SFMTA Municipal Transportation Agency Image: Historic Car number 1 and 162 on Embarcadero 10 | 29 | 2014 SAN FRANCISCO, CALIFORNIA October 23, 2014 Mr. Leslie Rogers Regional Administrator, Region IX Federal Transit Administration U.S. Department of Transportation 201 Mission St., Ste. 1650 San Francisco, CA 94105-1800 Subject: Submittals for the October 29, 2014 Quarterly Progress Review Meeting Dear Mr. Rogers: Enclosed for your review are the following reports in advance of the Meeting: Safety Program Fleet Management, Maintenance and Procurement Van Ness BRT Islais Creek Maintenance Facility TIGER IV Mission Bay Central Subway State of Good Repair I look forward to our meeting scheduled for Wednesday, October 29, 2014 at 9 a.m. at One South Van Ness Avenue, 7th floor, in the Union Square Conference Room. If you have any questions, please call me at 701.4720 or Kathleen Sakelaris at 701.4339. Very truly yours, Edward D. Reiskin Director of Transportation Enclosures cc: Ed Carranza, FTA Jeffrey Davis, FTA Bernardo Bustamante, FTA Alex Smith, FTA Steve Espinal, CPUC Tilly Chang, SFCTA Luis Zurinaga, SFCTA Kathleen Sakelaris, SFMTA Bill Byrne, David Evans and Associates (PMO) 1 South Van Ness Avenue 7th Floor, San Francisco, CA 94103 415.701.4500 www.sfmta.com SFMTA CAPITAL PROGRAM QUARTERLY PROGRESS REVIEW MEETING AGENDA One South Van Ness, Union Square Room Wednesday, October 29, 2014, 9:00 a.m. – Noonish 1) Introductions, Remarks, What’s New • FTA • SFMTA • Current Org Chart Changes 30 minutes Leslie Rogers Edward Reiskin Handout (if needed) 2) SFMTA Safety Program 20 minutes • Safety Highlights since last quarter Melvyn Henry • Safety Statistics Report – Accidents, Injuries, Fatalities • Corrective Action Plans Status Details since last quarter - New, Closed, Outstanding • CPUC Assessment & Observations CPUC 3) Triennial Review Findings Status EcoSys Module Development Status 4) Fleet Management, Maintenance, and Procurement (LRV Rehab, Damaged Vehicles, LRV, and Bus Procurements) 10 minutes Lucien Burgert 10 minutes John Haley 5) Van Ness BRT Project status • Schedule, Design, Costs • CTA to MTA Agency Transition & MOU status • Platform Weatherproofing Status • CM/GC Contract Procurement Status • Staffing 20 minutes Peter Gabancho 6) Islais Creek Maintenance Facility – Phase 2 status 10 minutes David Greenaway 20 minutes David Greenaway 7) TIGER IV Mission Bay Scope, Schedule, Budget Status, Risks Contract Award Status 8) Central Subway 45 minutes • Staffing Status to plan - vacancies, positions filled John Funghi Project Controls, Claims Specialist, Inspectors, Office Engineers • Contract 1252 & 1300 construction status • Quality Issues and Status • Schedule activity and availability, contingency, mitigation status - baseline vs. actuals schedule o Contract 1300 Baseline schedule approval o Contract 1300 delays and recovery efforts • Cost activity, cost reporting, contingency, mitigation status o Budget, Expenditures to date, Remaining budget, Forecast to Complete, Contingency. o Earned Value vs. Expenditures • PMOC Assessment & Observations Bill Byrne 9) State of Good Repair • Current Status of EAMS efforts 10 minutes, Maria Gartner 10) Old Actions/New Action Items 11) Future meeting date: TBD, 2015 10 minutes Bill Byrne FTA Pre-meeting Tuesday October 28, 9:00 am – 11:00 PDT @ FTA FTA Grant Closeout Report GRANT NO. FTA UNLIQUIDATED % GRANT BALANCE AS BILLED AWARD SHOWN ON AMOUNT TEAM ON 3/13/14 ($000) ($000) DATE OF LAST GRANT CLOSE- CLOSE-OUT DISBURSEMENT OBLIGATION OUT FORECAST REQUEST, PER (AWARD) DATE ON DATE TEAM ON 3/13/14 DATE GRANT COMMENTS ACTIVE GRANTS less than 4 YEARS OLD CA-55-0002-01 5,039 1,682 66.6% 9/8/2014 12/16/2010 6/30/2013 9/30/2015 CA-05-0259 CA-95-X164 CA-04-0008-03 CA-90-Y905-02 67,383 3,748 3,441 14,889 59,527 1,830 1,794 4,432 11.7% 51.2% 47.9% 70.2% 9/9/2014 9/10/2014 9/10/2014 9/10/2014 8/19/2011 8/25/2011 8/31/2011 9/22/2011 12/31/2016 12/31/2014 12/31/2013 12/31/2017 12/31/2016 12/31/2015 12/31/2015 12/31/2016 CA-05-0272 CA-90-Y995 CA-95-X199 CA-95-X179 69,409 9,940 517 2,035 68,853 2,029 512 1,594 0.8% 79.6% 1.0% 21.7% 9/8/2014 9/8/2014 9/8/2014 9/10/2014 