STATE OF VERMONT PUBLIC SERVICE BOARD Petition of Vermont Transco, LLC, and Vermont Electric Power Company, Inc. (collectively, “VELCO”), and Central Vermont Public Service Corporation (“CVPS”) for a Certificate of Public Good, pursuant to 30 V.S.A. § 248, for the “Southern Loop Project,” located in Vernon, Guilford, Brattleboro, Dummerston, Newfane, Brookline, Townshend, Grafton, Windham, Andover, Chester, Ludlow and Cavendish, Vermont, consisting of the following elements: (1) a new, approximately 51-mile, 345 kV transmission line between Vernon-Cavendish, to be built parallel to and within the same utility right-of-way as VELCO’s existing Vernon-Cavendish 345 kV line; (2) a new VELCO 345/115 kV Vernon substation, to be located just north of the Vermont Yankee Nuclear Power Station; (3) a new 345/115/46 kV Newfane substation; (4) a new, approximately one-mile, 345 kV transmission line loop between the new Newfane substation and the new VernonCavendish 345 kV line; (5) expansion of VELCO’s Coolidge substation in Cavendish, Vermont; and (6) the implementing of incremental energy efficiency to defer transmission upgrades in Southern Vermont ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) Docket No. ____ PREFILED TESTIMONY OF JEFFREY DISORDA ON BEHALF OF PETITIONERS November 8, 2007 The purpose of Mr. Disorda’s testimony is to address VELCO’s Transmission Vegetation Management Program. TABLE OF CONTENTS 1. Introduction ....................................................................................................................1 2. Overview Right-of-Way Maintenance ...........................................................................2 3. Transmission Vegetation Management Standards ..........................................................5 4. VELCO’s Transmission Vegetation Management Program........................................13 5. Clearing the ROW for the Southern Loop Project .......................................................24 6. Conclusion ...................................................................................................................26 EXHIBITS Exhibit Petitioners JD-1 Resume of Jeffrey Disorda Exhibit Petitioners JD-2 VELCO Transmission Vegetation Management Plan Exhibit Petitioners JD-3 Utility Vegetation Management and Bulk Electric Reliability Report from the Federal Energy Regulatory Commission (September 7, 2004) Exhibit Petitioners JD-4 NERC Transmission Vegetation Management Reliability Standard FAC-003-1 Exhibit Petitioners JD-5 Order on Violation Risk Factors, Docket Nos. RR07-12-00 (FERC, June 26, 2007) Exhibit Petitioners JD-6 ISO New England Operating Procedure No. 3, Appendix C Exhibit Petitioners JD-7 American National Standards Institute Standard A300 Exhibit Petitioners JD-8 Permit to Conduct Rights of Way Herbicide Treatment Exhibit Petitioners JD-9 Agency of Natural Resources Department of Environmental Conservation Notice of Issuance of Conditional Use Determination #2005-240 Exhibit Petitioners JD-10 Study of the Impacts of Vegetation Management Techniques on Wetlands for Utility Rights-of-Way in the Commonwealth of Massachusetts (June, 1989) Exhibit Petitioners JD-11 W.C. Bramble and W.R. Byrnes, Thirty Years of Research on Development of Plant Cover on an Electric Transmission Right-of-Way, Journal of Arboriculture 9(3), March 1983 Exhibit Petitioners JD-12 W.C. Bramble and W.R. Byrnes, Integrated Vegetation Management of an Electric Utility Right-of-Way Ecosystem, Down to Earth, Vol 51, No. 2 (1996) Exhibit Petitioners JD-13 R.H. Yahner, R.J. Hutnik, and S.A. Licinsky, Bird Populations Associated with an Electric Transmission Right-of-Way, Journal of Arborculture 28(3), May 2002 Exhibit Petitioners JD-14 Habitat Appraisal VETCO DC Line Exhibit Petitioners JD-15 ANR Memorandum Regarding Herbicide Applications on Rights of Way Exhibit Petitioners JD-16 Coolidge Substation Tree Clearing Plan (1 sheet, sheet 216-TCP-1) Exhibit Petitioners JD-17 Newfane Substation Tree Clearing Plan (1 sheet, sheet NEW-TCP-1) STATE OF VERMONT PUBLIC SERVICE BOARD Petition of Vermont Transco, LLC, and Vermont Electric Power Company, Inc. (collectively, “VELCO”), and Central Vermont Public Service Corporation (“CVPS”) for a Certificate of Public Good, pursuant to 30 V.S.A. § 248, for the “Southern Loop Project,” located in Vernon, Guilford, Brattleboro, Dummerston, Newfane, Brookline, Townshend, Grafton, Windham, Andover, Chester, Ludlow and Cavendish, Vermont, consisting of the following elements: (1) a new, approximately 51-mile, 345 kV transmission line between Vernon-Cavendish, to be built parallel to and within the same utility right-of-way as VELCO’s existing Vernon-Cavendish 345 kV line; (2) a new VELCO 345/115 kV Vernon substation, to be located just north of the Vermont Yankee Nuclear Power Station; (3) a new 345/115/46 kV Newfane substation; (4) a new, approximately one-mile, 345 kV transmission line loop between the new Newfane substation and the new VernonCavendish 345 kV line; (5) expansion of VELCO’s Coolidge substation in Cavendish, Vermont; and (6) the implementing of incremental energy efficiency to defer transmission upgrades in Southern Vermont ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) Docket No. ____ PREFILED TESTIMONY OF JEFFREY DISORDA ON BEHALF OF PETITIONERS 1 1. Introduction 2 Q1. Please state your name, occupation, business address, and qualifications. 