Document Reference: Version: 1.0 CLNR-L209 Date of Issue: December 2014 1 Technical recommendation for the purchase of Enhanced Automatic Voltage Control for HV systems 1. Purpose The purpose of this document is to set out and describe the technical requirements developed, that enabled the purchase of the various Enhanced Automatic Voltage Control schemes applied on the Northern Powergrid High Voltage power distribution networks that were trialled on the Customer-Led Network Revolution project. 2. Scope This recommendation details the technical requirements for all equipment to be used in the enhanced automatic control of voltage at High Voltage networks. The document applies to: Primary transformers that have a primary winding operating at Extra High Voltage (greater than 30 kV but less than 100 kV); and their secondary windings at High Voltage (greater than 1 kV but less than 30 kV); HV Switched capacitor banks i.e. greater than 1kV but less than 30kV; HV in-line voltage regulators The document applies to all equipment involved in the control of an OLTC, switched capacitor bank or in-line voltage regulator including its ability to accept communication links with external systems. This recommendation includes the interfacing requirements with a remote controller called the Grand Unified Scheme (GUS) as part of the Customer-Led Network Revolution (CLNR) project. The use of the EAVC in the CLNR project is to demonstrate its interaction with other smart grid solutions and control of the network voltage. A summary table of the supplier/product technical compliance is given in Appendix 1 - 6 for manufacturers to complete, detailing specifics about their offers and any variations from this standard. Manufacturers are encouraged to offer more than one option if they have a number of possible solutions to the overall functionality of the EAVC scheme. The Technical Requirements detailed in the main body of this document are designed to be functionally generic, so that other possible solutions are not over looked. Additional site specific data will be discussed with the potential supplier. Copyright Northern Powergrid (Northeast) Limited, Northern Powergrid (Yorkshire) Plc, 2014 Document Reference: Version: 1.0 CLNR-L209 Date of Issue: December 2014 2 Contents 1. PURPOSE ............................................................................................................................................................... 1 2. SCOPE .................................................................................................................................................................... 1 2.1 2.2 3. CONTENTS...................................................................................................................................................................2 COMPONENTS ..............................................................................................................................................................4 TECHNICAL REQUIREMENTS.............................................................................................................................. 5 3.1 GENERAL REQUIREMENTS...............................................................................................................................................5 3.1.1 Service Conditions ............................................................................................................................................5 3.1.1.1 3.1.1.2 3.1.1.3 3.1.1.4 3.1.1.5 3.1.1.6 Indoors ...........................................................................................................................................................................5 Outdoors ........................................................................................................................................................................5 Degrees of Protection ....................................................................................................................................................5 Marking and Labelling....................................................................................................................................................6 Small Wiring and Terminal Blocks ..................................................................................................................................6 Equipment Location .......................................................................................................................................................7 3.2 OPERATING CHARACTERISTICS .........................................................................................................................................7 3.2.1 Essential inputs ................................................................................................................................................7 3.2.2 Desirable but not Essential Inputs ....................................................................................................................8 3.2.3 Essential Outputs .............................................................................................................................................8 3.2.4 Desirable but not Essential Outputs .................................................................................................................9 3.2.5 GUS Inputs .......................................................................................................................................................9 3.2.6 Essential Functionality .....................................................................................................................................9 3.2.7 Desirable but no Essential Functionality ........................................................................................................12 3.3 COMMUNICATIONS .....................................................................................................................................................12 3.3.1 Electromagnetic Compatibility .......................................................................................................................13 3.4 OPERATING ENVIRONMENT ..........................................................................................................................................13 3.4.1 Local Controllers ............................................................................................................................................14 3.5 INSTALLATION, OPERATION AND MAINTENANCE ...............................................................................................................14 3.5.1 Installation .....................................................................................................................................................14 3.5.2 Indicators .......................................................................................................................................................15 3.5.3 Alarms ............................................................................................................................................................15 3.5.4 Earthing of Enclosure Cubicles .......................................................................................................................15 3.5.4.1 Earthing of Small Apparatus and Equipment ...............................................................................................................16 3.5.5 Maintenance ..................................................................................................................................................16 3.6 TRAINING REQUIREMENTS ............................................................................................................................................16 3.6.1 OLTC at Primary Substations..........................................................................................................................16 3.6.2 Switched Capacitor Bank ...............................................................................................................................16 3.6.3 In-line Regulator ............................................................................................................................................16 3.7 SUPPORT AND DEVELOPMENT REQUIREMENTS .................................................................................................................16 4. WEEE REGULATIONS ......................................................................................................................................... 