Point 1 A:
We need to change the Task 3 constraint date as we can’t change the start
project date and no way any task can start before the project starting date.
Point 3. A:
20-07-2014
Point4 A:
83% of the project completed
Point5 A:
Ravi has the most remaining working hours
172 Remaining hours
Point6 A:
Sam has 40 hours remaining
Choreographer completed 89% of th work
Point7 A:
There is no late tasks
Point 8 A:
Point 9 A:
Completed tasks
Point 10 A:
The tasks colored in pink are a critical task
Point 12 A:
The WBS code as follow:
WBS
1.1.1
1.1.2
1.1.4
1.1.5
1.1.6
1.1.7
1.1.8
1.1.9
1.1.10
1.1.11
1.1.12
1.2
1.3.1
1.3.2
1.3.3
The symbol of overallocated can be found in Indicator field and will
be in red
Point 13 A:
Point 14 A:
1. Fast-Tracking:
I have changed the predecessors of task 19- Assemble final version
of video type from Finish to Start to Start to Start
2. Lead
Add lead into task 18 with Task 17 by -2 days
3. Crashing
Add another resource to Task 19 to reduce the duration but will keep
the same amount of work as is