3 A1. My name is Jeffrey Disorda. My business address is Vermont Electric Power 4 Company, Inc. (“VELCO”), 366 Pinnacle Ridge Road, Rutland, Vermont 05701. Southern Loop Project, PSB Docket No. _____ Prefiled Testimony of Jeffrey Disorda November 8, 2007 Page 2 of 26 1 I am the Supervisor of Right-of-Way (“ROW”) Management at VELCO. I have 2 been in this position for three years. My resume is attached as Exhibit Petitioners 3 JD-1. 4 5 Q2. Please describe your educational background and work experience. 6 A2. I have an associates degree in Urban Tree Management from Paul Smith’s 7 College. I have 16 years of experience in Utility Vegetation Management. 8 9 Q3. Do you hold any professional licenses or certifications? 10 A3. Yes, I am an International Society of Arboriculture Certified Arborist and 11 Certified Arborist Utility Specialist. 12 13 Q4. What is the purpose of your testimony in this proceeding? 14 A4. I will describe VELCO’s Transmission Vegetation Management Plan (“TVMP”), 15 which is attached as Exhibit Petitioners JD-2. 16 17 2. Overview Right of Way Maintenance 18 Q5. Why is transmission vegetation management important? 19 A5. Vegetation management is important because inadequate vegetation management 20 presents a serious risk to the safety and reliability of the Vermont and 21 interconnected regional and national electric grid. VELCO is responsible for 22 maintaining the integrity and reliability of over 688 miles of high voltage (115 kV Southern Loop Project, PSB Docket No. _____ Prefiled Testimony of Jeffrey Disorda November 8, 2007 Page 3 of 26 1 and above) electric transmission lines, which includes managing vegetation on 2 nearly 12,000 acres of ROW which extends throughout the State of Vermont and 3 portions of New Hampshire. As the Transmission Operator (“TO”) of the 4 Vermont high voltage electric transmission network, and TO of a portion of the 5 interconnected regional and national transmission electric grid, VELCO must 6 manage vegetation in its ROWs to prevent contact between its transmission lines 7 and vegetation. Contact between vegetation and conductors can result in 8 sustained transmission system outage and could directly contribute to power 9 system instability, separations, or a cascading sequence of failures. 10 11 Q6. 12 13 Are there examples of system outages that have been attributed to conductorvegetation contact? A6. On August 14, 2003, an electric power blackout occurred over large portions of 14 the northeast and midwest United States and Ontario, Canada. The blackout 15 lasted up to two days in some areas of the United States, and even longer in some 16 areas of Ontario. It affected an area with over 50 million people and 61,800 17 megawatts of electric load. See Exhibit Petitioners JD-3, Utility Vegetation 18 Management and Bulk Electric Reliability Report from the Federal Energy 19 Regulatory Commission (September 7, 2004) (“FERC Report”), at 4. On April 5, 20 2004, a joint U.S-Canada Power System Outage Task Force issued a Final Southern Loop Project, PSB Docket No. _____ Prefiled Testimony of Jeffrey Disorda November 8, 2007 Page 4 of 26 1 Blackout Report1 (the “Blackout Report”) stating that one of the four primary 2 causes of the blackout was inadequate vegetation management. Specifically, 3 during the hour before the cascading blackout occurred, three FirstEnergy 4 Corporation 345 kV transmission lines failed as a result of contact between the 5 lines and overgrown vegetation that encroached into the clearance zones for the 6 lines. The Blackout Report also compared the August 2003 blackout with seven 7 previous major outages and concluded that conductor contact with trees was a 8 common factor among the outages. 9 10 In March of 2004, the Federal Energy Regulatory Commission (“FERC”) issued a 11 128-page vegetation management report to supplement the Blackout Report. In it, 12 FERC concluded that the 2003 blackout likely would not have occurred had 13 FirstEnergy’s ROWs been adequately maintained to prevent conductor-vegetation 14 contact. The report also concluded that FirstEnergy’s vegetation maintenance 15 practices were consistent with industry standards, but that industry standards were 16 inadequate. 17 18 1 U.S.-Canada Power System Outage Task Force, Final Report on the August 14 th Blackout in the United States and Canada: Causes and Recommendations (April 2004). Southern Loop Project, PSB Docket No. _____ Prefiled Testimony of Jeffrey Disorda November 8, 2007 Page 5 of 26 1 2 3. Transmission Vegetation Management Standards Q7. Have there been any industry or regulatory initiatives undertaken as a result of the 3 findings relating to the role of vegetation management practices in causing or 4 contributing to power system blackouts? 5 A7. Yes, several. In response to the Blackout Report, the FERC directed all 6 designated TOs to submit reports regarding their vegetation management 7 practices, and the FERC staff worked with the National Association of Regulatory 8 Utility Commissioners’ (“NARUC”) ad-hoc Committee on Critical Infrastructure 9 to analyze the reports and look for significant patterns and potential problems in 10 the vegetation management practices of the electric industry. The FERC issued 11 the FERC Report to Congress on September 7, 2004, summarizing its findings 12 and recommendations. See Exhibit Petitioners JD-3. The FERC Report 13 summarized ten principal recommendations: 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1) Congress should enact mandatory and enforceable reliability standards; 2) Effective transmission vegetation management requires clear, unambiguous, enforceable standards that adequately describe actions necessary by each responsible party. 3) It is important that state and federal regulators continue to coordinate so that jurisdictional considerations do not impede effective vegetation management. 