Saudi Aramco’s
Experience with
FOUNDATION Fieldbus
Hamad S. Balhareth
Saudi Aramco
Presentation Outline
The Objective.
Saudi Aramco’s Fieldbus Installation History.
FF-SIF…Where are we?
Concerns & Wish List.
Conclusion & Questions?
2
The Objective
• Present Saudi Aramco’s FF Standard
Update.
• Installation History and Future Projects.
• FF-SIF… where are we?
3
Saudi Aramco’s Fieldbus Installation
History
FF has Benefits you can’t Ignore

PIB
Project Savings
Junction Box
D
D
“Home Run” Cable
(Trunk)
D
Conventional Wiring
TB’s
87 devices
TB’s for FF
16 segments
Up to 256 devices
4
Fieldbus Installation History & Future
Projects

5
Current FF Installations/Projects in Aramco
•
Abqaiq Plants – 3 Separate (expansion 1000pts - installed)
•
Qatif GOSP (grassroots 2000pts - installed)
•
Jeddah Refinery (moderization 500pts - installed)
•
Riyadh Refinery DHT (new unit 1000pts - installed)
•
Zuluf GOSP2 (modernization 400pts - installed)
•
SA GOSPs (modernization 400pts - installed)
•
Hawiyah NGL (grassroots 5000+ FF points - installed)
•
AFK GOSP/Gas Plant (grassroots 7000+ FF points - installed)
•
KURS GOSP (grassroots 1000+ FF points - installed)
•
Rabigh Refinery/Chemical (grassroots16000+ FF points - installed)
•
Khurais Producing Dept. (grassroots 4490 points – installed)
•
Ras Tanura Refinery DHT (new unit 737pts - Installed)
•
Karan Projects (grassroots 2324pts - Installed)
•
Manifa Project (grassroots 19000+ FF points – development)
•
WASIT (grassroots 9059+ FF points – design) – 69910 total so far.
•
RTIP Projects(grassroots 40000+ FF points – design) close to 110,000 total so far
Saudi Aramco’s Fieldbus Standard
Update
• Requirements for FF
Installation
• SAES-J-904:
 Requirements for a
Quality FF Installation
6
Saudi Aramco’s Fieldbus Installation
History
• Requirements for FF Installation
7

J-904 Requirements:

Redundant H1 Interface Cards

Redundant FF Power Supply / Segment

Spur Short Circuit Protection EEx nL Installation

With Control - Max. 10 devices per Segment

Monitor Only - Max. 12 devices per Segment

Max. 2 final control devices (valves) per Segment

Risk Assessment – Spare Capacity

Plus Much More
Saudi Aramco’s FF-ISD
H1 Interface
Card
FF Power
Supply w/
Terminator
Spur Length
& Min Voltage
Block with
Short Circuit
Protection
Field Devices
8
Terminator
Saudi Aramco’s FF-ISS
SAES-J-904: ISS Additions
for FF
•
•
•
•
•
•
•
9
LAS capable (yes/no)
Minimum Operating Voltage (Vdc)
Quiescent Current Draw (mA)
Polarity Sensitive Termination (yes/no)
DD revision level
Channel number and Description,
(e.g., Channel 1 - Sensor 1, Channel 2 - Body
Temperature, Channel 3 - Sensor 2, etc.).
Function Blocks Available, (e.g., AI_1, AI_2,
PID_1, etc.)
Saudi Aramco’s FF Concerns & Wish
List

Aramco’s Biggest FF Problems:
1. Investigating Plug-In and Snap-On Software
2. Reliability of Diagnostic Alerts
3. Contractor knowledge of Commissioning FF
Devices
4. Lack of True OpEx Saving Experience
10
Conclusion
• FF technology is the way to go.
• It would be a complete failure if FF-SIF
diagnostic alerts are not reliable.
• Can the black channel technology be
implemented for control instruments?
11