Uploaded by Ahmad Sulhi Ghazali

303624354-PRINCE2-Quick-Reference-Guide

advertisement
Process Fundamentals
Theme Fundamentals
Starting Up a Project (SU)
Business Case
There must be a business requirement that triggers a project.
The question ‘Do we have a worthwhile and viable project’ needs to
be answered. This process clarifies this answer and sets up an
organization structure to manage the project throughout its life.
The project starts with an idea which is considered to have potential
value for the organization concerned. This Theme addresses how the
idea is developed into a viable investment proposition for the
organization and how project management maintains the focus on the
organization’s objectives throughout the project.
Directing a Project (DP)
Organization
This process is conducted by the Project Board, above the Project
Manager. The Project Board manages by exception, monitors via reports
and controls through a small number of decision points. These are the DP
activities.
The organization sponsoring the project needs to allocate the work to
managers who will be responsible for it and steer it through to
completion. Projects are cross-functional so the normal line
management structures are not suitable. This theme describes the
roles and responsibilities in the temporary PRINCE2® project
management team required to manage the project effectively.
Initiating a Project (IP)
A project needs planning and setting up properly. IP plans the project
at high level and sets up all the controls and files. The main document
for the project is created - the Project Initiation Document (PID). The PID
forms the basis of a ‘contract’ which ensures there is a common
understanding of the project and encourages the Project Board to take
ownership of the project.
PRINCE2®
Quick Reference
Guide
Controlling a Stage (CS)
Quality
The initial idea will only be understood as a broad outline. This
Theme explains how the outline is developed so that all participants
understand the quality attributes of the products to be delivered – and
then how project management will ensure that these requirements are
subsequently delivered.
Plans
PRINCE2® projects proceed on the basis of a series of approved
plans. This theme complements the Quality theme by describing the
steps required to develop plans and the PRINCE2® techniques that
should be applied. In PRINCE2®, the plans are matched to the needs
of the personnel at the various levels of the organization. They are
the focus for communication and control throughout the project.
Once a decision has been made to proceed with work, and the
appropriate resources have been committed, the project management
team must be focussed on delivering within the tolerances agreed. CS
describes the work of the Project Manager in handling the day-to-day
management of the project. It starts after the Project Board approves the
Stage Plan. It is closely linked with the MP process.
Risk
Projects typically entail more risk than stable operational activity.
This theme addresses how project management manages the
uncertainties in its plans and in the wider project environment.
Managing Product Delivery (MP)
This process allows a ‘controlled break’ between the Project
Manager, Team Manager and the creation/provision of the products. In
MP products are created, quality checked and delivered.
Managing Stage Boundaries (SB)
All projects, need to be focussed on delivering business benefit, either in
their own right, or as part of a larger programme. At each stage end, the
continuing viability of the project should be confirmed. If needed, the
project can be redirected or stopped to avoid wasting time or money.
Change
CIPFA
3 Robert Street, London WC2N 6RL
prince2@cipfa.org.uk
www.cipfa.org.uk/training/accredited
Closing a Project (CP)
One of the defining features of a project is that it is finite – it has a start
and an end. Just as SU and IP ensure a controlled start to the project,
this process ensures a controlled end (closure). All loose ends are tied
off and lessons identified.
CUPE Limited © 2012 – Version 5.July 2009
PRINCE2® is a registered trade mark of the Cabinet Office.
The Swirl Logo™ is a Trade mark of the Cabinet Office.
This theme describes how project management assesses and acts
upon issues which have a potential impact on any of the baseline
aspects of the project (its plans and completed products). Issues may
be unanticipated general problems, requests for change or instances
of quality failure.
Progress
This theme addresses the ongoing viability of the plans. The theme
explains the decision-making process for approving plans, the
monitoring of actual performance and the escalation process if events
do not go according to plan. Ultimately, the Progress theme
determines whether and how the project should proceed.
Based upon PRINCE2® Manual 2009 Edition
Processes & Activities
Starting Up a Project (SU)
• Appoint Executive and Project Manager
• Capture Previous Lessons
• Design & Appoint PM Team
• Prepare the Outline Business Case
• Select Project Approach & Assemble Project Brief
• Plan the Initiation Stage
Directing a Project (DP)
• Authorise Initiation
• Authorise the Project
• Authorise a Stage or Exception Plan
• Give Ad Hoc Direction
• Authorise Project Closure
•Plans
•Quality
•Risk
•Organization
•Business Case
Stages
Business Case
Themes Used
The key philosophy of PRINCE2® is that the project is driven by the
Business Case. The focus on the Business Case should be on its totality of
business change, not just one element of it. The following diagram shows
where the Business Case is created and updated throughout the project
life-cycle.
