: • ERW- Electric Resistance Welding • EFW- Electric Fusion Welding • HFW- High-frequency welding • SAW- Submerged Arc Welding (Long seam & Spiral Seam) PIPE SIZE AND DIMENSION Pipe Dimensions are covered in following Standard ASME B36.10 – Welded and Seamless Wrought Steel Pipe (Carbon & Alloy Steel) ASME B36.19 – Stainless Steel Pipe Three different terms are commonly used to define the size of the pipe. 1. NPS – Nominal Pipe Size: All American standard used NPS designation to define pipe size. This is a modern derivation of earlier IPS – Iron Pipe Size. NPS is not an OD or ID of the pipe it is in-between of the outer and the inner diameter of the pipe. For example, NPS 2 size pipe outside diameter is 60 mm or 2.375 inches. In general, NPS 12 and the smaller pipe has outside diameter greater than the size and for NPS 14 and above size pipe outside diameter is the same as the size in inches. 2. NB – Nominal Bore: This is the European equivalent of NPS. In this standard pipe sizes are mentioned in millimeter 3. DN – Diameter nominal: This is the German equivalent of NPS. In this standard also, pipe sizes are mentioned in millimeter In the Table 1, you can see the correlation of size and OD (outside diameter). Table 1: Correlation of size and outside diameter (OD) PIPE THICKNESS - SCHEDULE NUMBER Pipe Thickness are expressed in Schedule number. A schedule number is an approximate value of the equation = 1000 P/S Where; − P is the service pressure in (psi) − S is the allowable stress in (psi) 9 Common carbon steel pipe schedule numbers are 5, 10, 20, 30, 40, 60, 80, 100, 120, 140, 160.Pipe Thickness are also expressed as STD, extra strong-XS, double extra strong-XXS. Higher the schedule number, Higher the thickness of the pipe and smaller the inside diameter of the pipe as outside diameter of each pipe size is standardized. The thickness of stainless steel pipe is also expressed in Schedule number. Schedule number with S suffix is as per ASME B36.19, and it is used with stainless steel pipe. There is only four schedules are mentioned in ASME code which are 5S, 10S, 40S, 80S. So, please remember schedule number 10 and 10S do not have the same thickness. PIPE ENDS Pipe comes in following 4 end types 1. Plain End – This kind of end used when socket type weld fittings are used. 2. Beveled End – This kind of end used when butt type weld fittings are used. 3. Threaded End – This kind of end used with threaded connections in piping system 4. Socket & Spigot – This type of end generally used in ductile iron pipeline and non-metallic piping pipeline such as PVC, GRE/GRP. PIPE FITTINGS It is used to connect straight pipe or tubing sections, to adapt to different sizes or shapes, to branch or re-direct the piping system and if necessary to provide a jointing method if two dissimilar piping materials are used in the one system. Fittings for pipe and tubing are most often made from the same base material as the pipe or tubing being connected, e.g., stainless steel, steel, copper or plastic. The images below show some common fittings that are used in piping systems. Figure 1:Screwed stainless steel and Butt weld mild steel fittings 10 Fittings are piping component which helps in changing the direction of the flow such as elbows, tee, changing the size of the pipe such as reducers, reducing tees, Connect to components together such as couplings and stop the flows such as Caps and plugs. The most common type of pipe fittings are: Elbow A pipe fitting installed between two lengths of pipe or tube allowing a change of direction, usually 90° or 45°. The ends may be machined for butt welding, threaded (usually female), or socketed, etc. When the two ends differ in size, it is called a reducing or reducer elbow. Most elbows are available in short radius or long radius of types. The short radius elbows have a center to end distance equal to the nominal diameter, while the long radius is 1.5 times the nominal diameter. Elbows used on powder transfer systems have a much longer radius (radius of bend can be 10 times the nominal diameter of the pipe) to ensure smooth flow, reduce wear to both product and piping and to reduce the chance of getting blockages. When fluids are transported to long distances or go frequent directional changes, short radius elbows are not recommended because of their greater friction loss, which may require installation of larger pump or compressor. Figure 2: 90° short radius and 45° Elbows Tees A Tee is used to either combine or split a fluid flow. There are different types of Tee used in piping, • Equal/Straight Tee– in this type of Tee, Diameter of Branch is same as the Diameter of the Run Pipe • In Reducing Tee – Diameter of the Branch size is