8/22/2012 8/22/2012 12/7/2012 8/8/2013 12/31/2016 12/31/2016 12/31/2014 12/31/2015 12/31/2016 12/31/2016 6/30/2015 12/31/2015 CA-04-0278 CA-90-Z086 CA-54-0010 6,352 53,785 30,552 3,664 14,591 30,260 42.3% 72.9% 1.0% 9/9/2014 9/9/2014 9/9/2014 6/12/2013 7/30/2013 7/30/2013 6/12/2016 12/30/2014 12/30/2017 9/30/2016 12/31/2017 12/30/2017 CA-79-0002 10,000 9,275 7.3% 9/10/2014 2/3/2014 8/1/2015 9/30/2015 CA-95-X219 37,620 30,747 18.3% 9/9/2014 8/6/2014 12/31/2016 12/31/2016 CA-54-0026 17,730 17,730 0.0% --- 8/6/2014 6/30/2017 6/30/2017 CA-90-Z180 CA-95-X150 CA-95-X303 CA-03-0767-07 CA-04-0196 18,399 20,000 12,498 448,929 60,800 18,399 19,656 12,498 207,239 36,182 0.0% 1.7% 0.0% 53.8% 40.5% --9/8/2014 --9/10/2014 9/9/2014 8/18/2014 8/26/2014 8/27/2014 9/11/2014 9/22/2014 6/30/2017 6/30/2016 6/30/2018 12/31/2017 12/30/2018 6/30/2017 6/30/2018 6/30/2018 12/31/2017 12/30/2018 Subtotal 893,066 542,494 39.3% SFgo Van Ness Corridor traffic signal infrastructure improvements. FY2011 5309 Funds for various fixed guideway projects. Transit/ped improvements on Market/Haight Streets. Glen Park Facility Improvements. FY2011 5307 Formula Funds for various capital projects. FY2012 5309 Funds for various fixed guideway projects. FY2012 5307 Formula Funds for various capital projects. Signal rehab on 2nd Street. Transit/ped improvements at Phelan Loop and Church & Duboce Streets. 8x Transit Enhancements. FY2013 5307 Formula Funds for various capital projects. FY2013 5337 State of Good Repair Funds for various capital projects. TIGER IV Grant: Mission Bay Loop and Roadway Improvements Mission & N-Judah Mobility Projects, LRV Rehab, Preventive MTC., & Trolley Coach Replacement FY2014 5337 State of Good Repair Funds for various capital projects. FY2014 5307 Formula Funds for various capital projects. SFgo project on and around the Van Ness Corridor. Central Subway. Central Subway. State of Good Repair Grant: Islais Creek and Transportation Asset Management System; Buy Replacement 40-FT Bus. FTA Grant Closeout Report GRANT NO. FTA UNLIQUIDATED % GRANT BALANCE AS BILLED AWARD SHOWN ON AMOUNT TEAM ON 3/13/14 ($000) ($000) DATE OF LAST GRANT CLOSE- CLOSE-OUT DISBURSEMENT OBLIGATION OUT FORECAST REQUEST, PER (AWARD) DATE ON DATE TEAM ON 3/13/14 DATE GRANT COMMENTS ACTIVEGRANTS GRANTSmore less than ACTIVE than44YEARS YEARSOLD OLD CA-90-Y124 82,157 1,860 97.7% 9/8/2014 7/26/2002 12/31/2007 6/30/2015 CA-03-0708-01 23,306 2,226 90.4% 9/9/2014 9/7/2005 12/30/2008 6/30/2015 CA-05-0215 46,547 4,530 90.3% 9/8/2014 8/3/2007 12/30/2011 6/30/2015 CA-90-Y533 31,854 5,750 81.9% 9/9/2014 8/3/2007 12/30/2011 6/30/2015 CA-05-0225 41,180 5,307 87.1% 9/8/2014 8/18/2008 12/30/2012 12/30/2015 CA-90-Y624 38,170 4,184 89.0% 9/8/2014 8/18/2008 12/31/2013 12/30/2015 CA-05-0241 CA-90-Y749 37,331 30,917 21,485 10,919 42.4% 64.7% 9/9/2014 9/10/2014 7/31/2009 7/31/2009 12/31/2014 12/31/2015 12/31/2015 12/31/2015 CA-03-0811 CA-90-Y822 CA-05-0742 Subtotal 15,396 23,553 63,772 434,183 10,755 3,868 59,373 130,257 30.1% 83.6% 6.9% 70.0% 9/9/2014 9/10/2014 9/10/2014 9/14/2010 9/16/2010 9/23/2010 12/31/2014 12/31/2016 12/31/2015 12/31/2016 12/31/2015 12/31/2016 CA-90-Y348 CA-57-X077 CA-04-0247 CA-26-0057 CA-37-X180 65,841 200 6,822 241 289 0 95 373 8 0 100.0% 52.5% 94.5% 96.7% 100.0% Subtotal 73,393 476 99.4% FY2003 5307 Formula Funds. Balances relate to renovation of Potrero Facility and providing Bayview pedestrian access. Balances remain for 2 projects: Overhead Rehab and CPCS project. FY2007 5309 Funds. Balances relate to unprogrammed and existing Cable Car Infrastructure Rehab projects, N & L Train Signal Prioritization, and Historic Vehicle Rehab. FY2007 5307 Formula Funds. Balances relate to Misc Security Expenditures, Historic Car Rehab, and Rehab of Escalators. FY2008 5309 Funds. Balances relate to Green Center Rail Replacement and LRV ATCS Antenna Replacement. FY2008 5307 Formula Funds. Balances relate to Rehab Escalators, Islais Creek, Renovate Woods & Potrero Hoists, and Subway Fire Alarm. FY2009 5309 Funds for various fixed guideway projects. FY2009 5307 Formula Funds. Balances relate to Rehab Escalators, unprogrammed Cable Car Infrastructure