Saudi Aramco’s Approach to Fieldbus Copyright © Saudi Aramco 2004. All rights reserved. No portion of this article may be reproduced by any process or technique without the express written consent of Saudi Aramco Honeywell Users Group Meeting 2004 - Bahrain How will YOUR company approach Fieldbus on your next project? Copyright © Saudi Aramco 2004. All rights reserved. No portion of this article may be reproduced by any process or technique without the express written consent of Saudi Aramco Honeywell Users Group Meeting 2004 - Bahrain Aramco’s Fieldbus Approach 1. Fieldbus Strategy 2. Approving a Fieldbus Solution 3. Requirements for Fieldbus Installation Copyright © Saudi Aramco 2004. All rights reserved. No portion of this article may be reproduced by any process or technique without the express written consent of Saudi Aramco Honeywell Users Group Meeting 2004 - Bahrain Aramco’s Fieldbus Approach 1. Fieldbus Strategy 2. Approving a Fieldbus Solution 3. Requirements for Fieldbus Installation Copyright © Saudi Aramco 2004. All rights reserved. No portion of this article may be reproduced by any process or technique without the express written consent of Saudi Aramco Honeywell Users Group Meeting 2004 - Bahrain Aramco’s Fieldbus Approach 1. Fieldbus Strategy – FOUNDATION Fieldbus (FF) will be our Strategic Bus – FF Solutions must be Approved – Start Small & Grow FF Experience Copyright © Saudi Aramco 2004. All rights reserved. No portion of this article may be reproduced by any process or technique without the express written consent of Saudi Aramco Honeywell Users Group Meeting 2004 - Bahrain Aramco’s Fieldbus Approach 1. Fieldbus Strategy – FOUNDATION Fieldbus (FF) will be our Strategic Bus • FFH1 is now a Mainstream Product • FF has Benefits We can’t Ignore • What are Our Options?! Copyright © Saudi Aramco 2004. All rights reserved. No portion of this article may be reproduced by any process or technique without the express written consent of Saudi Aramco Honeywell Users Group Meeting 2004 - Bahrain Aramco’s Fieldbus Approach FF H1 is Now a Mainstream Product z FF H1 Product is Mature z Major Oil & Gas Company’s use of FF z Engr Firm FF Expertise Available z FF Training Here & Acceptance High Oil & Gas Major’s Use of FF H1 Copyright © Saudi Aramco 2004. All rights reserved. No portion of this article may be reproduced by any process or technique without the express written consent of Saudi Aramco Honeywell Users Group Meeting 2004 - Bahrain Aramco’s Fieldbus Approach 1. Fieldbus Strategy – FOUNDATION Fieldbus (FF) will be our Strategic Bus • FFH1 is now a Mainstream Product • FF has Benefits We can’t Ignore • What are Our Options?! Copyright © Saudi Aramco 2004. All rights reserved. No portion of this article may be reproduced by any process or technique without the express written consent of Saudi Aramco Honeywell Users Group Meeting 2004 - Bahrain Aramco’s Fieldbus Approach FF has Benefits you can’t Ignore – Project Savings – FF Device & Process Diagnostics – Resistance to Obsolescence Copyright © Saudi Aramco 2004. All rights reserved. No portion of this article may be reproduced by any process or technique without the express written consent of Saudi Aramco Honeywell Users Group Meeting 2004 - Bahrain Aramco’s Fieldbus Approach FF has Benefits you can’t Ignore – Project Savings – FF Device & Process Diagnostics – Resistance to Obsolescence PIB Junction Box D Conventional Wiring TB’s 87 devices D “Home Run” Cable (Trunk) D TB’s for FF 16 segments Up to 256 devices Copyright © Saudi Aramco 2004. All rights reserved. No portion of this article may be reproduced by any process or technique without the express written consent of Saudi Aramco Honeywell Users Group Meeting 2004 - Bahrain Aramco’s Fieldbus Approach FF has Benefits you can’t Ignore – Project Savings – FF Device & Process Diagnostics – Resistance to Obsolescence • No Problem Found Work Tickets • Device & Process Diagnostics • Increase in Plant Uptime Copyright © Saudi Aramco 2004. All rights reserved. No portion of this article may be reproduced by any process or technique without the express written consent of Saudi Aramco Honeywell Users Group Meeting 2004 - Bahrain Aramco’s Fieldbus Approach FF has Benefits you can’t Ignore – Project Savings – FF Device & Process Diagnostics – Resistance to Obsolescence • Infrastructure to Apply High Value Diagnostics • Infrastructure to Apply FF HSE Copyright © Saudi Aramco 2004. All rights reserved. No portion of this article may be reproduced by any