smaller than the Diameter of the Run Pipe 11 Figure 3: Reducing and Straight (Equal) Tees Cross A cross has one inlet and three outlets, or vice versa and like tees come in equal and reducing forms and are also known as four-way fittings. A cross is more expensive than two tees but has the advantage of reduced space and requires less labour to install. Generally, crosses are not used in process piping to transport fluid. But forged crosses are common in fire water sprinkler line. Figure 4: Cross or Four ways fittings Reducer Reducers are used to join two different pipe sizes together. They can be either concentric or eccentric which refers to the relative position of the center lines of the outlet and inlet. In Concentric reducer, center of the both the ends are on same axis. It maintains the center line elevation of pipe line. Whereas in Eccentric reducer, center of the both the ends are on different axis as shown in image. It maintains BOP (bottom of pipe) elevation of pipe line. Special attention must be given when using reducers in a horizontal orientation as the slope will prevent free draining of a system if not installed correctly. 12 Figure 5: Eccentric and Concentric Reducers Pipe Caps A type of pipe fitting which is liquid or gas tight, and is used to cover the end of a pipe. A cap has a similar function to a plug. For screwed systems the cap would have female threads where a plug would have male threads. Pipe caps are used at the dead end of the piping system. It is also used in piping headers for future connections. Figure 6: Pipe Cap and Hexagonal Head Plug Stub ends Stub ends are used with lap joint flange. In this type of flange, stub is butt welded with pipe, whereas flange is freely move over the stub end. Figure 7: Stub Ends Unions A union is similar to a coupling, except it is designed to allow quick and convenient disconnection of pipes for maintenance or fixture replacement. While a coupling is usually a permanent joint or requires the ability of being able to rotate all the pipe to one side of it to unscrew it, a union provides a simple nut transition, allowing easy release at any time. When using unions with dissimilar metals (such as copper and galvanized steel) a dielectric union 13 should be used. This breaks the electric current with a plastic liner between two halves of the union, thus limiting galvanic corrosion. Figure 8: NPS 2 Union Flanges Gaskets and Bolting The flange is second most used joining method after welding. Flanges are used when joints need dismantling. It provides flexibility for maintenance. Flange connects the pipe with various equipment and valves. Breakup flanges are added in the pipeline system if regular maintenance in required during plant operation. A flanged joint is composed of three separate and independent although interrelated components; the flanges, the gaskets, and the bolting; which are assembled by yet another influence, the fitter. However, it is not advisable to used flange connection in underground piping when it supposed to be buried. The flange is also a most common source of leak and fire in a process plant. There are variety of flanges available to suit the standards and requirements. Flanges can be classified in several alternate ways as follows: 1. Based on Types of Connection 2. Based on Flange facing Types 3. Based on Pressure Temperature Ratings 4. Based on Material Types Types of Flange based on connection Threaded Flanges Threaded Flanges are also known as screwed flange, and it is having a thread inside the flange bore which fits on the pipe with matching male thread on the pipe. This type of joint connection is Speedy and simple but not suitable for high presser and temperature applications. A screwed or threaded flange requires no welding and is used to connect other 14 threaded components in low pressure non-critical applications and is mostly used in utility services such as air and water. Figure 9: Threaded Flanges Socket-weld Flanges Socket-Weld Flanges has a female socket in which pipe is fitted. A socket flange is counterbored to accept the pipe, then fillet welding is done from outside on the pipe. Generally, it is used in small bore piping and only suitable for low pressure and temperature application. Figure 10: Socket-Weld Flange Slip-On Flanges Slip-On flange has a hole with matching outside diameter of pipe from which pipe can “slip in” (can pass). The flange is placed on pipe and fillet welded from both inside and outside. Slip-On Flange is suitable for low pressure and temperature application. This type of flange is available in large size also to connect big bore piping with storage tank nozzles. Normally, these flanges are of forged construction and are