SPM 0212 Communications and Condition Monitoring Infrastructure

advertisement
SPM 0212
COMMUNICATIONS & CONDITION
MONITORING INFRASTRUCTURE
Version 1.1
Issued February 2012
Owner:
Engineering Communications Manager, Communications & Control Systems
Approved
by:
Navin Hegde
A / Communications Delivery
Manager
Communications & Control
Systems
Authorised
by:
Jeff Byron
Chief Engineer
Telecommunications
Disclaimer
This document was prepared for use on the RailCorp Network only.
RailCorp makes no warranties, express or implied, that compliance with the contents of this document shall be
sufficient to ensure safe systems or work or operation. It is the document user’s sole responsibility to ensure that the
copy of the document it is viewing is the current version of the document as in use by RailCorp.
RailCorp accepts no liability whatsoever in relation to the use of this document by any party, and RailCorp excludes
any liability which arises in any manner by the use of this document.
Copyright
The information in this document is protected by Copyright and no part of this document may be reproduced, altered,
stored or transmitted by any person without the prior consent of RailCorp.
UNCONTROLLED WHEN PRINTED
Page 1 of 75
Engineering Specification
Engineering Specification
Telecommunications
RailCorp Engineering Specification — Telecommunications
Communications & Condition Monitoring Infrastructure
SPM 0212
Document control
Version
1.0
Date
January 2012
Reviewers
Chris Go
Wireless Systems Manager
Summary of change
First issue
Pat Kerrigan
Telecommunications Network Manager
Llewellyn Mead
Data Networks Manager
1.1
February 2012
Thuan Ngo
Condition Monitoring Systems Manager
Chris Go
Wireless Systems Manager
Thuan Ngo
Condition Monitoring Systems Manager
Correction to GRN and
Police Radio coverage
requirement.
Correction to earthing for
Condition Monitoring
systems
Summary of changes from previous version
Summary of change
Correction to GRN and Police Radio coverage requirement.
Correction to earthing for Condition Monitoring systems
© RailCorp
Issued February 2012
UNCONTROLLED WHEN PRINTED
Section
10
11.5
Page 2 of 75
Version 1.1
RailCorp Engineering Specification — Telecommunications
Communications & Condition Monitoring Infrastructure
SPM 0212
Contents
1
1.1
1.2
1.3
Introduction .............................................................................................................................6
Background ...............................................................................................................................6
Purpose .....................................................................................................................................6
Scope and Application ..............................................................................................................7
2
2.1
2.2
Definitions and abbreviations................................................................................................8
Definitions .................................................................................................................................8
Abbreviations ............................................................................................................................9
3
3.1
General requirements ...........................................................................................................10
Design process .......................................................................................................................10
3.1.1
Requirements Specification .....................................................................................10
3.1.2
Concept Design .......................................................................................................10
3.1.3
Detail Design ...........................................................................................................11
3.1.4
Test Strategy and Plans ..........................................................................................12
3.1.5
RATM.......................................................................................................................12
3.1.6
As Built Documentation ...........................................................................................12
Coordination of design ............................................................................................................12
Acceptance testing and commissioning..................................................................................13
Other obligations .....................................................................................................................13
3.2
3.3
3.4
4
4.1
4.2
4.3
4.4
Facilities and DC Power .......................................................................................................13
Telecommunications equipment rooms ..................................................................................13
Standards, Specifications and Drawings ................................................................................13
4.2.1
General ....................................................................................................................13
4.2.2
Site specific design documentation .........................................................................14
Equipment cabinets.................................................................................................................15
4.3.1
Standards, Specifications and Drawings .................................................................15
4.3.2
Requirements ..........................................................................................................15
DC Power supplies..................................................................................................................17
4.4.1
Standards, Specifications and Drawings .................................................................17
4.4.2
Requirements ..........................................................................................................17
5
Cables.....................................................................................................................................19
5.1.1
Standards, Specifications and Drawings .................................................................19
5.1.2
Requirements ..........................................................................................................19
6
Transmission Networks........................................................................................................21
6.1.1
Standards, Specifications and Drawings .................................................................21
6.1.2
Requirements ..........................................................................................................21
7
Emergency and Operations PABX Telephones .................................................................23
7.1.1
Standards, Specifications and Drawings .................................................................23
7.1.2
Requirements ..........................................................................................................23
8
8.1
Data Networks .......................................................................................................................27
General Requirements ............................................................................................................28
8.1.1
Standards, Specifications and Drawings .................................................................28
8.1.2
Type approved equipment .......................................................................................28
© RailCorp
Issued February 2012
UNCONTROLLED WHEN PRINTED
Page 3 of 75
Version 1.1
RailCorp Engineering Specification — Telecommunications
Communications & Condition Monitoring Infrastructure
8.2
8.3
8.4
8.5
9
9.1
9.2
10
10.1
10.2
SPM 0212
8.1.3
C&CS ManageNet ...................................................................................................28
8.1.4
Network Management and Monitoring.....................................................................28
8.1.5
Naming Conventions ...............................................................................................29
8.1.6
IP Addressing ..........................................................................................................29
8.1.7
Power and location ..................................................................................................29
8.1.8
Commissioning Tests ..............................................................................................29
8.1.9
Fibre Connectivity ....................................................................................................29
ATM Network Requirements ...................................................................................................29
8.2.1
ATM Network VPNs.................................................................................................29
8.2.2
Access to an ATM Network VPN .............................................................................30
8.2.3
ATM Node Access Network.....................................................................................30
OCDN Requirements ..............................................................................................................30
8.3.1
OCDN Hierarchy......................................................................................................30
8.3.2
OCDN VPNs – Ethernet/IP Networks......................................................................31
8.3.3
Provider Access.......................................................................................................31
8.3.4
Customer Access.....................................................................................................31
8.3.5
Interfaces .................................................................................................................32
8.3.6
Availability................................................................................................................32
8.3.7
Aggregation (Distribution) ........................................................................................32
8.3.8
Core .........................................................................................................................32
Site Specific Requirements .....................................................................................................33
8.4.1
High Voltage (HV) Sites...........................................................................................33
8.4.2
Stations ....................................................................................................................33
Serial Data ..............................................................................................................................33
8.5.1
Interfaces .................................................................................................................33
8.5.2
Real Time Critical Serial data ..................................................................................33
8.5.3
Non Real Time Critical Serial data ..........................................................................33
8.5.4
Signalling Applications.............................................................................................33
8.5.5
Serial Device Management .....................................................................................34
8.5.6
Serial Data Modems ................................................................................................34
8.5.7
Serial to Fibre Optical Converters ...........................................................................34
8.5.8
Serial to Ethernet Converters ..................................................................................34
Network Control Communications Systems (NCCS) ........................................................34
Voice Communication System ................................................................................................34
9.1.1
Standards, Specifications and Drawings .................................................................34
9.1.2
Requirements ..........................................................................................................34
Voice Recorder Network .........................................................................................................37
9.2.1
Standards, Specifications and Drawings .................................................................38
9.2.2
Requirements ..........................................................................................................38
Wireless infrastructure .........................................................................................................39
General Requirements ............................................................................................................40
10.1.1 Standards, Specifications and Drawings .................................................................40
10.1.2 Requirements ..........................................................................................................40
Antenna Systems ....................................................................................................................43
10.2.1 Standards, Specifications and Drawings .................................................................43
10.2.2 Requirements ..........................................................................................................43
© RailCorp
Issued February 2012
UNCONTROLLED WHEN PRINTED
Page 4 of 75
Version 1.1
RailCorp Engineering Specification — Telecommunications
Communications & Condition Monitoring Infrastructure
10.3
10.4
10.5
10.6
10.7
10.8
10.9
10.10
10.11
10.12
11
11.1
11.2
11.3
11.4
11.5
SPM 0212
RF EME Assessment and Site Compliance............................................................................46
10.3.1 Standards, Specifications and Drawings .................................................................46
10.3.2 Requirements ..........................................................................................................46
Wireless Infrastructure equipment rooms ...............................................................................47
10.4.1 Standards, Specifications and Drawings .................................................................47
10.4.2 Requirements ..........................................................................................................47
Wireless Infrastructure equipment cabinets............................................................................48
10.5.1 Standards, Specifications and Drawings .................................................................48
10.5.2 Requirements ..........................................................................................................48
Digital Train Radio System (DTRS) ........................................................................................49
10.6.1 Standards, Specifications and Drawings .................................................................50
10.6.2 Requirements ..........................................................................................................50
Without Brake-van (WB) Radio...............................................................................................51
10.7.1 Standards, Specifications and Drawings .................................................................51
10.7.2 Requirements ..........................................................................................................52
Station Radio...........................................................................................................................53
10.8.1 Standards, Specifications and Drawings .................................................................53
10.8.2 Requirements ..........................................................................................................53
Yard Radio ..............................................................................................................................55
10.9.1 Standards, Specifications and Drawings .................................................................56
10.9.2 Requirements ..........................................................................................................56
Government Radio Network (GRN) ........................................................................................58
10.10.1 Standards, Specifications and Drawings .................................................................58
10.10.2 Requirements ..........................................................................................................58
Police Radio ............................................................................................................................59
10.11.1 Standards, Specifications and Drawings .................................................................59
10.11.2 Requirements ..........................................................................................................59
Public Mobile Network.............................................................................................................60
10.12.1 Requirements ..........................................................................................................60
Condition Monitoring Systems............................................................................................62
Types of Train Condition Monitoring Systems ........................................................................63
Typical Systems required on New Rail Corridors ...................................................................64
11.2.1 Bearing and Brake Temperature (BBT) Detection System .....................................64
11.2.2 Ground Borne Noise (GBN) and Wheel Impact Load Detector (WILD)
systems....................................................................................................................64
Classes of Systems.................................................................................................................65
11.3.1 Classes Relevant to New Corridors.........................................................................65
11.3.2 Determination of Classes.........................................................................................65
Site Selection Criteria..............................................................................................................66
General System Requirements...............................................................................................66
11.5.1 Standards, Specifications and Drawings .................................................................66
11.5.2 Hardware Requirements..........................................................................................68
11.5.3 Software Requirements & Server Requirements ....................................................70
11.5.4 Design......................................................................................................................71
11.5.5 Documentation.........................................................................................................73
Appendix A
© RailCorp
Issued February 2012
Subject Matter Experts..........................................................................................75
UNCONTROLLED WHEN PRINTED
Page 5 of 75
Version 1.1
RailCorp Engineering Specification — Telecommunications
Communications & Condition Monitoring Infrastructure
1
Introduction
1.1
Background
SPM 0212
RailCorp’s Communications and Control Systems (C&CS) division owns and operates a
geographically vast telecommunications and condition monitoring systems infrastructure
network throughout the Sydney metropolitan area. C&CS’s telecommunications and
condition monitoring infrastructure consists of multiple communications technologies
including train radio systems, telephony & data networks, transmission systems, optical
fibre & cable network systems, and rolling stock & infrastructure conditioning monitoring
systems.
The C&CS telecommunications infrastructure supports a wide range of services critical to
railway operations such as train control and signalling, emergency and driver
communication, train location systems etc. C&CS infrastructure also supports a number
of “on station” services such as CCTV, SPI, ticketing, station LAN.
The C&CS condition monitoring systems infrastructure provides vital alarm and trending
data that help maintenance crews take corrective and preventative action for rolling stock
asset and in future, infrastructure faults. Equipment used includes HBDs and AOA
systems.
RailCorp is continuing to expand the railway network in Sydney and areas of New South
Wales. Expansion to the network also includes the addition of new tracks or turn backs.
New telecommunications and condition monitoring infrastructure required for this
expansion has to interface with the existing network and needs to be compliant with
C&CS technical and system requirements.
1.2
Purpose
This document is intended to detail the technical and system requirements for
telecommunications and condition monitoring systems infrastructure if deployed for
expansion of the rail network.
This document is not intended to provide all the necessary information required for
construction or tendering purposes and thus shall only be used as a general design
requirement guideline.
Applicability of the various specifications/requirements set out in this document could vary
depending on the project requirements, complexity and/or location. The requirements
shall therefore be assessed on a case by case basis. SME’s for respective disciplines, as
listed in 0, should be consulted if in doubt.
This is a living document and is organised into infrastructure categories where the
relevant RailCorp design authority responsible for each category maintains and updates
that section of the document.
Sections are divided into:
•
•
•
•
•
•
•
© RailCorp
Issued February 2012
General
Facilities and DC Power
Cables
Transmission Networks
Emergency and Operations PABX Telephones
Data Networks
Network Control Communications Systems
UNCONTROLLED WHEN PRINTED
Page 6 of 75
Version 1.1
RailCorp Engineering Specification — Telecommunications
Communications & Condition Monitoring Infrastructure
•
•
SPM 0212
Wireless Infrastructure
Condition Monitoring Systems
All new telecommunications infrastructure in rail corridors is to be compliant with all
Australian Standards and RailCorp Standards, where this document provides
specification for design it is to be used in addition to these standards.
If there is a conflict between this document and the Australian Standards or RailCorp
Standards referenced in this document, then the Australian Standards and RailCorp
Standards shall take precedence and the Communications Engineering Manager of
C&CS Division shall be notified.
1.3
Scope and Application
The scope of this document is limited to providing C&CS’s requirements of
telecommunications and condition monitoring systems infrastructure for new rail corridors
and major expansions of existing rail corridors such as line duplication or quadruplication.
The following is in scope:
• Telecommunications Facilities and DC Power
Including equipment rooms, equipment cabinets, and DC power supplies
• Cables
Includes backbone cabling between telecommunications facilities, signalling
bungalows and other telecommunications infrastructure
• Transmission Networks
Voice and Data transmission equipment and interfaces
• Emergency and Operations PABX telephones
Telephone systems that are safety or operations critical and under C&CS’s
Operational and Maintenance responsibility
• Data Networks
Data switched network equipment supporting networks under C&CS’s Operational
and Maintenance responsibility
• Network Control Communications Systems
Including Voice Communication Systems, and Voice Recording systems for single
interface communication and recording of operations telephony and radio
• Wireless infrastructure
Including train radio, yard radio, station radio, the Government Radio Network, the
Police Radio Network and Public Mobile Networks
• Condition monitoring systems
Includes Bearing and Brake Temperature Detectors, Bearing Acoustic Monitors,
Dragging Equipment Detectors, Angle of Attack Detectors, Wheel Impact Load
Detector, In-Motion Weighbridge, Ground Borne Noise Detectors, Automatic
Equipment Identification, Wayside Information Management Systems
© RailCorp
Issued February 2012
UNCONTROLLED WHEN PRINTED
Page 7 of 75
Version 1.1
RailCorp Engineering Specification — Telecommunications
Communications & Condition Monitoring Infrastructure
SPM 0212
The following is out of scope:
• End user services
These are services that are supported by telecommunications and condition
monitoring systems infrastructure however fall outside the scope of this document,
such as Ticketing, CCTV and Passenger Information. These services may dictate
requirements for telecommunications and condition monitoring systems
infrastructure, however where and how they are implemented is as per the new
corridor or expansion design in consultation with their stakeholders.
• IT infrastructure for general administration
This is infrastructure that does not directly support railway operations such as IT
servers, desktop computers, printers and their associated networks, cables and
power. These services may dictate requirements for telecommunications
infrastructure; however where and how they are deployed is as per the new
corridor or expansion design in consultation with their stakeholders.
RailCorp’s Information and Communication Technology division (ICT) has
responsibility for operations and maintenance of administrations infrastructure.
• Telephony infrastructure for general administrative communications
This includes telephones located in offices and general station facilities on
desktops, which does not directly support railway operations. These services may
dictate requirements for telecommunications infrastructure; however where and
how they are deployed is as per the new corridor or expansion design in
consultation with their stakeholders.
RailCorp’s Information and Communication Technology division (ICT) has
responsibility for operations and maintenance of administrations telephony.
• Station “services” equipment rooms and on station “cable works”:
This document does not cover the technical requirements for station services
equipment rooms or related cable works. These services may dictate requirements
for telecommunications and condition monitoring systems infrastructure; however
where and how they are deployed is as per the new corridor or expansion design in
consultation with their stakeholders.
2
Definitions and abbreviations
2.1
Definitions
RailCorp’s Communications Engineering Communications Engineering in the C&CS
Division of RailCorp
Relevant Design Authority The SME Team Manager for the respective discipline, as
listed in 0
New Rail Corridors New rail corridors and major expansions of existing rail corridors
such as line duplication or quadruplication.
DTRS Digital Train Radio System.
RailCorp electrified area.
The train radio system implemented within the
SCADANet The SCADA system applied to the RailCorp electrical Network/traction
power.
© RailCorp
Issued February 2012
UNCONTROLLED WHEN PRINTED
Page 8 of 75
Version 1.1
RailCorp Engineering Specification — Telecommunications
Communications & Condition Monitoring Infrastructure
SPM 0212
OCDN The C&CS IP MPLS Backbone network
C&CS ATM The C&CS ATM Backbone network being replaced by the OCDN
Administration Telephones Desktop telephony which does not directly support railway
operations. This includes telephones located in offices and general station facilities on
desktops.
Administration infrastructure Infrastructure that does not directly support railway
operations such as IT servers, desktop computers, printers and their associated
networks, cables and power.
Station Services Equipment Room Services rooms house end user services
infrastructure and are separate from telecommunications rooms
On Station Cable Works Cable works at stations for end user services and services
equipment rooms
2.2
Abbreviations
AC Alternating current
AOA Angle Of Attack
AS Australian Standards
ATM Asynchronous Transfer Mode
C&CS Communications and Control Systems
CCTV Closed Circuit TV
DC Direct Current
DTRS Digital Train Radio System
EIRP Effective Isotropic Radiated Power
HBD Hot Box Detector, also BBT (Bearing and Brake Temperature detector)
IEEE Institute of Electrical and Electronic Engineers
IP Internet Protocol
IP Ingress Protection Rating
IT Information Technology
GRN Government Radio Network
LAN Local Area Network
MDF Main Distribution Frame
MUX Multiplexer and De-Multiplex unit
OCDN Operations Critical Data Network
PABX Private Automatic Branch Exchange
SDH Synchronous Digital Hierarchy
© RailCorp
Issued February 2012
UNCONTROLLED WHEN PRINTED
Page 9 of 75
Version 1.1
RailCorp Engineering Specification — Telecommunications
Communications & Condition Monitoring Infrastructure
SPM 0212
SME Subject Matter Expert
SPI Station Passenger Information
TDM Time Division Multiplexing
WB Without Brake-Van Radio System
WDM Wave Division Multiplexing
X-Ring An all ring, all talk, telephone arrangement
3
General requirements
3.1
Design process
Telecommunications and condition monitoring systems Infrastructure design shall follow
the established design process of RailCorp. Generally for large projects such as
expansions of the rail network or for new rail corridors, a design management plan is
required to demonstrate how the design process being followed meets the requirements
of RailCorp.
At a minimum, the design process will deliver the following:
3.1.1
Requirements Specification
The requirements specification brings together all the design requirements and inputs
sufficient for the design to proceed. The customer requirements are fully qualified and
may involve the production of design specifications, such as detailed user requirements
specifications, functional specification, performance specifications, and business
requirements specifications. The requirements specification requires agreement or signoff from the customer prior to proceeding further in the design.