17 5. REFERENCES ...................................................................................................................................................... 17 5.1 5.2 5.3 6. EXTERNAL DOCUMENTATION ........................................................................................................................................17 INTERNAL DOCUMENTATION .........................................................................................................................................18 SUMMARY OF AMENDMENTS ........................................................................................................................................19 DEFINITIONS........................................................................................................................................................ 20 APPENDIX 1A – SCHEDULE OF SUPPLIERS TECHNICAL DATA .......................................................................... 20 APPENDIX 1B – SCHEDULE OF SUPPLIERS TECHNICAL DATA – LOCAL CONTROLLER ................................ 22 APPENDIX 1C – SCHEDULE OF SUPPLIERS TECHNICAL DATA – EAVC ANCILLARY EQUIPMENT ................ 24 APPENDIX 1D – SCHEDULE OF SUPPLIERS TECHNICAL DATA – COMPLIANCE WITH SPECIFICATION ....... 25 Copyright Northern Powergrid (Northeast) Limited, Northern Powergrid (Yorkshire) Plc, 2014 Document Reference: Version: 1.0 CLNR-L209 Date of Issue: December 2014 3 APPENDIX 2A – SELF CERTIFICATION CONFORMANCE DECLARATION – TABLES 1-9 OF THIS SPECIFICATION .......................................................................................................................................................... 26 APPENDIX 2B – SELF CERTIFICATION CONFORMANCE DECLARATION ........................................................... 28 APPENDIX 2C – ENA TS 50-18 TYPE TEST SELF CERTIFICATION CONFORMANCE DECLARATION .............. 31 APPENDIX 3 – ADDENDUM TO SUPPLIER REQUIREMENTS................................................................................. 36 APPENDIX 4 – PRE-COMMISSION TESTING, ROUTINE INSPECTION AND MAINTENANCE REQUIREMENTS ......................................................................................................................................................... 37 APPENDIX 5 – TECHNICAL INFORMATION CHECK LIST ....................................................................................... 38 APPENDIX 6 – SCHEDULE OF COMPONENTS ........................................................................................................ 39 Copyright Northern Powergrid (Northeast) Limited, Northern Powergrid (Yorkshire) Plc, 2014 Document Reference: Version: 1.0 CLNR-L209 Date of Issue: December 2014 4 2.1 Components 1 2 3 4 5 6 7 8 9 10 11 12 Figure 1 - Components of an EAVC Scheme 19” Rack Cabinet Local Controller Communications Link Manual/Auto Switch Supervisory/Remote Switch GUS/Remote switch Tap Up button Tap Down button Test Block Static Over Voltage Relay Reset Button Fuses Copyright Northern Powergrid (Northeast) Limited, Northern Powergrid (Yorkshire) Plc, 2014 Document Reference: Version: 1.0 CLNR-L209 Date of Issue: December 2014 5 3. Technical Requirements This section gives the technical requirements of the EAVC scheme installed on HV networks. The recommendation illustrates the scope and accuracy required, however if manufacturers can offer other cost effective solutions that deliver the same outcomes by other means these should be considered. Manufacturers should detail additional functions, highlight any savings or justify the additional expenditure. The following schemes’ components and their properties are illustrated in the following Tables: Table 1 illustrates the essential inputs of the local controller Table 2 illustrates the desirable but not essential inputs of the local controller. Table 3 illustrates the local controller’s data outputs. Table 4 illustrates the local controller’s desirable but not essential data outputs. Table 5 illustrates the expected inputs from the GUS Table 6 illustrates the local controller’s essential functionality Table 7 illustrates the essential functionality of the other EAVC components. Table 8 illustrates the local controller’s desirable but not essential functionality. Table 9 illustrates the operating environment for the Local controller If manufacturers cannot meet a specification, they should indicate how close to the requirement they can achieve. Various systems, with which the EAVC solution may need to interact, may develop over the next few years with various possible approaches. It is therefore attractive that a solution is flexible and can integrate with a range of other technologies and software platforms. 3.1 General Requirements The individual components and mounting cubicles detailed in clause 2.2 should be designed and tested to be compliant with ENA TS 50-18 except where detailed separately within the body of this recommendation. 3.1.1 Service Conditions The EAVC scheme will use equipment designed for use in both indoor and outdoor environments. 3.1.1.1 Indoors Typically a brick built housing; this will provide protection from the direct effects of most elements of the weather, but is not usually temperature maintained, or climate controlled. Indoor units should be capable of continued operation whilst exposed to ambient temperatures with a minimum of -5°C. 3.1.1.2 Outdoors Open to the direct effects of all-weather elements and climatic effects. Outdoor units should be capable of continued operation whilst exposed to ambient temperatures with a range of -25°C to 55° (to allow for the effect of solar radiation on the equipment). Any equipment intended for external operation shall be UV stable with testing carried out in accordance with BS 2782-5:Method 552A:1999. 3.1.1.3 Degrees of Protection All equipment used by the EAVC should be compliant with ENA TS 50-18 clause 4.2.2 and be environmentally tested to the following minima: Copyright Northern Powergrid (Northeast) Limited, Northern Powergrid (Yorkshire) Plc, 2014 Document Reference: CLNR-L209 Version: 1.0 Date of Issue: December 2014 6 IP31 rating for indoor equipment; IP54 rating for outdoor equipment All IP ratings are in accordance with BSEN 60529. 3.1.1.4 Marking and Labelling The EAVC enclosures should be marked in accordance with clause 5.10 of IEC 62771-1. All equipment and apparatus should be labelled in accordance with clause 5.4.4.4 of IEC 62271-1 and the following: Labels should be provided where instruction, explanations or warning are appropriate to the operation or maintenance of the equipment. Circuit identification labels, secured with screw fixings, should be provided on the front of the EAVC door and at the back where rear access is provided. Where identification labels are fixed to doors an identical label should be provided internally on the fixed portion, at a point that is clearly visible. Safety warning labels should comply with BS ISO 3864-1:2011. All labels should be suitably rated for the environment conditions and last the lifetime of the equipment to which they apply. The function and rating of fuses and MCB’s should be marked adjacent to the device. All identification markings should be unambiguously associated with the relevant equipment and should be clearly visible from normal viewing angles of the equipment. Equipment wire end terminations should be identified using permanent Alpha-Numeric local end marking. All wiring within the enclosure should be fully compliant with ENA TS 50-19. 