provided with the hub. Sometimes, these flanges are fabricated from plates and are not provided with the hub. 15 Figure 11: Slip-On Flange Weld Neck Flange Weld neck flanges are used in critical applications. These are circumferentially welded onto the system at their necks which means that the integrity of the butt-welded area can easily be examined by X-ray radiography. The bores of both pipe and flange match thus reducing turbulence and erosion. Lap Joint Flanges Lap flange is having two components, a stub end, and a loose backing flange. Stub end is butt welded to the pipe and Backing flange freely move over the pipe. This type of joint is easily assembled and aligned, and it is favoured in low pressure applications. The backing flange can be of different material than stub material and normally of the carbon steel to save the cost. Lap flange is used where frequent dismantling is required, and space is constrained. Figure 12: Lap Joint and Weld-Neck Flanges 16 Blind Flanges The blind flange is a blank disc with bolt hole. These types of flanges are used with another type of flange to isolate the piping system or to terminate the piping as an end. Blind flanges are also used as a manhole cover in the vessel. It is sometimes called a blanking flange; also used for blanking off pipelines, valves and pumps and as an inspection cover. Figure 13: Blind Flange Types of flanges based on flange facing Based on flange facing it can be further classified as: Flat Face As name suggest, flat face flange has a flat face. Flat face flanges are used when the counter flanges are flat face. This condition occurs mainly on connection to Cast Iron equipment’s, valves and specialties. Full face gasket is used when flat face flange is used. Raised Face Raised face flange has small portion around the bore is raised from the face. The gasket seat on this raised face. The height of the raised face depends on the flange pressure temperature rating that is known as a class of the flange. For 150# & 300# height of the raised face is 1/6” and above 300# it is 1/4”. The inside bore circle type of gasket is used with raised face flange. RTJ Face Ring joint type face flange has a specially designed grove in which metal gasket seat. This type of flange is used in high pressure and temperature services. 17 Figure 14: Different Flange faces Types of Flange based on Pressure-Temperature Class (Service Rating) Flanges are classified as per their pressure-temperature ratings which are designated as 150#, 300#, 400#, 600#, 900#, 1500# and 2500#. Large diameter flanges that are 24” to 60” are available up to 900# class. Pressure-temperature ratings are maximum allowable working gage pressures in the bar & the temperatures in degrees Celsius. Higher the rating, heavier the flange and can withstand higher pressure and temperature. When the temperature goes up, the pressure goes down, and vice versa. Please note that different material has different pressure ratings. Types of Flange based on Material Flanges are manufactured from •Carbon steel •Low alloy steel •Stainless steel •Or Combination of Exotic materials (Stub) and other backing materials GASKET A Gasket is sealing material placed between connecting Flanges to create a static seal, which will maintain the leak-proof sealing in all operating conditions. Criteria for selecting gasket depend on the piping system service condition and the fluid parameters which include: • Temperature • Pressure • Corrosion resistance • Types of fluid 18 • Robustness • Availability • Cost Types of Gasket There are three types of gasket used in piping: Non-Metallic Metallic Composite Non-Metallic Gasket These gaskets are also known as a Soft gasket, most common materials used for this type of gaskets are Rubber, Teflon and Compressed Non-Asbestos Fiber (CNAF).Non-Metallic gaskets can easily compress with low tension bolting and these types of gaskets are used with low-pressure class flanged such as 150 or 300 Class and in low-temperature services. They are not used in hydrocarbon services but are cheapest and easily available. Metal Gasket • Metal gaskets are manufactured from material such as Soft iron, Low Carbon steel, Stainless Steel, Monel and Inconel • These gaskets are also known as ring gasket or RTJ gaskets • Metallic gaskets are used in high-pressure class flanges, normally above 900 Class, they can also be used for high-temperature services. • High tension bolting is required when we used metallic gaskets. • They are Very robust &most costly Composite Gasket Composite gaskets are Combination of metal and non-metal material. Different types of combination of materials are possible based on service requirement. Spiral wound, Metal Jacketed, and cam-profile gasket are well known in composite gasket category. They can be used in wide range of pressure and temperature services. These gaskets are cost effective with compare to metal gaskets but careful handling is required. 