4) Federal and state regulators should allow reasonable recovery for the costs of vegetation management expenses. 5) With respect to permitting on federally managed public lands, the FERC should work with the Council on Environmental Quality and land management agencies to better coordinate the requirements. 6) Federal, state and local land managers should develop “rush” procedures and emergency exemptions to allow utilities to correct “danger” trees that threaten transmission lines, from both on and off documented rights-of-way. 7) Five-year vegetation management cycles should be shortened and the FERC and states should look at the cost-effectiveness of more aggressive vegetation management practices. Southern Loop Project, PSB Docket No. _____ Prefiled Testimony of Jeffrey Disorda November 8, 2007 Page 6 of 26 1 2 3 4 5 6 7 8 9 10 11 8) Transmission owners should fully exercise easement rights for vegetation management and better anticipate the permitting process for scheduled vegetation management. 9) Variances in vegetation management practices may be resolved by NERC or by a stakeholder process. 10) State regulators and the utility industry should work through NARUC, the National Conference of State Legislators, and other organizations to help state and local officials better understand and address transmission vegetation management. Id. at 3-4. 12 13 Q8. 14 15 16 17 18 19 20 21 22 23 24 25 26 27 What did the FERC Report state regarding recommendation no. 8, that utilities should fully exercise their easement rights? A8. The FERC Report stated that: “In general, if a utility has a wider right-of-way, well documented easement rights, and exercises those rights fully, it will be more successful in avoiding vegetation-line contact than a utility that maintains narrower rights-of-way. A narrow right-of-way increases the risk of contact with vegetation that is outside of the right-of-way and adjacent to the transmission line. Expert Commentary included in the CNUC Final Vegetation Report stated, “[m]ost tree/power line contacts occur when trees fall onto lines from outside the rights-of-way. Utilities are slow to act to address this issue due to the perception of increased costs and the pressure from landowners etc. to leave the trees standing.’” Id. at 8. 28 Q9. Did the FERC Report address clearances between conductors and vegetation? 29 A9. Yes. The FERC Report concluded that the maintenance of sufficient vertical 30 clearances between conductors and vegetation is “essential” because direct 31 physical contact is not necessary for a line outage to occur. An electric arc can 32 occur between a part of a tree and a conductor without sufficient clearance. Southern Loop Project, PSB Docket No. _____ Prefiled Testimony of Jeffrey Disorda November 8, 2007 Page 7 of 26 1 Id. at 10. The FERC Report also identified a number of recommended good 2 utility vegetation management practices, including establishment of a wire zone – 3 border zone, which the FERC stated is both effective and environmentally 4 friendly in ensuring reliability. This method involves creating a low-growing 5 vegetation environment directly under transmission lines, which physically 6 prevents dangerous vegetation from encroaching into energized transmission 7 facilities. As I discuss below, this is the approach VELCO employs in its TVMP. 8 9 Q10. 10 11 Have reliability standards governing transmission vegetation management been developed? A10. Yes, both federal and regional standards have been developed. On August 8, 12 2005, Congress passed the Energy Policy Act of 2005 (EPAct 2005), which 13 requires FERC to certify an Electric Reliability Organization (“ERO”) to develop 14 mandatory and enforceable Reliability Standards, subject to FERC review and 15 approval. 16 17 On February 3, 2006, FERC certified the North American Electric Reliability 18 Council (“NERC”) as the Electric Reliability Organization, and in April and 19 August of 2006, NERC submitted 107 proposed Reliability Standards, including a 20 Vegetation Management Reliability Standard -- FAC-003-1 -- for FERC approval. 21 FERC, Mandatory Reliability Standards for the Bulk-Power System, 117 FERC 22 ¶61,084, ¶380 (Oct. 20, 2006) (Docket No. RM06-16-000). Southern Loop Project, PSB Docket No. _____ Prefiled Testimony of Jeffrey Disorda November 8, 2007 Page 8 of 26 1 2 On March 16, 2007, FERC adopted the NERC Transmission Vegetation 3 Management Reliability Standard, FAC-003-1 (Exhibit Petitioners JD-4), subject 4 to the requirement that NERC subject the standard to its development process to 5 extend the applicability of the standard to lower voltage facilities that have an 6 impact on reliability. FERC Order No. 693, at 201. 7 8 Q11. Please describe the NERC standard. 9 A11. The stated purpose of the NERC Transmission Vegetation Management 10 Reliability Standard is: “To improve the reliability of the electric transmission systems by preventing outages from vegetation located on transmission rightsof-way (ROW) and minimizing outages from vegetation located adjacent to ROW, maintaining clearances between transmission lines and vegetation on and along transmission ROW, and reporting vegetation-related outages of the transmission systems to the respective Regional Reliability Organizations (RRO) and the North American Electric Reliability Council (NERC).” 