3.1.2
Concept Design
The concept design is intended to confirm feasibility by establishing a design solution,
validating and verifying it to meet the overall objectives of the customer. This then forms
the basis for a detailed design. Once again, depending on the complexity of the project,
this may not be required for minor projects, but is mandatory for major projects.
For new or novel design solutions, the concept design phase is also the stage where a
“prototype” could be developed and the “proof of concept” established through a series of
tests and trials.
In some cases, a customer may require the design to just progress up to the concept
stage. Example: For establishing feasibility or project budgeting purposes and/or to
establish a business case.
The concept design is undertaken after the requirements have been developed and
analysed.
The concept design may also be undertaken in the form of a document, a drawing or
even a series of sketches. The following outputs are typical deliverables at the end of
concept design. However, for more specialised projects, additional documentation may
be required.
• System level schematics
• Network schematics
© RailCorp
Issued February 2012
UNCONTROLLED WHEN PRINTED
Page 10 of 75
Version 1.1
RailCorp Engineering Specification — Telecommunications
Communications & Condition Monitoring Infrastructure
•
•
•
•
•
•
•
•
•
•
•
•
•
SPM 0212
Preliminary loss budgets
Preliminary RAM (Reliability, Availability and Maintainability) analysis
Spare port and cable allocation checks
Material and equipment availability
Software identification
Typical Environmental limits
Typical floor plan
Changes to power and air-conditioning loads
Concept timing diagrams
Typical radio coverage
Feasibility and acceptance of a new design solution.
Indentify any changes to maintenance practises required.
Prototype development report or a proof of concept report.
The concept design may also be used to determine if there is a requirement to engage
other design workgroups and to provide input for the design planning such as scheduling,
costs, risks and issues.
3.1.3
Detail Design
The following outputs are typical deliverables at the end of detailed design:
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
Details of design for CCR purposes
Final system level and network schematics
Detailed equipment lists and final bill of materials.
Plant & equipment to be de-commissioned (if applicable)
Rack layout and distributor diagrams
Final port and cable allocations
Approved floor plan
Final loss budgets
Software and accompanying documentation
Software development and configuration management procedures
Availability calculations/RAM
IP addresses
Message formats
Environmental limits
Floor loads
Heat dissipation and air-conditioning loads
Timing diagrams
Test strategy, test and inspection plans
RATM (update)
Hazards & risk analysis (update)
FMECA
Additionally, the following documentation shall be included as part of the detailed design
documentation if appropriate:
• A Technical Maintenance Plan that includes corrective and preventative
maintenance routines.
• A requirement specification for appropriate maintenance level training.
• Identification of performance criteria for maintenance contracts to be put in place, if
applicable.
• A recommended spares holding based on availability requirements.
© RailCorp
Issued February 2012
UNCONTROLLED WHEN PRINTED
Page 11 of 75
Version 1.1
RailCorp Engineering Specification — Telecommunications
Communications & Condition Monitoring Infrastructure
3.1.4
SPM 0212
Test Strategy and Plans
The test strategy details the high level objectives to any testing required in the design, the
scope of the testing and key risks, assumptions and constraints in testing. It also details
at a high level, the testing methodology, types of testing to be conducted and test
deliverables. The types of testing required could vary on the complexity of the design and
could include FAT, SAT, Field Trials, Pilot Trials etc.
Test plans typically contain the following information:
•
•
•
•
•
•
•
•
•
•
•
3.1.5
Each test cases’ objectives
Entry and exit criteria
Resources required
Test environment
Prep activities
Components to be tested
Functions and features
Test cycles
Test cases or scenarios
Acceptance criteria
Tolerances
RATM
All requirements in the specification(s) must be traceable to one or more design outputs
via a Requirements Allocation and Traceability Matrix (RATM). The RATM is a matrix that
is used to tie the design output to the original requirements. If there is a change in the
design, the RATM must be revised to ensure that requirements are still met. Should a
requirement not be met, there must also be an approved change in the requirements
specification which will also be reflected in the concept design, risks, issues, costs and
scheduling etc.
3.1.6
As Built Documentation
At the completion of the infrastructure implementation the ‘as-built documentation’ should
be prepared and signed off. The final design involves the as-built documentation which
becomes the documented configuration of the system and which must only be changed in
the future by configuration control procedures.
3.2
Coordination of design
Telecommunications and condition monitoring systems infrastructure design shall be
developed in consultation with and reviewed by the relevant design approval authorities
within RailCorp, namely the subject matter experts with the delegated design authority
within RailCorp’s Communications Engineering and the Chief Engineers office.
Where telecommunications and condition monitoring systems infrastructure requires
design is to be completed by RailCorp’s Communications Engineering, it will follow the
existing RailCorp design process as per document TMM P025 (version 3.0).
Generally large design and implementation projects such as expansions of existing rail or
new rail corridors will require an Interface Management plan to show how the interface
between the party responsible for implementation, RailCorp and Transport NSW will be
managed for the coordination of design.
The external party responsible for implementation will also need to engage RailCorp’s
Communications Engineering for undertaking design and implementation of interface
works to existing infrastructure to satisfactorily integrate the new infrastructure being built.
© RailCorp
Issued February 2012
UNCONTROLLED WHEN PRINTED
Page 12 of 75
Version 1.1
RailCorp Engineering Specification — Telecommunications
Communications & Condition Monitoring Infrastructure
3.3
SPM 0212
Acceptance testing and commissioning
Telecommunications and condition monitoring systems infrastructure shall be tested and
commissioned as per existing specific infrastructure standards, specifications and
procedure. Where an existing specific process does not exist, acceptance testing and
commissioning will generally follow RailCorp Project Management Methodology (RPMM)
and be developed in consultation with and reviewed by the relevant design authorities
within RailCorp. Generally large projects such as expansions of existing or new rail
corridors requires a Testing and Commissioning plan to show how the testing and
commissioning requirements of RailCorp and Transport NSW will be met.
3.4
Other obligations
Implementation shall follow established project management process of RailCorp
(RPMM). Generally large projects such as expansions of existing, and new, rail corridors
require the following plans to demonstrate how the requirements of RailCorp are being
met:
•
•
•
•
•
•
•
Installation Management Plan
OH&S Management Plan
Quality Management Plan
RAM Management Plan
Risk Management Plan
Safety Management Plan
Through Life Support Management Plan
4
Facilities and DC Power
4.1
Telecommunications equipment rooms
4.2
Standards, Specifications and Drawings
4.2.1
Document
type
Document Title
Document
Number
Standard
Telecommunications Equipment Rooms
Standard
ESM 107
Standard
Communications Earthing and Surge
Suppression Standard
ESM 109
Drawing
Typical AC Power Supply Arrangements for
Telecommunications Equipment Rooms
MET SC 0476
General
a)
Telecommunications equipment rooms shall be provided in compliance with the
standard ESM 107. All telecommunications infrastructure equipment shall be
accommodated in dedicated telecommunications equipment rooms which shall
have a separate access. This room need not be on the platform or within the
structure of other station buildings, but shall be as closely as practicable
associated with the station.
b)
For interface equipment and/or new equipment, if space and power within an
existing telecommunications room is available, then a design proposal shall be
© RailCorp
Issued February 2012
UNCONTROLLED WHEN PRINTED
Page 13 of 75
Version 1.1
RailCorp Engineering Specification — Telecommunications
Communications & Condition Monitoring Infrastructure
SPM 0212
provided detailing the requirements and the solution for integration. The design
proposal shall include any upgrades that may be required to existing
infrastructure including power supply etc to accommodate the additional
infrastructure. In such cases, the final allocation and approval of the floor space
and/or rack space will be by the design approval authority within RailCorp’s
Communications Engineering.
4.2.2
c)
Telecommunications equipment belonging to third party service providers such
as carriers, GRN service providers, police radio equipment etc shall be
accommodated in a separate communications room.
d)
Other communications equipment associated with station services such as the
Public Address System, Help Points, station LAN, CCTV equipment, SPI,
ticketing etc will be housed in a separate dedicated “station” services
equipment room. Every station will require a “station” services equipment room
and this room shall have the necessary optical fibre and copper cable
interconnection to the telecommunications equipment room to facilitate
interconnection to the backbone network.
Site specific design documentation
Site specific design documentation shall be prepared for review and approval by the
design approval authority within RailCorp’s Communications Engineering. The site
specific design documentation shall specifically address the requirements of the standard
ESM 107.
The site specific design documentation shall also include (but not limited to):
a)
Room dimensions. The room size will be assessed on a site by site basis as it
may vary depending on the geographic location and strategic position within the
RailCorp telecommunications network.
b)
AC Power supply and distribution arrangements.
c)
Specific surge and lighting protection.
d)
Proposal for copper and optical fibre cables termination.
e)
General requirements for fire protection system.
f)
Cable management details including cable entry points and cable tray layout.
g)
Air conditioning and cooling requirements.
h)
Equipment rack space requirements.
© RailCorp
Issued February 2012
UNCONTROLLED WHEN PRINTED
Page 14 of 75
Version 1.1
RailCorp Engineering Specification — Telecommunications
Communications & Condition Monitoring Infrastructure
SPM 0212
Figure 1 - Example for Small Telecommunications Equipment Room Equipment Layout
4.3
Equipment cabinets
4.3.1
Standards, Specifications and Drawings
4.3.2
Document
type
Standard
Document Title
Standard
Communications Earthing and Surge
Suppression Standard
Telecommunications Equipment Rooms
Standard
Document
Number
ESM 107
ESM 109
Requirements
Provide new equipment cabinet/rack to accommodate communications equipment within
the telecommunications equipment rooms.
4.3.2.1
General
All new equipment cabinets to house telecommunications infrastructure shall be of
“approved” makes, which are generally included in existing RailCorp supply agreements.
4.3.2.2
Type approved equipment
Where an existing supply agreement and or specification are not in place, the equipment
cabinets called for in the design shall be subject to RailCorp’s type approval process.
© RailCorp
Issued February 2012
UNCONTROLLED WHEN PRINTED
Page 15 of 75
Version 1.1
RailCorp Engineering Specification — Telecommunications
Communications & Condition Monitoring Infrastructure
4.3.2.3
SPM 0212
Components
Generally equipment cabinets to house telecommunications infrastructure shall have:
•
•
•
•
•
4.3.2.4
19inch mounting rails.
Perforated front metal doors and flush mount handle.
3 point locking system.
Cable management system
The option of integrated AC Power distribution.
Cabinet width
The standard cabinet width is 600mm.
800 mm wide cabinets may be required where a large amount of cabling involved makes
it necessary to install cable trunking at the sides of the cabinet.
900 mm wide cabinet may be required for high density fibre enclosures.
4.3.2.5
Cabinet depth
The standard cabinet depth is 600 mm.
300 to 400 mm depth may be used for wall mount or back to back installations, for
example DC Power Supplies, Transmission equipment, PABX equipment etc.
800 mm depth may be used for miscellaneous data or radio equipment that is generally
not available in shallower depth.
Deeper than 800 mm depth shall only be used where there are no available suppliers of
equivalent equipment that would fit within 800 mm cabinets.
4.3.2.6
Cabinet height
The standard nominal rack height shall be within 2.1 to 2.2 metres.
Where less than a full height rack is required to accommodate particular systems
equipment, a full height rack shall still be provided to allow for future expansion/additions
or accommodation of equipment of other systems.
4.3.2.7
Cabinet design considerations
The design for the equipment cabinet shall consider:
The particular site requirements and location.
Telecommunications room equipment layout and clearance requirement as stated in
RailCorp standard ESM107.
The requirements for the communications equipment that will be housed in the rack.
Earthing arrangements in accordance with RailCorp standard ESM 109.
4.3.2.8
Environmental considerations
Equipment cabinets housing telecommunications infrastructure must be designed and
located in to protect against detrimental effects caused by the environment. For example
outdoor equipment cabinets close to the railway may be subject to hazards such as
© RailCorp
Issued February 2012
UNCONTROLLED WHEN PRINTED
Page 16 of 75
Version 1.1
RailCorp Engineering Specification — Telecommunications
Communications & Condition Monitoring Infrastructure
SPM 0212
vandalism, theft, dust contamination, flooding, earth potential rise, high temperatures and
train or vehicle strike.
4.4
DC Power supplies
4.4.1
Standards, Specifications and Drawings
Document
type
Document Title
Document
Number
Standard
Telecommunications Equipment Rooms
Standard
ESM 107
Specification
Battery Backed -48 VDC Power Supply
Systems Specification
SPM 151
4.4.2
Requirements
4.4.2.1
General
-48 VDC Power supply system shall be provided within RailCorp telecommunications
equipment rooms in accordance with RailCorp specification for battery backed -48 VDC
power supply systems specification SPM 151 and existing supply agreements.
4.4.2.2
Type approved equipment
Where an existing supply agreement and/or specification is not in place, the power
supplies offered in the design shall be reviewed/approved by the respective design
approval authority within RailCorp’s Communications Engineering or subject to RailCorp’s
type approval process.
4.4.2.3
Components
The new -48 VDC Power supply system shall be comprised of a combination of some or
all of the following elements:
•
•
•
•
•
•
•
4.4.2.4
Racking
Rectifiers
Batteries
DC/DC Converters
DC distribution module(s)
Inverters
Remote management by way of SNMP
Performance
A minimum battery backup time of 15 hours shall be provided (assuming battery
degradation will reduce backup to 12 hours after 5 years age).
Redundancy and availability of the power supply system shall comply with SPM 151
including N+1 configuration for Rectifier modules.
Redundancy based on site location and or criticality.
© RailCorp
Issued February 2012
UNCONTROLLED WHEN PRINTED
Page 17 of 75
Version 1.1
RailCorp Engineering Specification — Telecommunications
Communications & Condition Monitoring Infrastructure
4.4.2.5
SPM 0212
Documentation
Site specific design documentation shall be submitted for review and approval by the
appropriate design approval authority in RailCorp. The site specific documentation shall
include (but not limited to) the following:
•
•
•
•
•
•
•
•
•
•
Site details
Requirement Analysis
Proposed load calculations.
Equipment requirements
DC distribution arrangements.
Floor loading.
Rack dimensions and floor space allocation.
Rectifiers
Redundancy and availability
Reliability and availability performance including MTBF
Notes:
1. Rack depth may be
400mm deep or 600mm
deep dependent on site
layout of the Comms room.
2. The 400 deep rack will
have limitations on battery
sizes.
3. Wall mount DC load
distribution may be used at
some sites.
4. Example shown is for
illustration purposes only.
Disclaimer
Figure 2 - Example of Small DC Power Supply System Rack Layout
© RailCorp
Issued February 2012
UNCONTROLLED WHEN PRINTED
Page 18 of 75
Version 1.1
RailCorp Engineering Specification — Telecommunications
Communications & Condition Monitoring Infrastructure
5
Cables
5.1.1
Standards, Specifications and Drawings
SPM 0212
Document
type
Document Title
Document
Number
Standard
Telecommunication Outdoor Cabling
ESM 102
Standard
Signalling Bungalow Telecommunications
Cabling
ESM 105
Standard
Telecommunications for Traction Substations
and Section Huts
ESM 106
Standard
Telecommunications Equipment Rooms
ESM 107
Standard
Emergency Telephone Systems
ESM 108
Standard
Installation Requirements for Customer Cabling
AS/ACIF S009.
Standard
Australian / New Zealand Wiring Rules
AS 3000
Standard
Telecommunications Installations – Integrated
Telecommunications Cabling systems for
Commercial Premises
AS/NZ 3080ZA3.2
Specification
Reinforced Pre-Cast Concrete Cable Pits
SPM 0123
Specification
Construction of Cable Route and Associated
Civil Works
SPG 705
5.1.2
Requirements
5.1.2.1
General
All new outdoor telecommunications network cables, including re-configuration of the
existing outdoor cabling network will be in accordance with the Telecommunications
Outdoor Cabling standard ESM 102. Cabling in tunnels is considered to be outdoor
cabling.
Additional requirements to those specified in this standard also apply for special
situations such as cables in tunnels, aerial cable, cables associated with high voltage
installations.
5.1.2.2
Capacity
For new cables, minimum cable capacity shall be
Telecommunications Outdoor Cabling standard ESM 102.
5.1.2.3
provided
as
per
the
Diversity
Diverse paths may be required to ensure the availability of telecommunications
infrastructure. Types of diverse cable routes are detailed in the Telecommunications
Outdoor Cabling standard ESM 102. Cable diversity requirements are generally defined
in the specific telecommunications infrastructure or service that the cable supports.
© RailCorp
Issued February 2012
UNCONTROLLED WHEN PRINTED
Page 19 of 75
Version 1.1
RailCorp Engineering Specification — Telecommunications
Communications & Condition Monitoring Infrastructure
5.1.2.4
SPM 0212
Cabling in Telecommunications Equipment Rooms
All cabling inside of Telecommunications Equipment Rooms will be provided in
accordance with the Telecommunications Equipment Rooms standard ESM 107.
5.1.2.5
Cabling in and leading into Traction Substations and Section Huts
All cabling inside of Traction Substations and Section Huts will be provided in accordance
with the Telecommunications for Traction Substations and Section Huts standard ESM
106.
5.1.2.6
Cabling in and leading into Signal Bungalows
All cabling inside of Signal Bungalows and location cases will be provided in accordance
with the Signalling Bungalow Telecommunications Cabling standard ESM 105.
5.1.2.7
Cabling Systems Works
Installation shall be carried out by communications cabling installer that is accredited with
qualification relevant to the performance standards of various elements of specific cabling
systems.
All works shall be supervised at all times by a ACA registered cabler who is a holder of a
Open Licence with accreditation indicating completion specific endorsement courses
(applicable to works undertaken) in the areas of installation, testing, commissioning and
work safety practices.
5.1.2.8
Site Conditions
The cabling system provider shall carry out all required audits to fully inform themselves
of the condition of the site and other issues that could be impacting on the delivery of
works. This includes site conditions such as hazards that may be present at the site,
crown land, heritage listing, environmentally sensitive and local council regulations.
5.1.2.9
Enabling
Enabling works may be required to remove or relocate existing Signalling and
Communications services away from areas of high risk of construction risks. Installation
of Combined Services Route shall be installed and commissioned prior to any
decommissioning of existing cable routes in order to facilitate and operationally manage
the transition of services to the new route.
5.1.2.10
Health & Safety
The proposed layout of cable site installation system and routes shall ensure that
equipment, telehousing facilities and metallic components shall not be installed in areas
where earth potential rise (EPR) may exceed allowable power system fault conditions as
per Clause 5.1.4 of AS/ACIF S009.
5.1.2.11
Earthing
Earthing and related works shall be installed as per ESM 109 and the cabling provider
shall provide:
Where specified as part of the works, a provision of Communications Earth System
(CES).
© RailCorp
Issued February 2012
UNCONTROLLED WHEN PRINTED
Page 20 of 75
Version 1.1
RailCorp Engineering Specification — Telecommunications
Communications & Condition Monitoring Infrastructure
SPM 0212
Bonding of cabling system earth equipments, enclosures, pathways and earthing systems
including provision of earth bar (MDF, IDF etc.) where specified as part of the works.
In case of existing earthing systems, they shall be checked for compliance and upgraded
as necessary to meet the current standards.
5.1.2.12
Redundant Cabling
There are large numbers of redundant cabling in the rail network and opportunity should
be taken to remove this, if it is likely to impact on new cable works (where specified as
part of works). Documented disposal management systems as per RailCorp guidelines
shall take be complied for the disposal of redundant assets.