Project
Mandate
Project
Brief
PID
Stages are divisions of the project for management purposes. Each stage is
reviewed by the Project Board who approve them one at a time (at an End
Stage Assessment). Stages are major decision making points in PRINCE2®.
Management stages equate to commitment of resources and authority to
spend. Technical stages are groups of specialist skills / activities required
to create the specialist products.
Technical Stages
PID
Outline Business Case
Refined & Approved
Business Case
Reasons for the Project
Specification
Design
Business
Case
Build
•Progress
•Business Case
•Risk
Expected Benefits
Updated Business Case
Test
Reviewed Business Case
Benefits
Review
Plan
Implement
End
Stage
Report
Project
Issues
End-Stage
Assessments
(Project Board
Decision Points)
Controlling a Stage (CS)
• Authorise Work Package
• Review Work Package Status
• Receive Completed Work Package
• Review Stage Status
• Report Highlights
• Capture & Examine Issues and Risks
• Escalate Issues & Risks
• Take Corrective Action
Management Stages
Products
•Progress
•Plans
•Quality
•Risk
•Business Case
•Change
•Organization
•Progress
•Change
•Risk
•Quality
In PRINCE2® there are three types of management products, “Baseline”,
“Records” & “Reports”. Specialist products are the unique outputs of the
project.
A.1
A.2
A.3
A.4
A.5
A.6
A7
A.8
A.9
A.10
A.11
A12
A.13
Benefits Review Plan
Business Case
Checkpoint Report
Communication Management Strategy
Configuration Item Record
Configuration Management Strategy
Daily Log
End Project Report
End Stage Report
Exception Report
Highlight Report
Issue Register
Issue Report
A.14
A.15
A.16
A.17
A.18
A.19
A.20
A.21
A.22
A.23
A 24
A.25
A.26
Lessons Log
Lessons Report
Plan
Product Description
Product Status Account
Project Brief
Product Initiation Documentation
Project Product Description
Quality Management Strategy
Quality Register
Risk Management Strategy
Risk Register
Work Package
Managing Product Delivery (MP)
• Accept a Work Package
• Execute a Work Package
• Deliver a Work Package
•Progress
•Business Case
•Quality
From Customer
Project Response
Customer’s Quality
Expectations
Acceptance Criteria
Project Product
Description
Quality Management
Strategy
Quality Components
Quality Criteria &
Tolerances
Product Descriptions
PRINCE2®
Product-based
Planning Technique
Quality Methods
Quality Responsibilities
Quality Register
COMMUNICATE
PRINCE2®
Quality Review
Technique
Risk Assessment evaluates the risk using
the probability of it happening & the impact
if it does. Responses are considered to
decide the best way forward.
PRODUCT
Quality & Approval
Records
CONTROL
Closing a Project (CP)
• Prepare Planned Closure
• Prepare Premature Closure
• Hand Over Products
• Evaluate the Project
• Recommend Project Closure
•Progress
•Plans
•Business Case
•Risk
•Organization
Risk
Project management must control and
contain risks if a project is to stand any
chance of being successful. Assumptions
about risk have to be regularly revisited
and reconsidered, for example at each
End Stage Assessment. Risk requires,
identification prior to assessment
leading to a plan which is implemented.
This Risk Management Cycle diagram
shows the relationship between them.
• Identify all the Project’s Products.
• Define the products in Product Descriptions
• Implement and track the Quality Methods employed throughout the
Project.
QUALITY
Managing a Stage Boundary (SB)
• Plan the Next Stage
• Update the Project Plan
• Update the Business Case
• Report Stage End
• Produce an Exception Plan
•Progress
•Change
•Plans
•Quality
The specific treatment for quality in PRINCE2® is the focus on products from
the outset, requiring systematic activities to:
QUALITY
•Management products – shown in Appendix A of the manual.
The Quality Approach
PLANNING
Initiating a Project (IP)
• Prepare the Risk Management Strategy
• Prepare the Quality Management Strategy
• Prepare the Configuration Management Strategy
• Prepare the Communication Management Strategy
• Set up the Project Controls
• Create the Project Plan
• Refine the Business Case
• Assemble the Project Initiation Documentation
Acceptance Record
Crown Copyright 2009.
Reproduced under license from OGC
Crown Copyright 2009.
Reproduced under license from OGC
Download