11 12 13 14 15 16 17 18 19 20 Exhibit Petitioners JD-4, NERC Standard FAC-003-1 at ¶ A.3. The standard 21 establishes two primary reliability requirements. Requirement R1 22 requires a transmission owner to develop a transmission vegetation management 23 program, and Requirement R2 requires a transmission owner to implement the 24 program and to document its implementation. Each program must be designed 25 for the geographical area and specific design configurations of the transmission 26 owner’s system. FERC Order No. 693, at 198. The NERC Standard requires a Southern Loop Project, PSB Docket No. _____ Prefiled Testimony of Jeffrey Disorda November 8, 2007 Page 9 of 26 1 transmission owner to define a schedule for and the type (aerial or ground) of 2 ROW vegetation inspections. In addition, it requires a transmission owner to 3 determine and document the minimum allowable clearance between energized 4 conductors and vegetation before the next trimming. Id. The minimum clearance 5 distances must be “sufficient to prevent outages due to vegetation management 6 practices under all applicable conditions.” FERC, Mandatory Reliability 7 Standards for the Bulk-Power System, 117 FERC ¶61,084, ¶380 (Oct. 20, 2006) 8 (Docket No. RM06-16-000). 9 10 Q12. 11 12 Has VELCO prepared a Transmission Vegetation Management Plan in accordance with the NERC Standard? A12. Yes. It is attached as Exhibit Petitioners JD-2. Q13. Does the NERC Transmission Vegetation Management Reliability Standard apply 13 14 15 16 to the Southern Loop Project transmission lines? A13. Yes. The NERC standard is mandatory, and applies to all transmission lines 17 operated at 200 kV and above and to any lower voltage lines designated by the 18 Regional Reliability Organization (“NPCC”), as critical to the reliability of the 19 electric system in the region. Exhibit Petitioners JD-4, NERC Transmission 20 Vegetation Management Standard FAC-003-1 at ¶ A.4.3. The NERC standard 21 applies to the existing Vernon to Coolidge 345 kV line (the “340 line”), the 22 proposed new Vernon to Coolidge 345 kV line (the “360 line”), and to the Southern Loop Project, PSB Docket No. _____ Prefiled Testimony of Jeffrey Disorda November 8, 2007 Page 10 of 26 1 proposed Newfane Loop 345 kV line, since they are at voltages above the 200 kV 2 threshold. I would note that the 200 kV threshold adopted by NERC in FAC-003- 3 1, is a topic of continuing discussion. In its recent Order No. 293, FERC 4 instructed NERC to revise the standard through NERC’s Reliability Standards 5 development process, “with the expectation that the applicability of this 6 Reliability Standard will expand to include additional facilities that impact 7 reliability that currently are not covered by this Reliability Standard.” FERC 8 Order No. 293, at 202. 9 10 Q14. What is the consequence of non-compliance with the NERC standard? 11 A14. Under the Federal Energy Policy Act of 2005, NERC is empowered to impose 12 economic fines for non-compliance up to $1 million/day. While NERC’s 13 authority to impose fines was only recently enacted, it is likely that the level of 14 fines imposed will be determined by the severity of non-compliance which is 15 established by several factors, including the nature of the tree contact (e.g., a 16 grow-in from under the line is more serious than a fall-in from within the 17 corridor) and the adequacy of the utility’s Vegetative Management Plan. Just 18 recently, FERC affirmed NERC’s assignment of a “high” Violation Risk Factor to 19 Requirements R1 and R2 of the NERC Vegetation Management Reliability 20 Standard (development of a vegetation management program and implementation 21 of the program). NERC has defined three levels of Violation Risk Factors that it 22 will assign to its Reliability Standards: (1) high risk requirement; (2) medium risk Southern Loop Project, PSB Docket No. _____ Prefiled Testimony of Jeffrey Disorda November 8, 2007 Page 11 of 26 1 requirement; and (3) lower risk requirement. The Violation Risk Factors are used 2 by NERC and Regional Entities in determining financial penalties for violating 3 the Reliability Standards. FERC, Order on Violation Risk Factors, Docket Nos. 4 RR07-12-00, at 4 (June 26, 2007) (Exhibit Petitioners JD-5). In approving 5 NERC’s assignment of a “high” Violation Risk Factor to the vegetation 6 management standards, FERC stated that the assignment is appropriate because 7 “vegetation management presents a serious risk of sustained transmission outage 8 and could directly cause or contribute to Bulk-Power System instability, 9 separation, or a cascading sequence of failures. Both planning and 10 implementation are critical to vegetation management.” Id. at 4. The assignment 11 of a “high” Violation Risk Factor to a violation of the NERC Vegetation 12 Management Reliability Standard confirms that NERC expects transmission 13 owners to take vegetation management programs very seriously, and that any 14 violation could result in serious penalties. 15 16 Q15. Are there any regional transmission vegetation management standards? 17 A15. Yes. ISO-New England, Inc. (“ISO-NE”) recently adopted a standard, ISO-NE 18 Operating Procedure (OP) 3, Appendix C - ISO New England Right-of-Way 19 Vegetation Management Standard (February 1, 2005) (Exhibit Petitioners JD-6) 20 (the “OP3 Standard”). The stated objective of this standard is to “achieve and 21 maintain a high degree of reliability for the New England Transmission System.” 22 Id. at 1. The OP3 Standard applies to transmission voltages of 69 kV and above, Southern Loop Project, PSB Docket No. _____ Prefiled Testimony of Jeffrey Disorda November 8, 2007 Page 12 of 26 1 and therefore applies to all VELCO ROWs. ISO-NE’s Vegetation Management 2 Standards Task Force is currently in the process of revising line standard. I am a 3 member of this Task Force. Based upon discussions to date, I would anticipate 4 the new ISO-NE OP3 Standard to look very much like the NERC Standards, 5 although the ISO-NE Standard will apply to all Pool Transmission Facility 6 (“PTF”) portions of the New England transmission network. 