NACE-CIP2-001 Real Dumps https://www.certspots.com/exam/nace-cip2-001/ NACE-CIP2-001 Real Dumps 1. NACE Level 2 Inspectors have been authorized to perform: A. All types of inspection without supervision B. Visual inspection and Non-destructive testing C. Visual inspection, Non-Destructive and Destructive testing D. Visual inspection only Answer: C NACE-CIP2-001 Real Dumps 2. You have just your NACE CIP Level 2 certification when you are asked to supervise a team of uncertified field pipeline inspectors. Your FIRST preferred course of action is to: A. Accept assignment without hesitation B. Advise the prospective employer that you cannot accept the position C. Meet with the prospective employer to scope of your role D. Review the NACE Attestation prior to making a decision Answer: D NACE-CIP2-001 Real Dumps 3. You are the new NACE Level 2 Inspector on a job which had been very problematic. The previous Inspector was fired duo to personality conflicts with the Contractor's supervisor. Upon arriving onsite the Contractor's supervisor advises you in no uncertain terms that you will be the next to go, unless you cooperate with him. Your FIRST preferred course of action is to: A. Challenge the supervisor’s authority B. Defend the previous inspector C. Express a willingness to work with the site team and follow the specification D. Suggest to the Owner that the supervisor should be removed from site Answer: C NACE-CIP2-001 Real Dumps 4. NACE International Standards are developed by: A. Government mandates B. International mandates C. Standard committees D. Regional mandates Answer: C NACE-CIP2-001 Real Dumps 5. You are the NACE Level 2 inspector reviewing the documentation from a NACE Level 1 you notice significant documentation errors. Your FIRST preferred course of action is to: A. Correct the errors yourself and suggest the Level 1 inspector be replaced B. Correct the errors yourself and advise your supervisor that the Level 1 Inspector is incompetent C. Have the Level 1 Inspector correct the errors and set up remedial training to improve the quality of documentation D. Correct the errors yourself and submit the reports without any further action Answer: C NACE-CIP2-001 Real Dumps 6. As a NACE Level 2 Inspector on a field job; prior to submission your documentation should always reviewed and approved by: A. A NACE Protective Coating Specialist B. A NACE Level 1 Inspector C. Another NACE Level 2 Inspector D. A NACE Level 3 Inspector Answer: D NACE-CIP2-001 Real Dumps 7. You are a NACE Level 2 in-house inspector working in a shop. Your in-house requires you to perform a sleeve test to test for soluble salts; however the 3rd party NACE Level 3 inspector, the owner, has a san smart meter and has achieved a very different result and has rejected the pre-cleaning. Your FIRST course of action is to: A. Advise the other inspector he is using an incorrect method B. Redo the pre-cleaning based on the other inspectors results C. Review the specification with the other inspector to see what method was specified D. Advise your QC Manager to change the ITP to the use of the salt smart meter Answer: C NACE-CIP2-001 Real Dumps 8. You are the NACE Level 2 Coating Inspector where SSPC PA 2 has been specified with an additional requirement that no individual gauge reading shall be below a certain value. As this is not part of the standard you should: A. Ignore the additional requirement B. Enforce the additional requirement C. Call your supervisor D. Request clarification from the specifier Answer: B NACE-CIP2-001 Real Dumps 9. You are a NACE Level 2 Coating Inspector who has just arrived on a job in progress where there is no Inspection and Test Plan (ITP). The first morning you arrive the job is behind schedule and you are asked to take DIY Film Thickness readings. Your FIRST preferred course of action is to: A. Refuse to take readings until an is in place B. Develop your own methodology and proceed take the readings C. Use a generally accepted industry standard and to take readings D. Call your supervisor Answer: C NACE-CIP2-001 Real Dumps 10. You are working as the only in-house NACE Level 2 Inspector in a shop setting when an independent 3rd party NACE Level 3 Inspector, representing the owner, presents you with a copy of a Non Conformance Report (NCR) he has written for a NACE2/SSPC SP 10 centrifugal blast which you had previously approved. Your FIRST preferred course of action is to: A. Verbally challenge the NCR B. Request a re-blast of the item in question C. Consult your supervisor D. Review the NCR with the other Inspector Answer: C