3.1.1.5 Small Wiring and Terminal Blocks All small wiring should comply with Clause 5.4.4.5.1 of IEC 62271-1 and ENA TS 50-18 issue 3, clause 5.1 with the following exceptions: CT and VT Wiring DC Wiring AC Wiring (110V) AC Wiring (240V) Pilot Wiring - Phase Colour (Red, Yellow, Blue and Black) Grey Black Black (Double Insulated) Black (5kV Insulated up to 66kV and 15kV over 66kV) Small wiring cable should be single core multi-stranded, copper conductor, PVC insulated and compliant with BS 6231. In the interest of mechanical strength, the nominal minimum conductor size shall be 1.5mm² for applications e.g. SCADA, where smaller sizes are appropriate, their use should be the subject to agreement with the project engineer. Current transformer secondary connections should have a minimum conductor cross sectional area of 2.5mm² Terminal blocks and terminations should comply with the relevant provisions detailed in IEC 622711 clause 5.4.4.5.2, BSEN 60947-7-1 and ENA TS 50-18 issue 3 clause 5.2.1 and 5.2.2. They should generally be either screw or stud type for use with an approved ring type crimped termination or spring loaded insertion type incorporating an approved hook type crimped connector. Telecontrol / SCADA Terminal Blocks 1.5mm SAKR or equivalent AC/DC Terminal Blocks 2.5mm RSF3 or equivalent CT/VT Terminal Blocks 6.0mm RSF1 or equivalent Buswiring and Supply Terminal Blocks (J1/J2) 6.0mm RSF1 or equivalent Copyright Northern Powergrid (Northeast) Limited, Northern Powergrid (Yorkshire) Plc, 2014 Document Reference: Version: 1.0 CLNR-L209 Date of Issue: December 2014 7 All terminal blocks should be grouped on the terminal rails in the above order from the top of the rail to the bottom. Bus wiring terminal blocks should be located at the top of the panel and labelled accordingly. 3.1.1.6 Equipment Location The required components of an EAVC scheme are listed below with their locations and associated product specifications where available. Measurement Devices – Outdoor (Metering/protection Voltage Transformer (VT) to Northern Powergrid Specification - NPS/003/001 and Current Transformer (CT) to Northern Powergrid Specification -NPS/003/023 – used as part of the essential inputs of the local controller, however the monitoring devices are not part of the scope of this document; Actuators – Outdoor/indoor – used as part of the essential inputs and outputs of the local controller’s input and output signals, however the actuators are not part of the scope of this document; Local Controllers – Indoor (sub-station’s control room); Communications - Indoor and Outdoor according to requirements. Substation Where appropriate, equipment should be located in a substation fitting into a standard 19” rack. 3.2 Operating Characteristics The measurement devices are either, the equipment’s integral VT and CTs or the metering/protection VT and CTs already installed as part of the substation metering and protection systems. The measurement devices should be able to measure and output data to the recommendation given in Table 1 to Table 4. Note: For a switched capacitor bank with 3 capacitors (A, B & C), the local controller should only be able to connect one capacitor to the network at a time; therefore the switched capacitor bank will have 4 switching position maps that the local controller will need to replicate in response to a change of voltage request: 1. A – off, B – off, C – off; 2. A – on, B – off, C – off; 3. A – off, B – on, C – off; 4. A – off, B – off, C – on. 3.2.1 Essential inputs Table 1 Local Controller Essential Input Signals Type Sending Device Type Other Voltage VT Class ‘S’ or better as specified in IEC 61000-4-30 The local controller shall be capable of operating with VTs with outputs of between 63.5 and 250V. Current CT Class ‘S’ or better as specified in IEC 61000-4-30 The local controller shall be capable of operating with CTs of 1 or 5A secondary rating. The local controller shall be able to accept non-standard CT ratios to be used through configurable inputs. Copyright Northern Powergrid (Northeast) Limited, Northern Powergrid (Yorkshire) Plc, 2014 Document Reference: CLNR-L209 Version: 1.0 Date of Issue: December 2014 Tap or Switch Position OLTC / Capacitor Bank Voltage Signal / Data Communications 8 OLTC –The local controller shall be capable of measuring up to a minimum of 39 tap positions (for distribution OLTC) and 12 tap positions (for in-line regulator OLTC) using Resistor Chain, Binary, Binary Coded Decimal or Grey Code sender units. Capacitor Bank –The local controller shall be capable of detecting the switch configuration of the capacitor bank. Voltage reduction SCADA Data Communications Voltage Setpoint GUS Data Communications Supervisory/Remote Supervisory/Remote Switch Voltage Signal GUS/Remote GUS/Remote Switch Voltage Signal Manual/Auto Manual/Auto Switch Voltage Signal Tap or Raise Up Tap/Raise Up button Voltage Signal Tap or Lower Down Tap/Lower Down button Voltage Signal 3.2.2 The local controller shall be able to accept a signal from a SCADA RTU to reduce the system voltage in compliance with the voltage reduction scheme. The Manufacturer is required to detail, how the local controller will alter its setpoint from a signal received over a communications link. Manual two position switch that selects ‘Supervisory’ or ‘Remote’ Mode. Supervisory will enable the local controller to work in automatic mode but send and receive communications from SCADA. Remote enables the local controller to operate automatically and blocks all communications to SCADA. Manual two position switch that selects ‘GUS’ or ‘Remote’ mode. GUS enables the local controller to operate automatically and accept its setpoint via a communications link. Remote enables the local controller to operate automatically and block all communications to the ‘GUS’. Manual two position switch that selects ‘Manual’ or ‘Automatic’ Mode The ‘Tap/ Up’ / ’Raise volts’ button shall only be operable if the Manual/Auto switch is in the Manual’ position. The ‘Tap/ Down’ / ’Lower volts’ button shall only be operable if the Manual/Auto switch is in the ‘Manual’ position. Desirable but not Essential Inputs Table 2 Local Controller Desirable Input Signals Type Sending Device Type Other Feeder Current Feeder metering position Class ‘S’ or better as specified in IEC 61000-4-30 To help estimate the amount of distributed generation on each feeder. 3.2.3 Essential Outputs Below is a list of the minimum outputs that the local controller should be capable of sending to another device, these may be calculated or measured directly. Copyright Northern Powergrid (Northeast) Limited, Northern Powergrid (Yorkshire) Plc, 2014 Document Reference: CLNR-L209 Version: 1.0 Date of Issue: December 2014 9 Table 3 Local Controller Desirable Input Signals Type Tap Up/Raise Volts To Type Other OLTC/Capacitor Bank Voltage signal/ Data signal Raises the secondary voltage by tapping the OLTC up one tap/switched the capacitor bank accordingly to raise the network voltage. Tap Down/Lower Volts OLTC/Capacitor Bank Voltage signal/ Data signal Lowers the secondary voltage by tapping the OLTC down one tap/ switched the capacitor bank accordingly to lower the network voltage. Block Internal None Stops “tap runaway” by blocking all tap/switching operations Alarms User Interface, The GUS, SCADA Voltage signal/ Data signal Secondary Voltage The GUS Data Signal Secondary Current The GUS Data Signal 3.2.4 Desirable but not Essential Outputs Table 4 lists the outputs that are desirable to be sent to a remote position but not essential. Table 4 Desirable Data Outputs Type To Type Estimated Generation The GUS Data Signal 3.2.5 Other GUS Inputs Table 5 is a list of the inputs that the system should be able to receive. Table 5 Expected Signals from GUS Type To Type Frequency Handshake/Heartbeat Local Controller Data 1 minute Setpoint check/Change Local Controller Data 1 minute 3.2.6 Essential Functionality Table 6 Local controller Essential Functionality The local controller should be of the solid state/microprocesor type and have a true RMS measuring circuit supplied from a nominal 110V AC VT supply. Copyright Northern Powergrid (Northeast) Limited, Northern Powergrid (Yorkshire) Plc, 2014 Document Reference: Version: 1.0 CLNR-L209 Date of Issue: December 2014 10 Essential Inputs Description Function VT Monitoring The VT is constantly monitored and its ratio errors shall be considered and eliminated with adjustment. CT Monitoring The CT is constantly monitored and shall not be dependent on its connected phase for its compatibility. Control Outputs Description Function Raise signal Determine that a tap operation/raise in voltage is required and send a signal to the OLTC to tap up/to the capacitor bank to switch accordingly. Lower signal Determine that a tap operation/lowering in voltage is required and send a signal to the OLTC to tap down/to the capacitor bank to switch accordingly. Status Checks Description Function Auxiliary Voltage 110v panel auxiliary supply monitor. Line Voltage The local controller shall provide a permanent display of the primary line voltage in kV to one decimal place (This can be provided discreet or integral to the controller). Metering The local controller shall provide a selectable digital display of power factor to two decimal places, and three phase balanced power