Amendment no. 3 Protection Design Instruction Protection of embedded generation systems IMPORTANT DISCLAIMER As the information contained in this publication is subject to change from time to time, Endeavour Energy gives no warranty that the information is correct or complete or is a definitive statement of procedures. Endeavour Energy reserves the right to vary the content of this publication as and when required. You should make independent inquiries to satisfy yourself as to correctness and currency of the content. Endeavour Energy expressly disclaims all and any liability to any persons whatsoever in respect of anything done or not done by any such person in reliance, whether in whole or in part, on this document. Document no. PDI 5000 Amendment no. 3 51 Huntingwood Drive, Huntingwood NSW 2148 Postal address: PO Box 6366 Blacktown NSW 2148 Phone: 131 081 Fax: (02) 9853 6000 Copyright © Endeavour Energy 2011 PROTECTION DESIGN INSTRUCTION TRANSMISSION ENGINEERING PDI 5000 Document no. Amendment no. Approved by Approval date PDI 5000 3 MTEB 19 August 2010 Protection of embedded generation systems Contents 1.0 PURPOSE......................................................................................................................4 2.0 SCOPE...........................................................................................................................4 3.0 REFERENCES...............................................................................................................4 4.0 DEFINITIONS AND ABBREVIATIONS .........................................................................4 5.0 ACTIONS .......................................................................................................................5 5.1 Operations ....................................................................................................................6 5.1.1 Operational requirements..............................................................................................6 5.1.1.1. Parallel operation..................................................................................................6 5.1.1.2 Non-parallel operation ........................................................................................6 5.1.1.3 Standby operation (occasional parallel operation)................................................7 5.1.2 Generator control ..........................................................................................................7 5.1.2.1 Synchronising .......................................................................................................7 5.1.2.2 Frequency and load control ..................................................................................8 5.1.2.3 Power system frequency variation........................................................................8 5.1.2.4 Voltage and reactive power control ......................................................................8 5.1.2.5 Voltage control on distribution systems ................................................................8 5.1.3 Islanding ......................................................................................................................8 5.1.4 System earthing ............................................................................................................9 5.1.4.1 HV system earthing ..............................................................................................9 5.1.4.2 LV system earthing .............................................................................................10 5.1.5 Operation of unearthed systems (loss of mains) ..........................................................10 5.1.5.1 Neutral voltage displacement (NVD) ..................................................................10 5.1.5.2 Reverse power or directional protection .............................................................11 5.1.5.3 Inter-trip from feeder circuit breaker (CB) .........................................................11 5.1.6 General technical requirements....................................................................................11 5.1.6.1 Generator technical data ....................................................................................11 5.1.6.2 Fault levels..........................................................................................................11 5.1.6.3 Stability ...............................................................................................................12 5.1.7 Connection security standards .....................................................................................12 5.1.8 Fault clearance times ....................................................................................................12 PDI 5000 Copyright © Endeavour Energy 2011 Page 2 of 23 Protection of embedded generation systems Amendment no.3 5.1.9 Protection requirements ..............................................................................................13 5.1.9.1 Internal protection ...............................................................................................14 5.1.9.2 External or interconnection protection ................................................................14 5.1.10 Auto-reclose ................................................................................................................15 5.1.10.1 Generator reclose...............................................................................................15 5.1.10.2 Network auto-reclose .......................................................................................15 5.1.11 Installation maintenance.............................................................................................15 5.1.12 Remote monitoring and control ..................................................................................16 6.0 AUTHORITIES AND RESPONSIBILITIES..................................................................17 7.0 DOCUMENT CONTROL..............................................................................................17 ANNEXURE A1......................................................................................................................18 ANNEXURE A2......................................................................................................................20 ANNEXURE A3......................................................................................................................21 PDI 5000 Copyright © Endeavour Energy 2011 Page 3 of 23 Protection of embedded generation systems 1.0 Amendment no.3 PURPOSE To describe the minimum electrical protection and control requirements for privately owned generation intended to operate in parallel with the Endeavour Energy’s electrical distribution or transmission network. 