Space Project Update 2-2-2011

advertisement
University of North Florida
ADMINISTRATION & FINANCE
Departmental Status Report for Space Committee Meeting
Director:
Department:
Date:
Zak Ovadia
Campus Planning Design & Construction
February 2nd, 2011
I. SELECTED ACTIVE PROJECTS
NOTE ALL SCHEDULES ARE TENTATIVE
1.
Student Wellness & Sports Education Center Phase I: This project entails the
programming, design and construction of a Student Wellness and Sports Education
Center (Est. 116,000 GSF). Phase I in roughly 65,000 GSF.
Tentative Schedule:
Consultant Selection
Complete
Programming
Complete
RFQ for Design
Complete
Consultant Selection
Complete
Program Verification Complete
Schematic Design
Complete
Design Development Complete
Select CM
Complete
Const. Documents
June 2010
Construction
January 2011 – February 2012.
Changes from last month:
No Changes. Project on
schedule.
2.
Campus-wide Master Planning: Project to re-visit the 2005 Master Plan, update it for
the period 2010-2015, and add any new visions for the campus.
Tentative Schedule:
Consultant Selection
Complete
First Kick-Off Meeting Complete
Focus Groups
Complete
Changes from last month:
BOT approved Master Plan
on January 18. Copies were
sent to local authorities.
3.
Science and Humanities Building (Biological Sciences - TBD): It is anticipated that
the building will be roughly 118,000 GSF on three levels. The building will be located
adjacent to the Social Sciences Building (51).
Tentative Schedule:
Consultant Selection
Complete
Programming
Complete
Program Verification Complete
Schematic Design
Complete
Design Development Complete
Const. Documents
March 2010
Select CM
Complete
Construction
August 2010 to February 2012
Changes from last month:
No Changes from Last Month.
Zak Ovadia
1
JJ Daniel Hall Renovations: Programming of entire building after the decision was
made on who will relocate to UNF Hall. This project will be phased over a period of
about one year to accommodate occupant schedule.
Tentative Schedule:
Consultant Selection
Complete
Programming
Complete
Program Verification N/A
Schematic Design
Complete
Design Development January 2009
Const. Documents
Complete
Select CM
Complete
Construction
Jan 2010 to September 2010
Changes from last month:
No Changes. Cosmetic work in
Pres. Suite started the week of
October 8th but was
subsequently stopped. Met with
Ethan Allen.
4.
COE&HS Building with DRC, VCS, VCL and OCT:
Project to build a 2 story addition to the College of Education & Human Services of
approximately 15,000 GSF.
Tentative Schedule:
Consultant Selection
Complete
Programming
underway
Program Verification underway
Schematic Design
underway
Design Development August 2010
Const. Documents
September 2010
Select CM
October 2010
Construction
January 2011 to August 2011
Changes from last month:
Fencing is in place and site
work will begin first week in
February.
5.
Science & Engineering Building Remedial Work:
Corrective measures to mitigate building envelope deficiencies.
Tentative Schedule:
Consultant Selection
Complete
Programming
N/A
Program Verification N/A
Schematic Design
TBD
Design Development TBD
Const. Documents
September 2010
Select CM
Complete
Construction
Dec. 2010 – Dec. 2011
Changes from last month:
No Changes. The Weitz
Company has started
dismantling of west and south
facades.
Zak Ovadia
2
6.
Building 9 Restacking of Building to Accommodate Arts & Sciences needs:
Programming, design and construction of the entire building 9 to accommodate identified
needs for the expansion of the College of Arts & Sciences.
Tentative Schedule:
Consultant Selection
Complete
Programming
Complete
Program Verification Complete
Schematic Design
Complete
Design Development N/A
Construction Docs.
In Progress
Construction
November 2010 – August 2011
Changes from last month:
No Changes. Construction
started in November with
completion anticipated in midMarch, 2011.
7.
Sanctuary and Meditation Center: Design and Construction of sanctuary building of
approximately 3,500 square feet to serve as a venue for group meditation or events.
Tentative Schedule:
Programming
Complete
Conceptual Permitting Complete
RFQ for Consultants Complete
Short-listing & Interv. Complete
Program Verification Complete
Schematic Design
Complete
Design Development TBD
Construction Docs.
TBD
Construction
TBD
Changes from last month:
No Change.
8.
New Food Service Facility and General Purpose Building: Design and Construction
of a replacement food service facility to replace Osprey Café. Preliminary needs call for
a three or four-story building.
Tentative Schedule:
Programming
August 2010
Conceptual Permitting TBD
RFQ for Consultants Completed
Short-listing & Interv. Completed
Program Verification Completed
Schematic Design
February, 2011
Design Development March 2011 – April 2011
Select CM
Complete
Construction Docs.
May 2011 – August 2011
Demolition
May 2011
Construction
July 2011 to August 2012
Changes from last month:
Selected consultants are
Design Plus/Smith McCrary
Architects. CM firm selected
is Barton-Malow. Conceptual
Design started.
Zak Ovadia
3
9.
New Fine Arts Buildings and Art Gallery: Programming for a new fine arts building
to supplement the existing. Order of magnitude of project is yet to be determined. \
Tentative Schedule:
Programming
August 2010
C
onceptual Permitting TBD
RFQ for Consultants TBD
Short-listing & Interv. TBD
Program Verification TBD
Schematic Design
TBD
Design Development TBD
Select CM
TBD
Construction Docs.
TBD
Construction
TBD
Changes from last month:
Pre-Final Program Document was distributed for
review and comments. Final document due in mid
February.
Completed Projects:


















Zak Ovadia
Brooks College of Health Addition
Hodges Stadium Running Track
IPTM Storage Building
College of Education & Human Services
UPD Storage Building
Osprey Fountains Housing
Student Union
English Language Program (ELP)
Library Shuttle Bus Shelter
Building 8 Renovations for Auxiliary Services
Relocation of TV Studio
Outside Storage for CCEC
Installation of Campus-Wide Speakers
UNF Hall Renovations
Founders Hall Renovations
ROTC Storage Building
Relocation of Communication Dept
DRC Expansion in Building 10
4
Download