using three voltages and one current input. Tap Lock Prevents “tap runaway” by disabling the local controller from performing any tap change/switch operations. Tap Change Master Operated from the runaway protection which must require to be reset by hand before further operations can be carried out. Indication of operation shall be provided. The runaway Lock Out Feature prevention scheme shall also prevent runaway in the event of a raise contactor sticking in. Tap/Switch Position The local controller shall be able to determine the Tap position/capacitor bank switch configuration and permanently display it with a collection of suitable indicators; this may be provided discreet or integral to the controller. The indicators shall be suitably labelled to avoid any ambiguity. Additionally the system shall provide a tap change in progress indication lamp. OLTC/Capacitor Bank There shall be a tap change/capacitor bank variable that is incremented each time the operation OLTC/capacitor back is operated. Self-supervision Signal The local controller shall constantly monitor itself for correct operation and any error shall be sent as an alarm and an indicator on the user interface. Overcurrent Blocking Stops any operation if excessive load is detected. Overvoltage Blocking Prevents ‘Tap Up’ operations if a pre-set value is or will be breached by the tap/switching operation. ‘Tap Down’ operations are not blocked. Undervoltage Blocking Prevents ‘Tap Down’ operations if a pre-set value is or will be breached by the tap/switching operation. ‘Tap Up’ operations are not blocked. Locking Policy Operating switches shall accept a safety locking policy requirement. Tap Freeze Function A ‘Tap Freeze’ switch to be implemented whilst retaining relay power. When turning to Manual Mode a notification shall be displayed to communicate the ‘tap freeze’ status. External Inputs Description Function Manual Mode Determines the setting of the Manual/Auto switch and when selected to ‘Manual’ only tap operations via the ‘Tap Up’/’Raise Volts’, ‘Tap Down’/’Lower Volts’ buttons on the 19 inch rack cabinet will be carried out. Automatic Mode Determines the setting of the Manual/Auto switch and when selected to ‘Auto’ only automatic tap operations via the local controller will be carried out. The ‘Tap Up’/’Raise Volts’, ‘Tap Down’/’Lower Volts’ buttons on the 19 inch rack cabinet will be disabled. Copyright Northern Powergrid (Northeast) Limited, Northern Powergrid (Yorkshire) Plc, 2014 Document Reference: CLNR-L209 Version: 1.0 Date of Issue: December 2014 11 Supervisory Mode Allows SCADA to monitor the local controller and apply the voltage reduction scheme when required. This mode shall also provide the ability to take the voltage controller between Auto / Manual mode via the SCADA control providing a ‘Tap Freeze’ function. Reduce set voltage (-3% -6%) The ‘Grid Code’ voltage reduction will instantly drop the current voltage by 3 or 6 percent. The local controller will be restricted from compensating for the reduction. Additionally, for OLTC, a facility shall be provided to remotely bring either transformer to unity power factor. External Functions Accept a setpoint over a communications link. Hold a default setpoint. Load Drop Compensation (LDC) – equation that calculates the theoretical voltage drop along a circuit with a known load. Must be available, with a variable range of at least 0 – 10%. The CT rating for LDC input shall be user selectable for either 1A or 5A and have a continuous rating of 1.3 times nominal. Mode 1 – Calculate the target Voltage from the default setpoint using Load Drop Compensation, a method of reducing circulating current and whether there has been any voltage reduction applied by the control room. Mode 2 – Calculate the target Voltage from the setpoint via a communications link without using Load Drop Compensation; but applying a method of reducing circulating current and whether there has been any voltage reduction applied by the control room. Detect the handshake/heartbeat from the GUS and automatically switch between modes 1 and 2 depending on its presence: Mode 1 = No handshake/heartbeat Mode 2 = Handshake/heartbeat present Runaway Protection – Initiates a tap change master lock out to prevent tap runaway. Once operated it shall only be reset by hand operation. Time Delay 1 – operates once the voltage goes outside a given limit. If the voltage fluctuation is transient the delay will reset. Minimum 0-120 seconds. Time Delay 2 – after a tap change operation time delay 2 will start to allow for transient voltages. Minimum 0-120 seconds. Inter Tap Delay – Minimum 0-10 seconds. For OLTC – A method of reducing the amount of circulating current between paralleled transformers. The parallel coupling control method shall cover a variable range of transformer impedances up to at least 30%. For Capacitor Bank – Transient Free Switching – a method of transient free switching such as ‘Zero voltage crossing’. For Capacitor Bank – Hold a map of switching patterns that ensures the correct switching of capacitors for each MVAr injection stage. Table 7 EAVC Ancillary Equipment Essential Functionality Essential Inputs Description Function Static Overvoltage Relay A Static Over Voltage relay should be installed on the panel which is separate to the main voltage controller and is designed to lockout the tap changer if an overvoltage condition is detected Reset Button Resets the static over voltage relay. This action can only be carried out manually. Two position integral or discrete (‘ODS’ type) switch that a user can operate to place the local controller in: Supervisory/Remote Switch Supervisory Mode – enables the SCADA link for the local controller to communicate with SCADA for monitoring and instructional purposes. A SCADA instruction will override all other instructions. Remote Mode – Disables the SCADA link so that no communications are passed from the local controller to SCADA and vice versa. Copyright Northern Powergrid (Northeast) Limited, Northern Powergrid (Yorkshire) Plc, 2014 Document Reference: CLNR-L209 Version: 1.0 Date of Issue: December 2014 12 Two position integral or discrete (‘ODS’ type) switch that a user can operate to place the local controller in: GUS Mode – enables the GUS link for the local controller to communicate its local inputs to the GUS; plus the GUS can set the local controller’s setpoint. Remote Mode – Disables the GUS communication link so that no communications are passed from the local controller to the GUS and vice versa. GUS/Remote Switch Two position integral or discrete (‘ODS’ type) switch that a user can operate to place the local controller in either 'Manual' mode or ‘Automatic' mode. Manual/Automatic Switch Manual Mode – disables the local controller from operating the OLTC when there is a voltage excursion from the pre-set voltage bandwidth; enables the ‘Tap Up’/’Raise Volts’ and ‘Tap Down’/’Lower Volts’ buttons. Automatic Mode – enables the local controller to automatically operate the OLTC when there is a voltage excursion from the pre-set voltage bandwidth; disables the ‘Tap Up’/’Raise Volts’ and ‘Tap Down’/’Lower Volts’ buttons. A push button biased switch that, when pushed, sends a voltage signal to the local controller to, which raises the network voltage by operating the OLTC ‘Up’ one ‘Tap Up’/’Raise Volts’ button position/switching the capacitor bank accordingly. The voltage will only be raised if the button is enabled (Manual Mode) and the OLTC/Capacitor Bank is not at its top limit. A push button biased switch that, when operated, sends a voltage signal to the local controller, which lowers the network voltage by operating the OLTC ‘Down’ one ‘Tap Down’/’Lower Volts’ button position/switching the capacitor bank accordingly. The voltage will only be lowered if the button is enabled (Manual Mode) and the OLTC/Capacitor Bank is not at its lower limit. Voltage take off requirement for A direct reference upstream the outgoing LV fuses at the primary substation shall be provided to LV board, in addition to the voltage and reference provided LV board direct reference downstream the fuses. 