Rehab, Historic Vehicle Rehab, Renovation of Woods Facility, Automatic Wayside Fare Collection, and Clipper Limited Use Tickets. Van Ness BRT project. FY2010 5307 Formula Funds for various capital projects. FY2010 5309 Funds for various fixed guideway projects. GRANTS with EXPECTED SHORT TERM CLOSEOUT 9/8/2014 9/10/2014 9/10/2014 9/8/2014 9/8/2014 9/6/2005 7/11/2012 8/16/2012 8/27/2012 5/29/2013 12/30/2008 9/30/2013 12/31/2014 12/31/2014 4/1/2016 10/30/2014 12/31/2014 12/31/2014 12/31/2014 10/30/2014 FY2005 5307 Formula Funds. Ready to close out. New Freedom Grant: Accessible Light Rail Stops Phelan Loop project. SFgo Transit Priority project. Restoration of bus service on 6 Muni lines. Ready to close out. FTA Grant Closeout Report GRANT NO. TOTAL ALL GRANTS FTA UNLIQUIDATED % GRANT BALANCE AS BILLED AWARD SHOWN ON AMOUNT TEAM ON 3/13/14 ($000) ($000) 1,400,642 673,227 51.9% DATE OF LAST GRANT CLOSE- CLOSE-OUT DISBURSEMENT OBLIGATION OUT FORECAST REQUEST, PER (AWARD) DATE ON DATE TEAM ON 3/13/14 DATE GRANT ACTIVE GRANTS less than 4 YEARS OLD COMMENTS Federal Transit Administration LESLIE ROGERS Regional Administrator EDWARD D. REISKIN Director of Transportation OPENING REMARKS SAFETY PROGRAM UPDATE Melvyn Henry Chief Safety Officer 3 Safety Highlights • Training Section • • New transit operators trained from July 2014 through September 2014 96 operators assigned to Divisions • CPUC Corrective Actions (CAPs) and Order Instituting Investigation (OII) Items • • • 8 Incident Corrective Actions closed; 16 Incident Corrective Actions remain open; resolutions in progress 2012 CPUC Triennial Audit Findings: Five CAPS submitted for closure; remaining seven in progress for closure. Two open 2011 OII Capital Items completed, inspected, and verified by CPUC. • Section 11.3- Signal Standardization- Inspected 12/12/2013 • Section 11.4- MMT Revenue Track- Inspected 11/25/2013 • Formal Closure Request sent to CPUC 1/2/14: awaiting formal closure confirmation letter; copy of letter forwarded to FTA per FTA request 4 Safety Highlights (cont’d): • CPUC General Order 172: Rail In-Cab/Forward Facing cameras • All cameras installed before the October 6, 2014 deadline. Includes LRVs, PCCs, Cable Cars and Historic rail vehicles. 5 Third Street Safety Updates: Illegal Left Turn Collisions • Paint crews will stencil “No Turns” on pavement at intersections where left turns are prohibited. Work scheduled to be completed on October 31, 2014. • Safety Division and Sustainable Streets Division tested various GPS devices to see if left turn instructions are given to drivers at restricted streets. SFMTA is working with the GPS Garman company to correct left turn instructions given to drivers at 22nd and Third. • Test units included Google Maps, Garman, IPhone and Android. • All electronic train coming signs will be replaced with larger signs that are currently in service at other Rail Transit Agencies (RTAs). 6 2012 – Q3 2014 Bus Collision Trends 7 2012 – Q3 2014 Rail Collision Trends 8 CAPITAL PROGRAM CONTROLS SYSTEM UPDATE Lucien Burgert Capital Controls Manager 9 Project Overview • Develop and implement a scalable and flexible enterprise-wide Capital Program Controls System (CPCS) – COMPLETE • Roll out system to the Agency’s first user group: Capital Programs & Construction – COMPLETE • Expand system to include all capital projects across all SFMTA Divisions – IN PROGRESS • Enhance system configurations to include additional functionality, such as new electronic timesheets, Fund Programming and SCC cost reporting – IN PROGRESS • Utilize system to review project portfolios, identify areas of concern, and incorporate timely corrective actions – ONGOING 10 EcoSys Module Review Status • Enhanced review of SFMTA’s financial management module (EcoSys) completed by Milligan & Company, with the following recommendations identified: – Define detailed requirements for SCC cost reporting. – Evaluate data validation controls and update the automated interface process between EcoSys and FAMIS. – Review EcoSys/FAMIS data integration and ensure process is scalable. – Obtain detailed system documentation and training materials from Vendor and ensure all users are appropriately trained. – Ensure Vendor has thoroughly tested system functionality. – Standardize software versions used across multiple environments. 