2.0 SCOPE This instruction outlines the technical issues regarding electrical protection at the connection of embedded generation in the transmission or distribution network, where operation in parallel with the network is required. It also deals with privately owned generators within a customer’s network that are directly connected to, and able to run in parallel with, any part of Endeavour Energy’s network. 3.0 • • • • • • • • • • • • • • • • 4.0 REFERENCES Company Policy 9.2.2 0 Network Protection ENA National Electricity Network Safety Code (NENS 01-2008) Integral Energy Network Management Plan 2009-2014 AS/NZ 61000.2.12:2003 Electromagnetic Compatibility (EMC) AS/NZS 3000:2000 Wiring Rules Coal Mines Regulation (Electrical – Open Cut Mines) 1984 Division 4 IEC 60255 (BS142) Electrical Relays Network Service Provider General Terms and Conditions or Customer Connection Contract Service and Installation Rules of New South Wales The National Electricity Code Engineering Technical Report No. 113 Rev 1(1995) Notes of Guidance for the Protection of Embedded Generating Plant for Operation in Parallel with Distribution Systems Customer Guidelines for the Connection of Private Generation to Integral Energy’s Distribution Network – June 2005 Protection Design Instruction PDI 4000 – Protection definitions, vocabulary and symbology PDI 4001 – Protection design principles Substation Design Instruction SDI 519 – Communications in substations SDI 538 – Supervisory Control and Data Acquisition (SCADA) DEFINITIONS AND ABBREVIATIONS AEMO Australian Energy Market Operator. Connection agreement An agreement between a Network Service Provider (Endeavour Energy) and the customer (Generation Company) by which the customer (generation plant) is connected to the transmission or distribution network and/or receives transmission services or distribution services. Customer The proponent of the generating scheme, finally responsible for ownership and operation of the scheme. PDI 5000 Copyright © Endeavour Energy 2011 Page 4 of 23 Protection of embedded generation systems Amendment no.3 Embedded generator A generator that generates electricity and the generating unit is directly connected to the transmission or distribution system and includes customers with their own generation. Grid Endeavour Energy’s network and its connections to the National Electricity Grid. Islanding Islanding occurs when a private generator or generating system remains connected to a portion of the network and continues to supply electricity to that portion of the network, but is disconnected from the general electrical network or main source of generation. Network connection point (NCP) The point of electrical connection between the apparatus owned by the Network Service Provider (Endeavour Energy) and the apparatus owned by the customer. NEC National Electricity Code. Network Service Provider A person who engages in the activity of owning, controlling, or operating a transmission or distribution system and who is registered in that capacity with AEMO under Chapter 2. Point of common coupling (PCC) Point on a public power supply network, electrically nearest to a particular load, at which other loads are, or could be, connected. Scheduled generating unit (SGU) Unless otherwise approved by AEMO under the provisions of clause 2.2.3(b), a generating unit that has a nameplate rating of 30MW or greater, or is part of a group of generating units connected at a common connection point with a combined nameplate rating of 30MW or greater, is classified as a scheduled generating unit. Synchronism Synchronism occurs when two (2) a.c. voltages are of the same frequency and magnitude, and have zero phase difference. 5.0 ACTIONS There must be proper coordination between the protection systems of the customer and Endeavour Energy’s network in order to ensure safety of the plant and stable operation of the electrical network. Typical issues are: • correct protection grading; • tripping sequences; • correct reclosing of faulted lines; and • machine network synchronising. The primary aim of protection and stability coordination is to ensure that the protection is designed and set to rapidly clear faults, or restrain from operating when necessary in order to maintain the security and integrity of the electrical network. Details of the proposed protection arrangements associated with the embedded generator’s plant must be submitted to the Network Service Provider (Endeavour Energy) to determine if additional protection is required in the interests of safe and stable operation of the network. PDI 5000 Copyright © Endeavour Energy 2011 Page 5 of 23 Protection of embedded generation systems 5.1 Amendment no.3 Operations 5.1.1 Operational requirements Three (3) modes of operation will be considered for private generating units, namely: Parallel operation: Connected continuously to the network, with or without the ability to export energy to the grid. Non-parallel operation (break before make operation): Operating in isolation from the supply network by way of a changeover switch. For this type of installation, suitable controlling switchgear is required that can be electrically, mechanically or key interlocked. The major disadvantage of this arrangement is that the customer load must be interrupted each time there is a changeover from one supply source to the other. Standby operation (synchronise, close, transfer trip operation - SCTT): This mode of operation has similar connection arrangements to the non-parallel scheme, except that both the normal supply and generator supply may be connected for a short time in order to allow testing of the generator’s operation without interrupting the customer’s