19” Rack Cabinet 3.2.7 Free standing 19” rack Desirable but no Essential Functionality Table 8 Local Controller Desirable Functionality Essential Inputs Description Function Estimated Generation Estimate the generation connected to the network 3.3 Communications Communications are required for EAVC components between: The measurement devices and the local controller, The local controller and a SCADA RTU, and The local controller and the GUS. The individual sites at which the EAVC equipment will be installed are Primary Substations or locally on the regulator. Therefore the measurement devices will already be installed a) as part of the substation’s protection/metering systems or b) fitted on the regulator. A manufacturer should indicate if they have a solution that uses different monitoring equipment to the standard protection/metering transformers. Manufacturers should also confirm what the communications media for the three categories are. It is expected that the communications media that should be used are: Between Measurement Devices and Local Controller – hardwired link; Copyright Northern Powergrid (Northeast) Limited, Northern Powergrid (Yorkshire) Plc, 2014 Document Reference: Version: 1.0 CLNR-L209 Date of Issue: December 2014 13 Between the local controller and a SCADA RTU– standard LAN (i.e. a hardwired link for local communications); Between the local controller and the GUS – ADSL (i.e. fast communications over fixed lines), GPRS (i.e. cellular communications) or standard LAN (i.e. a hardwired link for local communications). If manufacturers use a different communication media, they should give evidence that they achieve a similar level of performance. The local controller and a GUS controller may be housed in the same facility e.g. the Primary substation control room. In which case communicating between the two systems could be via an IP based LAN (i.e. a hardwired link for local communications). Should the GUS controller be installed at another location, then a robust communication media must be provided. By any means, the local controller should be able to detect a loss of communication to the GUS, and depending on this connectivity operate in one of two modes: Mode 1 will be will full communications with the GUS – the control module will use the voltage set point from the GUS communications. Mode 2 is where communications with the GUS have failed – the control module will use its default voltage set point and use Load Drop Compensation in its nominal voltage calculation. It is desirable that devices can use as many different types of communication media as possible for flexibility. The types of communication protocols required are given in Table 9. Further work with the manufacturer will be required to agree the format of data. In all cases all GPRS communications equipment must be compliant with the EMC requirements given in clause 3.3.1. 3.3.1 Electromagnetic Compatibility Communications GPRS Electromagnetic Compatibility Tests for the communication equipment. All equipment should be compatible with the following generic EMC standards: BS EN 61000-6-3: 2007 - Generic Emissions standard BS EN 61000-6-2: 2005 - Generic Immunity standard BS EN 61000-4-2: 2009 - Electrostatic discharge immunity Test ((Requirement Air 8kV, Contact 4kV) BS EN 61000-4-3: 2006 Radiated radio Frequency, Electromagnetic Field Immunity. (Requirement 80MHz - 1GHz @ 10V/m) BS EN 61000-4-6: 2009 Immunity to conducted disturbances induced by radio frequency fields (Requirement 150kHz - 80MHz @ 10V/m) BS EN 61000-4-4: 2012 Electrical Fast Transient/Bursts Immunity (Requirements +/- 1kV). 3.4 Operating Environment The components installed on the network should be the measurement devices, local controller and communications links. They should be able to operate under the following environment criteria given in Table 9. Copyright Northern Powergrid (Northeast) Limited, Northern Powergrid (Yorkshire) Plc, 2014 Document Reference: CLNR-L209 Version: 1.0 3.4.1 Date of Issue: December 2014 14 Local Controllers Table 9 Operating Environment for Local Controller Parameter/Component Requirement Comments Mounting 19” Rack mounted, for substation installation where appropriate 1 x freestanding 19” rack cabinet per controller 110v AC Power supply 48v – 110v DC Insulation IEC 60255-5 test between all terminals and earth 2.0 kV rms levels for 1 minute Insulation IEC 60255-5 test between independent circuits 2.0 kV rms levels for 1 minute Insulation IEC 60255-5 test across 1.0 kV rms levels for 1 minute normallyProtection Ingress open contacts IP54 Humidity IEC 68-2-3 Operational test 56 days at 40 °C and 95% RH Maintenance / chronological lifetime Ability to operate without any intervention for 10 years and a lifespan of 40 years Physical size Be able to fit a 19 inch rack -5°C to +35°C Indoors Operating ambient temperature Communications protocol compatibility. -25°C to +55°C Outdoors ≤ 5% variation Communicate with supported protocols, this can be direct communication or by using an intermediate device. The communications will run separately from the standard NMS/SCADA system. For example system may require systems below or similar: ENMAC interconnectivity DNP3 compatibility IEC 60870-5-103 3.5 Installation, Operation and Maintenance 3.5.1 Installation The extent of the upgrade from an AVC system to an EAVC scheme will depend on the existing AVC’s functionality. However it would be safe to assume that the existing cabling and voltage and current signals from the metering/protection VT and CTs are able to be re-used. While this document refers to them and uses their resultant signals, these items are physically outside of the scope of the EAVC solution. 19” Rack Mounted cubicles sited in the substation control room are required to house the EAVC scheme which should be 2280 (H) x 750 (W) x 720 (D) with a 75mmp plinth supplied without any front access doors. The cubicles should be protected with a final external coat of semi-gloss paint in Light Admiralty Grey Ref 697 to BS381C. The cubicle should be water-proof and have a steel metal hinged rear door, padlockable, and the door should open within the width of the panel. An internal light (240V ac) should be provided in the panel, operated by a rear door switch. The panels should be fully vermin-proof, with bottom gland plates provided for all cable entries. Copyright Northern Powergrid (Northeast) Limited, Northern Powergrid (Yorkshire) Plc, 2014 Document Reference: Version: 1.0 CLNR-L209 Date of Issue: December 2014 15 Equipment that is mounted inside of the cubicle should not prevent access to terminals or wires at the rear or at the front of the panel. No equipment should be mounted across the width of the panel. The local controller and any associated switches, fuses/links should be located at a height that is easily operated by the user. They should be mounted not less than 450mm and not more than 1800mm from floor level. All switches, fuses/links, and instruments should be mounted to be clearly visible in the normal operating position. Access to such apparatus should not require the use of tools. For safety security reasons on substation installations, the control relay should sit outside of where the heavy equipment is installed and a lockable weather-proof steel cabinet with a side hinged door for the relay board should be provided. 3.5.2 Indicators The local controller should be capable of displaying the following LED indicators as standard or as configurable indicators. They can be integral to or discrete from, the user interface with suitable labelling: Voltage above the dead band Voltage below the dead band Relay voltage above a pre-set level Relay voltage below a pre-set level Tap freeze applied Tap change lockout For OLTC: Excessive circulating current 3% and 6% voltage reduction and call to unity power factor applied 3.5.3 Alarms The local controller should be able to initiate the following alarms via a configurable time delay: Voltage remaining outside the dead band (over and under voltage). Panel Aux. Supply Fail. Tapchange Incomplete. Tapchange Lockout. AVC VT supply fail. Inter controller communications fail. 3.5.4 Earthing of Enclosure Cubicles Earthing of panels should be in line with ENA TS 41-24. Means should be provided for connecting the 19” EAVC enclosure cubicle to the substation earthing system. For non-directly connected equipment the minimum cross sectional area of these connections should be 70mm² copper cable or 25mm x 3mm copper tape. For directlyconnected equipment the earth connection to the main equipment should comply with the specification for the main equipment. Where the EAVC enclosure cubicle is installed as part of a suite of cubicles, the earth bar should extend across the cubicle and should be drilled and provided with a drilled link of the same material and cross sectional area as the cubicles earth bar, for the connection to adjacent cubicles. The cubicle design should facilitate this connection. The earth bar and connection link should be so designed so that any one cubicle can be removed from the suite without compromising the earthing of other cubicles. Copyright Northern Powergrid (Northeast) Limited, Northern Powergrid (Yorkshire) Plc, 2014 Document Reference: Version: 1.0 CLNR-L209 Date of Issue: December 2014 16 All connections to the substation earthing system should be bolted. The faces of all bolted connections should be clean and either tinned or suitably protected against corrosion for the life of the equipment. The bolted connections should have a resistance which is not more than that of an equivalent length of bar. Where earth connections are made to metalwork, the system used should ensure good electrical contact between the connections and metalwork, whilst maintaining necessary protective and corrosion resistant finishes. 