7 8 Q16. 9 10 Has the VELCO TVMP been developed to meet the requirements of the NERC and ISO-NE transmission vegetation management standards? A16. Yes. In addition, we looked to the American National Standards Institute 11 (“ANSI”) Standard A300 – Standard Practices for Tree, Shrub and Other Woody 12 Plant Maintenance (Integrated Vegetation Management - Electric Utility Rights- 13 of-Way) Exhibit Petitioners JD-7. I expect that the VELCO TVMP will be 14 revised from time to time as both the NERC and ISO-NE standards continue to 15 evolve. 16 17 Q17. Please describe the ANSI standard. 18 A17. ANSI A300 Part 7 standards are intended as guides for federal, state, municipal, 19 and private authorities, including property owners, property managers, and 20 utilities in the drafting of their vegetation management practices. The ANSI 21 standard calls for Integrated Vegetation Management designed to promote 22 sustainable plant communities that are compatible with the intended use of the Southern Loop Project, PSB Docket No. _____ Prefiled Testimony of Jeffrey Disorda November 8, 2007 Page 13 of 26 1 utility corridor, and discourage incompatible plants that may pose concerns, 2 including safety, security, access, fire hazard, electric service reliability, 3 emergency restoration, and other requirements. Exhibit Petitioners JD-7. NERC 4 FAC-003-1 cites to the ANSI standard as “an industry best practice.” Exhibit 5 Petitioners JD-4, at n.1. The “wire zone – border zone” concept endorsed by 6 FERC was developed and is more fully explained in the ANSI Standard. 7 VELCO’s TVMP utilizes a wire zone – border zone approach to vegetation 8 management. 9 10 4. VELCO’s Transmission Vegetation Management Program 11 Q18. Please describe VELCO’s Transmission Vegetation Management Plan or TVMP. 12 A18. VELCO’s “TVMP”, Exhibit Petitioners JD-2, describes VELCO’s Transmission 13 Vegetation Management Program. The goal of VELCO’s TVMP is to prevent 14 physical contact between transmission lines and nearby vegetation that could 15 cause a transmission line to fail. In accordance with the NERC and ISO-NE 16 standards, VELCO’s TVMP includes minimum clearances and an approach to 17 vegetation management intended to preserve those clearances. 18 19 VELCO utilizes a system of vegetation management that manages plant 20 communities in which compatible and incompatible vegetation are identified, 21 action thresholds are considered, control methods are evaluated, and selected 22 control(s) are implemented. Choice of control methods is based on safety, Southern Loop Project, PSB Docket No. _____ Prefiled Testimony of Jeffrey Disorda November 8, 2007 Page 14 of 26 1 environmental impact, effectiveness, site characteristics, security, and economics. 2 This system of vegetation management is called Integrated Vegetation 3 Management, a concept recommended in the ANSI Standard, Exhibit Petitioners 4 JD-7. 5 6 VELCO has established a four year vegetation management cycle as an action 7 threshold. This vegetation management cycle has been time tested since 1980, 8 and is based upon engineering design of the lines, the growth rate potential of the 9 vegetation, and required minimum vegetation to conductor clearances. 10 The primary clearance factor is the design of the line. For 345 kV line corridors, 11 such as those involved with the Southern Loop Project, conductor to vegetation 12 clearance requirement at time of clearing and maintenance, is 12 feet, with a 13 maximum safe tree height of 12 feet. Vegetation that generally may mature to 14 greater than 12 feet in height is considered incompatible and removed from the 15 corridor. The 12 foot maximum vegetation height limitation is established based 16 upon growth rates, and the fact that once exceeded, vegetation will encroach into 17 the conductor-vegetation clearance zone before the next clearing cycle, thus 18 posing a risk of vegetation to conductor contact. 19 20 21 Q19. Please explain how the wire zone – border zone approach to vegetation management is applied. Southern Loop Project, PSB Docket No. _____ Prefiled Testimony of Jeffrey Disorda November 8, 2007 Page 15 of 26 1 A19. The wire zone is the area under the conductors and extends to fifteen (15) feet 2 beyond the outside conductor. The objective of the four-year cycle is to reduce 3 the number of stems per acre of the tall-growing, incompatible species tree 4 species in the ROW. Once this is accomplished, the program performs basically 5 to control tree seeds germinating throughout the four-year vegetation management 6 cycle. All tall-growing, incompatible species are eliminated in both the wire zone 7 and the border zone. These incompatible species are identified in the TVMP. 8 The TVMP also identifies lower growing, compatible trees and shrubs that may 9 be allowed to remain in the corridor. The TVMP breaks down compatible tree 10 species into these categories: compatible species allowed within the wire zone, 11 and compatible species allowed within the border zone. The type of compatible 12 vegetation permitted within the border zone includes vegetation that does not 13 normally mature to greater than 12 feet tall, but could exceed 12 feet in height. 