Participants: xxx Purpose: Agree the workplan for completing “once in decade” repairs to the mill back-end. Payoff: We are all clear on the safety, throughput and recovery impacting work packages that need to be completed when the plant is down due to OLC off-line Process: 1.Spence to give an overview of mandate from CEO and GM to complete repairs to identified safety, throughput and recovery impacting gaps 2.Spence to share updated work plan to identify repairs needed to safety, throughput and recovery impacting gaps 3.Rest of team to point out omissions, issues etc. and assigned team members take actions to resolve and update plan to 4.What other work outside priority#1 do we pause vs. stop vs. continue? 5.Rough sketch of timelines on whiteboard 6.Recap of what – who – when actions Prep – read the 5Ps.