5.1.2.13
Combined Services Route
The combined services route is a multi disciplinary route asset used to distribute and
protect cables for new installation, expansion and maintenance. Combined Services
route shall be selected and designed to, comply with the minimum segregation from other
services as mandated by ESM 102, SPG 705, AS/ACIF S009 and AS3000 in accordance
with AS/NZ 3080ZA3.2. The construction of new cable route shall not impact or damage
any existing services, where it is necessary to construct cable route in areas that has
potential of having live services - communications, gas, power etc. The use of nondestructive method i.e. digging by slit-trenching or pot holing using hydro vacuum
excavation -“sucker trucks” shall be used as much as possible in existing rail corridors.
5.1.2.14
Ground Level Troughing (GLT)
GLT shall only be used for short distances typically for local routes and from the cable pit
to the cable entry through of the Signalling bungalow and Communications room.
6
Transmission Networks
6.1.1
Standards, Specifications and Drawings
Document
type
Document Title
Document
Number
Specification
Synchronous Digital Hierarchy Equipment for
Fibre Optical Cable
SPM 0098
Specification
Channel Multiplexer Equipment
STM 0097
6.1.2
Requirements
6.1.2.1
General
Transmission networks to support telecommunications are generally required to be
extended to or modified to support the expansion of existing or new rail corridors.
Transmission networks are required to cater for trunking of voice and data channels to
efficiently utilise backbone cabling between telecommunication equipment rooms.
All new Transmission network equipment shall be provided in accordance with existing
RailCorp supply agreements. Where existing supply agreements and or specifications are
not in place, the Transmission network equipment offered in the design shall be subject to
review and approval by the respective design authority in RailCorp’s Communications
© RailCorp
Issued February 2012
UNCONTROLLED WHEN PRINTED
Page 21 of 75
Version 1.1
RailCorp Engineering Specification — Telecommunications
Communications & Condition Monitoring Infrastructure
SPM 0212
Engineering. Alternatively, the new equipment shall be subject to RailCorp’s type
approval process.
6.1.2.2
Diversity
Backbone transmission networks shall have diverse paths to ensure high availability and
cable diversity (See 5.1.2.2) is used to provide diverse paths.
6.1.2.3
Synchronous Digital Hierarchy (SDH)
RailCorp has an extensive network of SDH nodes based on a protective ring topology
and a consistent equipment platform. All new SDH equipment is required to fit into the
wider RailCorp network and so needs to be designed and structured in consultation with
RailCorp Communications Engineering subject matter experts or design authority. The
SDH equipment shall comply with the Communications Engineering Specification No.
SPM 0098 and be provided in accordance with existing RailCorp supply agreements.
6.1.2.4
Time Division Multiplexing (Channel MUX)
RailCorp has an extensive network of TDM equipment based on a consistent equipment
platform. All new TDM equipment is required to fit into the wider RailCorp network and so
needs to be designed and structured in consultation with RailCorp’s Communications
Engineering. The TDM equipment shall comply with the Communications Engineering
Specification No. STM 0097 and be provided in accordance with existing RailCorp supply
agreements.
Some of the type of Channel Cards used by RailCorp is as follows:
•
•
•
•
•
•
4Wire + E&M,
2Wire,
Subscriber and Exchange cards for Telephones,
N x 64k Data cards,
RS232 Data cards and
Modem Line Driver cards.
MUX systems provided for Signal SCADA data links and possibly other critical
applications shall be designed with separate MUX systems providing “A” and “B” legs of
any data links that require diversity.
Field equipment cabled back to the “A” and “B” MUX systems generally require diverse
paths/routes and is arranged by having “A” and “B” links following opposite directions
towards “A” and “B” equipment in different rooms.
6.1.2.5
Wave Division Multiplexing (WDM / CWDM / DWDM)
Generally new WDM infrastructure is best incorporated into RailCorp’s existing WDM
systems and so, it shall be designed and provided by or in close consultation with
RailCorp’s Communications Engineering, in accordance with RailCorp’s design process
and RailCorp’s existing supply agreements.
6.1.2.6
Microwave
Where it is not feasible to provide cabling for transmission, Microwave links may be
considered. All new Microwave equipment shall be provided by or in close consultation
with RailCorp’s Communications Engineering, in accordance with RailCorp’s design
process and RailCorp’s existing supply agreements.
© RailCorp
Issued February 2012
UNCONTROLLED WHEN PRINTED
Page 22 of 75
Version 1.1
RailCorp Engineering Specification — Telecommunications
Communications & Condition Monitoring Infrastructure
6.1.2.7
SPM 0212
Power and Location
Generally Transmission Network infrastructure is to be located in telecommunication
equipment rooms in a Transmission infrastructure specific cabinet/s, specified in
section 4.1 and 4.3 respectively, and powered by the telecommunications equipment
room power supply specified in section 4.4.
7
Emergency and Operations PABX Telephones
Telephone Services used throughout the RailCorp Network support a variety of business
needs categorised as follows:
Tunnel Emergency Telephones (Fire phones)
Train Control Telephones
Signal Post Telephones (SPTs)
X-ring Telephones.
Operational Telephones
Administrative/Office Telephones
7.1.1
Standards, Specifications and Drawings
Document
type
Document Title
Document
Number
Standard
Emergency Telephone Systems
ESM 108
Standard
Tunnels Engineering Standard
ESC 340
Specification
Weatherproof Telephones
SPM 0082
Specification
Signal Post Telephone
SPM 0082
7.1.2
Requirements
7.1.2.1
Tunnel Emergency Telephones
RailCorp tunnels standard ESC 340 requires emergency telephones to be installed in
new RailCorp railway tunnels using electric passenger rolling stock.
Tunnel Emergency telephone systems and supported handsets shall comply with the
RailCorp Standard ESM 108.
Miscellaneous Emergency Telephones not associated with the rail tunnels shall be
catered for by the Train Control Telephone Network where they are track side or
associated with train running and by the Operational Telephone Network in other cases.
7.1.2.2
Train Control Telephones
Train Control telephones support the movement of rolling stock throughout the RailCorp
Network. These provide direct communication between Rail Management Centres/Signal
Boxes and the wider rail network.
© RailCorp
Issued February 2012
UNCONTROLLED WHEN PRINTED
Page 23 of 75
Version 1.1
RailCorp Engineering Specification — Telecommunications
Communications & Condition Monitoring Infrastructure
SPM 0212
At Major Control Centres Touch Screen based Voice Communications Systems
integrated with the C&CS Train Control Telephone Network shall be used. Other Control
Centres and Signal Boxes shall use integrated feature rich digital telephones.
In the wider network a combination of weather proof analogue telephones, standard
analogue telephones and digital feature telephones shall provide voice communications.
Telephones on the Train Control Network shall be battery backed for protection against
the primary source of power being unavailable.
Telephone calls on this network shall be recorded on External Voice Recorders interfaced
with the telephone network.
Refer to 7.1.2.8 for a list of locations where Train Control Telephones shall be provided.
7.1.2.3
Signal Post Telephones (SPTs)
Signal Post Telephones (SPTs) and other trackside telephones associated with signalling
shall be provided at locations as shown on the Signalling Plan.
SPT equipment shall be in accordance with SPM 0082.
SPTs shall be connected to the Train Control telephone network.
7.1.2.4
X-ring Telephones
X-ring telephones shall be provided so that a Signaller can call multiple stations with a
single call to convey information on “out of the ordinary” train running information such as
train diversions or cancelled trains.
These telephones shall be grouped in logical arrangements that generally follow stopping
patterns at stations.
X-ring telephones shall be connected to the Train Control Telephone Network as a
standard office type handset that could be sourced from a C&CS store.
The arrangement for providing the X-ring functionality is normally incorporated into the
VCS provided for the Signaller.
7.1.2.5
Operational Telephones
Operational telephones provide the communications to locations that support the rail
network infrastructure.
Telephones on the Operational Network shall be battery backed for protection against the
primary source of power being unavailable.
A combination analogue, digital and VoIP telephone handset types are supported on the
RailCorp C&CS Operational Network. The phones shall be from the current schedule
selected for general issue from the C&CS store.
Analogue and digital telephone utilise the cable network, where as the VoIP telephones
shall be deployed over the C&CS Data Network.
Refer to 7.1.2.8 for a list of locations where Operational Telephones shall be provided.
© RailCorp
Issued February 2012
UNCONTROLLED WHEN PRINTED
Page 24 of 75
Version 1.1
RailCorp Engineering Specification — Telecommunications
Communications & Condition Monitoring Infrastructure
7.1.2.6
SPM 0212
Administrative/Office Telephones
Administrative/Office Telephones are used in office type environments where
communications is required to support Rail business other than those mentioned above.
The supported telephone types on this system include standard analogue and VoIP
feature phones.
The phones connect to RailCorp ICT Administrative Telephone Network and are provided
over the same ICT data network that supports the desktop personal computers.
Telephones on the Administrative/Office Telephone Network are not necessarily (or
generally) battery backed.
Refer to 7.1.2.8 for a list of location where Administrative/Office Telephones are used
7.1.2.7
PABX design requirements
PABXs shall be incorporated into the wider RailCorp Emergency, Train Control and
Operational Telephone networks
PABXs shall be dedicated to the purpose of the system.
PABXs shall be installed in a Telecommunications Equipment Room 1 and powered from
the room’s 48VDC power supply, which shall have a minimum nominal battery backup
time of 12 hours.
PABX network design shall be referred to RailCorp’s Communications Engineering
designers at concept design stage for direction and/or advice on networking aspects
including:
a)
where the PABXs are to fit into the wider network
b)
suitability of the model of PABX proposed
c)
availability and suitability of use of existing rooms
PABX installation and configuration design shall be referred to RailCorp’s
Communications Engineering designers at detail design stage for direction and/or advice
on site aspects including:
1
a)
rack location within the room and any cable tray work required
b)
MDF allocation for cable termination or any MDF extension required
c)
DC Circuit Breaker allocation or any DC Power Supply extension required
d)
number allocation
e)
routing plans
f)
trunk signalling protocols
g)
synchronisation plans
As described in ESM 107
© RailCorp
Issued February 2012
UNCONTROLLED WHEN PRINTED
Page 25 of 75
Version 1.1
RailCorp Engineering Specification — Telecommunications
Communications & Condition Monitoring Infrastructure
7.1.2.8
SPM 0212
Telephone locations
The list below should be used as a guide to determine the type of telephone required at a
location and the provider network. Generally more specific locations and quantities for
any station shall be determined by the station working group:
Building
Location
Application
Railway
Tunnel
Tunnel
Emergency
Railway
Station
Station Masters
Office
Control Telephone, Xring
Supervisors Office
Operational Telephone
Operational Telephone,
facsimile
Booking Office
Meeting, Meal,
Train Crew rooms
Communications
Rooms
Lift Phones
Gate Access
Control
Visitor Access Entry
Phones
Security Guard
Other locations
within building
Type
2 Wire Analogue
Weather Proof Smart
Telephone
Railway
Corridor
Rail
Managem
ent Centre
Operational Telephone
VoIP feature phone
C&CS Operational
Network
2 Wire Analogue
Weather Proof Smart
Telephone
Standard 2wire
analogue phones
Standard 2wire
analogue phones
VoIP feature phone
C&CS Train Control
Network
C&CS Operational
Network
C&CS Train Control
Network
Operational Network
VCS & backup Digital
Feature phone
VCS & backup Digital
Feature phone
VCS & backup Digital
Feature phone
Analogue, Digital or
VoIP feature phones
C&CS Train Control
Network
C&CS Train Control
Network
C&CS Train Control
Network
C&CS Operational
Network
Rail Network Operation
Rail Network Operation
Rail Network Operation
Rail Network Operation
Track Side Phones
Signal locations
cases
Signal Post/EOL/ESML
Maintenance phones
M1&M2
Traffic Huts
Wayside Huts
Train Control
Rail Network Operation
Train Controllers
Panels
Train Control
Signallers Panels
Line Information
Controllers
Other locations
within building
© RailCorp
Issued February 2012
C&CS Train Control
Network
C&CS Operational
Network
C&CS Operational
Network
C&CS Operational
Network
C&CS Operational
Network
C&CS Operational
Network
C&CS Operational
Network
C&CS Operational
Network
C&CS Operational
Network
C&CS Operational
Network
External Public
Network Provider
External Public
Network Provider
Rail Network Operation
General Purpose
Maintenance/Test
Telephones
Vending Machines
High Voltage
Locations
Emergency Telephone
Network
VoIP & Analogue
VoIP & Digital feature
phones
VoIP & Digital feature
phones
Standard 2wire
analogue phones
VoIP & Digital feature
phones
Standard 2wire
analogue phones
Standard 2wire
analogue phones
Standard 2wire
analogue phones
Standard 2wire
analogue phones
VoIP feature phone /
Analogue
Public Phones
Substation
s&
Section
Huts
Telephone Network
Train Control
Train Control
Rail Business
UNCONTROLLED WHEN PRINTED
Page 26 of 75
Version 1.1
RailCorp Engineering Specification — Telecommunications
Communications & Condition Monitoring Infrastructure
Building
Signal
Boxes
SPM 0212
Location
Application
Type
Signallers Desks
Train Control
Digital Feature phones
Operations phone
Digital Feature phones
Digital Feature
phones, External
Conference Bridge
Unit
Line Information
Controllers
Train Control
Operations phone
Telephone Network
C&CS Train Control
Network
C&CS Operational
Network
C&CS Train Control
Network
C&CS Operational
Network
C&CS Operational
Network
Other locations
within signal box
Rail Network Operation
Digital Feature phones
Analogue, Digital or
VoIP feature phones
Offices
Rail Network Operation
Analogue, Digital or
VoIP feature phones
Car Sheds
Rail Network Operation
DECT
C&CS Operational
Network
C&CS Operational
Network
Emergenc
y
Operation
s Centres
Control Room
Rail Network Operation
Analogue, Digital or
VoIP feature phones
C&CS Operational
Network
Security
Centre
Control Room
Security
VCS & backup Digital
Feature phone
C&CS Operational
Network
Train
Crewing
Centre
Control Room
Train Crew
VCS & backup Digital
Feature phone
C&CS Operational
Network
Desks
Non Critical Rail
Business
VoIP feature phones
Meeting Rooms
Non Critical Rail
Business
VoIP feature phones
Offices
Non Critical Rail
Business
VoIP feature phones
facsimile
VoIP Analogue
Telephone Adaptor
Maintenan
ce Depots
Office
Building
ICT
Administrative/Office
Network
ICT
Administrative/Office
Network
ICT
Administrative/Office
Network
ICT
Administrative/Office
Network
Table 1 - Telephone Locations
8
Data Networks
The C&CS Data Network shall provide network connectivity for data, VoIP and video
applications installed along new rail corridors. The data network shall provide backbone
connectivity for a number of operational and non operational train services. The critical
operational services shall include DTRS,
CCTV etc. The non operational business
services shall include ticketing, EFTPOS, station LAN etc.
This section describes the access requirements for both the ATM Network and
Operations Critical Data Network (OCDN).
The ATM Network is currently the backbone of the C&CS Data Network. The OCDN is
designed to replace the ATM Network and it is anticipated that this network will be ready
for general use by mid 2012. Sites and new corridors requiring access to the Data
Network before July 2012 should be designed to connect to the ATM Network with
© RailCorp
Issued February 2012
UNCONTROLLED WHEN PRINTED
Page 27 of 75
Version 1.1
RailCorp Engineering Specification — Telecommunications
Communications & Condition Monitoring Infrastructure
SPM 0212
provision for migration to the OCDN. Sites and new corridors requiring access after July
2012 should be designed for connection to the OCDN.
8.1
General Requirements
8.1.1
Standards, Specifications and Drawings
Document
type
Document Title
Document
Number
Standard
Telecommunications for Traction Substations
and Section Huts
ESM 106
Supply
agreement
OCDN Customer Access and Provider Access
switch panel supply agreement*
WS15292
Drawing
RailCorp ATM Network Core, Edge and Access
Switches
MET - SC 0004
Drawing
OCDN Aggregate Sections Block Diagram
MET - SC 0275
Drawing
OCDN Sect.04 Central to Warwick Farm
Aggregate Section Block Diagram
MET - SC 0265
Specification
Element Naming Convention
TMM P181
Specification
Naming Convention for Switch Ports
TMM P197
*
8.1.2
Current OCDN switch panel supply agreement list to be sourced from RailCorp’s Communication
Engineering when required.
Type approved equipment
All new Data network equipment shall be provided in accordance with existing RailCorp
supply agreements. Where an existing supply agreement and or specification are not in
place the data network equipment called for in the design shall be subject to RailCorp’s
type approval process.
8.1.3
C&CS ManageNet
The C&CS ManageNet is a network that extends to all Simple Network Management
Protocol (SNMP) compatible equipment required to be monitored by C&CS. All
telecommunications equipment supplied including Ethernet switches, Transmission
equipment, PABXs and Radio base stations etc shall be SNMP compatible and
connected to the C&CS ManageNet.
IP Addressing for Data Network elements on ManageNet shall be allocated by C&CS.
8.1.4
Network Management and Monitoring
All data network infrastructure shall be monitored and managed in band or out-of-band by
Simple Network Management Protocol (SNMP) and be integrated with ManageNet and
the Rail Technology Operations Centre (RTOC) monitoring systems. Where an SNMP
interface is not available this shall be provided by Remote Terminal Unit (RTU).
© RailCorp
Issued February 2012
UNCONTROLLED WHEN PRINTED
Page 28 of 75
Version 1.1
RailCorp Engineering Specification — Telecommunications
Communications & Condition Monitoring Infrastructure
8.1.5
SPM 0212
Naming Conventions
The naming of data network elements shall conform to the convention specified in
document TMM P181. The names applied to individual Ethernet switch and router ports
shall conform to the convention specified in TMM P197.
Element names and port names use C&CS site codes. For each new site a request for a
site code must be made to the Telecommunications Network Configuration (TNC) group
within C&CS.
8.1.6
IP Addressing
The allocation of IP addresses for VPNs on both the ATM Network and OCDN is the
responsibility of C&CS.
8.1.7
Power and location
Generally data networks infrastructure is to be located in equipment rooms in data
network infrastructure specific cabinet/s, specified in section 4.1 and 4.3 respectively. In
telecommunications equipment rooms, the data network infrastructure shall be powered
by the telecommunications equipment room power supply specified in section 4.4.
8.1.8
Commissioning Tests
All new data services shall be tested for throughput and latency as per RFC 2544.
8.1.9
Fibre Connectivity
All sites where data services are required shall have access to fibre. Where this is not
possible, access to copper shall be provided and modems (serial data or Ethernet
SHDSL) shall be installed.
8.2
ATM Network Requirements
The ATM network is the current backbone of the C&CS data network (refer to drawing SC
0004) and consists of a fully redundant core with diverse links to Edge nodes. Access
nodes connect to the Edge nodes by single STM-1 links.
8.2.1
ATM Network VPNs
Two types of VPNs are available for connection across the ATM:
• Layer 2 Point to Point or Multi-point
These VPNs may be as simple as a transparent layer 2 (Ethernet) point to point
connections or a complex mesh of point to multi-point PVC’s.