load. Detailed operating arrangements will be negotiated for each case and included in the operating agreement between the customer and Endeavour Energy. The general operating requirements for the different connection methods are listed below: 5.1.1.1. Parallel operation The generator continuously supplies energy to the grid. Salient points to consider include: • • • Protection equipment is required to meet the outcomes specified in this Standard. Appropriate synchronising equipment is required to connect and disconnect the generator to and from the network. Engraved all-weather signs are to be placed at all switch points at which the generator can be isolated from the network, warning of the generator risks at that point. Any switch at which the generator and the grid can be separated must switch all phases simultaneously (this is to reduce the risk of transient over-voltages or voltage unbalances adversely affecting other customers connected to the network). 5.1.1.2 Non-parallel operation Operating aspects for non-parallel (alternative) operation include: • • • • • • Inadvertent parallel connection cannot be made under any circumstances. Interlocks and suitable deliberate time delays are required between the closing and opening of the change-over circuit breakers. Provision of a fail-safe design so that one (1) circuit breaker cannot possibly be closed if the other circuit breaker in the change-over sequence is closed. Connection is to be made on the load side of metering equipment. Switchgear to allow manual or automatic changeover should be located on or adjacent to the switchboard supplying the electrical load. Where automatic switch-on and connection of the generator system is possible, suitable warning hazard notices shall be openly displayed at appropriate locations. PDI 5000 Copyright © Endeavour Energy 2011 Page 6 of 23 Protection of embedded generation systems 5.1.1.3 Amendment no.3 Standby operation (occasional parallel operation) This mode of operation has similar connection arrangements to the non-parallel scheme, with the exception that both the normal supply and generator supply may be connected for a short time in order to allow testing of the generator’s operation without interrupting the customer’s load. Typically, the generator is allowed to synchronise with the network before the network is disconnected so that the generator then supplies only the customer’s load. Usually, the conditions that apply to this arrangement are: • an assurance that the generator shall be used for standby supply only; • the generator will run only in parallel with Endeavour Energy’s network when switching the generator on and off for generator testing purposes; and, • the time period for operation in parallel with the network for any circumstance shall be no longer than 15 seconds. The 15 seconds time period includes: synchronising with the electrical network; closing the generator isolating device to the network at zero power import or export increasing the generator load to the desired test level; and, isolation from the network. The period for reconnection includes: synchronising the generator with the network; removing the generator load; and, disconnecting the generator. Other aspects of standby opration are: • The switching scheme must incorporate blocking to ensure that the generator does not attempt to energise a dead Endeavour Energy connection. • The installation must be approved before commissioning. • Switching times must be scheduled with System Operations. • The transfer process must not adversely affect the quality of the supply to other customers. 5.1.2 Generator control 5.1.2.1 Synchronising Automatic synchronising on to the network will be required: • • To connect a generator in parallel with the grid. To re-connect an isolated system to the network. Whenever such synchronising is required, in addition to meeting the generator’s own parameters, the settings shall be such as to maintain the voltages (transient and steady state) on the network at the point of connection within the normally accepted bounds for the voltage level concerned. Special conditions may be imposed at certain critical points of the network, and these will be advised on a case-by-case basis. The generator shall parallel with the grid without causing a voltage fluctuation at the network connection point greater than ± 5% of the prevailing voltage level at the NCP. PDI 5000 Copyright © Endeavour Energy 2011 Page 7 of 23 Protection of embedded generation systems 5.1.2.2 Amendment no.3 Frequency and load control The prime mover must be equipped with suitable speed and power controls to allow the plant to respond rapidly and without overshoot should the system frequency rise or fall, or a sudden change in load occur. 5.1.2.3 Power system frequency variation All plant shall operate with a nominal frequency of 50Hz. The main grid frequency may vary in the range of 49.8 Hz to 50.5 Hz and generators are expected to be able to operate safely over this range. Continued operation is also expected during system disturbances, when the frequency may go as low as 47.0 Hz or as high as 52.0 Hz for periods of 10 to 20 cycles. Safe operation can include controlled shut-down or continued operation under load, depending on the machine capability. 5.1.2.4 Voltage and reactive power control Automatic control equipment will be necessary to ensure that the voltage and power factor at the point of connection are within the limits required by Endeavour Energy’s connection agreements. In general, the Australian Standards on voltage and disturbance limits (AS 61000 series) apply. The generator must ensure a stable and well-damped response under all operating conditions within the designed range. Where two (2) or more generators are in close proximity to each other, appropriate control circuitry is required to ensure that the possibility of interaction between the machines causing deleterious impacts on the grid are minimised. The voltage control performance will be assessed on the basis that stable voltage control must be maintained following the most severe credible single contingency. 