University of North Florida ADMINISTRATION & FINANCE Departmental Status Report for Space Committee Meeting Director: Department: Date: Zak Ovadia Campus Planning Design & Construction February 2nd, 2011 I. SELECTED ACTIVE PROJECTS NOTE ALL SCHEDULES ARE TENTATIVE 1. Student Wellness & Sports Education Center Phase I: This project entails the programming, design and construction of a Student Wellness and Sports Education Center (Est. 116,000 GSF). Phase I in roughly 65,000 GSF. Tentative Schedule: Consultant Selection Complete Programming Complete RFQ for Design Complete Consultant Selection Complete Program Verification Complete Schematic Design Complete Design Development Complete Select CM Complete Const. Documents June 2010 Construction January 2011 – February 2012. Changes from last month: No Changes. Project on schedule. 2. Campus-wide Master Planning: Project to re-visit the 2005 Master Plan, update it for the period 2010-2015, and add any new visions for the campus. Tentative Schedule: Consultant Selection Complete First Kick-Off Meeting Complete Focus Groups Complete Changes from last month: BOT approved Master Plan on January 18. Copies were sent to local authorities. 3. Science and Humanities Building (Biological Sciences - TBD): It is anticipated that the building will be roughly 118,000 GSF on three levels. The building will be located adjacent to the Social Sciences Building (51). Tentative Schedule: Consultant Selection Complete Programming Complete Program Verification Complete Schematic Design Complete Design Development Complete Const. Documents March 2010 Select CM Complete Construction August 2010 to February 2012 Changes from last month: No Changes from Last Month. Zak Ovadia 1 JJ Daniel Hall Renovations: Programming of entire building after the decision was made on who will relocate to UNF Hall. This project will be phased over a period of about one year to accommodate occupant schedule. Tentative Schedule: Consultant Selection Complete Programming Complete Program Verification N/A Schematic Design Complete Design Development January 2009 Const. Documents Complete Select CM Complete Construction Jan 2010 to September 2010 Changes from last month: No Changes. Cosmetic work in Pres. Suite started the week of October 8th but was subsequently stopped. Met with Ethan Allen. 4. COE&HS Building with DRC, VCS, VCL and OCT: Project to build a 2 story addition to the College of Education & Human Services of approximately 15,000 GSF. Tentative Schedule: Consultant Selection Complete Programming underway Program Verification underway Schematic Design underway Design Development August 2010 Const. Documents September 2010 Select CM October 2010 Construction January 2011 to August 2011 Changes from last month: Fencing is in place and site work will begin first week in February. 5. Science & Engineering Building Remedial Work: Corrective measures to mitigate building envelope deficiencies. Tentative Schedule: Consultant Selection Complete Programming N/A Program Verification N/A Schematic Design TBD Design Development TBD Const. Documents September 2010 Select CM Complete Construction Dec. 2010 – Dec. 2011 Changes from last month: No Changes. The Weitz Company has started dismantling of west and south facades. Zak Ovadia 2 6. Building 9 Restacking of Building to Accommodate Arts & Sciences needs: Programming, design and construction of the entire building 9 to accommodate identified needs for the expansion of the College of Arts & Sciences. Tentative Schedule: Consultant Selection Complete Programming Complete Program Verification Complete Schematic Design Complete Design Development N/A Construction Docs. In Progress Construction November 2010 – August 2011 Changes from last month: No Changes. Construction started in November with completion anticipated in midMarch, 2011. 7. Sanctuary and Meditation Center: Design and Construction of sanctuary building of approximately 3,500 square feet to serve as a venue for group meditation or events. Tentative Schedule: Programming Complete Conceptual Permitting Complete RFQ for Consultants Complete Short-listing & Interv. Complete Program Verification Complete Schematic Design Complete Design Development TBD Construction Docs. TBD Construction TBD Changes from last month: No Change. 8. New Food Service Facility and General Purpose Building: Design and Construction of a replacement food service facility to replace Osprey Café. Preliminary needs call for a three or four-story building. Tentative Schedule: Programming August 2010 Conceptual Permitting TBD RFQ for Consultants Completed Short-listing & Interv. Completed Program Verification Completed Schematic Design February, 2011 Design Development March 2011 – April 2011 Select CM Complete Construction Docs. May 2011 – August 2011 Demolition May 2011 Construction July 2011 to August 2012 Changes from last month: Selected consultants are Design Plus/Smith McCrary Architects. CM firm selected is Barton-Malow. Conceptual Design started. Zak Ovadia 3 9. New Fine Arts Buildings and Art Gallery: Programming for a new fine arts building to supplement the existing. Order of magnitude of project is yet to be determined. \ Tentative Schedule: Programming August 2010 C onceptual Permitting TBD RFQ for Consultants TBD Short-listing & Interv. TBD Program Verification TBD Schematic Design TBD Design Development TBD Select CM TBD Construction Docs. TBD Construction TBD Changes from last month: Pre-Final Program Document was distributed for review and comments. Final document due in mid February. Completed Projects: Zak Ovadia Brooks College of Health Addition Hodges Stadium Running Track IPTM Storage Building College of Education & Human Services UPD Storage Building Osprey Fountains Housing Student Union English Language Program (ELP) Library Shuttle Bus Shelter Building 8 Renovations for Auxiliary Services Relocation of TV Studio Outside Storage for CCEC Installation of Campus-Wide Speakers UNF Hall Renovations Founders Hall Renovations ROTC Storage Building Relocation of Communication Dept DRC Expansion in Building 10 4