Network Resource Interconnection Service September 12, 2013 1 MISO Process 2 Presentation Purpose • Presentation given at the request of stakeholders during the last meeting • Purpose is to explain why MISO uses the deliverability methodology – MISO adapted the methodology from the one PJM uses for the same purposes – MISO’s belief and experience shows this method superior to an increment/decrement methodology – MISO’s belief is that the increment/decrement methodology artificially limits commerce to the detriment of the ratepayer 3 Drivers of Deliverability Methodology Order 2003 • Created Network Resource Interconnection Service Product • Drove MISO to review how new gens were studied Energy Market • Complete paradigm shift away from bilateral service requests and scheduling • Needed study methods to reflect the new tariff Ancillary Serv. Market • Consolidated the Balancing Authorities • Dispatch as one fleet, need study method alignment Resource Adequacy • Deliverability now key to capacity construct • Test for universal deliverability key to making zonal construct work Deliverability Concepts …. Deliverability Testing: • Study technique to examine ability of generation in aggregate, to serve load in aggregate • Tests non-dispatched generation without building multiple cases • Determines individual generator’s ability to contribute to aggregate service • Pre-certifies generator for designation by a network load Deliverability Testing DOES NOT: • • • • • Provide firm transmission service Create new transmission capability without upgrades Take away firm service already granted Influence Real-Time market dispatch Absolve any load serving responsibilities 5 Deliverability Concepts Applied to Resource Adequacy and Planning • Generators generally have to be deliverable to the whole footprint to be a capacity resource • Location of deliverable generators counted on for capacity is dependent on 3 major values: • Zonal Import Limit • Zonal Export Limit • Local Clearing Limit • These limits ensure that we are not counting on capacity resources over and above what the transmission system can handle 6 Basic Deliverability Concepts … Load Deliverability Generator Deliverability Generation can get out of the local area at a time of need Generation can get into the local area at a time of need Generator Load Load reliability Assessment Generator Interconnection Studies All other studies Reliable System Differences Between Tradition and Deliverability Algorithms … • Deliverability algorithm ensures generation can operate at maximum capability without being “bottled up” Traditional • Set up a handful of base cases • Determine flow on the transmission elements • System intact • Selected contingencies • Assess change in flow from the proposed transfer Deliverability • Set up one base case • Determine flow on transmission elements • System intact • Selected contingencies • Determine the flow on transmission elements from undispatched generation • Find pockets of constrained generation 8 SPP Process 9 Generator Interconnection Studies • No deliverability of energy implied in the Generator Interconnection Process • Generators must go through the Transmission Service Process to be designated as a Resource • Network Resource Interconnection Service is available, but grants no deliverability. 10 Generator Interconnection Studies • Source – – Generator being studied • Sink – – ERIS – entire SPP footprint – NRIS – Host Transmission Owner System • Constraints Identified for Transmission Reinforcement – ERIS – overloads with 20% sensitivity factor – NRIS – overloads with 3% sensitivity factor 11 Transmission Service – Designation of a Network Resource • Source – – Resource being studied • Sink – – Network Customer’s Network Load • Constraints Identified for Transmission Reinforcement – overloads with 3% sensitivity factor 12