5.1.2.5 Voltage control on distribution systems There is a range of voltage variations that can exist on the network because of load variations, load rejection, short circuit or open-circuit faults. These may include: • Voltage dips, typical duration between 0.1 and 1 second [5 – 50 cycles] of random magnitude and on any one (1) or more phases simultaneously due to fault clearance. • Voltages may rise above the nominal voltage level on one or more phases under fault conditions. • Voltage variations due to tap-changer operations, variation of other customer loads, sudden load shifts due to switching. It is the responsibility of the generator operator to ensure the safe operation of the machine, and that any adverse effects of the generator on the grid are minimised under the conditions prevailing at the connection point. In particular, the generator operator must: • be satisfied that the fault clearance times are within the transient stability requirements of the machine; and, • ensure that the steady state output of the machine is stable for all expected operating conditions at the network connection point. 5.1.3 Islanding Islanding is an occurrence where a generator or generating system, that continues to supply electricity, is disconnected from the general electrical network. In this state, the embedded generator is potentially out of synchronisation with the grid. The electrical load being supplied by the generator may be only for itself or may include some of the Network Service Provider’s (Endeavour Energy) network. PDI 5000 Copyright © Endeavour Energy 2011 Page 8 of 23 Protection of embedded generation systems Amendment no.3 All reasonable precautions must be taken to prevent the intentional or unintentional islanding of private generation systems where there is a loss of supply from the network, unless special provisions have been negotiated within the Customer Connection Agreement. The generator may continue to supply the customer’s own plant downstream of the network connection point from local generation, but there must be no connection to the grid. Other issues to be considered include: • Islanding can cause potential quality of supply problems for other customers and the legal implications of acceptance of risk and liability must be resolved before providing isolated supply to other customers. • Automatic reclosing may be installed on network overhead lines. There could be a possibility of severe generator equipment damage if the network feeder is reclosed out of synchronism onto a live generator. • Anti-islanding protection must complete its operation in less than five (5) seconds, or less than half of the feeder reclose time, whichever is the less. • The reclose time delay varies for different parts of the network. • Faults on the network must be isolated from all sources of supply. 5.1.4 System earthing Earthing is required to be independent of the network. Satisfactory earthing is required to: • • Prevent electric shock. Cause protection equipment to operate when required. All earthing must meet all statutory requirements under all operating conditions. 5.1.4.1 HV system earthing System grounding (neutral grounding) refers solely to the method of power source grounding and not to the earthing of metal structures for personal safety. Earthing of the generator neutral must be coordinated with the network earthing. Network earthing may be solid or consist of neutral earthing resistors or reactors. The possible earth fault current will depend on the neutral earthing system used. Under some fault conditions, it may be possible for a portion of unearthed network to remain energised with no current flow at phase to ground fault. It is important that the protection system detects this condition and isolates the generator from the network. This is dealt with in more detail in section 5.1.5. If a generator is to continue operating on a network isolated from the grid, all relevant system and safety earthing criteria must be met, including but not limited to AS 3000. PDI 5000 Copyright © Endeavour Energy 2011 Page 9 of 23 Protection of embedded generation systems 5.1.4.2 Amendment no.3 LV system earthing For LV system neutral earthing, solid earthing principals should apply. If neutral earthing impedances are used to limit the generator earth fault currents, a generator transformer must be used to ensure compliance with all statutory and supply authority safety earthing requirements on the LV system for all operating scenarios. The neutral busbar must be continuously connected to the source of supply as well as being locally earthed. At all times, the provisions of the Wiring Rules and the Service and Installation Rules apply. 5.1.5 Operation of unearthed systems (loss of mains) The sensitivity of loss of mains protection depends on the relative mismatch between the generation capacity and the connected load if an islanding situation develops. It is essential that the generator’s protection equipment isolate the generator before a network reclose occurs, after a fault has caused the network protection to trip the mains supply. If the ratio of the generation capacity to the minimum load on the connecting feeder is greater than 70%, or if other protection such as rate of change of frequency (ROCOF) or vector shift protection is difficult to set, an inter-trip may be required in addition to the loss of mains protection. The generator’s operator is responsible for calculating and applying the loss of mains protection settings. The assumptions used to calculate the settings and the final settings are to be approved by Endeavour Energy before they are put into service. Set out below are the commonly accepted methods of addressing the issue of not allowing embedded generation to supply an unearthed network. 