14 Any trees that grow taller than 12 feet within the border zone are removed on the 15 next cycle. Vegetation allowed within the wire zone does not mature to greater 16 than 12 feet. Over time, the plant community (trees, shrubs, forbs, ferns and 17 grasses) retained within the ROWs stabilizes into a very low maintenance 18 condition of compatible species. As I discuss later in my testimony, this low 19 growing plant community in the ROW has been found to promote and sustain 20 wildlife habitat in the ROWs. 21 22 Q20. What methods of tree clearing are employed by VELCO? Southern Loop Project, PSB Docket No. _____ Prefiled Testimony of Jeffrey Disorda November 8, 2007 Page 16 of 26 1 A20. Tree clearing is typically performed by VELCO-approved vegetation 2 management contractors using chainsaws. On large tracts such as the Southern 3 Loop Project, trees are cleared with mechanical, specialized tree-clearing 4 equipment. Trees are cut as close as possible to grade (e.g., typically six inches or 5 less), and the stumps are left intact, as this minimizes ground/soil disturbance and 6 promotes soil stability. In some cases, VELCO will remove stumps that are 7 located within access roads, in the immediate vicinity of structure locations, 8 within proposed excavation areas, or based upon other construction-specific 9 needs. 10 11 Q21. Does VELCO use herbicides as part of its vegetation management program? 12 A21. Yes. It is an integral part of our TVMP. Q22. Is VELCO required to obtain any regulatory permits or approvals before it applies 13 14 15 16 herbicides in ROW corridors? A22. Yes, a Permit to Conduct Rights of Way Herbicide Treatment is required from the 17 Agency of Agriculture annually. VELCO’s current permit is attached as Exhibit 18 Petitioners JD-8. The Herbicide Treatment Permit applications are also reviewed 19 annually by the Vermont Pesticide Advisory Council (“VPAC”), which includes a 20 representative from each of ANR’s three departments. VELCO’s Herbicide 21 Treatment Permit restricts the use of herbicides in buffer areas for waters of the 22 state. 10 V.S.A. § 1251 defines “waters of the state” as rivers, streams, creeks, Southern Loop Project, PSB Docket No. _____ Prefiled Testimony of Jeffrey Disorda November 8, 2007 Page 17 of 26 1 brooks, reservoirs, ponds, lakes, springs, and all bodies of surface waters, public 2 and private water supplies, and domiciles. The allowed distance from surface 3 waters depends upon the type of herbicide applied. VELCO’s 2007 Herbicide 4 Treatment Permit allows herbicides to be applied within 10-30 feet of surface 5 waters, depending upon the type of herbicide used, but does not restrict herbicides 6 in uplands or wetlands without surface waters. VELCO’s Conditional Use 7 Determination (“CUD”) for the West Rutland to New Haven 345 kV line, 8 included with my testimony as Exhibit Petitioners JD-9, expressly notes, with 9 respect to herbicides use in wetlands, that “VELCO’s current vegetation 10 management plan presents an overall vegetation management strategy that 11 provides guidelines to appreciate vegetation control while minimizing negative 12 environmental impacts within the ROW and specifically in wetlands.” The use of 13 herbicides has been determined an allowed use in wetlands in accordance with the 14 Vermont Wetland Rules at subsection 6.2(1). In fact, VPAC opined that seasonal 15 application of herbicides to railroad rights of way is exempt under the same 6.2(1) 16 in a memo from Andy Raubvogel, ANR General Counsel, included with my 17 testimony as Exhibit Petitioners JD-15. The TVMP cites to several studies that 18 support the use of herbicides in utility ROWs as an environmentally sound 19 vegetation management technique. 20 21 22 Q23. How does mechanical clearing in ROW compare to herbicide applications in terms of wildlife and environmental resource impacts? Southern Loop Project, PSB Docket No. _____ Prefiled Testimony of Jeffrey Disorda November 8, 2007 Page 18 of 26 1 A23. Several well known studies have evaluated the impacts and benefits of herbicide 2 applications as compared to mechanical clearing of utility ROWs. For example, a 3 study was conducted in Massachusetts in 1989 concerning the use of ROW 4 management techniques, including the use of herbicides to control undesirable 5 vegetation in wetlands. The executive summary of the report is included with my 6 testimony as Exhibit Petitioners JD-10. The study concluded that there is no 7 significant impact to wetlands from vegetation management techniques. 8 Mechanical treatments result in relatively higher impacts than selective herbicide 9 use. Mechanical techniques had a significantly higher impact on the cover value 10 of herbaceous vegetation than herbicide techniques. Wildlife habitat values were 11 rated low for mechanical techniques and medium for herbicide techniques. 12 Residues from petroleum products such as bar and chain oil or hydraulic fluid 13 were found in the leaf litter on mechanically treated sites. No herbicide residues 14 were found on herbicide treated sites. Many wetland species are low growing and 15 are desirable species. By removing the undesirable species the desirable species 16 can out compete undesirable species which reduces need for additional vegetation 17 management during subsequent cycles. 