3.5.4.1 Earthing of Small Apparatus and Equipment The EAVC enclosure should be provided with a suitable means of connecting equipment and apparatus to the earth bar of the enclosure. Protective bonding of equipment housed within the enclosure should be afforded by means of a direct radial connection from the enclosures bonding terminal or integral earth bar. The bonding and earthing of all ancillary components within the EAVC enclosure such as doors, covers supports, gland plates and sub-racks should be continuous and afforded by means of an insulated wire, of a cross section not less than 2.5mm². Specific means should be provided for earthing, e.g. the use of assembly bolts is not permitted. The disconnection of any component within the enclosure should not compromise the integrity of the bonding to earth of any other equipment in the enclosure. 3.5.5 Maintenance All equipment should operate for a minimum of 3 years. All equipment should operate without any intervention or maintenance. 3.6 Training Requirements 3.6.1 OLTC at Primary Substations There are no extra training requirements for the EAVC scheme as it operates primarily as an ordinary AVC scheme except that it accepts a variable setpoint and sends its inputs as outputs to the GUS. 3.6.2 Switched Capacitor Bank The manufacturer should indicate what training they can provide to ensure that staff are fully conversant with the installation and maintenance of switched capacitor bank’s local controller and ancillary equipment. 3.6.3 In-line Regulator There will not be any need for training of staff in the installation and use of the control equipment due to their experience of using such control equipment in primary transformer voltage control. The manufacturer should detail what training ability they have and the likely costs of that training for any additional functions that may be desirable to have that would be additional to the standard skill sets. If the manufacturers have other functions that are, desirable to have, or add to the schemes usability over and above a standard AVC scheme, they should detail what training ability they have and the likely costs of that training, to enable staff to be compliant in its use. 3.7 Support and Development Requirements The EAVC scheme should be integrated into part of an overall smart grid system. Manufacturers should detail the support services that they offer. Copyright Northern Powergrid (Northeast) Limited, Northern Powergrid (Yorkshire) Plc, 2014 Document Reference: CLNR-L209 Version: 1.0 Date of Issue: December 2014 17 4. WEEE Regulations Under the 2002/96/EC directive of the European Parliament and council, for the collection, separation and treatment of electronic waste, manufacturers must: State whether any of their products come under the Waste Electrical and Electronic Equipment Regulations (WEEE). If not the manufacturer should explain why they are exempt. State what provisions they have in place for the collection and recycling of the product at the end of its useful life. State what discounts would be available to switch the responsibility of the products disposal from the manufacturer to DNOs. 5. References The products described within this recommendation should comply with all current versions of the relevant International Standards, British Standard Specifications and all relevant Energy Networks Association Technical Specifications (ENATS) current at the time of supply. 5.1 External Documentation Reference BS EN60529 Title Degrees of protection provided by Enclosures (IP Code) BS EN 60255 Measuring relays and protection equipment ENA TS 50-18 :2013 Application of Ancillary Electrical Equipment ENA TS 50-19 Standard Numbering for small wiring ENA TS 41-24 Guidelines for the Design, Installation, testing and maintenance of main earthing Systems in Substations High voltage switchgear and controlgear IEC 62271-1 BS ISO 3864-1:2011 Electromagnetic compatibility (EMC) – Part 4-30: Testing and measurement techniques – Power Quality measurement methods Graphical symbols and signs – safety signs, including fire safety signs BS EN 61000-6-2:2005 Generic standards – Immunity standards for industrial environments. IEC 61000-4-30 BS EN 60801-2:1993, IEC Electromagnetic compatibility for industrial-process measurement and 60801-2:1991 control equipment. Electrostatic discharge requirements BS EN 61000-43:2006+A2:2010 BS EN 61000-4-4:2012 Testing and measurement techniques. Radiated, radio-frequency, electromagnetic field immunity test Testing and measurement techniques – Electrical fast transient/burst immunity test BS EN 61000 Electromagnetic compatibility BS 2782-5:Method 552A:1999, ISO 4582:1998 Methods of testing plastics — Optical and colour properties, weathering — Determination of changes in colour and variations in properties after exposure to daylight under glass, natural weathering or laboratory light sources The supplier should provide with the tender full technical details of the equipment offered and should indicate any divergence from these standards or specifications. Copyright Northern Powergrid (Northeast) Limited, Northern Powergrid (Yorkshire) Plc, 2014 Document Reference: Version: 1.0 CLNR-L209 Date of Issue: December 2014 18 5.2 Internal Documentation Reference Title (For Northern Powergrid) see: NPS/003/001 Other DNO’s please refer to your Technical Specification for 66kV and 132kV Voltage Transformers current specifications for Transformers required for your PCS output step voltage (For Northern Powergrid) see: NPS/003/023 Other DNO’s please refer to your Technical Specification for 33, 66 & 132kV Post CT’s current specifications for Transformers required for your PCS output step voltage (For Northern Powergrid) see: NPS/003/021 Other DNO’s please refer to your current specifications for Transformers required for your PCS output step voltage Technical Specification for System Transformers CMR (Continuous Maximum Rated) (For Northern Powergrid) see: NPS/003/012 Other DNO’s please refer to your Technical Specification for System Transformers CER (Continuous Emergency Rated) current specifications for Transformers required for your PCS output step voltage Copyright Northern Powergrid (Northeast) Limited, Northern Powergrid (Yorkshire) Plc, 2014 Document Reference: Version: 1.0 CLNR-L209 Date of Issue: December 2014 19 5.3 Summary of Amendments Reference Clause 1 Clause 3.2.6– Table 6 Local controller Clause 3.2.6– Table 6 Essential Clause 3.2.6– Table 67 FunctionalityTable Clause 3.5.1 – 3rd and 6th paragraph Clause 5.1 and entire document Clause 3.3 Title Update superseded documents table Addition of locking Policy requirements for operating switches Addition of tap freeze function while retaining relay power Addition of voltage take off requirement for LV Board direct reference Addition of asset security requirements Update on external documentation references and addition of reference checks when possible Addition of operational failure mode in the event of communications failure Copyright Northern Powergrid (Northeast) Limited, Northern Powergrid (Yorkshire) Plc, 2014 Document Reference: Version: 1.0 CLNR-L209 Date of Issue: December 2014 20 6. Definitions Term CLNR DNO EHV GUS HV MVA NMS SCADA GPRS Local control Remote control Supervisory control Enhanced Automatic Voltage Control (EAVC) Local controller Definition Customer Led Network Revolution Distribution Network Operator Extra High Voltage (the 33kV network and above) High level control system that gathers network information