19 Figure 15: Gasket of different made of Materials BOLTS Bolts are used to assemble the piping system through the flanges. They are graded for tensile strength which is affected by temperature and pressure ratings of the piping system. Flange bolts Two types of bolts are available for the assembly and tightening of flanges: 1. The machine bolt, which uses one nut 2. The stud bolt, which uses two nuts Stud bolts have become the preferred method of bolting flanges. They offer the following advantages. ● They can be removed easily (especially when corroded). ● They are not easily confused with other bolts used on site. ● They can be made from round stock. ● The bolt sizes required for flanged joints are readily available from manufacturers’ tables. Figure 16: Machine Bolt, Stud and Nuts 20 PROCEDURE FOR APPLICATION OF BOLT TORQUE ON FLANGED JOINTS During my Industrial training I participate in connecting of flange joints; both flange to flange joint and flange to valve or equipment joint. These are the following steps for the application of bolt torque on flanged joints: Step 1 Component parts must be aligned and clamped together with the hold down. Step 2 Stud (or bolt) threads in area of nut (or forged ring) engagement should be lubricated. The face of nuts (or bolt heads) should also be lubricated using a suitable lubricant. Step 3 All bolts should be installed so that torqueing requirements can be followed. Step 4 All bolts should be numbered so that torqueing requirements can be followed. Step 5 Torque should be applied in 20% (1/5) steps of required final torque, with all bolts loaded at each step before the next step is undertaken. Step 6 Bolts should be tightened in sequential order: 0°–180°, 90°–225° and 135°–315° at each step until final torque is reached. (See Figures on the next page.) Step 7 Rotational tightening should be used until all bolts are stable at final torque level; two complete times around are usually required. 21 Figure 17: Bolt Torque Procedure VALVES Valves are mechanical devices that control the flow and pressure of fluid within a system or process. Fluids do not just flow freely through piping systems. They must be regulated and at certain points stopped. Valves may be operated manually, either by a hand wheel, or a lever or operated automatically by a pneumatic actuator or electrical drive motor. Complex control systems will use feedback from an instrument to control these types of valves to regulate pressure, temperature or flowrate depending on the control parameters required. 22 Types of Valves Based on the mechanical or cyclical motion of the valve closure member, valves are classified as follows: Linear Motion Valves: The valves in which the closure member, as in gate, globe, diaphragm, pinch, safety, relief and lift check valves, moves in a straight line to allow, stop, or throttle the flow. Rotary Motion Valves: When the valve-closure member travels along an angular or circular path, as in butterfly, ball, plug, eccentric- and swing check valves, the valves are called rotary motion valves. Quarter Turn Valves: Some rotary motion valves require approximately a quarter turn, 0degree through 90 degree, motion of the stem to go to fully open from a fully closed position or vice versa. Some of the valves I participated in its procurement and installation are: Gate Valves Gate valves are primarily designed to serve as isolation valves. In service, these valves generally are either fully open or fully closed. When fully open, the fluid or gas flows through the valve in a straight line with very little resistance. Gate valves should not be used in the regulation or throttling of flow because accurate control is not possible. Furthermore, high-flow velocity in partially opened valves may cause erosion of the discs and seating surfaces. Vibration may also result in chattering of the partially opened valve disc. Advantages of Gate Valves 1. They have good shutoff characteristics. 2. They are bidirectional. 3. The pressure loss through the valve is minimal. Disadvantages of Gate Valves The following are some of the disadvantages of gate valves that must be considered when selecting a gate valve for an application: 23 1. Gate valves are not quick opening or closing valves. Full-stem travel to open or close a gate valve requires many turns of its hand wheel or an actuator. 2. Gate valves require large space envelope for installation, operation, and maintenance. 