18 19 Another well known study was the 50-year research study of vegetation 20 development and production of wildlife cover on a transmission ROW in 21 Pennsylvania. A copy of each of three articles reporting on this study are 22 included with my testimony as Exhibits Petitioners JD-11 to JD-13. In terms of Southern Loop Project, PSB Docket No. _____ Prefiled Testimony of Jeffrey Disorda November 8, 2007 Page 19 of 26 1 impacts on wildlife habitat, this study has reported that “several important habitat 2 changes that are considered favorable to wildlife were caused by the construction 3 of the ROW and its subsequent maintenance with herbicide sprays.” Exhibit 4 Petitioners JD-12, at 6. Habitat values for areas of the sprayed ROW were much 5 higher than the adjoining forest or even as compared to wildlife clearing in 6 adjacent state gamelands. Id. 7 8 Q24. Does VELCO restrict the use of herbicides near river or stream crossings? 9 A24. Yes. VELCO adheres to buffer distances as set forth in its Herbicide Treatment 10 Permits issued by the Agency of Agriculture. 11 12 Q25. Please explain VELCO’s TVMP approach regarding soil erosion control. 13 A25. Erosion control is a concern when vegetation is completely removed. Promoting 14 stable plant communities on the ROW allows strong, healthy root-mat conditions 15 that are effective in stabilizing soil and controlling erosion. The TVMP 16 encourages compatible plants such as: ferns and grasses, sweet-fern, blueberries, 17 blackberries, raspberries, dogwood and other low-growing shrubs as well as a 18 variety of wild flowers. In areas where there are compatible species, erosion 19 control is typically less of a concern due to the fact that most plant species are not 20 removed. In areas where incompatible species dominate the right of way, erosion 21 controls maybe more of a concern. In these areas the strong root-mat conditions Southern Loop Project, PSB Docket No. _____ Prefiled Testimony of Jeffrey Disorda November 8, 2007 Page 20 of 26 1 of the incompatible species are typically effective in controlling erosion until 2 either compatible species begin to grow in or incompatible species re-sprout. 3 4 Q26. 5 6 Does VELCO’s TVMP address impacts of vegetation management practices upon wildlife habitat? A26. Yes. VELCO’s TVMP strives to have an approach to vegetation management 7 that supports and enhances wildlife habitat. VELCO understands that properly 8 maintained rights of way result in improved wildlife habitat for numerous plant 9 and animal species, including songbirds and rare plants. General observations on 10 VELCO rights-of-way indicate a noticeable bio-diversity that provides very 11 favorable habitat for many wildlife species. Utility ROWs promote low growing 12 desirable vegetation that is maintained in a stable early successional habitat that is 13 disappearing throughout Vermont as farms are abandoned and developed. By 14 managing for early successional habitat, the ROW supports and promotes wildlife 15 habitat improvement. 16 17 There have been many studies on this subject that VELCO references when 18 making vegetation management decisions. The most well known is a continuing 19 research project initiated by Purdue University professors Dr. William Byrnes and 20 Dr. William Bramble. This study has been directed on a transmission line right- 21 of-way in Pennsylvania over the last 50 years. I mentioned the 1983 study 22 finding earlier in my testimony (Exhibit Petitioners JD-11 to JD-13 are articles Southern Loop Project, PSB Docket No. _____ Prefiled Testimony of Jeffrey Disorda November 8, 2007 Page 21 of 26 1 reporting on this study), regarding favorable habitat changes found to occur in 2 utility ROWs. A more recent report from this ongoing study addresses the 3 positive findings regarding bird populations associated with utility ROWs. See 4 Exhibit Petitioners JD-14. The study concentrated on the vegetation on utility 5 rights-of-ways and the relationship to the habitat of wildlife. The research 6 documented the effects that many different vegetation management techniques 7 have on food and cover for whitetail deer, cottontail rabbit, ruffed grouse, wild 8 turkey, songbirds and other small mammals and birds. The conclusions of this 9 study, initially reported in 1983 Exhibit Petitioners JD-11, have documented that 10 Integrated Vegetation Management on rights-of-way can be beneficial to wildlife. 11 12 VELCO also conducts its own wildlife Habitat Appraisal study, in consultation 13 with the Department of Fish and Wildlife at the Vermont Agency of Natural 14 Resources, United States Fish and Wildlife Service and Vermont Institute of 15 Natural Science (VINS) and uses consistent protocols that can be shared amongst 16 all parties. This assessment is conducted once during a cycle (i.e. every four 17 years) along a ten mile stretch of VELCO’s HVDC transmission line ROW. We 18 have learned from our assessments of that corridor that the ROW contributes a 19 diverse habitat of early successional vegetation in a landscape of a maturing 20 northern forest where routine timber harvesting operations are on a decline. 21 Vegetation management techniques have primarily been selective herbicide 22 applications with hand cutting of protective buffers at surface waters. These Southern Loop Project, PSB Docket No. _____ Prefiled Testimony of Jeffrey Disorda November 8, 2007 Page 22 of 26 1 vegetation management methods, applied to the ROW over several cycles, have 2 created a mosaic of herbaceous-plant communities, shrubs, and small trees. As 3 the surrounding forest continues to mature, the ROW becomes a significant 4 source of this diverse, early successional habitat that will help sustain populations 5 of shrubland birds as well as other wildlife. A copy of the recent report on this 6 ongoing study is included with my testimony as Exhibit Petitioners JD-14. 