5.1.5.1 Neutral voltage displacement (NVD) In the case of the interconnecting ungrounded transformer (delta winding on the line side) at NCP, the voltage on the ungrounded systems will experience a voltage shift under a phase to earth fault condition and no fault current flows in the isolated unearthed portion of the network. One way to detect this condition is to connect a voltage sensing relay (59N) to three (3) VTs in a broken delta configuration. A 3-phase, 5-limb broken delta voltage transformer is typically installed on the delta winding side (line side) of the connected step up transformer. The earthed star point of the VT primary provides a reference point for the neutral and allows a zero phase sequence voltage to be generated on the broken delta secondary under earth fault conditions. During normal conditions, the voltage unbalance will be minimal and the zero sequence voltage will be minimal. When a phase to ground fault occurs, the faulted phase voltage collapses and the zero sequence voltage (3V0) across the voltage sensing device increases to as much as full secondary phase to ground voltage. Primary voltage increases as much as 1.73 x nominal line to ground voltage. Protection Design should consider the following:: • Faults on adjacent feeder(s) could cause the NVD protection relay to respond and pick up. Therefore, NVD settings should be graded with other earth-fault protection relays. • The NVD relay needs to be set with sufficient time delay in order to allow other feeder’s protection earth-fault relay(s) to clear their own feeder’s earth-fault first. For example time delay setting of the NVD relay in the 11kV systems should be greater than 2.0 secs PDI 5000 Copyright © Endeavour Energy 2011 Page 10 of 23 Protection of embedded generation systems Amendment no.3 in order to allow the other earth-fault relay(s) in the neighbouring circuits to clear the earth-fault. • Sustained arcing faults because of the generator supply infeed. • Change of reach on nearby distance relays. • Earth fault contribution needs to be calculated based on two (2) separate earthing systems. • Impact on other protection relays as a result of the sudden removal of the earth. 5.1.5.2 Reverse power or directional protection If the agreed maximum generation is at all times less than the total customer load, or there is no intention to export power onto the grid, reverse power or directional current protection can be used to detect a loss of mains condition. The criteria for deciding if this is possible are: • The export at the NCP has a defined maximum value, and if this value is exceeded, a loss of mains condition is assumed to have occurred and the generator is separated from the grid. • The export is less than 70% of the expected minimum feeder load, with all other generation included. 5.1.5.3 Inter-trip from feeder circuit breaker (CB) An alternative to indirect measurement of loss of mains is to use a direct inter-trip from Endeavour Energy’s CBs controlling the portion of the network to which the generator is connected. If stability analysis shows that the fault clearance time could cause instability of other generators or the network, inter-trip facilities (which ensure stability) will be necessary. The inter-trip circuit must be supervised automatically, and inhibit generation if the inter-trip is not available. 5.1.6 General technical requirements 5.1.6.1 Generator technical data Generator system operating characteristics such as PQ, voltage, ratings, lead and lag limits. Machine characteristics such as Xd, Xq, _ve and 0 sequence impedances, time constants, and inertia constant. Machine control characteristics such as droop, AVR, and governor. All relevant data is required for installation as set out in Annexure A1. 5.1.6.2 Fault levels Generators in parallel with the network may raise fault levels beyond the fault rating of existing installed equipment. Calculations may be required of the contribution of the generation plant to fault levels on the network in order to determine: • Contribution to fault levels by the generator. • The impact on neighbouring installations and customers. • The level of protection required as a result of changed fault levels. PDI 5000 Copyright © Endeavour Energy 2011 Page 11 of 23 Protection of embedded generation systems Amendment no.3 The customer will be responsible for all costs associated with: • The required system studies. • Upgrading protection facilities as a result of connection of generation that requires additional protection equipment at other points in the network. 5.1.6.3 Stability Synchronous generating units must operate in a stable manner at all times when connected to the network. Any generator unit connected to the grid should: • • • Disconnect from the grid for a power system disturbance that causes in unstable operation. Provide damping of the system oscillations. Maintain steady state voltage stability criteria. Endeavour Energy will provide information on the design criteria and all data related to the network necessary to carry out the stability and other system studies. The proponent of the scheme is responsible for the execution of all required system studies. Steady state and transient stability study should include: • The impact of embedded generations on the dynamics of a distribution feeder. • The impact of embedded generations on the dynamic of an entire bulk power system. • Effects on transient stability. • Impact on damping. • Effect on voltage stability. 5.1.7 Connection security standards All high voltage plants and apparatus shall comply with the relevant Australian Standard. Plant and apparatus shall be designed, manufactured and tested in accordance with the quality assurance requirements of Australian Standard AS/NZ ISO 9001. Each connection between a customer and the network must be controlled by a circuit breaker and related equipment capable of interrupting the short circuit current at the network connection point (NCP). For connection to sub-transmission voltages, the protection system may be required to be fully duplicated, and operate separate trip coils of each circuit breaker. The provisions of Endeavour Energy’s Substation Design Instructions and Protection Design Instructions apply in all cases. Details of the proposed protection arrangements, along with general technical information of the proposed generating plant, as mentioned in Annexures A1 and A2, must be submitted to Endeavour Energy by the customer to determine if additional protection is required in the interests of safe and stable operation of the network. . 