PSE's Power Lines Puget Sound Energy has more than 20,000 miles of transmission and distribution power lines in our 6,000 square mile service area, primarily in the Puget Sound region of Western Washington. Transmission and distribution lines are both vital parts of our electric system, but they play very different roles. • • Transmission lines are high-voltage lines that carry electricity from generation plants to substations or from substation to substation. Transformers at the substation “step down” the electricity’s transmission voltage (55 – 230 kilovolts*) to our primary distribution voltage (12.5 kV). A distribution line is a medium-voltage (12.5 kV) line that carries power from a substation to customers. Roughly half of PSE’s distribution lines are underground. Distribution voltage is stepped down to service voltage through smaller transformers located along distribution lines. * A kilovolt (kV) is equal to 1,000 volts of electric energy. Generation Transmission via 230/500 kV lines Transmission via 115 kV lines Distribution via 12.5 kV lines Electric Transmission Lines Above ground versus underground lines Nearly all of PSE’s transmission lines are located above ground. While we are able to build underground transmission lines, overhead transmission lines are the first option for their combination of reliability and affordability – both of which are important to our customers. Per state regulated tariffs, if an overhead route is viable, the additional cost to underground must be paid for by the group requesting it. This is to help keep costs low for all of our customers. The construction costs for overhead power lines compared to underground lines can be seen in this table: Distribution Overhead Underground $590,000 to $830,000 per mile $2.3 million to $3.2 million per mile 115 kV Transmission $825,000 to $2.1 million per mile $4.7 million to $9.5 million per mile 230 kV Transmission $3 million to $4 million per mile $20 million to $28 million per mile In addition to cost, there are other factors to consider. For example: • • Putting power lines underground can have bigger environmental and neighborhood impacts. Undergrounding transmission lines requires extensive vegetation removal, trenching and installation of large (as much as 20 feet x 30 feet) access vaults every quarter mile and can be very disruptive to neighborhoods and the environment. Underground lines typically take longer to repair, and repairs are more difficult. When an overhead line fails, our crews can often repair it within hours. Repair of underground transmission lines can take days and even weeks, depending on the repairs that need to be made. Ultimately, the local community must weigh the benefits of undergrounding against these significantly increased costs. Should the community decide to invest in an underground solution, PSE will work with the community in this effort. PSE’s power distribution system: • • • 2,597 miles of transmission lines (55 kV and above) 20,428 miles of distribution lines (under 55 kV) ○○ 10,357 miles of overhead lines ○○ 10,071 miles of underground lines 428 transmission and distribution substations pse.com 230kV transmission lines Line maintenance Overhead transmission line maintenance includes visual line inspections, pole treatment, and vegetation management. Further investigation can include infrared (IR) scanning and radio frequency scanning. Underground transmission lines are difficult to maintain due to their sensitivity to design and operating conditions. The cables are sensitive to changes in soil cover and aboveground changes. The main maintenance activity is patrolling the cable route to verify there have been no changes in soil depth, cover type, vegetation changes, or other activity that would impact the ability of the cable to dissipate heat effectively. Visual inspection and IR inspection of the cable ends and vaults is also important to maintain the cable. Outages and restoration Transmission outages are less common than outages on the distribution system; usually less than 0.5% of customer outages are transmission outages. The lower failure rate is due to differences in design, construction, and operation. When there are transmission outages they typically affect thousands of customers. If an outage occurs, PSE crews focus first on restoring power to transmission lines that provide power to substations serving large numbers of customers in a broad geographic area. Priority for power restoration also goes to essential services such as hospitals, water/waste water systems, energy and transportation. Once the high-voltage transmission system and substations are back online, PSE crews focus on repairing damage to distribution and service lines – the lines that directly serve homes and businesses. During an outage, one part of a neighborhood may have its lights on while another remains without power. Because our electric system works in sections or circuits, PSE crews re-route power around the damaged areas, thereby isolating the section that requires repairs. Electric Distribution Lines Roughly half of our distribution lines are underground. PSE typically undergrounds distribution lines in all new developments. This is because it is cost-effective to install buried cables at the time a neighborhood or building site is constructed and the costs are shared by the developer. Burying distribution lines in an older, established neighborhood could carry a price tag as much as 15 times the cost of installing above-ground lines. This is because it requires excavating asphalt and concrete and, in some cases, working in difficult terrain, particularly in the Puget Sound region where there are many wetlands. If a business, neighborhood or community asks PSE to underground an existing distribution system with overhead lines, PSE’s regulated tariffs require that business, neighborhood or community to help pay the costs. Line maintenance Overhead distribution line maintenance includes visual line inspections, pole treatment, and vegetation management; further investigation can include infrared (IR) scanning and radio frequency scanning. Underground lines are more difficult to maintain and require diagnostic testing to verify proper operation; though vaults can still be visually inspected and IR scanned similar to overhead components. Annual outage restoration costs and preventive maintenance is slightly higher for underground lines due to the difficulty in troubleshooting and maintaining. Outages and restoration 12.5 kV distribution lines While underground distribution cables are better able to withstand wind storms, falling trees and other above-ground hazards, they may at times fail due to corrosion, fatigue and other stresses below ground. Additionally, since underground cables are often fed from an overhead power line, an outage on the overhead line can result in an outage to the downstream underground cable. Placing distribution lines underground may result in fewer outages caused by storms; however, when outages do occur they are typically of much longer duration. PSE workers can visually inspect overhead power lines to determine the location of damage, and due to easy access, can typically make repairs in a few hours. Locating damage to underground cables, however, is not as easy; we must first locate a fault by testing the cable with specialized fault-finding equipment, which can take several hours. Once located, we must dig up the area around the fault to repair the cable. pse.com 4153_109 12/14