process or technique without the express written consent of Saudi Aramco Honeywell Users Group Meeting 2004 - Bahrain Aramco’s Fieldbus Approach 1. Fieldbus Strategy – FOUNDATION Fieldbus (FF) will be our Strategic Bus • FFH1 is now a Mainstream Product • FF has Benefits We can’t Ignore • What are Our Options?! Copyright © Saudi Aramco 2004. All rights reserved. No portion of this article may be reproduced by any process or technique without the express written consent of Saudi Aramco Honeywell Users Group Meeting 2004 - Bahrain Aramco’s Fieldbus Approach What are our Options? – Analog or Proprietary – Analog with HART – Profibus PA – FOUNDATION Fieldbus Copyright © Saudi Aramco 2004. All rights reserved. No portion of this article may be reproduced by any process or technique without the express written consent of Saudi Aramco Honeywell Users Group Meeting 2004 - Bahrain Aramco’s Fieldbus Approach 1. Fieldbus Strategy – FOUNDATION Fieldbus (FF) will be our Strategic Bus – FF Solutions must be Approved – Start Small & Grow FF Experience Copyright © Saudi Aramco 2004. All rights reserved. No portion of this article may be reproduced by any process or technique without the express written consent of Saudi Aramco Honeywell Users Group Meeting 2004 - Bahrain Aramco’s Fieldbus Approach 1. Fieldbus Strategy – FF Solutions Must be Approved • Aramco DCS RVL - Must bid projects • Each Vendor has a FF ‘solution’ • Aramco developed basic FF requirements • Honeywell EPKS is Aramco approved for FF Copyright © Saudi Aramco 2004. All rights reserved. No portion of this article may be reproduced by any process or technique without the express written consent of Saudi Aramco Honeywell Users Group Meeting 2004 - Bahrain Aramco’s Fieldbus Approach 1. Fieldbus Strategy Experion PKS TDC3000 FF (not) Copyright © Saudi Aramco 2004. All rights reserved. No portion of this article may be reproduced by any process or technique without the express written consent of Saudi Aramco Honeywell Users Group Meeting 2004 - Bahrain Aramco’s Fieldbus Approach 1. Fieldbus Strategy – FOUNDATION Fieldbus (FF) will be our Strategic Bus – FF Solutions must be Approved – Start Small & Grow FF Experience Copyright © Saudi Aramco 2004. All rights reserved. No portion of this article may be reproduced by any process or technique without the express written consent of Saudi Aramco Honeywell Users Group Meeting 2004 - Bahrain Aramco’s Fieldbus Approach 1. Fieldbus Strategy – Start Small & Grow FF Experience • Aramco ‘Started Small’ to get experience • Proponent must commit to FF • Current Aramco FF Installations: – – – – 4 FF Installations (50-250 FF points each) 7 projects ongoing (100-500 FF points each) 1 larger project ongoing (>1000+ FF points) Multiple LARGE FF projects coming ! Copyright © Saudi Aramco 2004. All rights reserved. No portion of this article may be reproduced by any process or technique without the express written consent of Saudi Aramco Honeywell Users Group Meeting 2004 - Bahrain Aramco’s Fieldbus Approach 1. Fieldbus Strategy 2. Accepting a Fieldbus Solution 3. Requirements for Fieldbus Installation Copyright © Saudi Aramco 2004. All rights reserved. No portion of this article may be reproduced by any process or technique without the express written consent of Saudi Aramco Honeywell Users Group Meeting 2004 - Bahrain Aramco’s Fieldbus Approach 1. Fieldbus Strategy 2. Approving a Fieldbus Solution 3. Requirements for Fieldbus Installation Copyright © Saudi Aramco 2004. All rights reserved. No portion of this article may be reproduced by any process or technique without the express written consent of Saudi Aramco Honeywell Users Group Meeting 2004 - Bahrain Aramco’s Fieldbus Approach 2. Approving a Fieldbus Solution – Must be an Aramco approved DCS. – Must meet Aramco’s FF Host Requirements: – Must Pass 3 Aramco Tests : FF Basic Functionality consistent with conventional FF Reliability meets that of conventional FF Configuration consistent with Conventional Copyright © Saudi Aramco 2004. All rights reserved. No portion of this article may be reproduced by any process or technique without the express written consent of Saudi Aramco Honeywell Users Group Meeting 2004 - Bahrain Aramco’s Fieldbus Approach 2. Approving a Fieldbus Solution – Must Meet Aramco’s FF Host Requirements z z z z z z z z Redundant H1 Card & Power Online/Offline FF Configuration Consistent with Conventional Bulk Import Config Capability for Large FF Projects FF Operation Consistent with Conventional FF (& HART) Instrument Maintenance Tools FF Training & Support Locally Must have installed FF base Internal Interoperability Verification Copyright © Saudi Aramco 2004. All rights reserved. No portion of this article may be reproduced by any process or technique without the express written consent of Saudi Aramco Honeywell Users Group Meeting 2004 - Bahrain Aramco’s Fieldbus Approach 2. Approving a Fieldbus Solution – Must Pass 3 Aramco Tests that Verify: • FF Basic Functionality consistent with conventional • FF Reliability meets that of conventional • FF Configuration consistent with Conventional Copyright © Saudi Aramco 2004. All rights reserved. No portion of this article may be reproduced by any process or technique without the express written consent of Saudi Aramco Honeywell Users Group Meeting 2004 - Bahrain Process Simulation Panel FF Positioner FF DP transmitter and flow orifice Copyright © Saudi Aramco 2004. All rights reserved. No portion of this article may be reproduced by any process or technique without the express written consent of Saudi Aramco Honeywell Users Group Meeting 2004 - Bahrain Aramco’s Fieldbus Approach 2. Approving a Fieldbus Solution – Must Pass 3 Aramco Tests that Verify: • FF Basic Functionality consistent with conventional • FF Reliability meets that of conventional • FF Configuration consistent with Conventional Copyright © Saudi Aramco 2004. All rights reserved. No portion of this article may be reproduced by any process or technique without the express written consent of Saudi Aramco Honeywell Users Group Meeting 2004 - Bahrain Column Feed TC100 FC101 RC100 FC100 Column C-210 Steam Condensate E-200 Bottoms Product Test Purpose: Basic Functionality Test FF control & I/O operates consistently with conventional by: 1. "Invalid Value" Detection And Propagation. Fail FT100 & then restore. 2. Initialization Detection And Propagation. FIC100 to manual then Cascade. 3. Windup Detection, Propagation And Protection Set output limits on FIC100, then restore. 4. Controller Download From Configurator to FF Instrumentation. Evaluate control bumps. Copyright © Saudi Aramco 2004. All rights reserved. No portion of this article may be reproduced by any process or technique without the express written consent of Saudi Aramco Honeywell Users Group Meeting 2004 - Bahrain Aramco’s Fieldbus Approach 2. Approving a Fieldbus Solution – Must Pass 3 Aramco Tests that Verify: • FF Basic Functionality consistent with conventional • FF Reliability meets that of conventional • FF Configuration consistent with Conventional Copyright © Saudi Aramco 2004. All rights reserved. No portion of this article may be reproduced by any process or technique without the express written consent of Saudi Aramco Honeywell Users Group Meeting 2004 - Bahrain Test Objectives: Determine FF device & function block action on the following events: 1. Fail Redundant H1 Card & Controller 2. Add / Remove Device from Segment 3. Modify & Download Configuration Back Copyright © Saudi Aramco 2004. All rights reserved. No portion of this article may be reproduced by any process or technique without the express written consent of Saudi Aramco FF Reliability Test Honeywell Users Group Meeting 2004 - Bahrain Reliability Test Example Results Copyright © Saudi Aramco 2004. All rights reserved. No portion of this article may be reproduced by any process or technique without the express written consent of Saudi Aramco Honeywell Users Group Meeting 2004 - Bahrain Aramco’s Fieldbus Approach 2. Approving a Fieldbus Solution – Must Pass 3 Aramco Tests that Verify: • FF Basic Functionality consistent with conventional • FF Reliability meets that of conventional • FF Configuration consistent with Conventional Copyright © Saudi Aramco 2004. All rights reserved. No portion of this article may be reproduced by any process or technique without the express written consent of Saudi Aramco Honeywell Users Group Meeting 2004 - Bahrain Configuration Test Purpose Configuration: Verify that both DCS conventional and FF control and I/O configuration is done in similar way and on a consistent configurator. Offline Configuration: Verify that FF configurations may be made off-line , e.g. when no physical I/O is connected to the system. Displays: Verify that conventional and FF points operate consistently on faceplates, & custom graphics. Operator View: Verify on-line changes, saves, historization, trending and alarming is consistent for conventional and FF. Copyright © Saudi Aramco 2004. All rights reserved. No