5.1.8 Fault clearance times Fault clearance times (from fault inception to circuit breaker arc extinction) can vary depending on circuit breaker technology, age, and the system characteristics. The fault clearance times must be adequate to minimise equipment damage. In the case of the 132kV system, the fault clearance times, set out in the National Electricity Rules (NER) for both main protection and for breaker fail protection, must be achieved for all connected plants. PDI 5000 Copyright © Endeavour Energy 2011 Page 12 of 23 Protection of embedded generation systems Amendment no.3 If there are transient stability critical clearance time limits imposed by a generator, the cost of upgrading all protection systems in the affected area is the responsibility of the customer. 5.1.9 Protection requirements A generator should be automatically disconnected from the power system in response to abnormal conditions, including: • Loss of synchronism. • Sustained high or low frequency outside tolerance limits. • Voltage excursions beyond defined steady state limits. • Electrical fault on the network feeder. • Mechanical faults within the generator. • Power system disturbance that results in unstable operation. Normal operations of the network should not cause unnecessary tripping, and protective devices should not operate in cases of: • Switching of capacitor banks. • Faults on remote equipment. • Load swings (ensure adequate loss of mains protection settings). • Transformer automatic tap changing. • Other normal operating contingencies. The distribution system will usually carry short bursts of high frequency signalling for load control purposes. This is generally at 1050Hz or 750Hz or 283Hz and can typically have a magnitude of 2-3% of the system nominal voltage. Under abnormal (system resonance) conditions it may have excursions to 10% of nominal voltage. The generator protection and control systems must be able to cope in the presence of these signals. All protection associated with the generator and its connection to the grid must be designed with overlapping zones of protection to ensure that any fault is detected and cleared by at least one protective device. Circuit breaker failure protection must be provided at the NCP circuit breaker to cover the circuit breaker failing to operate when required. This circuit breaker failure protection must be arranged to isolate the generator from the grid to avoid the possibility of out-ofsynchronism operation. All generation plant connected to the 33kV or above sub-transmission network shall have at least two (2) schemes of protective equipment installed for each zone of protection. This includes provision of duplicate trip coils on the circuit breakers. All primary equipment shall have ratings suitable for the expected duty in the presence of the generation. This includes, but is not limited to, such things as ensuring adequate circuit breaker class for the system X/R, insulation coordination and power frequency voltage withstand capability. The settings of the protection equipment installed on a generating unit should: • • • • • Maximise plant availability. Protect the grid and other customer plant from damage. Assist the control of the power system under emergency conditions. Minimise the risk of inadvertent disconnection. Promote plant safety and durability. PDI 5000 Copyright © Endeavour Energy 2011 Page 13 of 23 Protection of embedded generation systems 5.1.9.1 Amendment no.3 Internal protection This covers generator and transformer faults as well as any other equipment within the generating plant. It is the responsibility of the customer to ensure that adequate protection is installed for their own equipment. Any protection scheme installed downstream of the network connection point does not need to be graded with Endeavour Energy’s protection systems, except as required by regulation. The following factors should be considered in the design of the generator protection schemes: • Each generator shall have protection installed that will operate within a minimum time having regard for network performance, stability and grading requirements. • Generator protection must cover permanent and transient faults under all permutations of phase and ground short-circuit. • Each generator must have protection to trip the generator and, where appropriate, shut down the excitation and the prime mover. • The protection should operate for all electrical or mechanical faults within the generator, transformer and prime mover. • Where a number of generators are operating in parallel, each machine should be equipped with reverse power protection to prevent motoring. In order to provide adequate protection of the generator, the following protection is considered as minimum: • Earth fault • Overcurrent • Over/under voltage • Under/over frequency • Negative phase sequence • Reverse power • Generator and/or transformer differential • Field failure protection (reverse VAR) • Pole slip (out of step) • Transformer protection – winding gas • Synchronism check • Circuit breaker fail 5.1.9.2 External or interconnection protection This includes the protection installed on the circuit breaker that interfaces the customer with Endeavour Energy’s network and has the potential to impact on power system security. The protection must operate before any automatic reclose operation can occur. The protection at the network connection point must grade satisfactorily with Endeavour Energy’s protection schemes, so that any fault internal to the customer’s plant will be cleared below or at the network connection point before any Endeavour Energy protection operates. The grading at the network connection point will be checked by Endeavour Energy and must be approved in terms of the customer connection process before operation commences. PDI 5000 Copyright © Endeavour Energy 2011 Page 14 of 23 Protection of embedded generation systems Amendment no.3 Protection arrangements and settings will depend on the individual installation and local requirement. The basic requirements must include the detection of: • Over and under voltage • Over and under frequency • Phase fault • Earth fault • Loss of mains • Battery under voltage • Circuit breaker fail The following loss of mains protective functions are considered as typical requirements: Negative phase sequence (46N) Neutral voltage displacement (59N) Rate of change of frequency (81) Voltage vector surge (96) Directional overcurrent (67) Reverse power (46) Intertrip 5.1.10 Auto-reclose 5.1.10.1 Generator reclose Generators connected to the 11kV and 22 kV (distribution) networks may use synchronising facilities to automatically reconnect the generation plant following a system disturbance no earlier than 60 seconds after the main supply is restored. Generators connected to the sub-transmission network may be reconnected only with agreement from Endeavour Energy system operators, or as negotiated in the Connection Agreement. Generator reclose is not allowed on to a dead feeder, except where there is an agreement for islanding. 