• Centrally Routed
These VPNs consist of PVC’s connected to a virtual router instance on a C&CS
operated core router. For redundancy the virtual router instance may be duplicated
on the two core routers.
Data services for new sites and corridors will be provided as an extension of one of the
existing VPN’s on the ATM Network (e.g. SPI, CCTV, Station LAN, etc). Where a
completely new type of service is required then a new VPN will need to be created.
© RailCorp
Issued February 2012
UNCONTROLLED WHEN PRINTED
Page 29 of 75
Version 1.1
RailCorp Engineering Specification — Telecommunications
Communications & Condition Monitoring Infrastructure
8.2.2
SPM 0212
Access to an ATM Network VPN
Ethernet and IP data services shall access their VPN on the ATM Network either by
connection directly to either:
• an ATM Edge or Access node LAN emulation interface or
• an Ethernet Access Switch (connected as described in section 8.2.3) or
• SHDSL modem (connected as described in section 8.2.3)
In all cases the access interface shall be Ethernet (IEEE 802.3) RJ45. Note that
exception may be made for services that for site specific reasons require a fibre
connection to host equipment (e.g. High Voltage Site RTU equipment).
8.2.3
ATM Node Access Network
The ATM Network consists of approximately 100 nodes distributed across the CityRail
network area. Additional ATM nodes shall not be added to the Network due to the nodes
nearing end of life and the soon to commissioned OCDN. Extension of the ATM Network
to new sites and corridors shall therefore be provided by Ethernet Switches.
Ethernet switches shall be installed at sites where Ethernet data services are required.
These switches shall be connected by Gigabit Ethernet back to an Ethernet switch colocated with the nearest ATM node.
New access switches shall be selected from the OCDN panel supply agreement for
Customer Access and Provider Access switches.
Where fibre is not available an Ethernet over SHDSL modem link shall be provided.
8.3
OCDN Requirements
The Operations Critical Data Network (OCDN) shall replace the ATM Network as the
backbone of the C&CS Data Network. The OCDN shall be extended along new rail
corridors and to new sites in a manner consistent with the overall OCDN hierarchical
design.
8.3.1
OCDN Hierarchy
The Operations Critical Data Network (OCDN) hierarchy consists of four layers; the Core,
Aggregation (Distribution), Provider Access (Distribution-edge) and Customer Access
(OCDN Points-of-Presence).
© RailCorp
Issued February 2012
UNCONTROLLED WHEN PRINTED
Page 30 of 75
Version 1.1
RailCorp Engineering Specification — Telecommunications
Communications & Condition Monitoring Infrastructure
SPM 0212
Figure 3 - Overview of the Operations Critical Data Network (OCDN)
The core of the OCDN uses IP/MPLS standards to provide Layer 3 Multiprotocol BGP
Virtual Private Networks (VPN) with virtual routers as redundant gateways to two logically
separate core partitions. The distribution of the OCDN uses carrier Ethernet to make lastmile connections to the OCDN Customer Access Switch. Each customer network is
provided with one or more VPNs, each with an associated Virtual LAN (VLAN), allowing
hosts connected to the Rail PoPs to communicate on the VLAN and over the Layer 3
VPN (using the Virtual Routers).
The OCDN is Core and Aggregate sections are shown in drawing SC 0275. Provider
Access details are shown in separate drawings, one per section. The drawing SC 0265 is
an example of a section drawing.
8.3.2
OCDN VPNs – Ethernet/IP Networks
The OCDN provides logically separate VPNs for each customer network. Data services
for new sites and corridors will be provided as an extension of one of the existing VPN’s
on the OCDN Network (e.g. SPI, CCTV, Station LAN, etc). Where a completely new type
of service is required then a new VPN will need to be created.
8.3.3
Provider Access
Provider Access equipment is required in locations requiring access to the OCDN and
shall be installed in equipment rooms with a diverse path to the rest of the OCDN
distribution layer.
Provision of a Provider Access switch is the responsibility of RailCorp’s Communications
Engineering. All new Provider Access equipment shall be provided in accordance with the
OCDN switch specification and the existing OCDN Provider Access switch panel supply
agreement.
For each site with a PA switch a single switch port shall be allocated for each customer
VPN required at that site. If a customer application has multiple devices at a site then a
Customer Access switch will be required (section 8.3.4).
8.3.4
Customer Access
For a site where a customer requires more than one port to access their OCDN VPN (e.g.
two or more host PCs) then a Customer Access switch shall be installed. Use of the CA
switch shall be dedicated solely for that customer.
© RailCorp
Issued February 2012
UNCONTROLLED WHEN PRINTED
Page 31 of 75
Version 1.1
RailCorp Engineering Specification — Telecommunications
Communications & Condition Monitoring Infrastructure
SPM 0212
Provision of a Customer Access switch is the responsibility of the customer. All new
Customer Access switches shall be provided in accordance with the OCDN switch
specification or the existing OCDN
8.3.5
Interfaces
CA and PA switch interfaces shall comply with the relevant IEEE standards. Customer
connection to PA switches shall be made using commercially available Ethernet
transceivers at speeds of either 100Mbps or 1000Mbps over Category 5e UTP or SMOF
media.
A typical arrangement for access to the OCDN is shown in the below figure.
Figure 4 - Typical OCDN Access Arrangement (CityRail Station)
8.3.6
Availability
Where a data service requires a higher than 99.9% network availability, a diverse path to
the Provider Access layer is required and the Customer Access equipment must be
selected from a specific subset of the OCDN switch specification and the existing OCDN
Customer Access switch panel supply agreement.
Generally OCDN diverse paths are to be provided by cable diversity (See 5.1.2.3).
8.3.7
Aggregation (Distribution)
Generally modifications or expansions of the OCDN distribution layer if required shall be
designed and provided by RailCorp’s Communication Engineering, in accordance with
RailCorp’s Communications Engineering design process and RailCorp’s existing supply
agreements.
8.3.8
Core
Generally changes to the Core segment shall not be required however in the case that
the OCDN Core is required to be modified or expanded it shall be designed and provided
by RailCorp’s Communications Engineering, in accordance with RailCorp’s
Communications Engineering design process and RailCorp’s existing supply agreements.
© RailCorp
Issued February 2012
UNCONTROLLED WHEN PRINTED
Page 32 of 75
Version 1.1
RailCorp Engineering Specification — Telecommunications
Communications & Condition Monitoring Infrastructure
8.4
Site Specific Requirements
8.4.1
High Voltage (HV) Sites
SPM 0212
HV sites include substations and section huts. A number of data services are required at
these sites (Electrical Traction SCADA, VoIP and access to the RailCorp ICT Network)
and shall be provided by installation of a C&CS Customer Access switch. These switches
shall be of an industrial type designed to operate in harsh environments. At each site two
separate and independently connected switches shall be installed for A and B network
diversity.
For further information on the data service requirements of HV sites refer to the document
Telecommunications for Traction Substations and Section Huts ESM 106
8.4.2
Stations
At each station a C&CS Provider Access (if the OCDN is available) or ATM Network
Ethernet Access switch shall be installed in a 19” cabinet within the station services room.
Space shall be allocated within the station services room for an OCDN rack and other
racks as required for SPI, Ticketing and CCTV.
Separate Customer Access Ethernet switches shall be installed for VoIP, SPI, CCTV,
Station LAN and Ticketing. Responsibility for the installation of these switches is with the
application owner. Connection between these switches and the OCDN switch shall be
Gigabit Ethernet over single mode optical fibre.
8.5
Serial Data
Data devices capable of communicating directly via Ethernet/IP are preferred. Due to
technological limitations or requirements some applications require the provision of serial
data links. This includes applications such as Signal SCADA, ATRICS links and the
legacy ticketing (AFC) network.
Serial data links shall be provided either using two/four wire serial modems, serial to
optical converters or over Ethernet using serial to Ethernet converters.
8.5.1
Interfaces
Serial data links shall use standardised interfaces and protocols, i.e. RS232, RS485,
RS422 and X21.
8.5.2
Real Time Critical Serial data
Real Time critical Serial data links shall have a round trip time less than 100ms. They
shall have full redundant paths either via transmission system or copper system. A risk
analysis for these services shall be provided to RailCorp’s Communications Engineering.
8.5.3
Non Real Time Critical Serial data
Non real time critical Serial data links shall have a round trip time less than 150ms.
8.5.4
Signalling Applications
Serial data services for Signalling applications (e.g. Signal SCADA) shall not be provided
over Ethernet (using Serial to Ethernet converters). They shall be provided with modems
and use the SDH/PDH network as a backbone.
© RailCorp
Issued February 2012
UNCONTROLLED WHEN PRINTED
Page 33 of 75
Version 1.1
RailCorp Engineering Specification — Telecommunications
Communications & Condition Monitoring Infrastructure
8.5.5
SPM 0212
Serial Device Management
All serial devices shall provide facilities for remote monitoring or capable to integrate to
C&CS network management system (i.e.: ManageNet).
8.5.6
Serial Data Modems
Serial Data modems shall use standardised protocols i.e. V110/V.11/V.28/V.24/X.21.
Modems shall be capable of interfacing with a carrier system (i.e.:-VF channel, G703 via
TDM system or copper system).
8.5.7
Serial to Fibre Optical Converters
Serial to Fibre Optic Converters shall be capable of
• Interfacing to Single mode fibre with remote monitoring.
• Use single fibre with two different wavelengths
• Integrate with C&CS management system (i.e.: ManageNet).
8.5.8
Serial to Ethernet Converters
Serial to Ethernet converters shall be capable of
• interfacing to the ATM Network or OCDN as RJ45 10/100/1000 Base-T,
• sending serial link data via an IP Gateway (i.e. through an IP network),
• sending and receiving tagged VLANs on the Ethernet interface with a separate
VLAN for device management.
9
Network Control Communications Systems (NCCS)
9.1
Voice Communication System
The Base2 Voice Communication Systems (VCS) system is a single integrated front end
interface used by Train Controllers and Signallers at RMC, Sydenham and Strathfield to
communicate over several communication mediums such as Telephony, Metronet and
Countrynet.
9.1.1
Standards, Specifications and Drawings
Document
type
Document Title
Document
Number
Standard
VCS Engineering Specification
TMM R953
9.1.2
Requirements
9.1.2.1
VCS Control location
VCS communications platforms are provided at major Signal box locations such as RMC,
Sydenham and Strathfield. For new railway corridors, if radio and telecommunications
traffic are to be controlled by an existing signaller or train controller at any of these
locations, then such traffic must be routed to an existing VCS console at a designated
Signal Box or Train Control location. In this case, the NCCS Design group must be
involved in the redesign and configuration changes required to implement this addition of
responsibilities to an existing signallers operations.
© RailCorp
Issued February 2012
UNCONTROLLED WHEN PRINTED
Page 34 of 75
Version 1.1
RailCorp Engineering Specification — Telecommunications
Communications & Condition Monitoring Infrastructure
SPM 0212
If a new console is required, then new hardware will need to be purchased and NCCS
Design will need to be engaged to provide a new VCS console for the installation.
9.1.2.2
VCS Interfaces
Over the years as Network Control systems have evolved and the function of the network
controller has expanded to include additional duties and responsibilities, there have been
requests to expand the functionality of the VCS network to interface with other systems.
These developments have been handled by the vendor base2 and they have provided a
number of solutions to meet RailCorp’s needs.
This has been done by utilizing the USCs (Universal Signalling Cards) to interface
different types of field communication equipment to a PABX. USCs take various 4wire or
2wire connections from the field and convert them to a 4wire E&M connection to the
PABX. This enables the PABX to see these different types of field phones and radios as
a normal telephone connection.
Additional interfaces which have been added over the years are for:
• NTCS Radio
• GRN Radio
• ENS – HBD Monitoring Systems
For more details on these interfaces, please see the VCS Technical Specification
document TMMR953.
9.1.2.3
VCS communication hardware requirements
For any new installation, the following equipment shall generally be required. All
components for the VCS system are procured from Base2 who are the sole vendors,
distributors and developers for this system.
The communication room equipment required for a typical VCS installation is as follows:
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
Rack-mounted KVM units
SMT computer
KVM Switches
DBA computer
ACBU
Cabling from Equipment rooms to Control Room
ECBU (2MB Digital)
Equipment monitoring for Rack
CCUR/422 cards for Primary ICU equipment
CCUR/422 cards for Backup ICU equipment
ICU Racks
USC Racks
Go-NoGo Testing Rack
USC Magneto & CB Interfaces
USC WB Interfaces
USC Train Radio (Metronet/DTRS) Interfaces
42U Rack including:
–
–
–
–
–
–
© RailCorp
Issued February 2012
PC Shelves
Rack mount power boards
Electrical Distribution Panel
Krone Termination Panels
RJ45 Patch Panels
Fan
UNCONTROLLED WHEN PRINTED
Page 35 of 75
Version 1.1
RailCorp Engineering Specification — Telecommunications
Communications & Condition Monitoring Infrastructure
SPM 0212
Figure 5 - VCS Equipment room Hardware/Connections per VCS console
For individual hardware and software requirements for the various VCS interfaces such
as Train Radio (Metronet/DTRS), NTCS, GRN and ENS please refer to the VCS
Technical Specification Document.
9.1.2.4
VCS Operator requirements
The following components will be required for the provisioning of VCS system at the
operator side (signallers desk)
• 19” LCD Touch Screen
• Post Mounting Arm
–
–
–
–
–
–
–
–
–
–
–
© RailCorp
Issued February 2012
KVM Extender
Digi Interface
Footswitch
Cordless Headset
Handset
Operator Control Panel
Audio Console
2 x Bose Loud speakers
Bose Monitor speakers
2 x Microphones
Windows 2000 Professional
UNCONTROLLED WHEN PRINTED
Page 36 of 75
Version 1.1
RailCorp Engineering Specification — Telecommunications
Communications & Condition Monitoring Infrastructure
SPM 0212
Figure 6 - VCS Console operator hardware
9.2
Voice Recorder Network
The Voice Recorder network consists of 23 voice recorders installed at strategic train
operational centres across the Rail network such as signal boxes and control centres with
the primary objective aim of recording safety critical operational voice traffic between
qualified workers in the RailCorp network.
A safety critical communication is any communication which if not delivered or incorrectly
delivered, there is a reasonable likelihood of result being:
• Death or serious injury
• Health or safety effects
• Significant damage to property or infrastructure
The currently recorded voice traffic is mainly from the control and administration phones
of signallers and train controllers and also from the various radio systems such as WB
and Train Radio (Metronet/DTRS) which are used for communication between network
controllers and train drivers. Other locations/services which are recorded also include
Traffic Huts, Emergency Phones, Track Side telephones and other services which are
deemed critical to train operations.
© RailCorp
Issued February 2012
UNCONTROLLED WHEN PRINTED
Page 37 of 75
Version 1.1
RailCorp Engineering Specification — Telecommunications
Communications & Condition Monitoring Infrastructure
SPM 0212
The aim of recording is to allow for routine monitoring and auditing of the quality of
communication between workers which may be reviewed in case of a safety incident.
At the time of writing of this document, the existing Voice Recorder network is being
replaced due to obsolescence. The new Voice Recorder network will provide additional
functionalities such as recording of VoIP calls and bulk-download of call recordings.
9.2.1
9.2.2
Standards, Specifications and Drawings
Document
type
Document Title
Document
Number
Specification
Network Communications
NGE 204
Specification
Communications Equipment
NGE 230
Specification
Spoken and Written communication
NPR 721
Specification
Safety Critical Communications.
SMS-12-OS-0919
Specification
Managing Audio Safety Recordings
SMS-12-OI-1144
Specification
Audio Safety Recordings
SMS-12-OI-1145
Drawing
New Voice Recorder Network Diagram
MET SC 0304
Requirements
It is the responsibility of RailCorp or alternatively the organization developing the new rail
corridors to identify activities involving communications which are safety critical and
monitoring communications to ensure that they meet the requirements identified above.
If there is an existing voice recorder within range of the newly built infrastructure, it may
be possible to record the services there. If not, then the organization will be required to
install new voice recording infrastructure at the site, this will require the involvement of
the ATRO (Audio Technical Research Officer) and also NCCS who are responsible for
the design of the Voice Recorder Network.
Currently the new voice recorder network consists of satellite/core architecture with 23
satellite sites being connected to two core servers providing redundancy to the system.
Any new installation will require the addition of a new satellite Voice Recorder to the
network and the party responsible for developing new rail corridors will need to involve
RailCorp’s Communications Engineering – NCCS in the process. Please see New Voice
Recorder Network Diagram – MET SC 0304 for details of existing network architecture.
9.2.2.1
General
All new Voice Recorder Network equipment shall be provided in line with RailCorp’s typeapproved equipment as specified in Section 9.2.2.2 below.
After using the guidelines in the referenced standards to determine the safety critical
nature of communications and nominating them for recording, all recording and retrieval
duties for these newly added services will be entrusted to the ATRO (Audio Technical
Research Officer) who is the responsible entity within RailCorp for managing, responding
to requests for and retrieving voice recorded traffic from the RailCorp Voice Recorder
Network. RailCorp’s Communications Engineering will have design authority for the Voice
Recorder Network with the ATRO responsible for managing the operations of those Voice
Recorders which have been identified as recording safety critical voice traffic.
© RailCorp
Issued February 2012
UNCONTROLLED WHEN PRINTED
Page 38 of 75
Version 1.1
RailCorp Engineering Specification — Telecommunications
Communications & Condition Monitoring Infrastructure
9.2.2.2
SPM 0212
Type Approved Equipment
The type approved equipment for a Voice Recorder unit is the Addcom Recorderlink Pro
which includes:
• Voice Recorder Satellite
• Digital Channel Cards (as required)
• Analogue Channel Cards (as required)
NCCS Design will be responsible for incorporating the new site into the existing Network.
This will involve several processes including but not limited to Network Design,
modification of maintenance contract to incorporate new site, site specific design and
configuration changes to records to reflect additional services.
9.2.2.3
Integration of new Voice Recorder Unit
Any new Voice Recorder unit installed as part of the new rail line will be required to be
integrated into the existing RailCorp Voice Recorder Network.
9.2.2.4
Increase of Channel Capacity
If an existing RailCorp Voice Recorder unit is within the limits of distance to allow
additional voice services to be recorded, the Contractor is required to:
Integrate the recording of the new voice services into the existing RailCorp Voice
Recorder.
Ensure a minimum 10% spare channel capacity is maintained after the introduction of the
additional voice services into the existing Voice Recorder.
Procure additional channel cards to meet the minimum 10% spare capacity requirement
after the introduction of the new voice services.
10
Wireless infrastructure
There are three train radio systems currently in use in NSW. They are the MetroNet,
CountryNet, and the Local radio system. Each of these systems have been designed to
provide a specific functionality that has been optimised to address the different
communication needs across the metropolitan area and the regional parts of the NSW
radio network. RailCorp uses all the three radio systems to support train operations.
MetroNet, owned and managed by RailCorp is a system tailored for the high traffic and
demand experienced in the metropolitan areas of NSW. In general, the system covers the
electrified area, which extends from Newcastle to Kiama, Macarthur and Lithgow. It
provides discrete voice communications between Drivers and Signallers or Drivers and
Train Controllers, with provision for drivers to speak to Mechanical Control or Operations
Control.