portion of this article may be reproduced by any process or technique without the express written consent of Saudi Aramco Back Honeywell Users Group Meeting 2004 - Bahrain Honeywell FF Test Hardware Copyright © Saudi Aramco 2004. All rights reserved. No portion of this article may be reproduced by any process or technique without the express written consent of Saudi Aramco Honeywell Users Group Meeting 2004 - Bahrain Currently Approved FF Solutions Emerson DeltaV Yokogawa Centum ALF111 Honeywell EPKS – All 3 FF solutions well integrated in DCS. – High consistency between FF and conventional. – FF Redundancy provided. – A few issues, but... – All committed to make FF project successful. Copyright © Saudi Aramco 2004. All rights reserved. No portion of this article may be reproduced by any process or technique without the express written consent of Saudi Aramco Honeywell Users Group Meeting 2004 - Bahrain Aramco’s Fieldbus Approach 1. Fieldbus Strategy 2. Approving a Fieldbus Solution 3. Requirements for Fieldbus Installation Copyright © Saudi Aramco 2004. All rights reserved. No portion of this article may be reproduced by any process or technique without the express written consent of Saudi Aramco Honeywell Users Group Meeting 2004 - Bahrain Aramco’s Fieldbus Approach 1. Fieldbus Strategy 2. Approving a Fieldbus Solution 3. Requirements for Fieldbus Installation Copyright © Saudi Aramco 2004. All rights reserved. No portion of this article may be reproduced by any process or technique without the express written consent of Saudi Aramco Honeywell Users Group Meeting 2004 - Bahrain Aramco’s Fieldbus Approach 3. Requirements for FF Installation z SAES-J-904: – Requirements for a Quality FF Installation – Includes Discussion of ‘Intent’ Copyright © Saudi Aramco 2004. All rights reserved. No portion of this article may be reproduced by any process or technique without the express written consent of Saudi Aramco Honeywell Users Group Meeting 2004 - Bahrain Aramco’s Fieldbus Approach 3. Requirements for FF Installation J-904 Requirements: – – – – – – – Redundant H1 Interface Cards Redundant FF Power Supply / Segment Spur Short Circuit Protection With Control - Max. 8 devices per Segment Monitor Only - Max. 12 devices per Segment Max. 2 final control devices (valves) per Segment Plus Much More Risk Assessment – Spare Capacity Copyright © Saudi Aramco 2004. All rights reserved. No portion of this article may be reproduced by any process or technique without the express written consent of Saudi Aramco Honeywell Users Group Meeting 2004 - Bahrain Aramco’s Fieldbus Approach H1 Interface Card FF Power Supply w/ Terminator Spur Length & Min Voltage Relcom Megablock w/ Spurguard Field Devices Copyright © Saudi Aramco 2004. All rights reserved. No portion of this article may be reproduced by any process or technique without the express written consent of Saudi Aramco Terminator Honeywell Users Group Meeting 2004 - Bahrain Aramco’s Fieldbus Approach SAES-J-904: ISS Additions for FF z LAS capable (yes/no) z Minimum Operating Voltage (Vdc) z Quiescent Current Draw (mA) z Polarity Sensitive Termination (yes/no) z DD revision level z Channel number and Description, (e.g., Channel 1 - Sensor 1, Channel 2 - Body Temperature, Channel 3 - Sensor 2, etc.). z Function Blocks Available, (e.g., AI_1, AI_2, PID_1, etc.) Copyright © Saudi Aramco 2004. All rights reserved. No portion of this article may be reproduced by any process or technique without the express written consent of Saudi Aramco Honeywell Users Group Meeting 2004 - Bahrain Aramco’s Fieldbus Approach 1. Fieldbus Strategy 2. Approving a Fieldbus Solution 3. Requirements for Fieldbus Installation Copyright © Saudi Aramco 2004. All rights reserved. No portion of this article may be reproduced by any process or technique without the express written consent of Saudi Aramco Honeywell Users Group Meeting 2004 - Bahrain Aramco’s Fieldbus Approach 1. Fieldbus Strategy 2. Approving a Fieldbus Solution 3. Requirements for Fieldbus Installation How will YOU approach Fieldbus on your next project? Copyright © Saudi Aramco 2004. All rights reserved. No portion of this article may be reproduced by any process or technique without the express written consent of Saudi Aramco Honeywell Users Group Meeting 2004 - Bahrain END Copyright © Saudi Aramco 2004. All rights reserved. No portion of this article may be reproduced by any process or technique without the express written consent of Saudi Aramco Honeywell Users Group Meeting 2004 - Bahrain