in real time from distributed monitors, and uses specified algorithms to determine each voltage control device’s setpoint for the optimum network voltage levels. High Voltage (network from 6kV to 33kV) Megavoltamperes (apparent power) Network management System Supervisory control and data acquisition General Packet Radio Services (GPRS) is a packet-based wireless communication service that provides data rates from 56 up to 114 Kbps and continuous connection to the Internet for mobile phone and computer users. GPRS is based on Global System for Mobile (GSM) communication system. Control at the Primary transformer OLTC Control at the AVC local controller Control inputs/outputs from SCADA/Control Room/GUS An automatic voltage control system that becomes enhanced by its ability to: Send its monitor inputs as outputs to a high level control system (GUS) Receives network goals from a high level control system (GUS) Voltage relay or other suitable device that provides automatic voltage control. Copyright Northern Powergrid (Northeast) Limited, Northern Powergrid (Yorkshire) Plc, 2014 Document Reference: CLNR-L209 Version: 1.0 Date of Issue: December 2014 21 Appendix 1a – Schedule of Suppliers Technical Data The following Technical schedules must be completed by suppliers Essential & Desirable Data Outputs (Table 3 & 4) Type Comments Tap Up/Raise Volts Tap Down/Lower Volts Block Alarms Voltage Current Estimated Generation Supported Communication methods Ability to Accept Expected Inputs from GUS (Table 5) Input Comments Handshake/Heartbeat Setpoint Check/Change Copyright Northern Powergrid (Northeast) Limited, Northern Powergrid (Yorkshire) Plc, 2014 Document Reference: Version: 1.0 CLNR-L209 Date of Issue: December 2014 22 Appendix 1b – Schedule of Suppliers Technical Data – Local Controller Local Controllers Functionality – (Compliance with table 6 and 8) Function Comments Essential Inputs Description Function VT Monitoring CT Monitoring Control Outputs Description Raise signal Lower signal Status Checks Description Function Function Auxiliary Voltage Line Voltage Metering Tap Lock Tap Change Master Lock out feature Tap position OLTC/Capacitor Bank operation Self-supervision signal Overcurrent Blocking Overvoltage Blocking Undervoltage Blocking Estimated Generation External Inputs Copyright Northern Powergrid (Northeast) Limited, Northern Powergrid (Yorkshire) Plc, 2014 Document Reference: Version: 1.0 CLNR-L209 Date of Issue: December 2014 Function Comments Description Function 23 Manual Mode Automatic Mode Supervisory Mode Reduce set voltage (-3%, -6% ) Internal Functions Acceptance of a setpoint over a communications link Hold a Default setpoint Load Drop Compensation An ability to function in Mode1 and Mode 2 The ability to detect a handshake/heartbeat Runaway Protection Time Delays For OLTC - A method of reducing the amount of circulating current between paralleled transformers. For Capacitor Banks – Transient Free switching. For Capacitor Banks – Method of ensuring the capacitors are in their correct switching pattern. Copyright Northern Powergrid (Northeast) Limited, Northern Powergrid (Yorkshire) Plc, 2014 Document Reference: Version: 1.0 CLNR-L209 Date of Issue: December 2014 24 Appendix 1c – Schedule of Suppliers Technical Data – EAVC Ancillary Equipment Ancillary Equipment Functionality - (Compliance with Table 7) Parameter/Component Comments Static Over voltage Relay Reset Button Supervisory/Remote Switch GUS/Remote Switch Manual/Automatic Switch ‘Tap Up’/’Raise Volts’ button ‘Tap Down’/’Lower Volts’ button 19” Rack Cabinet Copyright Northern Powergrid (Northeast) Limited, Northern Powergrid (Yorkshire) Plc, 2014 Document Reference: Version: 1.0 CLNR-L209 Date of Issue: December 2014 25 Appendix 1d – Schedule of Suppliers Technical Data – Compliance with Specification Parameter/Component Comments Mounting Power supply Insulation IEC 60255-5 test between all terminals and earth Insulation IEC 60255-5 test between independent circuits Insulation IEC 60255-5 test across normally open contacts Ingress Protection – Clause 3.1.1.2 & 3.1.1.3 Humidity IEC 68-2-3 Operational test Maintenance / chronological lifetime Physical size – Clause 3.5.1 Operating ambient temperature Communications protocol compatibility. Clause 3.3 Small wiring and terminal blocks clause 3.1.1.5 Marking & Labelling – clause 3.1.1.4 Indicators - clause 3.5.2 Alarms - clause 3.5.3 Earthing of enclosures – clause 3.5.4 Copyright Northern Powergrid (Northeast) Limited, Northern Powergrid (Yorkshire) Plc, 2014 Document Reference: Version: 1.0 CLNR-L209 Date of Issue: December 2014 26 Appendix 2a – Self Certification Conformance Declaration – Tables 1-9 of this specification Supplier/Product Technical Compliance Grid (to be completed by the supplier for each variant offered). The EAVC’s shall comply with the latest issues of the IEC’s and British Standards quoted within this specification. Key elements from the above standards and this specification have been quoted to amplify and/or clarify the requirements of those Standards. This check sheet identifies the particular clauses of the aforementioned Standards relevant to EAVC’s. The manufacturer shall declare conformance or otherwise, clause by clause, using the following levels of conformance declaration codes for each conductor. Instructions for completion N Conformance declaration codes When Cs1 code is entered no remark is necessary o N/A = Clause is not applicable/ appropriate to the product t Cs1 = The product conforms fully with the requirements of this clause e Cs2 = The product conforms partially with the requirements of this clause When any other code is entered the reason for non-conformance S Cs3 = The product does not conform to the requirements of this clause shall be entered e Cs4 = The product does not currently conform to the requirements of this clause, p but the manufacturer proposes to modify and test the product in order to conform. Prefix each remark with the relevant ‘BS EN’ or ‘ENATS’ a r ate Self Certification Conformance Declaration sheets shall be completed for each product being offered. Manufacturer: Product Reference: Name: Signature: Date: Copyright Northern Powergrid (Northeast) Limited, Northern Powergrid (Yorkshire) Plc, 2014 Document Reference: Version: 1.0 CLNR-L209 Date of Issue: December 2014 27 Specific requirements within this specification Clause/Sub Requirements -clause Conformanc e Code Table 1 Compliance with Essential Inputs Table 3 Compliance with Essential Outputs Table 4 Compliance with Essential Data Outputs Table 5 Compliance with Expected Inputs from GUS Table 6 Compliance with Essential Functionality of the local controller. Table 7 Compliance with Essential Functionality of the EAVC Ancillary Equipment. Table 9 Compliance with the Operating environment requirements for the Local Controller Remarks Copyright Northern Powergrid (Northeast) Limited, Northern Powergrid (Yorkshire) Plc, 2014 Document Reference: Version: 1.0 CLNR-L209 Date of Issue: December 2014 28 Appendix 2b – Self Certification Conformance Declaration The EAVC’s shall comply with the latest issues of the relevant International and British Standards. ENATS 50-18 is intended to amplify and or clarify the requirements of those standards This check sheet identifies the particular clauses of the aforementioned Standards relevant to EAVC’s. The manufacturer shall declare conformance or otherwise, clause by clause, using the following levels of conformance declaration codes for each conductor. Instructions for completion N Conformance declaration codes When Cs1 code is entered no remark is necessary o N/A = Clause is not applicable/ appropriate to the product t Cs1 = The product conforms fully with the requirements of this clause e Cs2 = The product conforms partially with the requirements of this clause When any other code is entered the reason for non-conformance S Cs3 = The product does not conform to the requirements of this clause shall be entered e Cs4 = The product does not currently conform to the requirements of this clause, p but the manufacturer proposes to modify and test the product in order to conform. Prefix each remark with the relevant ‘BS EN’ or ‘ENATS’ a r ate Self Certification Conformance Declaration sheets shall be completed for each product being offered. Manufacturer: Product Reference: Name: Signature: Date: Copyright Northern Powergrid (Northeast) Limited, Northern Powergrid (Yorkshire) Plc, 2014 Document Reference: Version: 