At the time of writing, the MetroNet radio system is in the process of being replaced by
the Digital Train Radio System (DTRS). Commissioning of the DTRS is expected to
complete around mid 2016 in which by then, Metronet will be decommissioned. Given the
average timeframe for design and construction of new rail corridors, no MetroNet
requirement is included in this document. DTRS will be the primary requirement for train
radio system replacing MetroNet. DTRS requirements are outlined in Section 10.6.
The CountryNet radio system, now managed by ARTC, is optimised for all other areas of
the state. CountryNet uses the Optus MobilSat satellite to provide coverage over all the
regional areas of the state. The CountryNet radio system is being replaced by ARTC’s
National Train Communication System (NTCS).
© RailCorp
Issued February 2012
UNCONTROLLED WHEN PRINTED
Page 39 of 75
Version 1.1
RailCorp Engineering Specification — Telecommunications
Communications & Condition Monitoring Infrastructure
SPM 0212
Local or Without Brakevan (WB) radio is a legacy radio system that has been retained for
specific purposes in a variety of configurations. Requirements for WB radio system are
outlined in Section 10.7.
In addition to the above three train radio systems, RailCorp also utilise a number of other
radio systems for its operation. These are:
•
•
•
•
Station Radio System – Section 10.8.Error! Reference source not found.
Yard/Shunting Radio System – Section 10.9.
Worksite Radio System
GRN – Section 10.10.
As specified in TMM P095 – Worksite Communication Procedures document, the primary
communication system for trackside workers is the GRN while the Worksite Radio system
provides secondary communication channels for trackside workers. Upon introduction of
DTRS, it is expected that DTRS will provide communication facility for trackside workers
therefore no specific requirements for Worksite Communication System is included for
new rail corridors.
Both GRN and Police Radio systems coverage are required within tunnels and
underground section of the rail corridor as specified in ESC 340 - Tunnels Engineering
Standard. As RailCorp Security and Transit officers are the primary GRN users within
RailCorp, requirement for GRN coverage outside these areas is to be consulted with both
the GRN system owners and RailCorp Security. Requirement for Police radio system
coverage is to be consulted with NSW Police.
10.1
General Requirements
10.1.1
Standards, Specifications and Drawings
Document
type
Document Title
Document
Number
Standard
Tunnels Engineering Standard
ESC 340
10.1.2
Requirements
10.1.2.1
Wireless Subsystem Integration
Each wireless subsystem shall be integrated into existing radio networks and operational
control as required.
10.1.2.2
Coverage
All Wireless systems shall be capable of establishing calls and effect reliable and clear
communications between users over any section of track and within the station areas as
defined within each wireless subsystem.
Coverage prediction and link budget calculations with indicative signal strength shall be
provided for at the design stage of the wireless system.
As per Section 9.9 of ESC 340 – Tunnels Engineering Standard, The following
communication systems shall be provided in the tunnel:
• Train Radio
© RailCorp
Issued February 2012
UNCONTROLLED WHEN PRINTED
Page 40 of 75
Version 1.1
RailCorp Engineering Specification — Telecommunications
Communications & Condition Monitoring Infrastructure
SPM 0212
• GRN
• Police Radio
• Mobile Phone network
10.1.2.3
Frequency Planning
Detailed frequency planning including identification, selection and application of
frequencies through ACMA shall be arranged in consultation with RailCorp, Police and
the GRN owner as applicable.
10.1.2.4
Intermodulation Study
Intermodulation studies on all frequencies sharing a common antenna shall be provided
at the design stage.
10.1.2.5
Compatibility
The DTRS, WB radio, Station Radio, Yard Radio, GRN and Police Radio systems shall
be compatible with existing operational system, equipment, and remote control functions.
10.1.2.6
Remote control functions
Remote control functions and configurations will be the responsibility of RailCorp, the
GRN owner and the NSW Police Service.
10.1.2.7
Signal strength
Signal strength measurements for voice and voice quality checks and on intended
coverage areas for each wireless system shall be performed as per the specification of
each wireless system. Results of signal strength and voice quality checks shall be
provided to RailCorp for approval. Data BER tests shall also be conducted and submitted
for RailCorp’s review.
10.1.2.8
Signal quality
Voice quality on radios shall be clear and free from noise and interference. Refer to the
relevant section on specific coverage and signal quality requirements for each
radio/wireless system
10.1.2.9
Documentation
Design, test and as-built documentation shall be submitted to RailCorp’s Communications
Engineering for comments and approval.
10.1.2.10
Acceptance testing
RailCorp, GRN, Police and relevant stakeholder’s representatives shall witness Site
Acceptance Test on the relevant wireless systems. Stakeholders are to approve scope of
witnessing activities.
10.1.2.11
Compliance with fire regulations
All items used in underground tunnel, stations and equipment rooms shall be low smoke,
low toxicity and zero halogen.
© RailCorp
Issued February 2012
UNCONTROLLED WHEN PRINTED
Page 41 of 75
Version 1.1
RailCorp Engineering Specification — Telecommunications
Communications & Condition Monitoring Infrastructure
10.1.2.12
SPM 0212
Compliance with substance regulations
Dangerous materials and substances shall not be used.
10.1.2.13
Compliance with EMI/EMC Standard
Radio/wireless system equipment shall be designed to the relevant EMI/EMC standards
and shall not interfere with itself and other equipment in the vicinity.
10.1.2.14
Availability
Unless specified for the particular radio/wireless system, in general radio/wireless system
availability shall exceed 99.95%.
Documentation is to be provided to support the systems availability including reliability
analysis such as Reliability Block Diagrams.
10.1.2.15
Equipment supply
Where RailCorp has type-approved equipment or component for particular radio /
wireless system, supply of new equipment / component shall be sourced from the
RailCorp type-approved list.
Where the proposed equipment or component is not one of the RailCorp type-approved
equipment, standard reliable commercial-off-the-shelf components meeting the
requirement specification for the particular wireless system shall be used where possible.
10.1.2.16
Spares
Spare equipment shall be provided to allow the equipment to be returned to service by on
site replacement of modules. Factors such as the length of time for module repair and
critically of modules shall be considered in determining the number of spares to be
provided.
10.1.2.17
Network Management and Monitoring
All Wireless infrastructure shall be monitored in band or out-of-band by Simple Network
Management Protocol (SNMP) and be integrated with Managenet and the Rail
Technology Operations Centre (RTOC) monitoring systems. Where a standard SNMP
interface is not available monitoring shall be provided by Remote Terminal Unit (RTU).
All wireless infrastructure equipment shall be capable to be managed remotely either inband or out-of-band. Where possible, remote management interfaces shall be IPcompatible.
10.1.2.18
Antennas
Wireless infrastructure Antenna Systems shall comply with Australian and RailCorp
standards and specifications (See Section 10.2).
10.1.2.19
RF EME Site Compliance
The party responsible for implementation is to prepare all necessary RF EME
assessment and compliance documentations for any new radio/wireless infrastructure
site built or if any alterations are made on an existing wireless infrastructure site
arrangement.
© RailCorp
Issued February 2012
UNCONTROLLED WHEN PRINTED
Page 42 of 75
Version 1.1
RailCorp Engineering Specification — Telecommunications
Communications & Condition Monitoring Infrastructure
10.1.2.20
SPM 0212
Power and location
Radio/wireless infrastructure is to be provided in telecommunication equipment rooms in
radio/Wireless infrastructure specific cabinet/s.
Wireless Infrastructure equipment rooms shall be as specified in Section 4.1.
Wireless Infrastructure equipment cabinets shall be as specified in Section 4.3.
Wireless infrastructure shall be powered by the telecommunications equipment room
power supply as specified in Section 4.4 and any wireless infrastructure specific
requirements detailed in following Sections.
10.2
Antenna Systems
10.2.1
Standards, Specifications and Drawings
Document
type
Document Title
Document
Number
Specification
Tunnels Engineering Standard
ESC 340
Standard
Telecommunications
Protection Standard
Standard
Insulation Coordination
10.2.2
Requirements
10.2.2.1
Design
Earthing
and
Surge
ESM 109
AS 1824.1 – 1995
Wireless systems design shall include antenna systems to provide adequate coverage
within tunnels, cuttings and the above ground rail corridor.
10.2.2.2
Mounting structure
Antenna systems above ground along rail corridor shall include foundation, building,
antenna and mounting structure at each site as required. Design and components used
for above ground infrastructure shall be compatible and common with existing designs.
10.2.2.3
Earthing
Earthing of base station huts and masts including antenna systems shall be in
accordance with RailCorp specifications.
10.2.2.4
Radiating coaxial cable Earthing
Radiating coaxial cable shall float free of earth at all times. Devices such as earthing
switches shall not be provided.
10.2.2.5
Tunnel Coverage
Wireless infrastructure coverage in tunnels shall be provided by radiating coaxial cable
(leaky cables).
© RailCorp
Issued February 2012
UNCONTROLLED WHEN PRINTED
Page 43 of 75
Version 1.1
RailCorp Engineering Specification — Telecommunications
Communications & Condition Monitoring Infrastructure
10.2.2.6
SPM 0212
Radiating coaxial cable frequency compatibility
The leaky cable systems in the tunnel shall optimise performance at specific Ultra High
Frequency (UHF) bands. 400 - 470 MHz for UHF radios, 1.8 GHz for DTRS and up to
2.1GHz for mobile phones.
10.2.2.7
Radiating coaxial cable loss
Radiating coaxial cables (leaky cables) shall be the constant system loss type, where
signal strength output at one end is identical to signal strength output at the other end.
10.2.2.8
a)
Radiating coaxial cables
b)
Two separate Radiating coaxial cables (leaky cables) shall be installed at
suitable locations within the tunnels and station areas where applicable.
c)
Where technically feasible, the two leaky coaxial cables should be the same
type of cable capable of handling between 400 MHz to 2.1GHz.
d)
One of the two leaky coaxial cables is to be dedicated to RailCorp Radio
systems.
Segments in Tunnels
Leaky coaxial cables in the tunnel shall be divided into segments in the up and down
directions from respective station.
10.2.2.9
Compliance with fire regulations
The leaky coaxial cable and mounting hardware shall be of low smoke, fire retardant and
zero halogen type.
10.2.2.10
10.2.2.11
Safe locations and installation
a)
The antenna systems installed shall be operationally safe. Electromagnetic
emission from the antenna system shall comply with relevant ARPANSA
frequency exposure standards.
b)
No part of the radiating system shall be located directly underneath live parts of
the overhead system or where there is a reasonable probability that parts of the
overhead system might fall on it as a result of failure or damage.
c)
All electrical parts forming the radiating system shall be physically located out of
normal reach of rail staff and passengers, and suitably protected in areas where
mechanical damage might occur (for example due to ladders being carried or
rested against a wall).
d)
Antenna systems (excluding leaky coaxial), mast, or poles shall be designed to
maintain a clearance of at least 3m from the nearest rail or traction power
structure or overhead wire at all times including while conducting service
activities.
Radiating coaxial cable safe locations and installation
a)
© RailCorp
Issued February 2012
Radiating coaxial cable (leaky cable) shall be located at safe locations with
adequate separations between the cables, out of reach by the public and a
minimum clearance of 300mm from the overhead 1500Vdc power lines.
UNCONTROLLED WHEN PRINTED
Page 44 of 75
Version 1.1
RailCorp Engineering Specification — Telecommunications
Communications & Condition Monitoring Infrastructure
10.2.2.12
SPM 0212
b)
Radiating coaxial cable (leaky cable) shall be supported in accordance with the
manufacturer's recommendations.
c)
Spacing of cable supports shall be sufficiently close that sag does not exceed
100 mm
d)
Radiating coaxial cable (leaky cable) shall be retained using non-flammable
materials (e.g. stainless steel cable tie) at pre-determined intervals to prevent
the cable from falling down in the event of a fire in that section of the tunnel.
Aesthetics
Antennas in public area shall be aesthetically compatible with its surrounding building
structure and design.
10.2.2.13
Sub systems
The antenna systems shall include multicoupling subsystems for transmitters and
receivers to include combiners, splitters, filters, diplexer, isolators, amplifiers and
associated components to combine different frequencies into antennas and radiating
coaxial cable (leaky cable).
10.2.2.14
Splitters
Where splitting of the signal is required to connect more than one radiating cable to the
base station, or one or more radiating cables and an antenna, the isolating device(s) and
the splitter shall be installed together in a sealed non-conductive housing.
10.2.2.15
Interference
There shall b e no interference between all radio, wireless, and mobile phone services.
10.2.2.16
Lightning protection
Above ground antenna system shall include lightning protection.
10.2.2.17
Installation procedure
Installation procedure for the radiating antenna cable used in the tunnel shall be as used
for the RailCorp City underground network.
10.2.2.18
Isolation
• An isolating device shall be provided to separate the radiating system from the
base station equipment.
• Electrical isolation shall be provided by an isolating device (capacitive or
transformer) installed between the radiating system and the base station.
10.2.2.19
Radiating coaxial cable Isolation
Radiating cables shall not be brought into equipment rooms.
10.2.2.20
Isolation specification
• Isolating device shall be rated to withstand 2kV continuously and 5kV for a period
of 1 min.
• Isolating device insertion loss shall be less than 1.5dB and VSWR less than 1.5:1.
© RailCorp
Issued February 2012
UNCONTROLLED WHEN PRINTED
Page 45 of 75
Version 1.1
RailCorp Engineering Specification — Telecommunications
Communications & Condition Monitoring Infrastructure
SPM 0212
• The isolation level shall be in accordance with IEC 820.3 Protection Level Class 3
10.2.2.21
Insulation
Insulation performance of the radiating system shall be tested after installation in
accordance with relevant clauses of AS 1824.1 Insulation Co-ordination
10.3
RF EME Assessment and Site Compliance
10.3.1
Standards, Specifications and Drawings
10.3.2
Document
type
Document Title
Standard
Radiocommunications
License
Conditions
(Apparatus License) Determination 2003
Standard
Maximum Exposure Levels to Radiofrequency
Fields – 3 kHz to 300 GHz
Document
Number
ARPANSA RPS
No. 3 (2002)
Requirements
As per the Radiocommunications License Conditions (Apparatus License) Determination
2003, provision of new wireless infrastructure and/or alteration of existing wireless
infrastructure should ensure that electromagnetic energy (EME) levels from the facility do
not exceed mandatory health exposure limits.
The ACMA has produced a booklet explaining the EME health exposure regulatory
arrangements and how they apply to licensees of radio communication transmitters. This
booklet can be obtained from the following website:
http://www.acma.gov.au/webwr/consumer_info/issues_alerts/emrbook_licensees.pdf
10.3.2.1
Transmitter sites and regulations
Transmitter sites shall achieve RF EME compliance in accordance with ACMA, OH&S,
ARPANSA’s RPS 3 - Radiation Protection Standards, and all other environmental
legislation, whether State, Territory or Commonwealth, in so far as they relate to or
regulate, whether directly or indirectly, the emission of RF EME and any other legislation
or the common law relating to or regulating, whether directly or indirectly, the emission of
RF EME.
10.3.2.2
Transmitter site assessments
Assessments shall be undertaken including measurements through a NATA accredited
RF assessment specialist to conduct RF Electromagnetic Emission (EME) assessments
of each RF transmission site, including the tunnel leaky coaxial antenna systems to
confirm compliance to the RF EME requirements for both general public and occupational
worker.
A Radio Communications Site Management Book (RCSMB) and a Site Compliance
Certificate (SCC) for each of the transmitter location shall be provided.
© RailCorp
Issued February 2012
UNCONTROLLED WHEN PRINTED
Page 46 of 75
Version 1.1
RailCorp Engineering Specification — Telecommunications
Communications & Condition Monitoring Infrastructure
10.3.2.3
SPM 0212
On-Site Documentation
The RF EME site management book for each transmitter site shall be provided in A4
format, placed inside a document holder to be affixed on the equipment room wall near
the cabinet.
10.4
Wireless Infrastructure equipment rooms
10.4.1
Standards, Specifications and Drawings
Document
type
Document Title
Document
Number
Standard
Telecommunications Equipment Rooms
ESM 107
10.4.2
Requirements
10.4.2.1
RailCorp Specifications
Where possible, wireless infrastructure equipment shall be accommodated in the
RailCorp Telecommunications Room. Refer to Section 4.1 for the specification
requirement of RailCorp Telecommunications Room.
Where the wireless infrastructure equipment is to be housed / accommodated on a
separate equipment room to the RailCorp Telecommunications Room, the following
requirements outlined below apply.
10.4.2.2
Separation
GRN, Police radio equipment and other non-RailCorp telecommunications equipment
shall be accommodated in a separate telecommunications equipment room.
10.4.2.3
Security
The equipment room shall be secured with a standard RailCorp keying system to be
agreed at design stage. Keys shall be provided to RailCorp for maintenance access.
10.4.2.4
Dimensions
Equipment room doors shall be designed to sufficient size (2200Hx850W minimum) to
allow removal of equipment cabinets in upright position.
10.4.2.5
Layout
Equipment layout design shall be logical and optimise for short cabling, maintainability,
interference control and compliment with room interior design.
10.4.2.6
Spare capacity
The design of room size, power shall include 50% spare capacity for future expansion.
Sufficient spare ventilation shall be provided to cater for additional equipment in the
future.
© RailCorp
Issued February 2012
UNCONTROLLED WHEN PRINTED
Page 47 of 75
Version 1.1
RailCorp Engineering Specification — Telecommunications
Communications & Condition Monitoring Infrastructure
10.4.2.7
SPM 0212
Position
The equipment room shall be no more than 20m away from the tunnel leaky coaxial cable
connection point as far as possible. Where the equipment room is within the rail corridor,
it shall not lie within the Danger Zone.
10.4.2.8
Equipment installation
Radio repeater equipment shall be avoided in tunnels but where required shall be
accommodated in a Tunnel Communications Equipment room
10.4.2.9
Tunnel equipment rooms
Tunnel equipment rooms (where required for radio systems equipment) shall be
separated from the mobile phone equipment and specifications for communications room
shall apply.
10.5
Wireless Infrastructure equipment cabinets
10.5.1
Standards, Specifications and Drawings
Document
type
Document Title
Document
Number
Standard
Installation Requirements for Customer Cabling
(Wiring Rules)
AS/ACIF
S009:2006
10.5.2
Requirements
10.5.2.1
RailCorp Specifications
Where the Wireless equipment cabinet is to be housed in the RailCorp
Telecommunications Room, equipment cabinets shall be provided as specified in
Section 4.3.
Where the Wireless equipment cabinet is to be housed on a non RailCorp
Telecommunications Room, equipment cabinets shall be provided as specified in the
following sections.
10.5.2.2
Dimensions
Wireless infrastructure radio and multicoupling equipment shall be installed in 19"
Cabinets with a minimum 20% spare capacity for future expansion.
10.5.2.3
Separation
GRN, Police and other non-RailCorp radio/wireless subsystems shall be in separate
cabinets adjacent to each other.
10.5.2.4
Cabling separation standards
Low Voltage Power and communications cabling shall be separated in accordance with
AS/ACIF S009
© RailCorp
Issued February 2012
UNCONTROLLED WHEN PRINTED
Page 48 of 75
Version 1.1
RailCorp Engineering Specification — Telecommunications
Communications & Condition Monitoring Infrastructure
10.5.2.5
10.5.2.6
SPM 0212
Identification
a)
All equipment cabinets, enclosures, equipment, terminals and cabling shall be
identified using permanent labels.
b)
Permanent labels shall be affixed at top front and rear (where applicable) door
of the cabinet or enclosure.