11 Next Steps • Using sample Van Ness BRT data, validate design of SCC cost reporting and complete final testing. • Finalize EcoSys Fund Programming design documentation and begin importing all funding plans for all capital projects. • Continue Agency-wide system expansion, including requirements gathering sessions, and import all new project portfolios. • Complete configuration of new electronic timesheet software and begin parallel testing in December. 12 TRANSIT OPERATIONS UPDATE John J. Haley, Jr. Director of Transit 13 Light Rail Procurement – The Right Vehicle to Meet Our Demands • Signed contract in September with Siemens for up to 260 cars 14 15 Light Rail Procurement – Moving Forward • NTP issued on September 30, 2014 • Held initial project meeting on September 26th • Siemens scheduling testing of system • Public outreach process initiated • Discussion with key internal stakeholders • Allocation of Prop K Sales Tax Funds • SFMTA hiring project team • Project Management Plan developed following FTA guidelines • Prototype due in December 2016 16 Operator’s Cab Final layout will be determined via public process and vetting with stakeholders 17 Other Rail Fleet Programs • Wreck Repair Program • Five of eight LRVs back in service: #1407, #1433, #1459, #1499, #1540 • Additional LRV(#1522) to be delivered and back in service by midNovember • SFMTA awaiting FTA response to request to dispose of #1429 and #1435 prior to end of useful life and future investment of remaining federal interest in like-kind property • PCC Rehabilitation • Rehabilitation of sixteen cars – remaining non-rehabilitated cars • MTAB approved award of contract to Brookville Equipment Corporation on May 20, 2014; approved by Board of Supervisors on July 29, 2014 • LRV Rehabilitation Program • Over half of the fleet has been rehabilitated (83 cars) • Board of Supervisors approved a change in scope to focus on the 18 trucks on October 7, 2014 LRV Rehabilitation Effect on Mean Distance Between Failures (MDBF) (average number of monthly road calls*) Item Before Rehab After Rehab Effect on MDBF Doors & Steps 28.75 25 13% increase Air Supply Unit 2.5 4.25 70% decrease 3 1.5 50% increase Articulation and PSC-2 Wiring 12.5 3 76% increase Traction Motor Bearings 12.75 3.25 75% increase Trucks and Resilient Pins 14.5 2 86% increase Couplers * source: 2012/2013 Central Control road call data 19 Rubber Tire Fleet • Bids received for replacement and expansion of 30’, 40’, and 60’ motor coach fleets • Replace Neoplan fleet of over 200 buses and expand for the future • First articulated motor coaches expected to start arriving in early 2015 • Trolley coach design finalized and articulated trolley coaches moving to manufacturing • Production of the pilot trolley coach to start in November 2014 • First articulated trolley coach (pilot) expected in February 2015 • Will replace SFMTA’s oldest rubber tire fleet 20 VAN NESS AVENUE BUS RAPID TRANSIT Peter Gabancho Project Manager III – Capital Programs & Construction – SFMTA Robert Masys Senior Engineer – Capital Projects - SFCTA 21 Center-Running BRT 22 Last Quarter Accomplishments • Public Meeting for Parking Legislation Aug. 22, 2014 • Held First CM/GC Taskforce Meeting Aug. 27, 2014 • Caltrans Project Study Report – Project Report (PSR/PR) Aug. 28, 2014 • Received Caltrans Comments Sept. 4, 2014 • Distributed Construction Charrette Report (Charrette held July 16, 2014) Oct. 2, 2014 • Received SFMTA Board Approval for CM/GC Oct. 7, 2014 23 Project Schedule Milestones • Local CEQA Approval • Final EIR/EIS – Record of Decision (ROD) • 30% Design complete • SFMTA Board Approval CM/GC • Submit Draft SSGA to FTA • Project Specific Ordinance • 65% Design complete • CM/GC Contract Certification • SSGA Execution • 100% Design complete • Arrival of new transit vehicles • Construction period • Revenue Service Sept. 2013 Dec. 2013 April 2014 Sept. 2014 Oct. 2014 Nov. 2014 Nov. 2014 Feb. 2015 April 2015 July 2015 2015 - 2016 Late 2015–Mid 2018 