Uploaded by Uchenna Egwuatu

367165799-Layout

advertisement
Basics of Piping layout
Activities Involved







Pipe Rack Planning/Area Planning
Pipe Routing/modeling
Interference check
Discrepancy check
Visual walk through of plant model
Preparation of piping isometric drawings
Preparation of Piping composite drawings
Inputs Required











Plot Plan
G.A. drawing of building or specific area
Equipment GA drawings
3 D Models
Civil/ Structural drawings
Piping and Instrumentation Diagrams (P&IDs)
Terminal Point Details
In Line Component details
Instrument installation drawings or guide line.
Design Criteria document
Piping Design Tables (PDTs)
Piping Layout Considerations:
 Operation
 Maintenance
 Constructability
 Economics
 Safety
 Aesthetics
A
B
C
Pipe racks and Pipe Trenches
 Piping outside process units shall be supported on
sleepers, at ground level in Pipe racks or below ground
level in Pipe Trenches.
 The choice between Pipe tracks and Pipe trenches is
dictated by technical and economic considerations.
 The distance between sleepers in pipe tracks and in pipe
trenches shall be based on maximum allowed free span of
the majority of pipes.
 Elevation of sleepers shall be such that there is access for
maintenance and for operation of valves, drains and
instrumentation.
 Flanged connection shall not be installed in trenches.
 Concrete trenches shall be adequately drained.
The Headroom normally provided
is as below.
Sr.
No.
1.
2.
3.
4.
5.
Description
Clear head room under
Structures/pipe lines
inside operating area.
Head room over rail
(from top of rails)
Clear headroom above
crest of road for crane
movement.
Clear headroom above
crest of road for truck
movement.
Clear headroom above
crest of road between
Headroom
(mm)
2200
7000
7000
6000
4500
Flexibility
Flexibility
General Piping layout Guidelines











Shall be done in line with process requirement.
Bottom of lines should be on same elevation.
Avoid pipe in Trenches.
Avoid valves in vertical run
Proper accessibility of inline components
Pipe to pipe spacing shall be as recommended
Distance between pipes shall allow for turning of spectacle
blind, if present.
Piping shall be supported properly.
Standard and easily available pipe fittings to be used.
For large dia buried pipe line air release valves, manholes
to be provided.
Slopes to be provided in pipeline as per the process
requirement.
General Piping Layout Guidelines
 For cold lines with stretch beyond 80 meter, expansion loop
shall be provided.
 Flanges installed to facilitate maintenance and inspection.
 Branch connection for air, steam or gas line should be on top
and for water or liquid line should be from bottom of main
header.
 Installation of valves.
 Control valve installation.
 Drain and vent connections.
Specific guidelines for piping around
Pumps
 General
 Strainers
 Pressure relief
 Suction piping of centrifugal pumps
Specific guidelines for Fuel Gas Piping
 Branch connection taken from top of main header.
 All flanged joints shall be provided with jumper
arrangement to avoid any discontinuity which may
cause sparking due to static electricity generation
and shall be suitably earthed afterwards.
Specific guidelines for Tank Farm Area
Piping
 Within the bund/dyke area the number of pipes shall be
minimized and shall be routed in shortest practicable way.
 Pipes shall be grouped together
 Pipes connected to tanks shall be sufficiently flexible to
cope with thermal expansion/contraction.
 Piping shall be connected and supported after hydrostatic
testing of tank.
 Piping shall be supported by concrete sleepers or steel
frames.
 There shall be access to manholes, mixing nozzles, drains
and other facilities on the tanks.
Specific guidelines for Steam Piping









Branch lines from steam header should be taken from top of
header
Low point drains should be provided in steam lines
Drain should be provided upstream side of valve
Loop shall be provided to provide flexibility in long straight run of
pipe
All steam piping should be sloped down in the direction of flow a
minimum of 5mm/meter or as specified
All high points should be vented
Temperature elements (TI, TW, TE) tap point shall be provided on
top and pressure elements tap points shall be provided in
horizontal direction.
All valves shall be placed at accessible position.
All steam lines shall preferably be supported from top.
Specific guidelines for Large Diameter
Piping
 Pipes DN 900 and Larger shall be provided with inspection
and maintenance manholes of minimum size DN 600 and
distance between manholes should be no more than 100m
 Cooling towers shall have isolation valves
 Main distribution pipes shall have drain and vent facilities.
 Underground piping shall have minimum 1.0m soil cover
 Mitre bends to be used for 90 degree or 45 degree bends.
 Tees should generally be welded.
Piping For Instruments
 Flow measurement instruments need certain straight
length, normally 15D on the upstream and 5D on
downstream.
 Pipe lines in which flow meters are located should be fill
with Liquid all the time.
 Isolation valves for level gauges and pressure gauges shall
be made accessible.
 Rotameters shall be placed on vertical line and the inlet
should be from the bottom of the instrument
 Specific requirements for instrument installation to be
checked, like temperature gauge can not be installed in
pipe which is less than 4 inch in size
 Enough operating and maintenance access shall be
considered while locating any instrument.
Verification Points
 The layout to be checked properly considering support
location, feasibility of supports.
 Accessibility of all inline valves, instruments, equipment to be
checked.
 Piping layout should be interference free.
 Piping Layout should be inline with P&ID.
 Sufficient gaps are maintained between pipes for the
expansion due to high temperature.
 Piping layout to be checked with analysis for flexibility.
 Nozzle loads for Piping connection with any equipment should
be within vendor certified allowable limit.
 Layout to be checked for upstream downstream length
requirements of flow elements.
 Work Process MPD7.01
 Isometric check list
Suction of Pump
Valve location
 Easily accessible
1200-1500mm from
operating level
 Chain arrangement should
be provided where ever
required
Pipe line Vents and Drains
 Pipes are also
slopped towards low
points.
Download