5.1.10.2 Network auto-reclose Endeavour Energy’s network provides automatic reclosing function on all of its overhead lines so that if a protection relay trips the line as the result of a fault, the circuit breaker will automatically close after a defined time delay. This delay time can vary for different parts of the network. The embedded generator must be disconnected from the network before any auto-reclose takes place. 5.1.11 Installation maintenance All protection equipment associated with the generator must be: • • Tested and verified on site prior to connection to the network. Tested at least once every three (3) years, or as specified by the Customer Connection Agreement. Settings of the protection relays and control equipment or associated wiring must not be altered unless written authorisation is received from the Network Service Provider (Endeavour Energy). PDI 5000 Copyright © Endeavour Energy 2011 Page 15 of 23 Protection of embedded generation systems Amendment no.3 Protection equipment must comply with the relevant parts of IEC 60255 or equivalent. 5.1.12 Remote monitoring and control Remote monitoring and control equipment is required for remote operational purposes, intertripping, load or voltage control. This requirement will be negotiated for each situation, as any such requirements depend on the relative capacities of the generator and grid at the connection point. A Supervisory Control and Data Acquisition (SCADA) system is the preferred method of providing control and monitoring functions. A communication media between the generator premises and Endeavour Energy’s control centre is required in order to send and receive data. If remote inter-tripping is required to Endeavour Energy’s installation, the preferred option is for a dedicated optical fibre link. Alternatives include a dedicated copper wire link and UHF radio or, if no other option is practical, a leased telecommunications circuit. The reliability of leased links can be very poor. Generation may be inhibited while the link is out of service, but supply of load to the customer’s installation will not be interrupted. A list of signals that are to be sent and received via SCADA systems must be negotiated with Endeavour Energy. The signals include but tot limited to the following: • • • • • Status Indications of all relevant generator and feeder circuit breakers. Analogue indication of 3-phase Amps, volts, kW and kVAr. Feeder CB fail to trip alarm. Protection operation alarms as agreed. Low battery/battery warning alarms. The generator must also provide the following: • A suitable remote terminal unit compatible with Endeavour Energy’s SCADA system. At present only the ABB RTUs are used in Endeavour Energy's system. • Confirmation that a communication path is readily available for SCADA. • SCADA equipment in accordance with SDI 538. • SCADA equipment may have to comply with IEC 61850. • Communications equipment installed in accordance with SDI 519. • Wiring connection schedule for the RTU to allow the software to be developed for the master station and the RTU. • Software development for the RTU and the master station. • Testing and commissioning of above. In addition to the above requirements, if a generator is scheduled in terms of the National Electricity Rules, additional remote control and monitoring equipment must be installed, if required by AEMO, on each scheduled generating unit in accordance with the rules. The specific requirements for scheduled generators and rules compliance are covered in Endeavour Energy’s customer connection guidelines. PDI 5000 Copyright © Endeavour Energy 2011 Page 16 of 23 Protection of embedded generation systems 6.0 Amendment no.3 AUTHORITIES AND RESPONSIBILITIES It is the responsibility of all protection engineers/protection specialists to be familiar with the contents of this Standard. 7.0 DOCUMENT CONTROL Documentation content coordinator: Network Protection & Control Manager Documentation process coordinator: Branch Process Coordinator PDI 5000 Copyright © Endeavour Energy 2011 Page 17 of 23 Protection of embedded generation systems Amendment no.3 Annexure A1 Generator characteristic data (for all rotating machines) Rotating frequency: (rpm) Neutral grounding resistor (if applicable): Additional information for synchronous generating units Synchronous reactance (PU): Xd Synchronous reactance (PU): Xq Transient reactance (PU): X’d Transient reactance (PU): X’q: Subtransient reactance (PU): X”d Subtransient reactance (PU): X”q Neg sequence reactance (PU): X2 Zero sequence reactance (PU): Xo KVA base: Field voltage: (Volts) Field current: (Amps) Additional information for synchronous machines: Electrical data for transient studies (armature R, time constants) AVR data (if applicable) Governor data (if applicable) Additional information for induction generating units Rotor resistance, Rr: Stator resistance, Rs: Rotor reactance, Xr: Stator reactance, Xs: Magnetising reactance, Xm: Short circuit reactance, Xd”: Exciting current: temperature rise: Frame size: Total rotating inertia, H: per unit on KVA base: Reactive power required in vars (no load): Reactive power required in vars (full load): Additional information for induction generating units that are started by motoring: Motoring power: (kW) Transformer data (if applicable, for customer-owned transformer): Will a transformer be used between the generator and the point of interconnection? Yes/No Will the transformer be provided by customer? Yes/No Nameplate rating: (kVA) Single or three (3) phase Transformer impedance on kVA base: (%) Vector group: Transformer primary: (Volts) Transformer secondary: (Volts) Transformer fuse data (if applicable, for customer-owned fuse): PDI 5000 Copyright © Endeavour Energy 2011 Page 18 of 23 Protection of embedded generation systems Amendment no.3 (Attach copy of fuse manufacturer’s minimum melt and total clearing time-current curves) Manufacturer: Type: Size: Class/speed: Interconnecting circuit breaker: Manufacturer: Type: Load rating: Interrupting fating: Trip settings: Protection current transformer data: (Enclose copy of manufacturer’s excitation and ratio correction curves) Manufacturer (HV): Type: Class and accuracy: Manufacturer: (LV) Type: Class and accuracy: Potential transformer data: Manufacturer (HV): Type: Accuracy class: Manufacturer (LV): Type: Accuracy class: Interconnection protective relays: (If microprocessor-controlled) List of functions and adjustable setpoints for the protective equipment or software: Function 1. 