3. Repair or machining of valve seats in place is difficult. Ball Valve A ball valve is a valve with a spherical centre which controls the flow through it. The sphere has a hole, or port, through the middle so that when the port is in line with both ends of the valve, flow will occur. When the valve is closed, the hole is perpendicular to the ends of the valve, and flow is blocked. The handle or lever is also in-line with the port through the sphere which allows the operator to know whether the valve is opened or closed. The ball valve is a quarter-turn valve suitable for clean gas, compressed air, and liquid service. Ball valves do not offer the fine control that may be necessary in throttling applications; however they are durable and usually work to achieve perfect shutoff even after years of disuse and are suitable for high pressures and temperatures. Figure 18: NPS 1and NPS 2 Ball Valve Butterfly Valve The butterfly valve like the ball valve is part of the family of quarter turn valves, i.e. they only require a quarter turn to achieve their fully open position. The butterfly valve can be used for isolating or regulating flow. The closing mechanism takes the form of a disc whose 24 position is again indicated by the position of the opening lever. Butterfly valves are generally favored because they are lower in cost to other valve designs as well as being lighter in weight, meaning less support is required. The disc is positioned in the center of the pipe, but unlike a ball valve, the disc is always present within the flow, therefore a pressure drop is always induced in the flow, regardless of valve position. Figure 19: Butterfly Valve Relief valve Relief valves are used to prevent build-up of excessive pressure of gas or liquid in lines or vessels. They usually operate against a pre-set spring loading. Relief valves for gas are designed to permit a large flow; a small flow which will rapidly decrease pressure is usually all that is required for liquids. 25 PRESSURE GAUGE Most pressure gauges in piping systems are based on the Bourdon gauge which was patented in France in 1849 by Eugene Bourdon. The bourdon tube, which is a hollow metallic tube sealed at one end, flexes when pressure is applied. It flexes because it naturally wants to straighten out, but cannot because it is linked to a geared movement. As it tries to flex, this linear movement is changed to a rotational one by means of small gears, this in-turn cause the pointer to indicate the measured pressure. Gauges like this are designed for clean, nonclogging liquids and gases. Figure 20: 0-40 bar Pressure Gauge 26 NON-DESTRUCTIVE TESTING (NDT) OF PIPING SYSTEM Non-Destructive Testing (NDT) is the process of inspecting, testing and evaluating materials, components without destroying the serviceability of the part or system.NDT is concerned with revealing flaws in the structure of a product. It, however, cannot predict where flaws will develop due to the design itself. All NDT methods have the following common characteristics: (a) The application of a testing medium to the product to be tested. (b) The changes in the testing medium due to the defects in the structure of the product. (c) A means by which it detects these changes. (d) Interpretation of these changes to obtain information about the flaws in the structure of the product. The following are the NDT methods performed and participated during my industrial training: 1. Hydrostatic Testing (Hydro-test) 2. Pneumatic Testing 3. Bubble Test HYDROSTATIC TESTING OF PRESSURE PIPING SYSTEM Hydrostatic testing of pressure piping is a mandatory activity before commissioning of any new or modified piping system. It is the final check of mechanical integrity of the whole system and should be followed religiously as after this activity the piping system has to be commissioned. This test is carried out at a pressure 1.5 times higher than the design pressure of a system regardless of the services condition of a piping system. Test Procedure 1. All equipment and piping to be pressure tested should be thoroughly cleaned of all dirt, welding slag, construction debris. 2. Equipment such as pressure gauges, Hydrotest pump, dead weight tester and other connections like flanges, temporary spades and blank installed properly on the piping system. 3. Connections which serve as vent should be open during filling so that all air is completely evacuated and tightened after filling. 27 4. Drain point for fluid (water) disposal after testing should be provided. 5. Hydrostatic pump is then used to pump water, maintain pressure for 10 minutes and then gradually increase pressure in the steps for one tenth of the pressure until the test pressure is attained. 