Fall 2018 24 Project Rendering 25 Conceptual Drive Through 26 Separate but Related Projects • • • • • • • Overhead Contact System / Poles / Lighting ‒ Design work is proceeding in conjunction with BRT facilities. SFGo Traffic Signal System Upgrade / Replacement ‒ Design work is proceeding in conjunction with BRT facilities. Vehicle Procurement ‒ Work proceeding in parallel; to be completed 2016. Radio Replacement ‒ Work proceeding in parallel; to be completed late 2016. Sewer Work ‒ Design work is proceeding in conjunction with BRT facilities. Water and Auxiliary Water Supply System ‒ Design work is proceeding in conjunction with BRT facilities. Other Utilities ‒ Coordination with AT&T and PG&E is ongoing. 27 BRT Project Cost Summary Costs below in $ Millions per SCC Code Funds below in $ Millions 5 10 Guideway & Track 14.4 20 Stations, Terminals 180 51.1 Other Local, Regional & State Programs 160 140 67.7 40 Sitework & Special Conditions 120 100 18.1 50 Systems 80 36.0 Proposition K – SF ½ Cent Sales Tax* *$15M subject to SFCTA Board approval anticipated March 2014 4 70 Vehicles 75.0 5309 FTA Small Starts Funds 60 52.9 80 Professional / Support Services 40 20 0 Estimated Cost $162.1M Planned & Committed Funding $162.1M • Estimate does not include the majority of the cost of replacement vehicles (local or federal), electrical overhead lines replacement, new streetlights / poles, and signal priority, which are funded separately. • Estimate includes a 30% contingency . 28 SCC Format Cost M A I N W O R K S H E E T - SCC SFMTA & SFCTA Van Ness Bus Rapid Transit, San Francisco, CA Small Starts Project Development Phase YOE Dollars Total (X000) 10 GUIDEWAY & TRACK ELEMENTS (route miles) 20 STATIONS, STOPS, TERMINALS, INTERMODAL (number) 30 SUPPORT FACILITIES: YARDS, SHOPS, ADMIN. BLDGS 40 SITEWORK & SPECIAL CONDITIONS 50 SYSTEMS Construction Subtotal (10 - 50) 60 ROW, LAND, EXISTING IMPROVEMENTS 70 VEHICLES (number) 80 PROFESSIONAL SERVICES (applies to Cats. 10-50) Subtotal (10 - 80) 90 UNALLOCATED CONTINGENCY Subtotal (10 - 90) 100 FINANCE CHARGES Total Project Cost (10 - 100) 4,491 12,984 0 60,909 16,313 94,697 0 3,980 52,876 151,553 10,522 162,075 0 162,075 29 Costs as of 9/30/2014 Project Cost Details Project / WBS ID Project / WBS Name CPT6401 Van Ness Avenue BRT Approved Budget Allocated Funding Spent to Date Encumbrances Remaining Balance Estimate to Complete $162,075,000 $17,691,186 $13,857,671 $44,301 $3,789,214.00 $145,048,248 0 Environmental $7,600,000 $7,600,000 $7,400,000 $0 $200,000.00 $0 1 Conceptual Engineering $8,880,058 $6,619,561 $6,120,048 $44,301 $455,212.00 $0 2 Detail Design $10,228,000 $3,471,625 $337,623 $0 $3,134,002.00 $9,681,306 3 Construction $135,366,942 $0 $0 $0 $0.00 $135,366,942 30 Van Ness BRT Organizational Chart 31 Permits and Agreements VAN NESS CORRIDOR TRANSIT IMPROVEMENT PROJECT Permit List # 1 2 3 4 5 Permits Agency Cooperative Agreement for Caltrans Design Project Study Report/Project Caltrans Report Cooperative Agreement for Caltrans Construction Phase 2 Design SF Arts Approval of Comm. public structures SF General Plan Planning Referrals Dept. Sidewalk 6 Legislation SFDPW /BSM Surface Mounted SFMTA Facility Permits /SDD Street Tree SFDPW 8 Removal Permit /BUF Parking SFMTA 9 Legislation /SSD Pre-final 10 Construction SFMTA Documents 7 Other Agencies Codes/Processes Phase Approx. Time Required Start Date Need Owner By Status SFMTA/ SFCTA Memorandum of Understanding Design 6 months 09/2014 03/2014 PG Completed SFCTA PSR/PR Design 1 year 05/2013 05/2014 PG Completed SFMTA Memorandum of Understanding Design 6 months 12/2014 06/2015 PG Not Started Civic Design Review Process Design 1 year 02/2014 02/2015 PG Started Design 6 months 11/2014 05/2015 PC Not Started Design 1 year 05/2014 06/2015 KK Not Started Design 3 months 11/2014 02/2015 KK Design 6 months 12/2014 06/2015 MK Design 6 months 05/2014 11/2014 KK Design 12 months 06/2014 06/2015 PG/TP Board of General Plan Referral Supervisors TASC, SF San Francisco Public Works Planning Code Dept & BOS San Francisco Public Works Code San Francisco Municipal SFDPW Code San Francisco Traffic Code TASC including department