University of North Florida
ADMINISTRATION & FINANCE
Departmental Status Report for Space Committee Meeting
Director:
Department:
Date:
Zak Ovadia
Campus Planning Design & Construction
March 2nd, 2011
I. SELECTED ACTIVE PROJECTS
NOTE ALL SCHEDULES ARE TENTATIVE
1.
Student Wellness & Sports Education Center Phase I: This project entails the
programming, design and construction of a Student Wellness and Sports Education
Center (Est. 116,000 GSF). Phase I in roughly 65,000 GSF.
Tentative Schedule:
Consultant Selection
Complete
Programming
Complete
RFQ for Design
Complete
Consultant Selection
Complete
Program Verification Complete
Schematic Design
Complete
Design Development Complete
Select CM
Complete
Const. Documents
June 2010
Construction
January 2011 – February 2012.
Changes from last month:
No Changes. Project on
schedule.
2.
Science and Humanities Building (Biological Sciences - TBD): It is anticipated that
the building will be roughly 118,000 GSF on three levels. The building will be located
adjacent to the Social Sciences Building (51).
Tentative Schedule:
Consultant Selection
Complete
Programming
Complete
Program Verification Complete
Schematic Design
Complete
Design Development Complete
Const. Documents
March 2010
Select CM
Complete
Construction
August 2010 to February 2012
Changes from last month:
No Changes from Last Month.
Project is on schedule.
Zak Ovadia
1
JJ Daniel Hall Renovations: Programming of entire building after the decision was
made on who will relocate to UNF Hall. This project will be phased over a period of
about one year to accommodate occupant schedule.
Tentative Schedule:
Consultant Selection
Complete
Programming
Complete
Program Verification N/A
Schematic Design
Complete
Design Development January 2009
Const. Documents
Complete
Select CM
Complete
Construction
Jan 2010 to September 2010
Changes from last month:
Work continues on
President’s Suite.
3.
COE&HS Building with DRC, VCS, VCL and OCT:
Project to build a 2 story addition to the College of Education & Human Services of
approximately 15,000 GSF.
Tentative Schedule:
Consultant Selection
Complete
Programming
underway
Program Verification underway
Schematic Design
underway
Design Development August 2010
Const. Documents
September 2010
Select CM
October 2010
Construction
January 2011 to August 2011
Changes from last month:
No changes from last month.
Site work started.
4.
Science & Engineering Building Remedial Work:
Corrective measures to mitigate building envelope deficiencies.
Tentative Schedule:
Consultant Selection
Complete
Programming
N/A
Program Verification N/A
Schematic Design
TBD
Design Development TBD
Const. Documents
September 2010
Select CM
Complete
Construction
Dec. 2010 – Dec. 2011
Changes from last month:
No Changes. The Weitz
Company continues
dismantling of facades.
Repair work started on West
and South facades.
Zak Ovadia
2
5.
Building 9 Restacking of Building to Accommodate Arts & Sciences needs:
Programming, design and construction of the entire building 9 to accommodate identified
needs for the expansion of the College of Arts & Sciences.
Tentative Schedule:
Consultant Selection
Complete
Programming
Complete
Program Verification Complete
Schematic Design
Complete
Design Development N/A
Construction Docs.
In Progress
Construction
November 2010 – August 2011
Changes from last month:
No Changes. Construction
started in November with
completion anticipated in midMarch, 2011.
6.
Sanctuary and Meditation Center: Design and Construction of sanctuary building of
approximately 3,500 square feet to serve as a venue for group meditation or events.
Tentative Schedule:
Programming
Complete
Conceptual Permitting Complete
RFQ for Consultants Complete
Short-listing & Interv. Complete
Program Verification Complete
Schematic Design
Complete
Design Development TBD
Construction Docs.
TBD
Construction
TBD
Changes from last month:
No Change.
7.
New Food Service Facility and General Purpose Building: Design and Construction
of a replacement food service facility to replace Osprey Café. Preliminary needs call for
a three or four-story building.
Tentative Schedule:
Programming
August 2010
Conceptual Permitting TBD
RFQ for Consultants Completed
Short-listing & Interv. Completed
Program Verification Completed
Schematic Design
February, 2011
Design Development March 2011 – April 2011
Select CM
Complete
Construction Docs.
May 2011 – August 2011
Demolition
May 2011
Construction
July 2011 to August 2012
Changes from last month:
Conceptual Design started.
Demolition planned for April
2011. Project Substantial
Completion scheduled for
August 2012.
Zak Ovadia
3
8.
New Fine Arts Buildings and Art Gallery: Programming for a new fine arts building
to supplement the existing. Order of magnitude of project is yet to be determined. \
Tentative Schedule:
Programming
August 2010
C
onceptual Permitting
RFQ for Consultants
Short-listing & Interv.
Program Verification
Schematic Design
Design Development
Select CM
Construction Docs.
Construction
Changes from last month:
TBD
TBD
TBD
TBD
TBD
TBD
TBD
TBD
TBD
No changes from last month.
Final document is due in midFebruary.
Completed Projects:



















Zak Ovadia
Brooks College of Health Addition
Hodges Stadium Running Track
IPTM Storage Building
College of Education & Human Services
UPD Storage Building
Osprey Fountains Housing
Student Union
English Language Program (ELP)
Library Shuttle Bus Shelter
Building 8 Renovations for Auxiliary Services
Relocation of TV Studio
Outside Storage for CCEC
Installation of Campus-Wide Speakers
UNF Hall Renovations
Founders Hall Renovations
ROTC Storage Building
Relocation of Communication Dept
DRC Expansion in Building 10
Campus-wide Master Planning