6. Recommended inspector walks into the whole pipe system and check for leaks. Every single length of piping, welds, bolted, connection should be visually examined for any leakage. 7. Although span for Hydrotest varies for layer piping system, the minimum allowable time taken should be one hour for standard practice. 8. Any leakage from weld joint, piping base metal or other connections which requires repair should be allowed after depressurizing the piping under test. Pneumatic Leak Testing The fluid normally used for a pneumatic test is compressed air, or nitrogen if the source is bottled gas. Pneumatic tests are potentially more dangerous than hydrostatic because of the higher level of potential energy. Pneumatic tests may be performed only when at least one of the following conditions exists: When pressure systems are so designed that they cannot be filled with water. When pressure systems are to be used in services where traces of the testing medium cannot be tolerated. Test Procedure 1. Ensures that the test gauge has a current calibration sticker. (A pressure relief valve or non-reclosing relief device may be installed in the test medium supply line to ensure that this limit is not exceeded.) 2. Verifies that the pressure is continually monitored to ensure that pressure never exceeds the designated test pressure of the system 3. Pressurizes the system, raising pressure in the system gradually until not more than half of the test pressure is achieved 28 4. Increases the pressure slowly in steps of approximately 1/10 of the test pressure until the required test pressure has been reached 5. Reduces the pressure to the maximum operating pressure before proceeding with the inspection; holds the pressure for a sufficient period of time to permit inspection of the system 6. Checks the pressure gauge periodically for indications of leakage 7. Applies a soap solution to accessible welds, screwed pipe joints, flanges, et cetera where leakage is suspected 8. If there is evidence of structural distortion, either rejects the system or repairs as advised by the inspector 9. If there is leakage in the system, performs the following as appropriate; Ensures repair is performed and return to Step 3 or Rejects the system 10. When the test is completed, vents the test medium to approved discharge vicinity/atmosphere 11. Completes pressure test record and submits copy to the pressure systems project manager Figure 21: The images above shows a session during pneumatic leakage test and piping schematic for pneumatic testing Bubble Test Inspection for a leak is done with a soapy-water mixture that is applied to the joints and which produces bubbles when air is escaping. 29 FABRICATION AND INSTALLATION OF PIPING SYSTEM Fabrication is the cutting, bending, forming, and welding of individual pipe components to each other and their subsequent heat treatment and nondestructive examination (NDE) to form a unit (piping subassembly) for installation. Installation refers to the physical placement of piping subassemblies, valves, and other specialty items in their required final location relative to pumps, heat exchangers, turbines, generator, boilers, and other equipment; assembly thereto by welding or mechanical methods; final NDE; heat treatment; leak testing; and cleaning and flushing of the completed installation. Pipe fabrication Pipe fabrication involves assembling pieces such as elbows, tees and flanges into sections which, along with the pipe and all other equipment, can be accurately fitted together into the plant. Because of the cost and importance of such lines, pipe fabricators (fitters and welders) must assemble and weld pipes together with a high degree of precision. This requires careful thought and planning, accurate layout of work and control of welding operations as well as the competent use of jigs, templates and other precision tools. Fabricators (Fitters and Welders) Tools During my industrial training I was able to use and maintain some fabricators tools such as pipe wrench, welding machine, spirit level, chalk line, steel tape steel square grinder and pipe cutter Types of Pipe-Weld Joint Butt Welds: The most common type of joint employed in the fabrication of welded pipe systems is the circumferential butt joint. It is the most satisfactory joint from the standpoint of stress distribution. Its general field of application is pipe to pipe, pipe to flange, pipe to valve, and pipe to fitting joints. Butt joints may be used for all sizes, but fillet-welded joints can often be used to advantage for pipe NPS 2 (DN 50) and smaller. 