orders Caltrans Caltrans Constructability Review Checklist Not Started Not Started Started 32 Started ISLAIS CREEK MAINTENANCE FACILITY Phase II Status David Greenaway Project Manager 33 34 Progress Phase II - Operations and Maintenance Building • Completed final drawings, specifications and construction estimate • Advertised for bids Next Steps Phase II - Operations and Maintenance Building • Open and Review Bids – December 1st 35 Organizational Chart 36 Schedule Phase II - Operations and Maintenance Building 37 Project Funding and Budget Overview 38 Phase II Cost Estimate in SCC Format 39 MISSION BAY / UCSF HOSPITAL MULTIMODAL TRANSPORTATION NETWORK David Greenaway Project Manager 40 Project Scope • UCSF Medical Center Transportation Infrastructure: • Construct missing segments of two streets, widen the freeway off-ramp, install the transit infrastructure to accommodate the extension of an electric trolley coach route. Complete all pedestrian and bicycle connections to the existing light rail stop. • Traffic Circle Connectors Transportation Infrastructure: • Construct all remaining roadway connections to the Mission Bay traffic circle. Install transit infrastructure to accommodate the extension of an electric trolley coach route. • Transit Loop: • Complete a single-track transit loop for the T-line, including adjacent roadway surface improvements, between18th and 19th Streets. 41 Quarterly Progress Transit Loop • • Opened Bids on August 12th Awarded Construction Contract on September 16th Street Elements • • • Permit issued and received by MBDG August 1, 2014 for “Traffic Circle Connectors” street elements. Caltrans permit issued Began Grading Activities on Owens Street 42 Next Steps Transit Loop • Issue Notice to Proceed • Continue working with CPUC on the at-grade crossing application Street Elements • Issue surface improvement bid package for public bid for TIGER Scope work for the remaining section of MBB-North and South, Channel Street and the connection to the Traffic Circle. • Open bids for the “UCSF Medical Center and Hwy 280 Off-ramp Project” 43 Project Schedule 44 Project Funding and Budget Overview TIGER IV PROJECT BUDGET Current Budget 1) UCSF Medical Center Multimodal Transportation Infrastructure $2.753M 3) Traffic Circle Connectors Multimodal Transportation Infrastructure $4.036M 4) Transit Loop - Third Street Light Rail TOTAL TIGER IV Funding Match $5.128M $1.661M $6.283M $4.872M $1.565M (Prop K & State Bonds) $13.072M $10.000M $3.226M 45 Cost Estimate in SCC Format 46 Project Organization Chart 47 CENTRAL SUBWAY John Funghi Program Director 48 Latest Construction Activity 49 Construction Contract 1252 Description: Contract Details Contract Awarded: August 8, 2011 Notice to Proceed 1: January 27, 2012 Notice to Proceed 2: March 14, 2012 Partial NTP 3: April 13, 2012 Notice to Proceed 3: October 15, 2012 Substantial Completion: April 13, 2015 1.7-mile twin bore tunnels from Hwy I-80 to North Beach using two tunnel boring machines (TBMs) simultaneously; settlement monitoring and protection of existing utilities, buildings and BART tunnels; launch box and retrieval shaft excavation support; Yerba Buena/Moscone Station and Union Square/Market Street Station end walls; tunnel excavation and lining, 4th Street portal and cross passage. Contract Award Value: $233,584,015 Status: Modifications to Date: • $4,796,430 Current Contract Value: $238,380,445 • Removal of the Southbound TBM, Mom Chung continued, together with cleaning of the twin bore tunnels and the start of post construction surveys. Cross Passages 1-4 are complete. Cross Passage 5 initiated ground freezing. Budget/Expenditures Category Amount Current Budget $251,690,546 Expenditures to Date $221,485,998 Building the slab for the tunnel portal ramp Building the interior of Cross-passage #4 50 Construction Contract 1252 (Cont’d) Contract 1252 Forecast: • Retrieval Shaft: Restore site by January 2015 Photo courtesy of The Robbins Company Tunnel contractor removing TBM Mom Chung’s cutterhead and trailing gear at the retrieval shaft located at 1731-1741 Powell Street. 