7 8 The VELCO TVMP was also recently certified by the National Wild Turkey 9 Federation (one of the fastest growing, largest, and most respected conservation 10 organizations in the country) as having an approach to vegetation management 11 that promotes improvement to wildlife habitat. VELCO is actively involved with 12 many wildlife partnerships such as the National Wild Turkey Federation, The 13 Ruffed Grouse Society, Wildlife Management Institute, and Vermont Institute of 14 Natural Sciences to better understand its role in wildlife habitat and seek continual 15 improvement to its integrated vegetation management practices. 16 17 Q27. How does VELCO TVMP address wildlife crossing in the ROW? 18 A27. Wildlife travel lanes are maintained on VELCO rights of way in appropriate 19 locations to promote the movement of white tailed deer and other wildlife across 20 the ROW. In general, the management objectives are to favor vegetation that can 21 support snow (softwoods) and thereby keep the snow depth on the ground shallow Southern Loop Project, PSB Docket No. _____ Prefiled Testimony of Jeffrey Disorda November 8, 2007 Page 23 of 26 1 enough for deer to move about easily and conceal wildlife as they cross through 2 wildlife travel lanes. 3 4 Under the TVMP (page 6), specific vegetation management practices in wildlife 5 crossings include: 6 1. Selective removal of trees favoring crown closure. 7 2. Removing cut material or cutting up small enough so as not to 8 interfere with animal movement in the travel lane. 9 3. Promoting compatible species of trees and shrubs. 10 4. Favoring the continued growth and reproduction of coniferous 11 vegetation with canopies that intercept snow. 12 5. Avoid use of mechanical methods during bird nesting season. 13 14 Q28. How does the TVMP address vegetation management at stream crossings? 15 A28. This is discussed at page 7 of the TVMP. The objective of stream crossing 16 management is to favor vegetation that will shade the stream, control erosion, and 17 promote bank stability. Wildlife also use stream crossing as wildlife crossings, 18 and they are managed as such. 19 20 21 22 23 24 Specific vegetation management practices in stream crossings include: 1. Selective removal of trees favoring crown closure to provide shade to the stream. 2. Removing cut material or cutting up small enough so as not to interfere with animal movement in the travel lane. 25 3. Favoring the continued growth and reproduction of compatible 26 vegetation with canopies that provide shade to the stream. Southern Loop Project, PSB Docket No. _____ Prefiled Testimony of Jeffrey Disorda November 8, 2007 Page 24 of 26 1 4. Avoid use of mechanical methods that may cause soil 2 compaction or rutting to the greatest extent possible. 3 5. Leave all stumps in place so that root mat maintains bank 4 stability. 5 6. Remove all slash and debris from the stream. 6 7 5. Clearing the ROW for the Southern Loop Project 8 Q29. Please describe how VELCO plans to clear the ROW for the new Southern Loop 9 10 Project transmission lines. A29. We will expand the area of clearing on the existing 345 kV line from 150 to 250 11 feet (except in the approximately one mile segment on the southern end of the 12 ROW, which has only a 200 foot width), to make room for the second 345 kV line 13 (the 360 line). For the Newfane Loop, we will run parallel with the existing 14 CVPS 46 kV line in the same corridor; the existing CVPS line is located in a 150’ 15 wide ROW, maintained by CVPS generally as a 100’ wide cleared corridor. The 16 Newfane Loop route runs approximately 1 mile from the existing 345 kV corridor 17 in Dummerston to a proposed substation in Newfane. The proposed Newfane 18 Loop will require 78’ of new clearing on the north side of the existing CVPS 46 19 kV line. All vegetation will be removed in the expanded cleared area initially. In 20 addition, trees at the edge and outside of the corridor will be evaluated and 21 removed as necessary if they are deemed to pose a threat to the line because of 22 species, growth pattern, height, health, ledge, soil conditions, erosion or other Southern Loop Project, PSB Docket No. _____ Prefiled Testimony of Jeffrey Disorda November 8, 2007 Page 25 of 26 1 location conditions, disease, and other defects. The Danger Tree Identification 2 Criteria are set forth in our TVMP at pages 29-30. 3 4 Q30. How does VELCO dispose of vegetation that is cleared? 5 A30. To the greatest extent possible, VELCO attempts to chip all trees and brush, as the 6 chips are used to support erosion control measures. In locations where tree 7 clearing is minimal and large equipment is not required for tree clearing, trees will 8 be cut and lopped to lay as flat to the ground as possible to decompose naturally. 9 In some cases, landowners request that VELCO pile or windrow cut trees/logs, so 10 the landowners can use the wood for firewood or other commercial purposes. In 11 these cases, VELCO will chip brush and windrow the larger logs. 12 13 Q31. 14 15 Will VELCO be conducting any additional tree clearing in connection with the Southern Loop Project? A31. Yes. VELCO will be conducting tree clearing at the Coolidge and Newfane 16 substation sites. Those substations are described in detail by VELCO witness 17 Michael Barrett. The clearing at the Coolidge and Newfane substations sites will 18 be conducted in accordance with the Coolidge Tree Clearing Plan and Newfane 19 Tree Clearing Plan, which are Exhibit Petitioners JD- 15 and Exhibit Petitioners 20 JD-16, respectively. 21 22 Southern Loop Project, PSB Docket No. _____ Prefiled Testimony of Jeffrey Disorda November 8, 2007 Page 26 of 26 1 6. Conclusion 2 Q32. Does this conclude your testimony? 3 A32. Yes