ABSTRACT A smart grid is a technology that divides the electricity grid into a two-way flow of data and electricity. The technology includes energy measures ad operations such as smart appliances, smart meters, energyefficient resources, and more. The technology of the smart grid aims to support and integrate renewable energy into the conventional energy source. Not only does it use alternative energy sources, but the smart grid technology also allows consumers to monitor energy consumption. DR / Abd El-Latif Smart Grid SMART GRID Under Supervision: DR / Abd El-Latif by: Eng / Abdallah Khaled 1 Distribution System and Relay Coordination The problem of the relay coordination under different fault conditions has been solved for the three-phase unbalanced IEEE 13-bus distribution test system shown in Fig. 1. This system contains a mixture of single, double and three phase lines and loads. Note that the system lines 684-653 and 684-611 are single phase; lines 671-684, 632-645, 645-646 are two phase and the remaining lines are three phase. Directional over-current protection is used against fault current that could circulate in both directions through the system. When DG is present, there are multiple power sources. Hence, the nature of distribution network changes with multiple DG units. Consequently, directional relays are needed in the network. Directional relays should be placed along the line that links the main grid and the DG. Relay characteristic uses time delay to provide tripping. The relay, which is located at the furthest point from the source, is tripped in the shortest time. Other relays are tripped in a sequence with longer time delays, going back in the direction of the source. These relays are classified based on their characteristic curves. IEC 60255 defines a number of standard characteristics as follows: where t is the operating time of the relay, TMS is the time multiplier setting, Is is the pickup current of relay, If is the relay current (overload and/or fault), and n (0.14, 13.5, 80 and 120) are the constants which depend on the relay characteristics. Since relay operating time t is a nonlinear function of both TMS and Is, the time characteristics of overcurrent relay are generally nonlinear. In general, the current setting is selected to be above the maximum short time rated current of the circuit. The pick-up values of phase over-current relays are normally set at 30% above the maximum load current. 3 Analysis of The Various Fault Scenarios In this study, the IEEE-13 bus distribution system is chosen as test system to perform different fault scenarios. Five different regions on the test system such as a, b, c1, c2 and c3 which is shown in Figure 2 are defined to observe the effects of fault currents from the fault location. Four different scenarios are simulated using four DG connected to different regions mentioned before on the test system. Each DG unit is chosen as wind turbine which has 1.5 MW capacity considering the total system load. In simulations, three phase fault is applied to 675-bus for all scenarios and fault currents are observed for every bus in test system. Thus, it can be analyzed the effect of faults on DGs connected to different regions and the selectivity of relays. In first scenario, four DGs are connected to the regions c1, c3, a, and b as shown in Fig 3. Three phase fault is applied to node 675 and the fault currents are seen in red-dot-lines. In second scenario, two DGs are connected to region a and others are connected to region b. This configuration is given in Fig 4. In third scenario, all four DGs are located to region c1. This location is the furthest point from the fault as shown in the Fig 5. Finally, four DGs are connected to region c3 as a nearest location of master source which is a diesel generator. This configuration is seen from the Fig 6. The fault analyses are performed for all scenarios. 4 Test and Results Four different scenarios are considered in an island-mode for the study. Line 675, which is an effective node in distribution system, is selected as fault zone. Four wind turbines (WTs), each with a rating of 1.5 MW and one diesel generator with a rating of 3.125 MW are connected to the system for all scenarios. The fault currents occurred in the various nodes are given Table 1. The lines 632, 671, 692, 675 and 680 are investigated due to the fact that the fault substantially affects these lines, as shown in Table 1. The fault currents change significantly for various scenarios in the same node. For instance, considering the node 632, a difference of 900 A is observed comparing Scenario 1 and Scenario 3 during the fault. Similarly, there is a difference of 500 A at the node 692 comparing the Scenarios 2 and 3. The severe differences in the current values cause coordination problems, especially in DOCRs. The operation times of each DOCR are calculated according to the Eq. 1 and given in Table 2 for IEEE 13-bus distribution test system without DGs. In this study, the calculations of relay coordination are carried out separately for four scenarios and the operating times are obtained which is shown in Table 3. It is to be noted that the fault currents in different scenarios are the most influential factor on the operating times. For instance, an obvious time difference is observed for R4-R5 coordination comparing Scenario 1 and Scenario 2. Likewise, R10-R11 coordination has an important difference in Scenarios 2 and 3. The time differences cause false operations while disturbing the relay coordination. Besides, unplanned power outages can be realized in the distribution system and reliability of the protection system can be decreased. Therefore, it is worthy to mention that the adaptive relay coordination should be implemented in the system protection of smart grids.