51 Contract 1300 Stations, Track and Systems Update Contract Details Contract Awarded: May 21, 2013 Notice to Proceed: June 17, 2013 Substantial Completion: Feb. 10, 2018 Three subway stations (Chinatown, Union Square/Market Street, Yerba Buena/Moscone); One surface station (4th and Brannan); Concourse connection between Union Square/Market Street Station and existing Powell Street Station; Surface tracks on 4th Street between 4th and King streets and tunnel portal; Trackbed, tracks, switches and train control systems. Contract Award Value: $839,676,395 Status: Modifications to Date: $115,956 • CTS and YBM: Current Contract Value: $839,792,352 Slurry wall panel construction, rebar installation and concrete placement continues, forming the perimeter station walls. AWSS relocations and enhancements continue at both station sites STS: Budget/Expenditures Category • Amount Utility potholing on 4th Street between Bryant and King was completed. Installation work on the AT&T ductbank, streetlights and waterlines continues. UMS: Current Budget $859,676,395 Expenditures to Date $159,251,477 • South concourse excavation between Ellis and O’Farrell Street commenced. Pile installation continued on other portions of the station footprint. 52 Contract 1300 Stations, Track and Systems Update Contract 1300 Forecast: • • • CTS and YBM: Continue slurry wall construction and complete AWSS on 4th and Folsom STS: Continue AT&T conduit; begin 78 inch sewer UMS: Continue south concourse excavation; continue pile installation on Ellis 53 Real Estate Acquisition Real Estate Activity Update: Remaining license compensation to be obtained by Central Subway Station compensation grouting 1 • Outstanding Station Compensation Grouting Compensation: • 19 Stockton Street (Armani Exchange) • License granted to project through condemnation process • Settlement conference held on October 10, 2014 • Compensation trial was continued to November 2014 by the courts • • Final step in the condemnation process Continue to provide additional information and working to address concerns 54 Summary Cost 55 Schedule Contingency 56 Cost Contingency Drawdown/Post 1300 Award 57 Staffing Status Position Status Contract Administrator Position Filled Dispute Resolution 1st Quarter of 2015 58 ENTERPRISE ASSET MANAGEMENT SYSTEM (EAMS) UPDATE Maria Gartner EAMS Project Manager 59 EAMS Project Goals & Objectives • Establish EAMS: establish a single Enterprise Asset Management system, integrated agencywide, providing full visibility of the current and historical state of all active SFMTA assets • Support Renewal and Replacement Programs: support a state of good repair by establishing and sustaining complete and accurate data on SFMTA assets, tracking labor, and materials, including procurement and disposal, over the life-cycle of an asset, with long-term data integrity • Enable Accurate Data Tracking: enable accurate financial forecasting and planning based upon a complete, historically accurate and up-to-date asset data repository • Standardize Asset Management Practice: standardize SFMTA asset management business practices • Comply with Requirements: comply with federal and regional asset management requirements • Improve Work Environment: improve work practices and the work environment, enable internal culture change, and break down work silos • Sustain the EAMS Long-term: implement an EAMS program with a life-cycle of at least 25 years 60 Progress This Quarter Completed Selection Process for EAMS Professional Services (RFP# SFMTA-2014-35) Proposals accepted (8/6) Panel completed Strengths & Weakness session and written scoring (9/8) Panel conducted oral interviews (9/30) Completed Selection Process for Project Team Infor Training (RFP# SFMTA-2014-51) Proposals were accepted (8/19) Panel completed written scoring (9/4) Contract drafted (9/19) Staff Recruiting Hired a 1044 Principal Engineer – start date 10/14 Offer for 1824 Administrative IS Analyst in process Added a 1053 IS Analyst from existing FIT staff Discovery Analysis Completed Buildings & Grounds and Custodial Unit on 9/23 Initiated underground storage tanks discovery Continued Asset Identification for MOW Performed data analysis of MP2 and SHOPS data