1.0 CLNR-L209 Date of Issue: December 2014 IEC ENATS 50-18 Clause / Sub clause IEC IEC622 62271-1 71-200 2 2 Requirement Service conditions Confor mance code ENATS 50-18 Clause / Sub Requirement clause 2 3.2 3.3 3.4 Table 3.1 5.4 5.4 5.4.1 5.4.4.1 5.4.4.2 5.4.1.3 5.4.1.3 5.4.1.3 5.3 5.4.3 5.10 5.4.4.5.1 5.4.4.5.2 29 5.3 4.1 4.1 4.1 4.1 4.2 4.2.1 4.2.1 4.2.2 4.2.3 4.3 4.4 4.6.2 4.7 4.8 5.1 5.2 5.2.1 Confor mance code Service conditions Electromagnetic compatibility Type Tests (see separate conformance declaration) Voltage and frequency limits Correct operation at DC Voltage Limits at Apparatus Terminals General Materials - non-ignitable Materials – Dimensionally stable Dust protected contacts and mechanisms Minimum height of terminal block arrangements (100mm) Provision of padlocking on doors Selection of components Installation of components Access to apparatus and components Max/Min heights of components Degree of protection Padlocking Earthing of enclosures Earthing of small apparatus and equipment Access to connection interface Terminals and Apparatus Fire Hazard Marking and labelling Small wiring Connections Terminals and terminations Copyright Northern Powergrid (Northeast) Limited, Northern Powergrid (Yorkshire) Plc, 2014 Remarks Document Reference: Version: 1.0 CLNR-L209 Date of Issue: December 2014 IEC Clause clause IEC 62271-1 30 ENATS 50-18 / Sub IEC622 71-200 Requirement Confor mance code ENATS 50-18 Clause/ Sub Requirement clause 5.2.2 5.2.3 5.2.4 5.3 6.1 6.4 6.5 7 7.2.1 7.2.2 7.3 8.1 8.2 8.3 8.4 8.5 Confor mance code Terminal Blocks Termination clamps Insulation displacement connectors Plug and socket connectors Fuses and links Miniature circuit breakers Supply isolation Control and selector switches Classification Rating Design Instruments Electrical measurement transducers Control and interposing relays Small contactors Indicating lamps and fittings Copyright Northern Powergrid (Northeast) Limited, Northern Powergrid (Yorkshire) Plc, 2014 Remarks Document Reference: CLNR-L209 Version: 1.0 Date of Issue: December 2014 31 Appendix 2c – ENA TS 50-18 Type test Self Certification Conformance Declaration Instructions for completion When Cs1 code is entered no remark is necessary Manufacturer: Product Reference: Name: When any other code is entered the reason for non-conformance shall be entered Signature: 1. Test requirement Emission standards from the auxiliary and control 1 standards. Immunity Tests on auxiliary and control circuits 2 2. Specifications and standards Prefix each remark with the relevant ‘BS EN’ or ‘ENATS’ Date: 3. Rated Value 4. Test req’d (Y/N) IEC 62271-1 clause 6.9.1.2 Y Electrical fast transient/burst test IEC 62271-1 clause 6.9.2.3 Y Oscillatory wave immunity test IEC 62271-1 clause 6.9.2.4 Y 5. 6. Confor Test mance Value 7. Date of test 8. Test Station Report/ Cert No. Copyright Northern Powergrid (Northeast) Limited, Northern Powergrid (Yorkshire) Plc, 2014 9. Witness I,M or ENA** 10. Remarks Document Reference: Version: 1.0 Test requirement CLNR-L209 Date of Issue: December 2014 Specifications and standards Rated Value 32 Test req’d (Y/N) Confor Test mance Value Date of test Test Station Report/ Cert No. 3 Additional EMC test on auxiliary and control circuits Ripple on d.c. input power port immunity test IEC 62271-1 Clause 6.9.3.2 Y Voltage dips, short interruptions and voltage variations on d.c. input power port immunity tests IEC 62271-1 Clause 6.9.3.3 Y Functional tests IEC 62271-1 Clause 6.10.2 Y Electrical continuity of earthed metallic parts test IEC 62271-1 Clause 6.10.3 Y Auxiliary contact rated Continuous current IEC 62271-1 Clause 6.10.4.2 Y Auxiliary contact rated Short time withstand current IEC 62271-1 Clause 6.10.4.3 Y Auxiliary contact rated Breaking capacity IEC 62271-1 Clause 6.10.4.4 Y 4 Additional EMC test on auxiliary and control circuits Verification of the operational characteristics of auxiliary contacts: Copyright Northern Powergrid (Northeast) Limited, Northern Powergrid (Yorkshire) Plc, 2014 Witness I,M or ENA** Remarks Document Reference: Version: 1.0 Test requirement CLNR-L209 Date of Issue: December 2014 Specifications and standards Rated Value 33 Test req’d (Y/N) 5 Confor Test mance Value Date of Test test Station Report/ Cert No. Environmental Tests Cold test IEC 6.2271-1 clause 6.10.5.2 Y Dry Heat test (Outdoor) IEC 6.2271-1 clause 6.10.5.3 Y Damp heat test, steady IEC 6.2271-1 clause 6.10.5.4 Y IEC 6.2271-1 clause 6.10.5.5 Y Vibration response and IEC 6.2271-1 clause seismic tests 6.10.5.6 Y IEC 6.2271-1 clause Y state test (Outdoor) Cyclic humidity test Final condition check 6.10.5.7 6 Dielectric Test IEC 6.2271-1 clause 6.10.6 Y Communications GPRS Electromagnetic Compatibility Tests for the communication equipment 7 Emission standards for residential, commercial and light industrial environments. BS EN 61000-6-3:2007 Y Copyright Northern Powergrid (Northeast) Limited, Northern Powergrid (Yorkshire) Plc, 2014 Witness Remarks I,M or ENA** Document Reference: Version: 1.0 Test requirement 8 9 10 11 12 Immunity Standards –Immunity for industrial environments EMC for industrialprocess measurement and control equipment – Electrostatic discharge requirements EMC – Radiated, radio- frequency, electromagnetic Min values Air test – field immunity 4kV Contacts – 8kV EMC – Electrical fast transient/burst Min Values immunity test 27Mhz – 1Ghz @ EMC 10V/m- Immunity to Min values conducted 80Mhz – 1Ghz @ disturbances +/1kV 10V/m induced by radio frequency fields CLNR-L209 Date of Issue: December 2014 Specifications and standards Rated Value BS EN 61000-6-2:2005 Y BS EN 60801-2:1993 Y BS EN 61000-4-3:2002 Y IEC 61000-4-4:2012 Y BS EN 61000-4-6:2007 Y Test req’d 34 Confor Test mance Value ( Y / N ) Date of Test test Station Report/ Cert No. Witness I,M or ENA** Min Values 150khz – 80Mhz @ 10V/m Copyright Northern Powergrid (Northeast) Limited, Northern Powergrid (Yorkshire) Plc, 2014 Remarks Document Reference: CLNR-L209 Version: 1.0 Date of Issue: December 2014 35 *Conformance declaration codes Ct1 = Independent witnessed tests Ct2 = Not fully independent witnessed tests Ct3 = Self verified tests Ct4 = Alternative tests / evidence offered Ct5 = Manufacturer has underwritten that the product meets the functional and performance requirements without further testing Ct6 = Not tested Copyright Northern Powergrid (Northeast) Limited, Northern Powergrid (Yorkshire) Plc, 2014 Document Reference: Version: 1.0 CLNR-L209 Date of Issue: December 2014 36 Appendix 3 – Addendum to Supplier Requirements Please indicate Packaging/delivery information Details of how this product will be packaged and delivered shall be provided. Project specific requirements Any project specific requirements will be provided for inclusion in this appendix. Copyright Northern Powergrid (Northeast) Limited, Northern Powergrid (Yorkshire) Plc, 2014 Document Reference: Version: 1.0 CLNR-L209 Date of Issue: December 2014 37 Appendix 4 – Pre-commission testing, Routine Inspection and Maintenance requirements Suppliers shall provide details of any recommended pre-commission testing or installation requirements. Additionally suppliers shall also provide information regarding any periodic inspection or maintenance requirements to be undertaken during the lifetime of their product. Copyright Northern Powergrid (Northeast) Limited, Northern Powergrid (Yorkshire) Plc, 2014 Document Reference: Version: 1.0 CLNR-L209 Date of Issue: December 2014 38 Appendix 5 – Technical Information Check List The following information shall be provided by the supplier for technical review. Additional information shall be provided if requested. Requirement Provided (Y/N) Appendix 1 – Completed technical schedules Appendix 2 – Completed self-certification conformance declaration Appendix 3 – Packaging and delivery information Appendix 4 – Inspection and testing recommendations Type test evidence Routine test plan (example) Copyright Northern Powergrid (Northeast) Limited, Northern Powergrid (Yorkshire) Plc, 2014 Document Reference: Version: 1.0 CLNR-L209 Date of Issue: December 2014 39 Appendix 6 – Schedule of Components Item Description 1 2 3 4 5 6 7 8 9 10 11 12 Local Controller 19” Rack Cabinet Communications Link Manual/Auto Switch Supervisory/Remote Switch GUS/Remote switch ‘Tap Up’/’Raise Volts’ button ‘Tap Down’/’Lower Volts’ button Test Block Static Over Voltage Relay Reset Button Fuses Price Copyright Northern Powergrid (Northeast) Limited, Northern Powergrid (Yorkshire) Plc, 2014