University of North Florida ADMINISTRATION & FINANCE Departmental Status Report for Space Committee Meeting Director: Department: Date: Zak Ovadia Campus Planning Design & Construction August 6, 2014 I. SELECTED ACTIVE PROJECTS NOTE ALL SCHEDULES ARE TENTATIVE 1. Student Assembly Building (Sanctuary): Design and Construction of sanctuary building of approximately 6,500 square feet to serve as a venue for group events. Tentative Schedule: Programming Complete Conceptual Permitting Complete RFQ for Consultants Complete Short-listing & Interv. Complete Program Verification Complete Schematic Design August 2013 Design Development October 2013 Construction Docs. February 2014 Construction TBD Changes from last month: Construction Documents are about 50% complete. 2. Elevated Parking Deck: Feasibility, Design and Construction of a new elevated parking deck over part of an existing lot south of the FAC. Consultant tested the feasibility of adding additional parking levels to tie to the existing Fine Arts Garage. Program calls for a minimum of 170 stalls to serve the residential population. Currently the design provides over 550 stalls. Tentative Schedule: Programming August 2013 RFQ for Consultants Completed Short-listing & Interv. Completed Program Verification Completed Schematic Design Completed Design Development October 2013 Select CM January 2014 Construction Docs. March 2014 Construction Must be occupiable by January 2015 Changes from last month: Construction continues as scheduled. . Zak Ovadia 1 6. Aquatic Center Re-purposing for Basketball: Design and construction of basketball courts and general extensive renovations to the Aquatic Center to eliminate the pool. Tentative Schedule: Programming TBD RFQ for Consultants TBD Short-listing & Interv. November 2013 Program Verification December 2013 Schematic Design February 2014 Design Development February 2014 Select CM March 2014 Construction Docs. TBD Construction TBD Changes from last month: Barton Malow will be opening the bid packages on Wednesday afternoon. Subsequently, they will be submitting the GMP. 7. New Outdoor Swimming Pool: Design and Construction of an outdoor Olympic-size pool and diving pool north of the existing Student Wellness Complex. Tentative Schedule: Programming TBD RFQ for Consultants TBD Short-listing & Interv. TBD Program Verification TBD Schematic Design TBD Design Development TBD Select CM TBD Construction Docs. TBD Construction TBD Changes from last month: Programming meeting with users was held on June 4th. Consultant is revising Programming Documents for distribution to stake holders soon. 8. Skinner-Jones Hall NORTH: Programming and Schematic Design: Programming, Schematic Design, Feasibility Study to re-purpose this building. Program will include Skinner-Jones Hall SOUTH as well as other buildings having related departments (Math, Engineering, Health, etc). Tentative Schedule: RFQ for Consultants August 2013 Short List for interview September 2013 Programming February 2014 Schematic Design TBD Design Development TBD Select CM TBD Construction Docs. TBD Construction TBD Changes from last month: Received Structural Evaluation Report. Consultant was asked to summarize the potential options with associated construction costs. Mtg with Steering Committee scheduled for August 19. Zak Ovadia 2 9. Library Learning Commons: Reconfigure First and Second Floors to create a studentcentric learning commons. Co-locate the Help Desk from Bldg. 15, and remodel entry lobby. Tentative Schedule: Programming February 2014 Program Verification March 2014 Schematic Design March 2014 Design Development April 2014 Construction Docs. underway Construction various phases Changes from last month: Budget Estimate worksheets submitted to the administration showed a much higher cost estimate. Shari Shuman called for a meeting to discuss implications. Project team was asked to re-consider project scope reduction to stay within the available budget. Next meeting on August 7 will be for deliberation of options. 10. Bldg 9 – Second Floor: Project is to create 2 temporary spaces for the Theater Group practice as well as for Nofa Dixon to layout the tiles for the next project. CPDC met with Jay Coleman in the space on August 4 to discuss scope of project. CPDC is arranging for a preliminary cost estimate before proceeding further. Estimate due on Friday August 8. 11. Math Emporium: Met with Scott Hochwald to review program. There may be limitations regarding occupancy load in the space as well as availability of data and power for all stations expected to be in the space. Further evaluation of scope of project still ongoing. 12. Religious Centers: Engage Civil Engineer to provide a feasibility study and an order of magnitude cost for providing utility services to a grouping of four buildings. Tentative Schedule: NO CHANGE. Zak Ovadia 3