for MOW 61 High Level Timeline 2012 2015 2014 2013 2016 2017 Infor EAM Licensing Conceptual Engineering Report Initial Plan Developed RFI Consultant RFP Development Selection/NTP Recruiting Refine Plan Vehicle Maintenance; Motor Coach, Trolley, LRV, Historic, Cable Car, Non-revenue Vehicles and Fleet Appearance Discovery Phase One Maintenance of Way Purchasing Materials Management Underground Storage Tanks, Overhead Lines, Motive Power, Track Maintenance, Shops; e.g., Signal, Video, Digital, etc., Cable Car Machinery, Buildings & Grounds Phase Two Sustainable Streets Livable Streets, SSD Shops: e.g., Parking Meters, Signs, Paint, Traffic Signal, and SFgo, Parking, etc. Phase Three Transit Real Estate Central Subway IT 62 Project Organization * Executive Sponsor Ed Reiskin Director of Transportation Primary Stakeholders • • • • • • Finance – Sonali Bose Contracts – Ashish Patel Procurement – Virginia Harmon Materials – Angela Carmen Technology – Travis Fox Real Estate – Kerstin Magary Sustainable Streets – Tom Maguire Strategic Planning – Darton Ito Off-street Parking – Rob Malone Field Operations – George Reynolds Parking Enforcement - Chris Grabarkiewctz Transit – John Haley Maintenance of Way – Terrance Fahey Bus & Rail – Jeff Flynn Non-Revenue Vehicles - TBD Safety – Melvyn Henry Capital Projects –Vince Harris Controller’s Office – Ben Rosenfield Steering Committee Requirements Expectations Influence Expertise Acceptance Terrance Fahey, Maintenance of Way Travis Fox, Finance & Technology Hoppers, Finance & Technology Darton Ito, Long Range Planning Ashish Patel, FIT Contracts & Procurement Lucien Burgert, Capital Project Controls Advocates Garners Support Scope Clarification Expert Judgment Determine Priorities Complex Issue Resolution Change Management Board Project Manager Maria Gartner 9179 Manager V Business Transformation Jaime Ballesteros 1070 Project Manager Principal Engineer Ed Zvenigorodskiy 1044 Sr. IS Engineer Consultant Project Manager * Teams perform work on-site at business units, including Discovery work, business process mapping, requirements definition, data mapping, fit/gap analysis, etc. Field Engagement Teams Gordon Gottsche 1824 Lead Analyst (Vacant ) 1052 IS Analyst EAM Consultant* Technical Integration Team Software configuration, Data Migration, Interface Development, Postimplementation Application Support Infor EAM Expert Consultant * Pending 1824 Lead Analyst (Vacant) 1052 IS Analyst EAM Consultant * (Vacant) 1823 Lead Analyst (Vacant) 1052 IS Analyst EAM Consultant * Jeff Goldberg 1824 IS Analyst Hannah Staroselsky 1053 IS Analyst (Vacant) 1054 Sr. IS Analyst (Vacant) 1062 Programmer Analyst Consultant Sr. Programmer * Consultant Programmer * Consultant Lead Analyst * Consultant Analyst * EAM Consultant * * Consultant positions/roles in project organization are tentative pending contract finalization (in light blue font) Subject Matter Experts Project Team: Completes the work to meet project goals and objectives Strategic Planning Alex Demisch 5289 Transportation Planner III Leslie Bienenfeld 5288 Transportation Planner II (Vacant) 1942 Materials Coordinator Materials Coordinator Consultant * 63 EAMS Budget Summary as of 9/30/2014 Cost Summary Forecast PHASE BASELINE COST SPENT TO DATE REMAINING BALANCE CONCEPTUAL RFP DEVELOPMENT $927,492 $354,639 $927,492 $404,081 $0 -$49,442 IMPLEMENTATION PHASE 1 PHASE 2 PHASE 3 CONTINGENCY $10,891,137 $2,241,230 $3,149,336 $2,469,166 $138,589 $10,752,548 $2,241,230 $3,149,336 $2,469,166 TOTAL $20,033,000 $1,470,162 $18,562,838 Funding FUND SOURCE FEDERAL Section 5309 LOCAL Prop K Sales Tax SFMTA Operating Funds TOTAL ALLOCATED PROGRAMMED /PLANNED TOTAL BILLED %BILLED BY SOURCE $1,480,000 $7,320,000 $8,800,000 $1,161,627 13.2% $200,000 $170,000 $0 $10,863,000 $200,000 $11,033,000 $200,000 $108,535 100% 1.0% $1,850,000 $18,183,000 $20,033,000 $1,470,162 7.3% 64 Next Steps • Conduct contract negotiations for EAMS Professional Consulting Services and Project Team Training • Continue Staff Recruitments • Complete MOW Discovery Analysis Work • Motive Power • Shops • Cable Car Machinery • Conduct Project Team Training (Infor EAM V11.0) 65