Design
Wireless systems equipment cabinets and other equipment cabinets in the same room
shall be coordinated in size, height, colour and maintenance access.
10.5.2.7
Security
GRN and Police cabinets will be fitted with different locking systems to be agreed with the
relevant stakeholders.
10.5.2.8
Protection
All Wireless systems equipment cabinets shall be equipped with a vertical GPO power
rail, surge suppression, an earth bar, cable trays for power and communications cabling.
Where required, cable management for data and fibre cables.
10.5.2.9
10.5.2.10
Equipment Location
a)
Heavy items above 20kg shall be located towards the bottom of the cabinet and
supported by either support rails or telescopic arms.
b)
Space shall be allowed between sub-racks in aid of cooling.
c)
Equipment layout within an equipment cabinet shall permit ease of
maintenance.
d)
Equipment layout shall take into account for convection cooling with a typical
operational temperature not to exceed 30 degrees C.
Antistatic provision
An antistatic connection point and an antistatic strap shall be included in each cabinet in
aid of static control.
10.5.2.11
Document holder
An A4 document holder shall be securely affixed inside the cabinet for storage of
drawings and service documentation.
10.6
Digital Train Radio System (DTRS)
The digital train radio system (DTRS) is a GSM-R based train radio communication
system that provides secure point-to-point communication in the following scenarios:
a)
Between train drivers / guards and area signallers;
b)
Between train drivers / guards and train controllers;
c)
For track side worker user groups;
© RailCorp
Issued February 2012
UNCONTROLLED WHEN PRINTED
Page 49 of 75
Version 1.1
RailCorp Engineering Specification — Telecommunications
Communications & Condition Monitoring Infrastructure
SPM 0212
d)
For shunters user groups;
e)
For transit officer user groups; and
f)
For station staff user groups.
GSM-R voice call and messaging functionality (including emergency call, broadcast call,
group call, all stop messages etc) shall be provided. Train radio coverage must be
achieved to mobile radios installed on trains in all sections of track. The GSM-R base
station equipment must include a battery charging and battery backup system with a
minimum 4 hours backup capability in the event of loss of mains supply. At remote or
difficult to access GSM-R Base station sites, to be determined on a case by case basis, a
minimum of 8 hours backup capability is required.
10.6.1
Standards, Specifications and Drawings
Document
type
Document Title
Specification
DTRS
Technical
No. CW5901*
Specification
EIRENE
Functional
Specification v7.1
Specification
EIRINE System Requirements Specification v15.1
P0011D010
Standard
Communications Earthing and Surge Protection
Standard
ESM 109
*
Document
Number
Specification
Contract
Requirements
N/A
P0011D009
DTRS Technical Specification Contract No. CW5901
RailCorp train radio system project contract documents including technical specification
can be found at http://www.railcorp.info/about_railcorp/major_projects/dtrs
10.6.2
Requirements
10.6.2.1
Technical Requirements
The train radio system shall at a minimum, meet the current technical requirements
contained in the DTRS Technical Specification Contract No. CW5901. At the time of
document writing, the DTRS Technical Specification is planned to undergo a technical
review. The Contractor responsible for delivering the new rail corridor shall liaise with
RailCorp to obtain the most up-to-date specifications
10.6.2.2
Radio coverage
Train radio coverage shall be achieved to mobile radios installed on trains in all sections
of track.
10.6.2.3
Compatibility
The train radio infrastructure to be installed must be compatible with the RailCorp GSM-R
Digital Train Radio System.
© RailCorp
Issued February 2012
UNCONTROLLED WHEN PRINTED
Page 50 of 75
Version 1.1
RailCorp Engineering Specification — Telecommunications
Communications & Condition Monitoring Infrastructure
10.6.2.4
SPM 0212
Lightning protection
DTRS Equipment room shall facilitate lightning protection and earthing in accordance
with RailCorp specification ESM 109 "Communications Earthing and Surge Protection
Standard".
10.6.2.5
GSM-R Spectrum
RailCorp’s GSM-R system operates in the DCS 1800MHz band. GSM-R equipment shall
be selected and tuned to optimise performance at the DCS1800 frequency band.
10.6.2.6
Health monitoring
New base station health status and alarms shall be integrated to main communications
network for monitoring by existing RailCorp Network Operations Centre (NOC)
10.6.2.7
Signaller panels
Compatible signaller panel and associated equipment shall be installed at the relevant
signalling complex
10.6.2.8
GSM-R design
Design of GSM-R Digital Train Radio System shall be in consultation with, and endorsed
by RailCorp and its stakeholders.
10.6.2.9
GSM-R antenna
Antenna System for the GSM-R Digital Train Radio System shall comply with the DTRS
Technical Specification requirements specified in Contract No. CW5901
10.6.2.10
Transponders
DTRS Transponders (for enhanced Location Dependant Addressing) shall be installed at
designated track locations, in accordance with DTRS standard procedures. The number
of Transponders required is to be determined during the design stage.
10.7
Without Brake-van (WB) Radio
Without Brakevan (WB) radio is a single frequency UHF radio system used for
communication between train drivers, train guards and signallers. It utilises hand portable
radios, fixed radios in trains, fixed radios in signalling boxes and fixed base stations.
Fixed base stations are connected to a RailCorp signal box via a two-wire voice circuit to
allow WB radio traffic to be recorded on a voice recorder.
10.7.1
Standards, Specifications and Drawings
Document
type
Document Title
Document
Number
Specification
“Train Radio Systems – WB/Local
Radio/Mountain Radio Equipment Specification
WB Radio Systems Block Diagram
TC 001314 01 ES
Drawing
© RailCorp
Issued February 2012
UNCONTROLLED WHEN PRINTED
MET-RA 0403
Page 51 of 75
Version 1.1
RailCorp Engineering Specification — Telecommunications
Communications & Condition Monitoring Infrastructure
10.7.2
Requirements
10.7.2.1
Spectrum
SPM 0212
WB base stations shall be programmed with a channel bandwidth of 12.5 kHz on a
simplex carrier frequency 450.050 MHz, with receiver CTCSS sub-audible tone 173.8 Hz
and open CTCSS (i.e. no CTCSS) for transmitter.
10.7.2.2
Licensing
An Apparatus License is required to be issued by the ACMA for any new WB site prior to
the site being commissioned into service. The issuing of Apparatus License shall be
arranged through RailCorp Communications Engineering who will then make the license
application to the ACMA. The Contractor is responsible to provide sufficient information to
support the Apparatus License application.
10.7.2.3
Coverage Area
WB radio coverage shall be achieved to hand portable radios inside and outside the train
in all sections of track, including tunnels. WB coverage is not necessary in station
concourse areas.
10.7.2.4
Coverage Level
-100dBm over 100% of the Coverage Area with 98% Certainty and greater than 25dB
SINAD
10.7.2.5
Type Approved Equipment
The type-approved WB base station is the Imark 5208L Link Transceiver.
10.7.2.6
Signal Control Location
Each WB base shall be controlled at an assigned Voice Communication System (VCS).
RailCorp will be responsible for the supply of VCS equipment, configuration and
commissioning.
10.7.2.7
10.7.2.8
Voice circuit
a)
A 2-wire voice circuit shall be provided from the WB equipment room to an
agreed interface point/Main Distribution Frame (MDF). At the time of writing,
RailCorp is investigating the use of Radio-over-IP technology to allow
transmission of the voice circuit over an IP network.
b)
The 2-wire circuit shall use in-band signalling at 2175Hz and compatible with
existing VCS Universal Serial Card (USC). As an example, Omnitronics 925-FR
interface unit (built into the Imark 5208L radio) is compatible with the USC.
Voice recording
Each WB base shall be recorded by the Voice Recorder Network (See section 9.2) at the
relevant Signal Box location.
© RailCorp
Issued February 2012
UNCONTROLLED WHEN PRINTED
Page 52 of 75
Version 1.1
RailCorp Engineering Specification — Telecommunications
Communications & Condition Monitoring Infrastructure
10.7.2.9
SPM 0212
HMI
Where VCS is fitted in a Signal Box, the main interface to the WB system is through the
VCS HMI an Omnitronics 960HC handset shall be provided and installed to be used as a
back up to the VCS system handset.
Where VCS is not available in a Signal Box location, the main interface to the WB system
is through the Omnitronics 960 handset.
10.7.2.10
Equipment Housing
Where the WB base station is to be located inside the rail corridor, generally a concrete
equipment hut is required to house the WB radio equipment.
10.7.2.11
Power supply
The type approved WB Base equipment requires a 12VDC supply
Each WB base power supply shall achieve a minimum of 8 hours back-up time assuming
a 50% Tx/Rx duty cycle.
10.8
Station Radio
Station radio is a stand-alone UHF radio system used for communication between station
staff while located at stations and station surrounds. In the future, it is envisaged that
DTRS will provide Station radio functionality through its “Group Call” facility.
Where DTRS provides Station radio functionality, no 400MHz system is required. In the
event that DTRS is not available to provide Station radio functionality, the requirements
set out in the following sections apply for new station building.
10.8.1
Standards, Specifications and Drawings
Document
type
Document Title
Document
Number
Specification
Digital Mobile Radio (DMR) Systems
ETSI TS 102 361
Parts 1 to 4
Specification
Digital Private Mobile Radio (dPMR)
ETSI TS 102 658
10.8.2
Requirements
10.8.2.1
Spectrum
a)
Any new Station radio shall be provided utilising digital radio technology with
6.25 kHz spectrum efficiency.
b)
Duplex frequencies for the Station radio system shall be selected from the
following band (in order of preference):
© RailCorp
Issued February 2012
i)
418.1 MHz to 418.4875 MHz band (and corresponding 408.65 MHz to
409.0375 MHz duplex pair),
ii)
462.5 MHz to 467.5 MHz band (and corresponding 452.5 MHz to 457.5
MHz band)
UNCONTROLLED WHEN PRINTED
Page 53 of 75
Version 1.1
RailCorp Engineering Specification — Telecommunications
Communications & Condition Monitoring Infrastructure
10.8.2.2
SPM 0212
c)
The maximum EIRP of the Station radio system shall not exceed transmit with a
maximum EIRP of 8.3W.
d)
The Station radio must not adversely interfere with other RailCorp radio
systems.
Licensing
An Apparatus License is required to be issued by the ACMA for any new Station Radio
site prior to the site being commissioned into service.
The issuing of Apparatus License shall be arranged by RailCorp Communications
Engineering who will then make the license application to the ACMA. The Contractor is
responsible to provide sufficient information to support the Apparatus License application.
10.8.2.3
Coverage Area
Radio coverage shall be provided across all staff accessible areas including station
platforms, paid and unpaid concourse, staff offices, access passages, meal rooms and
station entries, stairways, escalators, lifts, public access footpaths and public walkway /
tunnels (if any) and tunnel cross passages.
10.8.2.4
Coverage Level
-85dBm over 100% of the Coverage Area with 95% Certainty and for:
• Analogue Systems, greater than 25dB SINAD; or
• Digital Systems, less than 2% BER
10.8.2.5
Type Approved Equipment
At the time of writing, RailCorp is assessing the two digital radio standards, DMR and
dPMR and therefore no Type-approved equipment is available at this stage. The generic
requirements for equipment are:
10.8.2.6
a)
Support both analogue and digital radio standard. Exact digital radio standard
to be supported is to be consulted with RailCorp at the design stage.
b)
Support digital and analogue Conventional mode of operation
c)
Support wide-area Digital Conventional mode of operation.
d)
Compatibility with IP network backbone for wide area Digital Conventional
mode of operation
Channel Assignment
Unless otherwise stated, generally a Station radio system is required to provide the
following channel assignment as a minimum:
a)
A duplex repeater channel, ,
b)
and a simplex “talk-through” (direct mode) radio channel
Additional channel arrangement shall be derived from the stakeholders / end-users
requirement and be consulted with RailCorp Communications Engineering.
© RailCorp
Issued February 2012
UNCONTROLLED WHEN PRINTED
Page 54 of 75
Version 1.1
RailCorp Engineering Specification — Telecommunications
Communications & Condition Monitoring Infrastructure
10.8.2.7
SPM 0212
Hand portable radios
A minimum of six 4-watts hand portable radios with rechargeable battery, antenna, belt
clip and programmed with the working channels shall be provided at each new station.
Hand portable radios shall be capable to operate in both Digital and Analogue mode. At
the time of writing, RailCorp is yet to adopt a particular Digital radio standard.
Consultation is required to be made with RailCorp Communications Engineering prior to
any procurement of hand portable radios.
Hand portable radios shall be engraved for asset capture. RailCorp has a nominated
engraver contractor which acts on RailCorp’s behalf for managing Handportable asset
list.
10.8.2.8
Emergency Functionality
All new Yard radio hand portables shall have the ability to transmit an Emergency
notification to the controller radio console. Generally this is provided by the Emergency
SELCALL Hand portable feature by transmitting a code to the controller radio console
which emits an emergency alert tone when an emergency SELCALL code is detected.
10.8.2.9
Radio charger
A minimum of one 6-gang charger shall be provided for each new station.
10.8.2.10
Batteries
A minimum of six spare rechargeable batteries shall be provided for each new station.
The battery shall be of Ni-MH or Li-Ion type. Ni-Cd batteries will not be acceptable.
10.8.2.11
Power supply
Station radio power supply shall achieve a minimum of 8 hours back-up time assuming a
50% Tx/Rx duty cycle.
10.9
Yard Radio
Yard radio is a stand-alone UHF radio system that allows RailCorp personnel in stabling
yards to communicate with each other and to coordinate administration, maintenance and
train shunting activities. Yard radio includes channels for:
a)
Shunting Radio – Used by shunters to communicate to either a train driver or a
signaller/controller during shunting operations;
b)
Administration radio – Used by shift managers to coordinate activities within the
stabling yard; and
c)
Maintenance radio – Used by maintenance staff within the stabling yard to
coordinate maintenance activities.
It is envisaged that the DTRS will provide the Yard radio functionality through the DTRS’
Shunting and Group Call facility. In the event that DTRS does not provide the facility for
Yard radio communication, the following requirements apply for a new Stabling Yard
build.
© RailCorp
Issued February 2012
UNCONTROLLED WHEN PRINTED
Page 55 of 75
Version 1.1
RailCorp Engineering Specification — Telecommunications
Communications & Condition Monitoring Infrastructure
10.9.1
SPM 0212
Standards, Specifications and Drawings
Document
Document Title
type
Document
Number
Specification
RailCorp Yard Radio Functionality
TC 001663 01 TR
Specification
Digital Mobile Radio (DMR) Systems
ETSI TS 102 361
Parts 1 to 4
Specification
Digital Private Mobile Radio (dPMR)
10.9.2
Requirements
10.9.2.1
Spectrum
10.9.2.2
ETSI TS 102 658
a)
Any new Yard radio shall be provided utilising digital radio technology with 6.25
kHz spectrum efficiency.
b)
Duplex frequencies for the Yard radio system shall be selected from the
following band (in order of preference):
i)
418.1 MHz to 418.4875 MHz band (and corresponding 408.65 MHz to
409.0375 MHz duplex pair),
ii)
462.5 MHz to 467.5 MHz band (and corresponding 452.5 MHz to 457.5
MHz band)
c)
The maximum EIRP of the Yard radio system shall not exceed transmit with a
maximum EIRP of 8.3W.
d)
The Yard radio must not adversely interfere with other RailCorp radio systems.
Licensing
An Apparatus License is required to be issued by the ACMA for any new Yard Radio site
prior to the site being commissioned into service. The issuing of Apparatus License shall
be arranged through RailCorp Communications Engineering who will then make the
license application to the ACMA. The Contractor is responsible to provide sufficient
information to support the Apparatus License application.
10.9.2.3
Coverage Area
Within the yard limits or area of operations.
10.9.2.4
Coverage Level
-95dBm over 100% of the Coverage Area with 98% certainty and for
10.9.2.5
a)
Analogue Systems, greater than 25dB SINAD; or
b)
Digital Systems, less than 2% BER
Type Approved Equipment
At the time of writing, RailCorp is assessing the two digital radio standards, DMR and
dPMR and has not made a decision to adopt a particular standard therefore no Typeapproved digital radio equipment is available at this stage.
© RailCorp
Issued February 2012
UNCONTROLLED WHEN PRINTED
Page 56 of 75
Version 1.1
RailCorp Engineering Specification — Telecommunications
Communications & Condition Monitoring Infrastructure
SPM 0212
The generic requirements for yard radio infrastructure equipment are:
10.9.2.6
a)
Support both analogue and digital radio standard. Exact digital radio standard
to be supported is to be consulted with RailCorp at the design stage.
b)
Support digital and analogue Conventional mode of operation
c)
Support wide-area Digital Conventional mode of operation.
d)
Compatibility with IP network backbone for wide area Digital Conventional
mode of operation
Channel Assignment
Unless otherwise stated, generally a Yard radio system is required to provide the
following channel assignment as a minimum:
a)
A duplex repeater channel for Shunting operation (Shunting channel)
b)
A duplex repeater channel for Yard administration activities (Administration
channel)
c)
and a duplex repeater channel for maintenance activities (Maintenance
channel)
Additional channel arrangement shall be derived from the stakeholders / end-users
requirement and be consulted with RailCorp Communications Engineering.
10.9.2.7
Interface to Signaller
In general, an interface from the Yard Radio system to the Signaller controlling the Main
Line interfacing to the Stabling Yard is required. This interface is usually provided on the
Shunting channel of the Yard Radio system through the provision of a line interface to the
Yard radio repeater.
While the line interface has been traditionally provided through a VF circuit, at the time of
writing, RailCorp is investigating on the use of Radio-over-IP technology to allow
transmission over IP network.
10.9.2.8
Voice recording
The Shunting radio channel of the Yard radio shall be recorded by the Voice Recorder
Network (See section 9.2)
10.9.2.9
Hand portables
All new Hand portable radios shall be capable to operate in both Digital and Analogue
mode. At the time of writing, RailCorp is yet to adopt a particular Digital radio standard.
Consultation is required to be made with RailCorp COMMUNICATIONS ENGINEERING
prior to any procurement of hand portable radios.
10.9.2.10
Emergency Functionality
All new Yard radio hand portables shall have the ability to transmit an Emergency
notification to the controller radio console. Generally this is provided by the Emergency
SELCALL Hand portable feature by transmitting a code to the controller radio console
which emits an emergency alert tone when an emergency SELCALL code is detected.
© RailCorp
Issued February 2012
UNCONTROLLED WHEN PRINTED
Page 57 of 75
Version 1.1
RailCorp Engineering Specification — Telecommunications
Communications & Condition Monitoring Infrastructure
10.9.2.11
SPM 0212
Power supply
Yard radio Power supply shall achieve a minimum of 8 hours back-up time assuming a
50% Tx/Rx duty cycle.
10.10
Government Radio Network (GRN)
Government Radio Network (GRN) is owned by the Department of Finance & Services,
referred to further as the GRN Owner. GRN is used by government agencies including
Ambulance, SES, Fire Brigade, transit officers and railway maintenance workers.
10.10.1
Standards, Specifications and Drawings
Consultation is required with the GRN Owner (Dept. of Finance & Services) for up-to-date
GRN system specification
10.10.2
Requirements
10.10.2.1
General
Radio infrastructure shall be provided to facilitate communications to and between
dedicated hand portables, integrated with the existing GRN as per the GRN
specifications.