30 Figure 22: Butt-Welded Joints Fillet Welds: Circumferential fillet-welded joints are generally used for joining pipe to socket joints in sizes NPS 2 (DN 50) and smaller. Figure A2.29 illustrates three typical filletwelded joints. These types of welds are subjected to shearing and bending stresses, and adequate penetration of the pieces being joined is essential. This is particularly important with the socket joint, since the danger of washing down the end of the hub may obscure, by reason of fair appearance, the lack of a full and sound fillet weld. This condition is one which cannot be detected in the finished weld by the usual visual inspection. Additionally, a 1/16-in (1.5-mm) gap (before welding) must be maintained between the pipe end and the base of the fitting to allow for differential expansion of the mating elements. 31 Figure 23: Fillet Weld Joints of Air Compressor piping system DRAWING The main purpose of a technical drawing is to communicate fabrication requirements clearly and simply. Before execution of project, there should be proper planning for the success of the project. I participated in site survey and drafting of different drawing which are used for fabrication and field erection. To design process piping, five types of drawings are developed in sequence. These drawings are developed from the schematics and specifications for process piping prepared by the process engineer. In order of development, the sequence is as follows: 1. General Arrangement (GA) 2. Process Flow Diagram (PFD) 3. Piping and Instrumentation Diagram (P&ID) 4. Plot plan layout 5. Isometric drawings. General Arrangement The piping plan or general arrangement (GA) drawing shows all major equipment to scale, its north/south and east/west orientation and all piping leading to and from the equipment. All 32 instrumentation, access ladders and platforms are shown. The GA will usually show a plan view (top) with elevations (side) and section elevations, as well as all pipe dimensions and piping details including line numbers, size and specifications with the direction of flow noted for all lines, so that the draftsperson will have all necessary information to create the final fabrication drawings or isometrics. Process Flow Diagram (PFD) A process flow diagram (PFD) is an unscaled drawing or schematic which describes the process of transferring material by piping. It will: ● State, for example, the materials (fluid) to be conveyed by the piping ● Specify the rates of flow ● List the pumps required ● Provide information such as pressure or temperature. At this point the pipe sizes, types of valves, etc., have not been determined. The PFD and specifications are then transferred to a piping and instrumentation (P&ID) diagram, plot plan or isometric drawing. Piping and Instrumentation Diagram (P&ID) The P&ID is similar to, but more detailed than, a PFD. It is a single-line schematic drawing that includes all major equipment items, instruments and controls, major valves and line sizes, It contains all the data necessary for the various design groups involved in the project to proceed to the next step in the design of the plant. Plot plan A plot plan or site plan is produced by the piping designer which shows schematic of the whole site with boundaries, roads, buildings, plant areas, equipment layouts, utility runs, and other constructions of the existing project, etc. at a properly defined scale. So it gives an overview of the entire plant. This allows the piping engineer to arrange equipment to optimize the design to reduce cost. Piping Isometric Drawing Piping Isometric drawings represent the pipe routing with proper dimensions including all piping items and equipment. They are not to the scale, single line diagram with symbols for pipe components, weld points, and supports. Isometric drawings are used: 33 By fabricator to fabricate the line. By piping material group for purchasing materials By the Construction team to erect the piping items in the site following proper routing. BELOW ARE SOME OF MY DRAWINGS I DRAFTED ON AUTOCAD Figure 24: Piping Isometric Drawing 34 Figure 25: Piping Isometric Drawing 35 Figure 26: General Arrangement showing position of Fire Hose Box and Hose Reel in a Production Floor 36 PAINTING OF FABRICATED PIPING Painting of piping and equipment’s as well as structures, is essential to avoid corrosion. It helps ensure long life of a constructed plant and low maintenance costs. Painting involves not only total surface cover but also markings of various types such as line numbers, fluid codes, flow arrows, equipment numbers etc. I participated in painting of different piping system such as natural gas piping and fire hydrant piping system. Painting Workflow 1. Ensure all tests are performed on piping system before starting painting work. 2. Clean painting surface to remove oils, grease, dirt. 3. Ensure proper room temperature and humidity levels. 