Point 1 A: We need to change the Task 3 constraint date as we can’t change the start project date and no way any task can start before the project starting date. Point 3. A: 20-07-2014 Point4 A: 83% of the project completed Point5 A: Ravi has the most remaining working hours 172 Remaining hours Point6 A: Sam has 40 hours remaining Choreographer completed 89% of th work Point7 A: There is no late tasks Point 8 A: Point 9 A: Completed tasks Point 10 A: The tasks colored in pink are a critical task Point 12 A: The WBS code as follow: WBS 1.1.1 1.1.2 1.1.4 1.1.5 1.1.6 1.1.7 1.1.8 1.1.9 1.1.10 1.1.11 1.1.12 1.2 1.3.1 1.3.2 1.3.3 The symbol of overallocated can be found in Indicator field and will be in red Point 13 A: Point 14 A: 1. Fast-Tracking: I have changed the predecessors of task 19- Assemble final version of video type from Finish to Start to Start to Start 2. Lead Add lead into task 18 with Task 17 by -2 days 3. Crashing Add another resource to Task 19 to reduce the duration but will keep the same amount of work as is