10.10.2.2
Coverage Area
GRN radio coverage shall be provided in all tunnels and underground section of the rail
corridor including inside train carriages, underground passages, stairways, equipment
rooms, platforms, and station concourses. RailCorp Security and Transit officers are the
primary GRN users within RailCorp, therefore coverage requirement for GRN outside the
underground and tunnel section of the corridor shall be consulted with both RailCorp
Security Division and the GRN owner.
10.10.2.3
Existing Coverage
Evidence shall be provided to demonstrate that sufficient coverage from existing GRN
network is available in the Rail Corridor, Tunnels and at Stations as required by RailCorp
operations, State Emergency Services, Fire, and Ambulance.
In the event that coverage from existing GRN network is deemed insufficient on the new
rail corridor and/or at Stations, the GRN network owner shall be consulted to arrange
possible coverage extension.
10.10.2.4
Antenna
Antenna system for the GRN in tunnels and cuttings shall share the leaky coaxial cable
with other radio systems, and comply with the requirements specified in the Antenna
System section (See section 10.2).
10.10.2.5
GRN design
Design of GRN system shall be in consultation with, and approved by the GRN Owner
and its maintenance provider.
© RailCorp
Issued February 2012
UNCONTROLLED WHEN PRINTED
Page 58 of 75
Version 1.1
RailCorp Engineering Specification — Telecommunications
Communications & Condition Monitoring Infrastructure
10.10.2.6
SPM 0212
Interference
The GRN must not adversely interfere with RailCorp radio systems.
10.10.2.7
Equipment Accommodation
GRN equipment shall be located in a GRN specific equipment cabinet in a
telecommunications equipment room dedicated to Non-RailCorp systems. Where
practically possible, the GRN equipment cabinet shall be a dedicated cabinet, separate
from RailCorp’s equipment cabinet.
10.10.2.8
Isolation
Antenna systems may be shared where there is no detrimental effect to RailCorp radio
systems (See section 10.2).
10.10.2.9
Voice and data links
Voice and data links shall be provided via allocated 64kbit/s timeslots within a DDS
Service with multiplexing equipment between base station site and the GRN Network
Operations Control Centre (NOCC)
10.11
Police Radio
The Police radio system is owned and maintained by the NSW Police and is used to
provide radio communications to the NSW Police and other emergency services.
10.11.1
Standards, Specifications and Drawings
Consultation is required with the Police Radio owner (NSW Police Service –
Communication Group) for up-to-date Police radio system specification.
10.11.2
Requirements
10.11.2.1
General
Radio infrastructure shall be provided to facilitate communications to and between
dedicated hand portables and to Police Central Operations, integrated with the existing
Police system.
10.11.2.2
Coverage Area
Police radio coverage shall be provided in all tunnels and underground section of the rail
corridor including underground passages, stairways, equipment rooms, platforms, and
station concourses. Coverage requirement for Police radio outside the underground and
tunnel section of the corridor shall be consulted with NSW Police.
10.11.2.3
Existing Coverage
Evidence shall be provided to demonstrate that sufficient coverage from existing Police
Radio network is available in the Rail Corridor, Tunnels and at Stations as required by the
NSW Police and other emergency services.
In the event that coverage from existing Police Radio network is deemed insufficient on
the new rail corridor and/or at Stations, the Police Radio network owner shall be
consulted to arrange possible coverage extension
© RailCorp
Issued February 2012
UNCONTROLLED WHEN PRINTED
Page 59 of 75
Version 1.1
RailCorp Engineering Specification — Telecommunications
Communications & Condition Monitoring Infrastructure
10.11.2.4
SPM 0212
Coverage Level
Coverage Level requirement for Police Radio System shall be in consultation with, and
approved by the NSW Police Service - Communications Group.
10.11.2.5
Antenna
Antenna system for the Police Radio in tunnels and cuttings shall share the leaky coaxial
cable with other radio systems, and comply with the requirements specified in the
Antenna System section (See section 10.2).
10.11.2.6
System design
Design of Police Radio System shall be in consultation with, and approved by the NSW
Police Service - Communications Group.
10.11.2.7
Interference
The Police radio must not adversely interfere with RailCorp radio systems.
10.11.2.8
Equipment Accommodation
Police Radio equipment shall be located in a Police Radio specific equipment cabinet,
housed in a telecommunications equipment room dedicated to Non-RailCorp systems.
Where practically possible, the Police Radio equipment cabinet shall be a dedicated
cabinet, separate from RailCorp’s equipment cabinet.
10.11.2.9
Isolation
Antenna systems may be shared where there is no detrimental effect to RailCorp radio
systems (See section 10.2).
10.12
Public Mobile Network
10.12.1
Requirements
10.12.1.1
Coordination
10.12.1.2
a)
The party responsible for implementation shall coordinate and manage mobile
network carriers to install Public Mobile Network equipment into the rail corridor.
b)
The party responsible or lead mobile network carrier shall seek approval from
RailCorp Rail Corridor Management Group (RCMG) prior to installation of
equipment in rail corridor.
c)
The party responsible for implementation shall involve mobile network carriers
at the early design stage.
Installation and maintenance
Carriers will be responsible for providing and maintaining Public Mobile Network
equipment other than shared tunnel leaky coaxial cables and communications bearers
specified herein.
Redundant low smoke zero halogen 12-core single mode fibre cables in physically
separate concrete encased conduits shall be provided. Fibre terminations shall be
© RailCorp
Issued February 2012
UNCONTROLLED WHEN PRINTED
Page 60 of 75
Version 1.1
RailCorp Engineering Specification — Telecommunications
Communications & Condition Monitoring Infrastructure
SPM 0212
accessible at both ends of the tunnel. The cables shall be installed between designated
equipment rooms and interface points to be specified by the mobile network carrier during
design phase.
10.12.1.3
Coverage
Public Mobile Network coverage shall include all public accessible areas including inside
train carriages in tunnels, station platforms, paid and unpaid concourse, access
passages, station entries, stairways, escalators, lifts, public access footpaths, public
walkways, station interchange areas and the whole rail corridor including maintenance
facilities/depots.
10.12.1.4
Antenna
The party responsible for implementation shall provide the radiating coaxial cable (leaky
cable) system for the tunnels as specified in the Antenna System section (See section
9.2), for use by the mobile network carriers.
The radiating coaxial cable (leaky cable) shall make provisions for multicoupling with the
DTRS (Digital Train Radio System). The party responsible for implementation and lead
mobile phone carrier shall coordinate with RailCorp for the mobile network integration
works with DTRS.
10.12.1.5
Antenna Maintenance and Ownership
RailCorp shall own and maintain the radiating coaxial cable (leaky cable) after the
warranty period.
10.12.1.6
Communications Links
The party responsible for implementation shall provide communication links including
fibre cables, telecommunication circuits between equipment rooms and external interface
points.
10.12.1.7
Fibre patch panels
The party responsible for implementation shall provision and commission mobile phone
dedicated fibre patch panels at agreed interface points at both ends of the tunnels, and
fibre terminations between equipment rooms.
10.12.1.8
Bearer Circuits
The mobile network carrier will be responsible for bearer circuits outside the new railway
infrastructure boundaries.
10.12.1.9
Separate Equipment Rooms
Separate equipment rooms for Public Mobile Network equipment for all carriers (e.g.
Telstra, Optus, Vodafone etc) throughout the tunnel and station infrastructure shall be
provided as required.
a)
© RailCorp
Issued February 2012
Public Mobile Network equipment rooms shall have separate access, clean,
sealed against moisture & dust. The equipment room shall be in adequate size,
equipped with power distribution board, GPOs, lighting, ventilation, and spare
capacity (including power and ventilation) for future expansion.
UNCONTROLLED WHEN PRINTED
Page 61 of 75
Version 1.1
RailCorp Engineering Specification — Telecommunications
Communications & Condition Monitoring Infrastructure
b)
SPM 0212
The Public Mobile Network equipment room shall be a telecommunications
equipment room dedicated to Non-RailCorp systems
10.12.1.10 Cable installation
Cable riser, cable entry penetrations in wall, ceiling or wall, cable ladders and cable
ducts, as agreed with RailCorp and the lead carrier, shall be provided.
10.12.1.11 Interference
Public Mobile Network infrastructure must not adversely interfere with RailCorp radio
systems.
10.12.1.12 Equipment Accommodation
Public Mobile Network equipment shall be located in a Public Mobile Network specific
equipment cabinet, housed in a Public Mobile Network telecommunications equipment
room. Where practically possible, each Public Mobile Network carrier’s equipment shall
be in a dedicated cabinet.
10.12.1.13 Isolation
Antenna systems may be shared where there are no detrimental effects to RailCorp radio
systems, (See section 10.2).
11
Condition Monitoring Systems
RailCorp, like most railways worldwide, already use condition monitoring to some extent.
For over a decade RailCorp has progressively introduced and operated remote condition
monitoring of rolling stock, some specific types of infrastructure as well as certain
environmental risks. As responsible stewards providing track access to freight and
passengers, condition monitoring provides the best and in some cases the only reliable
means to control some risks to the safety of rail passengers, train crews and rail
employees. As such, the use of condition monitoring systems for the control of some
specific hazards represents standard international practice.
It is a requirement of condition of use, and access to the Rail Corporation of NSW Rail
Network that all Operators (including independent operators) maintain their fleet to a
required level.
There is the requirement for Rail Corporation of NSW to provide an additional level of
protection on top of the requirements and conditions placed on the numerous operators
that utilise the RailCorp Network.
Condition monitoring also offers the opportunity to improve asset management
knowledge and asset reliability, to increase asset availability and to reduce the functional
failure of the critical assets being monitored. Condition monitoring is a standard method
to acquire asset information to support asset strategy and operational asset decisionmaking, and is utilised for this purpose in all major infrastructure industries.
Modern asset management demonstrates that condition monitoring is an important
component of good practice and this trend is increasing – across industries and
geographies. This trend has been driven in significant part by sustained, exponential
increases in the capability and capacity of information-gathering, transmission, storage
and computational systems. The traditional limitations of large volumes of “at the sensor”
data, low bandwidth communication to transmit the data, and inefficient computational
techniques to process the data have all been largely eliminated. Furthermore, with data
© RailCorp
Issued February 2012
UNCONTROLLED WHEN PRINTED
Page 62 of 75
Version 1.1
RailCorp Engineering Specification — Telecommunications
Communications & Condition Monitoring Infrastructure
SPM 0212
storage now a commodity and information management an accepted organisational
capability, long-term data storage, integration and mining is possible – opening up ever
increasing possibilities for improved asset management through better information.
11.1
Types of Train Condition Monitoring Systems
A list of the Train Condition Monitoring (TCM) Systems installed on the RailCorp Network
is shown below:
System
Description
Bearing and Brake Temperature
(BBT) Detection System
Previously known only as Hot Box Detectors
(HBD), the systems typically now also include Hot
Wheel Detectors (HWD), Dragging Equipment
Detectors (DED) and Automatic Equipment
Identification (AEI). The BBT system measures the
radiant heat/temperature of the axle bearings and
brakes (tread brakes and disc brakes) as they pass
over. The system also includes a Dragging
Equipment Detector (DED) for identifying low
hanging equipment. There are 3 generations of the
systems on the RailCorp network which are used
to prevent derailments due to bearing and brake
defects on passenger and freight rolling stock..
An array of microphones which analyses acoustic
signature and predicts potential bearing
faults/failure. The system also includes an AEI
Optical bogie geometry system. It measures the
distance of the wheel’s rim face and the angle of
the wheel-set relative to the rail and monitors for
high angles and wheel mis-alignment. High angles
of attack represent a greater risk of wheel squeal.
The system also includes an AEI
Accelerometers installed on track to measure the
impact forces that are attributed to wheel
flats/skids, spalls or wheel defects that could
damage the rolling stock and track infrastructure.
The system also includes load cells for dynamic
weights and an AEI.
Transducers installed on track that measures the
weight of the train at line speed (80km/h). These
systems can be annually certified to be used as a
weighbridge but are currently being utilised as
Overload detectors monitoring for overloaded or
incorrectly loaded wagons that could damage
infrastructure. The system also includes an AEI
Originally installed as part of the Ministers
Conditions of Approval for the ECRL tunnel. The
system utilises the base WILD electronics along
with some additional hardware and predicts the
vibration and ground borne noise attributed to the
passage of a train.
Series of active Radio Frequency antennas used to
read the passive Radio Frequency Identification
Tags located on all rolling stock.
AEI Tag readers are included in all trackside Train
Condition Monitoring Systems.
A system that integrates all the different train
condition monitoring systems’ data to allow for
Bearing Acoustic Monitor
(RailBAM)
Angle of Attack Detector (AoA)
Wheel Impact Load Detectors
(WILD)
High Speed In-Motion
Weighbridges (Overload
Detectors)
Ground Borne Noise (GBN)
Automatic Equipment
Identification (AEI) Tag Readers
Wayside Information
Management System (WIMS)
© RailCorp
Issued February 2012
UNCONTROLLED WHEN PRINTED
Page 63 of 75
Version 1.1
RailCorp Engineering Specification — Telecommunications
Communications & Condition Monitoring Infrastructure
System
SPM 0212
Description
ease of trending, analysis and reporting.
Please consult the Condition Monitoring Systems SME for a current map of RailCorp’s
train condition monitoring systems.
11.2
Typical Systems required on New Rail Corridors
11.2.1
Bearing and Brake Temperature (BBT) Detection System
The system is a combined system referred to as Bearing and Brake Temperature (BBT)
system and includes Hot Bearing Detector (HBD), Hot Wheel Detector (HWD) and
Dragging Equipment Detector (DED).
HBD and HWD systems ensure that the axle bearings are not overheating, that the
brakes are not sticking i.e. hot wheels or brake discs, and that the brakes are working i.e.
not cold. BBT also allows RailCorp to monitor in service operating conditions to mitigate
the risk of bearing, brake and dragging equipment defects causing issues with network
reliability.
RailCorp's current strategy is to implement BBT systems every 25 - 50km on all the main
routes to ensure that there are regular checks on bearing and brake temperatures
throughout a train’s journey and aims to cover the entire passenger fleet for the majority
of timetabled runs every day. For this strategy to be satisfied it requires a BBT system on
any new rail corridor if the new corridor causes a train path to have trains traversing more
than 50km without passing a BBT system. If any of the trains expected to traverse the
new corridor are captive then a BBT system is also required. If the new corridor allows
trains to crossover or, operate bi-directionally, or have different operating conditions in
each direction then there is also a requirement for a BBT system on both up and down
tracks. If there are more than 2 tracks an assessment is required to determine if the
coverage of the systems is adequate.
BBT system(s) installed shall provide equivalent or better functionality than the latest
generation of system that is currently in service in other areas of the RailCorp network.
11.2.2
Ground Borne Noise (GBN) and Wheel Impact Load Detector (WILD)
systems
For new corridors that require a tunnel it is assumed that the inclusion of a tunnel will
have similar Ministers Conditions of Approval on Ground Borne Noise as the Epping to
Chatswood Rail Line (ECRL). A GBN system will be required to ensure that the new
corridor complies with the conditions and that unacceptable carriages are indentified and
restricted and/or fixed. An assessment would be required to be conducted by the Rolling
Stock Division to determine whether the rolling stock proposed for the new corridor is
sufficiently covered by the existing GBN system. If the coverage is deemed to be
insufficient, then a new GBN system would be required in the new corridor.
The GBN system in its current form can not be installed without WILD electronics due to
hardware requirements, therefore RailCorp would require a WILD system to also be
installed at the same location as the GBN system. Installation of a WILD system would
also mitigate the risk of having a captive fleet of trains traverse a new corridor without
being monitored for wheel defects such as flats/skids and spalls that could damage track
infrastructure.
Both GBN and WILD systems require optimal pass speeds of between 60 and 120km/h.
© RailCorp
Issued February 2012
UNCONTROLLED WHEN PRINTED
Page 64 of 75
Version 1.1
RailCorp Engineering Specification — Telecommunications
Communications & Condition Monitoring Infrastructure
SPM 0212
The GBN and WILD systems installed shall provide equivalent or better functionality than
the latest generation of system that is currently in service in other areas of the RailCorp
network.
11.3
Classes of Systems
11.3.1
Classes Relevant to New Corridors
CM systems have been split into different classes since there are a number of constraints
required for CM systems but they don’t apply to every system. It has been recognised
that in the life cycle of Condition Monitoring Equipment that they go through different
phases of useability and that there is a different reliance on the data produced by each
system. This means that some systems are more critical than others and hence have
different requirements to make sure their availability targets are met.
Class 0 – Ad Hoc Systems designed for research and development purposes.
Class 1 – Monitoring and Low Data Volume and the systems are used for assets that
require some form of monitoring which does not directly impact on operations and is
generally not used for predictive maintenance.
Class 2 – Remote Monitoring systems used for assets that require monitoring which
includes an operational component and are used for predictive maintenance.
Class 3 – Remote Monitoring – Operation and Safety Significant systems are used for
assets that require monitoring which includes an operational component and are used for
predictive maintenance.
Class 4 – Safety Critical systems are used for operational assets that require monitoring
and have a safety critical function and are also used for predictive maintenance.
They have an agreed interface to enable retrieval of information externally, via network
connectivity. They use an open data format to allow third party access by RailCorp.
Please consult the Condition Monitoring Systems SME for the latest revision of the
interface standard for Condition Monitoring systems. The standard goes through in much
further detail the classes for systems.
11.3.2
Determination of Classes
The classes of the CM systems to be installed on any new corridor shall be determined
by RailCorp’s Communications & Control Systems Engineering in collaboration with the
Communications Chief Engineer.
At the time of writing, the system classes are as shown below:
BBT system - Class 3 system and a
GBN system – Class 2
WILD system – Class 2
High Speed in-motion weighbridges – Class 2
AoA Detectors – Class 2
ABM – Class 2
Standalone AEI systems – Class 2
© RailCorp
Issued February 2012
UNCONTROLLED WHEN PRINTED
Page 65 of 75
Version 1.1
RailCorp Engineering Specification — Telecommunications
Communications & Condition Monitoring Infrastructure
SPM 0212
Any additional CM systems to be included in a new corridor will be assessed as required.
11.4
Site Selection Criteria
Below are a standard set of selection criteria in selecting a typical site for a Train
Condition Monitoring system.
• Distance from load point (BBT only) – First system to be installed within 2025km of a load point. A load point is deemed to be the point at which a freight train
is loaded or at the boundaries of the RailCorp network.
• Spacing of subsequent Systems (BBT only) – The spacing between systems
should be between 25km and 50km depending on the level of traffic and high
secondary damage consequences
• Tangent track configuration – 100m of straight track in the vicinity of the system
• Level track – the track is to be as level as possible.
• Sidings (only alarming systems) – sidings or locations to mark-off carriages with
minimal interruptions to network services are within 5 – 10km of the site
• Train Speed – constant speed greater than 30km/hr, individual system
requirements also need to be considered.
• Signalling – no signals within a 200m on either side of the site and any on track
equipment to be installed a minimum of 20m from track circuit tuning loops.
• Level Crossings and Tunnels (only alarming systems) – The location of the site
is situated such that in the event of an alarm the train does not block level
crossings or be stopped inside a tunnel.