2. 3. 4. 5. 6. PDI 5000 Setpoint Minimum Copyright © Endeavour Energy 2011 Maximum Page 19 of 23 Protection of embedded generation systems Amendment no.3 Annexure A2 General technical detail • A copy of plant electrical single line diagram (SLD) showing the configuration of all generating facility equipment, current and potential transformers, and protection and control elements and all other relevant power system elements up to the network connection point. • A copy of any applicable site documentation that indicates the precise physical location of the proposed generating facility. • Proposed location of protective interface equipment on property. • A copy of any applicable documentation that describes and sets out in detail the operation of the protection and control schemes. • A copy of applicable schematic drawings showing philosophy of protection and control circuits relating to the network connection, including relay current circuits, relay potential circuits, and alarm/monitoring circuits (if applicable). • Any other information pertinent to this installation. PDI 5000 Copyright © Endeavour Energy 2011 Page 20 of 23 Protection of embedded generation systems Amendment no.3 Annexure A3 Additional points, general comments, typical settings and other information Rate of Change of Frequency (ROCOF): typically 0.4Hz / sec, 0.5 sec trip time (this high level is specified to ensure minimum spurious tripping). Vector shift: Typically 6 degrees, 0.5 sec trip time (it is susceptible to spurious tripping due to grid disturbances). Neutral voltage displacement (NVD) settings: NVD plug = 30%; NVD Time delay > earthfault clearance time of other earth-fault protection relay(s) in the connected network. Typical examples of interconnection protection requirements Following are five (5) cases of generation connections and the typical examples of the protection requirements. The factors that define which case applies are: • Generation site capacity. • Generator type. Interconnection protection, case 1 • All types of generator • The maximum cumulative export capacity is less than half the minimum distribution line (or captive) load • the maximum export capacity is less than 5MW. Protection required: • Overcurrent and earthfault • Under and over voltage • Under and over frequency • Three phase vector shift, subject to generator preference (optional). Interconnection Protection, case 2 All types of generator The maximum cumulative export capacity is less than 0.8 times the minimum captive load, and the maximum export capacity is less than 5MW. Protection Required Overcurrent and earthfault Under and over voltage Under and over frequency 3 phase vector shift Optional True ROCOF may be used as well as vector shift. True ROCOF detects the islanded condition rather than the onset of islanding. Some ROCOF relays may also be sensitive to an initial change in voltage vector. Interconnection protection, case 3 All types of generator except mains excited generators defined in case 5. PDI 5000 Copyright © Endeavour Energy 2011 Page 21 of 23 Protection of embedded generation systems Amendment no.3 The maximum cumulative generation export capacity is greater than 0.8 times the minimum captive load, such that load/generator balance is possible, and the maximum export capacity is less than 5 MW. Protection required Overcurrent and earthfault Under and over voltage Under and over frequency 3 phase vector shift, Rate of Change of Frequency (ROCOF) Neutral Voltage Displacement (NVD) Dead line check Interconnection protection, case 4 (1) All types of generator The maximum export capacity of an embedded generation site is greater than 5 MW. It is preferred that the embedded generator is connected directly to the primary bus rather than teed into an HV distribution feeder. Protection required Overcurrent and earthfault Under and over voltage Under and over frequency Intertripping from primary bus intake Parallel earthing or NVD protection Interconnection protection, Case 4 (2) If the Embedded Generator is teed into a distribution feeder, the following is also required: • Intertripping from the feeder breaker, or fault throwing or reverse VAR protection, where applicable. • Generators larger than 5 MW will be encouraged to obtain more secure connections. For large generators remote from the primary bus, adequate security may be achieved only by double circuit connection to the primary bus. Interconnection protection, Case 5 (1) Mains excited asynchronous (induction) generator with local power factor correction less than the reactive power demand, or a line commutated inverter. The network/circuit capacitance is not sufficient to self excite the generator. The maximum cumulative connected generation export capacity is greater than 0.8 times the minimum captive load. No synchronous generation or self-excited generation are connected. Protection required Overcurrent and earthfault Under and over voltage Under and over frequency 3-phase vector shift The total generation connected to a primary substation using the vector shift method for loss of mains protection, shall not exceed 20MW. The general requirements are covered with synchronous machines in cases 1-4. PDI 5000 Copyright © Endeavour Energy 2011 Page 22 of 23 Protection of embedded generation systems Amendment no.3 Inverters commonly include proprietary protection methods, including ROCOF. However, it is the responsibility of the generating company to demonstrate that the protection meets acceptable levels of dependability and reliability. PDI 5000 Copyright © Endeavour Energy 2011 Page 23 of 23