4. Use hand tools, scrapper, wire brush etc. to clean surface as per relevant standards and project requirements. 5. Apply primer within 4 hours of surface preparation. 6. Apply paint coats after previous coats have dried up. 37 CHAPTER FOUR NEW SKILLS ACQUIRED AND CHALLENGES ENCOUNTERED During my Industrial training I acquired new skills in different skill such as: 1. Safety (HSE) skills 2. Piping fabrication and Installation skills 3. Project management and Supervision skills 4. Tool maintenance Safety (HSE) Skills: this include how to use a fire extinguisher, where a formal ‘Permit To Work’ system is in force it must be complied with. Where there is no such system, it is recommended that a responsible person should know what work is going on and, where necessary, arrange to have an assistant whose primary responsibility is safety and proper handling of fabrication tools to achieve zero hazards. Piping fabrication and Installation skills: I can now tack weld, bolt flange Joint, assembly and installation of equipment’s such as filters, pressure gauge, gas regulator and valve, assembly of threaded fittings and valves. Project management and Supervision Skills: The main function of the project management includes effective communication, involvement of team in decision making and effective information distribution. Also, the project management makes sure that things happen on time and keeping the project on schedule. The stages of managing a Project are: Initiating the project Planning the project Executing the project Monitoring and controlling the project Closing the project Tool maintenance: during my Industrial training I maintained some tools but limited to tools such as grinding machine welding machine cutting machine etc. To maintain proper working condition of tools, Good House Keeping is required by: 38 Clean the store tools properly. Fix or report broken tools. Store materials properly. Clean and maintain machine properly. Keep work place clean. Maintain adequate lightening. Challenges Encountered During my Industrial Training, I experienced some challenges, which are; a. Accommodation was a major challenge for me after securing an Industrial training placement and caused me much inconvenience. b. I also faced a major challenge in transporting myself to and fro office, I had to travel over eighty kilometres and beat heavy gridlock which was stressful but I was supported by the company which lessen the financial problem. c. I was forced to stop work during the pandemic lockdown and I was home for two months. 39 CHAPTER FIVE CONCLUSION AND RECOMMENDATIONS In conclusion, I was offered an opportunity for industrial experience at Datumenergy Nigeria Limited where I engaged in industrial activities that help shape my career development. Beyond gaining industrial experience, I got adapted to the industrial work environment, acquired both working and professional ethics and socialization. Before and after completing my training experience, I realized that Datumenergy Nigeria Limited is the best place for industrial training, especially for engineering undergraduates who wishes to specialize as process and piping engineers, maintenance of pipelines and major construction works including civil works (silo and concrete platforms construction) fabrication and installation. I realized that I learnt lot new things that one would never be able to learn at our universities academic environment. Also I was able to practice and understand most things I learnt at the university as theory. Equally, I was not left out during the inspection of piping system, Non-Destructive Testing and bubble leakage testing of threaded joints and commissioning of piping system. Finally, I can say I completed my Industrial Training successfully; I got lots of experience and guidance of my future career. RECOMMENDATION I strongly recommend that there should be an improvement in the teaching of the workshop practices courses where student will be allowed to use all the workshop tools and machines. The School authorities should set up a well-tailored programme towards developing students’ career. All Engineering students should be encouraged on the use of CAD software’s before going on Industrial training. 40 REFERENCES https://siwesbeginner.com/siwes-introduction/ www.wikipedia.com www.whatispiping.com www.pipingdesigners.com http://www.datumergy.ng Piping Engineering Handbook –Mohinder L. Nayyar, P.E Hardhat Piping Engineering Handbook –Varun Patel Pipe Fabrication –Department of Training and workforce Development Australia http://www-group.slac.stanford.edu/esh/eshmanual/references/pressureProcedTest.pdf Trade of Pipefitting – Finbar Smith 41