• Infrastructure Access – proximity to power supply, communications, ground
conditions and road access.
• Maintenance Support – accessibility of trackside and track mounted equipment
by maintenance staff without compromising safety. Maintainability of the system
using lookout working without compromising safety.
• Track Condition – the track structure must be stable and not pumping.
• Inspection Location (only alarming system) – the locations where inspections
could be expected to occur should be suitable for train crews to safely walk the
whole length of the train at track level and should allow for trains to be worked
around a disabled train.
• Train Operating Conditions - the operating conditions of the rolling stock on
approach and departure from the site need to be assessed to determine suitability
of the data that would be recorded.
Please consult the Condition Monitoring Systems SME for a typical site selection report.
This report is required to be developed in selection of any Condition Monitoring system
with the appropriate approvals and sign-offs.
11.5
General System Requirements
This section sets out some of the general requirements that need to be adhered to in the
development and implementation of a Train Condition Monitoring system.
11.5.1
Standards, Specifications and Drawings
Document
type
Document Title
Document Number
Standard
Analogue interworking and non-interference
requirements for Customer Equipment for
connection to the Public Switched Telephone
Network
AS/ACIF S002
© RailCorp
Issued February 2012
UNCONTROLLED WHEN PRINTED
Page 66 of 75
Version 1.1
RailCorp Engineering Specification — Telecommunications
Communications & Condition Monitoring Infrastructure
SPM 0212
Document
type
Document Title
Document Number
Standard
Analogue interworking and non-interference
requirements for Customer Equipment for
connection to the Public Switched Telephone
Network
Installation requirements for customer
cabling
Customer Access Equipment for connection
to a Telecommunications Network
Telecommunications and information
exchange between systems in Local and
Metropolitan Area Networks – Specific
Requirements.
Part 3: Carrier Sense Multiple Access with
Collision Detection (CSMA/CD) Access
Method and Physical Layer Specifications
(standard for Ethernet technologies)
Quality Management Systems Requirements
Information technology - Radio frequency
identification for item management
Standard for Automatic Equipment
Identification
Electrical Installations
AS/ACIF S004
AS 1085.14
Standard
Railway track material
Part 14: Prestressed concrete sleeper
RIC Electrical Systems – General
Description
Transit Space
Standard
Low Voltage Distribution Earthing
EP 12 00 00 20 SP
Standard
Low Voltage Installations Earthing
EP 12 10 00 21 SP
Standard
Installation Inspections
EP 17 00 00 06 SP
Standard
Work on or Near Low Voltage Distribution
Equipment - Permit Requirements and Safe
Working Distances
Isolation of Low Voltage Distribution
Equipment for Work
Operating Work - Low Voltage Distribution
System
Standard Voltage Tolerances
EP 95 30 00 01 SI
ESM 109
Specification
Communications Earthing and Surge
Suppression Standard
Concrete Sleepers
Specification
Resilient Base plates
SPC 235
Specification
Connectors for Signalling Interface
SPG 1030
Specification
Lighting and Surge Protection Requirements
SPG 0712
Specification
Cables for Railway Signalling Applications General Requirements
SPG 1010
Standard
Standard
Standard
Standard
Standard
Standard
Standard
Standard
Standard
Standard
Standard
Standard
Standard
© RailCorp
Issued February 2012
UNCONTROLLED WHEN PRINTED
AS/ACIF S009
AS/ACIF S003
IEEE 802.3
ISO 9001:2008
ISO/IEC 18000-6c
S 918-94
AS/NZS 3000:2000
EP 00 00 00 01 T1
ESC215
EP 95 30 00 02 SI
EP 95 30 00 03 SI
EP 90 10 10 02 SP
SPC 232
Page 67 of 75
Version 1.1
RailCorp Engineering Specification — Telecommunications
Communications & Condition Monitoring Infrastructure
SPM 0212
Document
type
Document Title
Document Number
Specification
SPG 1011
Specification
Cables for Railway Signalling Applications Multi Core
Installation of Equipment Racks and
Termination of Cables and Wiring
Construction of Cable Route and Associated
Civil Works
Small Buildings and Location Cases
Specification
Connectors for Signalling Interface.
SPG 1030
Specification
General Requirements for Labelling of Signal
Equipment
Specification Installation of Trackside
Equipment
Trackside monitoring systems
SPG 1031
SPG 0706
Manual
Train Operating Conditions Manual
OS 001 IM
Standard
Sleepers and Track Support
ESC 230
Standard
Transit Space
ESC 215
Specification
Rolling Stock Outline Interface
RSS001/ RSU 110
Specification
Automatic Equipment Identifiers (AEI)
RSS001/RSU
Appendix H
Specification
Specification
Specification
11.5.2
Hardware Requirements
11.5.2.1
Electronic Equipment
SPG 0707
SPG 0705
SPG 0708
SC 00 70 00 00 EQ
All equipment shall be installed in a standard rack enclosure specified by RailCorp
All CPU equipment must be highly reliable, have high availability and must be industrial
grade and all components shall be specified.
11.5.2.2
On-Track and Trackside Equipment
All on-track and trackside equipment including junction boxes are preferred to be IP65 for
protection from flooding and high dust ingress from access tracks and ballast
embankments. IP rating of all trackside enclosures shall be provided.
Under no circumstances is the design of on-track and trackside equipment to incorporate
the drilling, welding or modification of any portion of the running rails. Clamps are to be
used instead; they will “hug” or be moulded to the shape of the rail footing.
Where there is a risk of short circuiting RailCorp’s signalling system, approval from
RailCorp’s track and signalling engineering divisions is required to be sought.
All track equipment must use an adequate securing system that prevents the equipment
dislodging and potentially fouling the running line.
Any arrangement for fitting of all devices to the rail shall be presented for type approval
during the Design Phase. This includes details of clearances from the rail including
© RailCorp
Issued February 2012
UNCONTROLLED WHEN PRINTED
Page 68 of 75
Version 1.1
RailCorp Engineering Specification — Telecommunications
Communications & Condition Monitoring Infrastructure
SPM 0212
meeting the requirements of Minimum Operating Standards for Rolling Stock RS 0001 –
General Interface Rolling Stock Outline Guidelines – Refer to Standard.
All Equipment installed on the track shall be more the 5mm below rail level or in
accordance with the civil standard ESC 215 Transit Space
Detection equipment must be mounted so that ballast movement does not affect the
alignment and calibration of detection equipment.
All on-track equipment shall be fastened using tamper proof and security fasteners
All on track equipment should be adequately protected from damage from dragging
equipment.
The System shall be designed for continuous all-weather operation with particular
reference to the following design parameters:
Relative Humidity is within the range 0% to 90% non-condensing.
Rail Temperature is within the range -20º to +70ºC.
Site ambient air temperature in the range -15º and +50ºC, as measured in shade 1.5
metres above the ground.
Equipment Located on Track is required to:
Be designed for exposure to prolonged UV and Sunlight:
Not be affected by Train & Mechanical greases and oils, dropped by rail traffic:
Be designed for exposure to sand blasting that is ejected for traction, by rail traffic:
Not be affected by heat sources from passing track work machinery:
Where possible, be Two Pack Enamel or powder coated in a consistent “Safety Yellow”
for all items on the track or outside the hut:
Not be affected or affect the operation of Audio Frequency Signalling Loops;
Not be affected by and withstand constant subjection to salt, sea mist, sand, or constant
high humidity in coastal areas.
Not be affected by track pumping.
11.5.2.3
Communication Network
All servers shall be connected to the C&CS Wayside Network. All the components of the
system will be configured on the same VLAN.
Communications between the wayside network and the ICT Network are governed by a
Firewall. The firewall shall be configured to allow communication between the system and
any servers on the ICT network. The email server, SMS server, NTP server, SFTP server
and the anti-virus server are located on the ICT network.
Network transfer of files, including audio files shall use open IP standards.
All data communications components connected shall have ACMA approval both C-tick
and A-tick. The ACMA approval number shall be clearly shown on either a label attached
to the modem (where separate modems are used) or on a label fixed to the system at a
location close to the communications line, in a position where it is clearly visible.
© RailCorp
Issued February 2012
UNCONTROLLED WHEN PRINTED
Page 69 of 75
Version 1.1
RailCorp Engineering Specification — Telecommunications
Communications & Condition Monitoring Infrastructure
SPM 0212
The bandwidth required for the data transported on the network shall be provided.
All communications protocols standards used and all ports to be accessed on each
device for the setup of firewall rules shall be provided.
11.5.2.4
Equipment Rack (provided by the Contractor)
In order to maximise room space utilisation and to ensure racks provided are consistent
with existing racks, the data processing and associated subsystems that form part of the
HBD/HWD/DED system shall be installed in a rack equivalent to a 19 inch (900mm
deep), 45 RU black cabinet, produced by MFB Products Pty Ltd.
The system shall also have a 1 RU rack mounted 17 Inches LCD drawer (which includes
keyboard and mouse), and has remote access capabilities using TCP/IP.
11.5.2.5
Lightning, Spike and Surge Protection
Protection for all equipment from damage arising from electrical transients, conforming to
RailCorp Specification SPG 0712 “Lightning and Surge Protection Requirement” shall be
provided.
11.5.2.6
Earthing
All earthing to be installed as per RailCorp Standard ESM 109 including but not limited to:
11.5.3
a)
All Cabinets, Chassis to be earthed;
b)
All antennas to be earthed;
c)
All electrical components, i.e. Industrial PC’s, to be earthed;
d)
All Track Side Components to be double insulated from the track.
Software Requirements & Server Requirements
All software and server requirements shall conform to the technical specification for each
of the Condition Monitoring Systems. These technical specifications are produced by the
RailCorp Communications Engineering – Condition Monitoring Design unit.
The requirements include:
•
•
•
•
•
•
•
•
•
•
•
•
•
•
© RailCorp
Issued February 2012
Operating system requirements
System configuration files
System Software
Maintenance Applications
Remote Access
Time Synchronisation
Virus Protection & Updates
Firewalls
Reduced Operating Performance
Communications failures
Servers and Redundancy
Graphical User Interfaces (GUI)
Alarms and Alerts
Emails and SMS requirements
UNCONTROLLED WHEN PRINTED
Page 70 of 75
Version 1.1
RailCorp Engineering Specification — Telecommunications
Communications & Condition Monitoring Infrastructure
11.5.4
SPM 0212
Design
During the design period, a detailed design shall be developed in enough detail to
implement any software and hardware to meet the requirements of the system technical
specifications document.
The software and hardware changes implemented during design period shall be recorded
and updated. The information provided in this documentation shall describe the
architecture and construction of the system to a sufficient level of detail to permit the
ongoing support and operation of the equipment by a third party. This documentation
shall include a Reliability Block Diagram (RBD).
The design documentation produced shall as a minimum, include the following:
• Evidence of ISO 9001 Quality Assurance;
• A description of each component of the system (hardware and software), with
sufficient details to permit purchasing or a compatible replacement to be identified
later in the life of the system;
• A description of the functions performed by each component;
• A Contractor document describing any implemented algorithms and parameters in
the design submission for review and acceptance;
• Graphical User Interfaces, email alerts, reports and queries;
• Drawings showing the assembly of the equipment including dimensions and parts
lists;
• Drawings showing the dimensions of each part in sufficient detail for repairing and
maintaining the equipment;
• Identify any special tools e.g. special compilers;
• Electrical wiring schematics showing the internal cabling and wiring between the
components within the system, sufficient for troubleshooting;
• Electrical wiring schematics of the inputs and outputs to/from the systems,
identifying the relevant voltages, signals or protocols used;
• Detailed earthing diagrams including trackside and on-track equipment;
• Data flow charts to and from all components;
• System and Application Diagrams aligning to data flow charts;
• System Database and file folder structures.
• Serial Numbers for all major components
• Issues registers
• Technical Maintenance Plans
• Trouble shooting guides
• Verification and Testing
11.5.4.1
General
Provision of documentation and templates for the testing of all modular components that
may be considered faulty or suspect for the return.
The Contractor is responsible for carrying out the following:
• The static testing (including alignment tests for scanners and wheel sensors);
• Assisting with any Dynamic Testing;
• Certification Testing;
11.5.4.2
Test Specification
• A Test Specification for the system defining the procedures to be applied to
demonstrate that the equipment performs in accordance with the specification.
• The Test Specification shall contain three sections:
© RailCorp
Issued February 2012
UNCONTROLLED WHEN PRINTED
Page 71 of 75
Version 1.1
RailCorp Engineering Specification — Telecommunications
Communications & Condition Monitoring Infrastructure
SPM 0212
– Factory Acceptance Testing (FAT);
– Site Acceptance Tests (SAT);
– System Commissioning Acceptance Tests (SCAT).
• The Test Specification shall include an audit during the commissioning activities for
each site to confirm that there are no outstanding actions remaining to be
completed prior to acceptance of the system.
11.5.4.3
Factory Acceptance Tests (FAT)
• All FAT Certificates and test sheets for all components used prior to installation on
site including cables and spare parts.
• Contractor shall detail Quality Control Measures in place to ensure quality of all
components.
• The FAT shall include any software testing to ensure that all features of the system
functions as expected.
• The RailCorp shall witness all or parts of the FAT if possible.
11.5.4.4
Site Acceptance Tests (SAT)
• Prior to the commissioning tests, a site acceptance test shall be performed to
confirm the equipment at each site is complete, installed and aligned correctly and
working.
• During tests, the system shall be thoroughly assessed to determine the output that
can be expected with the combinations of inputs that could most likely occur under
fault conditions.
11.5.4.5
System Commissioning Acceptance Tests (SCAT)
In addition to Site Acceptance Tests performed, a series of tests to demonstrate the
equipment conforms to the requirements of the technical specification shall be performed.
The SCAT shall be submitted with a traceability matrix showing the tests done that
correspond to each of the clauses of the technical specification.
Each test in the SCAT shall include at least the following:
a)
unique number to allow for traceability;
b)
the purpose of each test;
c)
equipment required to perform the test;
d)
traceability to the relevant clauses of the technical specification;
e)
details about the hardware being tested (such as serial numbers, part numbers,
calibration dates and numbers);
f)
details about the software being tested (such as version numbers);
g)
detailed procedures on how to perform each test;
h)
expected outcome with specific measurements and tolerances when applicable;
i)
the recorded outcomes resulting from performing the test;
j)
results section with a pass, failed or not tested;
k)
witnesses and signatures section;
© RailCorp
Issued February 2012
UNCONTROLLED WHEN PRINTED
Page 72 of 75
Version 1.1
RailCorp Engineering Specification — Telecommunications
Communications & Condition Monitoring Infrastructure
11.5.5
Documentation
11.5.5.1
Construction Drawings
SPM 0212
The Contractor shall provide drawings for each site with the following details:
•
•
•
•
•
•
•
•
•
11.5.5.2
The physical installation of the equipment at each site
Rack layouts identifying each part of electronic equipment installed
Details of footings, cable trenches and any other civil works required for the system
Details of sleeper mounted equipment
Details of the mechanical installation of sensors mounted on or near the track
showing the attachment to the track and with instructions for repair or reattachment to the track in the event they are damaged;
Details of the mechanical installation of all items that directly clamp or harness to
the rail. These are also to include proof of moulding to the rail instead of “biting” the
rail
Drawings of components with respect to the standard gauge rails
Drawings showing the range of adjustments of each of the components
Electrical cable (single-line) diagram for each site, and/or electrical schematic
wiring diagram for each site, as appropriate
As-Built Drawings
As-built drawings will provide the same details as construction drawings, however, they
will contain detailed of the system components as built and be marked as such.
11.5.5.3
User Manuals
System user manuals shall be produced by the contractor that include:
• All components and their functions of the Interfaces including but not limited to:
–
–
–
–
–
Menus;
Sub-Menus;
Parameter Fields and Settings;
Help Files;
Version Information.
• Terminology which is consistent throughout the manuals and commensurate with
the terminology used on drawings and the labels on the equipment.
• Specifications for all the system components
• Documentation to understand and interpret Train Pass Details, Alarms/Alerts and
System Information.
11.5.5.4
Maintenance Manuals
• Maintenance manuals shall be produced that include:
– Simple procedures permitting non-skilled personnel to confirm whether the
equipment is powered and working;
– Replaceable parts at each site, identifying the manufacturer, the manufacturer’s
part, serial number and a brief description of the function or purpose of the
component;
– Sources of supply for compatible replacement components;
– Planned maintenance procedures that shall be carried out to ensure the
continued operation of the equipment;
– Detailed step by step instructions on how to align and calibrate all track side
equipment after removal and reinstallation in the event of track maintenance;
© RailCorp
Issued February 2012
UNCONTROLLED WHEN PRINTED
Page 73 of 75
Version 1.1
RailCorp Engineering Specification — Telecommunications
Communications & Condition Monitoring Infrastructure
SPM 0212
– Unplanned maintenance tasks that may be needed to restore the equipment to
its working condition;
– Terminology which is consistent throughout the manuals and commensurate
with the terminology used on drawings and the labels on the equipment;
– Cable set up;
– Cable pin out drawings;
– Faults Matrix, outlining all possible faults and procedures and steps in place to
diagnose fault components and restore.
• The maintenance manual shall include a Technical Maintenance Plan (TMP) that
sets out the maintenance requirements of the system together with the
frequencies. The TMP shall be reviewed by RailCorp’s Integrated Support Unit.
11.5.5.5
Software Manuals
• Software manuals shall be produced that include:
– Detailed steps for installing and confirming all applications onto the computer
system
– Documentation of all files including locations and how to understand them
including temp files and archive files
– Current version of software and configuration file
– Detailed steps to configure the system
– Default Manufacturer Configuration Values
– Equipment and procedures to obtain access to the configuration and data held
by the system, both on-site and remotely (where applicable)
– How to modify the parameters of the system, including descriptions explaining
how to obtain the current configuration and how to change each of the
parameters. This shall explain the settings that can be used and how to
configure them
– Appropriate sources of support for non-replaceable components and software;
– Software patching procedures for operating systems and antivirus software as
well as periodically backing up of system and train data and hard-disk image
creation
– Firewall ports required
– Documentation of any export function
– Instructional documentation on how to re-install and re-configure server
applications and client PCs in the event of hardware or electronic failure
– A troubleshooting section that lists all the know errors that may be raised by the
system and how to restore the system to operational capabilities
© RailCorp
Issued February 2012
UNCONTROLLED WHEN PRINTED
Page 74 of 75
Version 1.1
RailCorp Engineering Specification — Telecommunications
Communications & Condition Monitoring Infrastructure
Appendix A
SPM 0212
Subject Matter Experts
Section
SME Team Manager
Facilities and DC Power
Telecommunications Networks Manager
Cables
Telecommunications Networks Manager
Transmission Networks
Telecommunications Networks Manager
Emergency and Operations
PABX Telephones
Telecommunications Networks Manager
Data Networks
Data Networks Design Manager
Network Control Communications
Systems
Wireless Systems Manager
Wireless Infrastructure
Wireless Systems Manager
Condition Monitoring Systems
Condition Monitoring Systems Manager
Contact e-mail address for all the above SME’s: telecommunications@railcorp.nsw.gov.au
© RailCorp
Issued February 2012
UNCONTROLLED WHEN PRINTED
Page 75 of 75
Version 1.1
Download